Responsibility Matrix
Responsibility Matrix
Instructions
The Responsibility Matrix (RM), also known as the Responsibility Assignment Matrix (RAM), is
used to show the connections between work that needs to be done and project team members.
(PMBOK, 3rd edition) This is a highly versatile tool that can be easily modified to suit multiple
project needs. RMs can be developed at various levels of detail, from high to low. It can be used
during any project phase, including the post-implementation support phase, and is especially
useful when activities require coordination between several different groups, agencies, or
vendors.
This document has the following sections:
1. Description of the Responsibility Matrix
2. Variations of Participation Types
3. Real-life Examples
Resource
1
Resource
2
Resource
3
Resource
4
Activity
1
Activity
2
Activity
3
Activity
4
Figure 1: Example of a Responsibility Matrix
The intersection points are used to describe each resources level of participation for the activity.
The participation type codes are inserted in these cells. A legend is included to define the codes.
Jerry
Review Resumes
Interview
Applicants
Hire Personnel
Purchase
Equipment
I
R
A
Elaine
R
R
I
Network
George
Staff
S
S
I
R
Glen
da
To
m
Sus
an
Investigate
Design
Software
Develop UAT
Plan
Obtain Signoff
Activity
Mar Crai
y
g
C
Responsible - The person or role who is assigned to achieve the task. There is only one
resource given this category type. Others may be required to assist in the work but they
are either given another participation code, such as Assist, or are not included as the RM
may only list the key people for the activities.
Accountable This person or role must sign off on work that Responsible provides. They
are ultimately accountable for the correct and thorough completion of the deliverable or
task, and the one to whom Responsible is accountable. There must be only one
Accountable specified for each task or deliverable.
Consulted - Those whose opinions are sought and with whom there is two-way
communication.
Informed - Those who are kept up-to-date on progress, often only on completion of the
task or deliverable, and with whom there is just one-way communication (informational
only).
In order for the matrix to be effective, it must accurately reflect people's expectations and
responsibilities. For instance, if the sponsor agrees that s/he will approve the Business
Requirements, then the matrix will reflect the sponsors approval is required. However, if the
sponsor delegated the approval of Business Requirements to a subordinate, that fact should be
represented on the matrix for all to see and approve. After the matrix is completed, it should be
circulated as a deliverable for the appropriate approval(s).
Figure 4 below is an example of a Responsibility Matrix for the development of project
deliverables. It lists the deliverables as activities and uses roles instead of specific individuals. It
also uses different participation types that may be more appropriate for this activity.
Project
Team
Steering
Committe
e
Project Definition
Communication
Plan
Business
Requirements
Status Reports
C means that the person (or role) creates the deliverable; this could be C (1) for primary,
C (2) for backup. Usually there is only one person who is responsible for creating a
deliverable, although many people may provide input.
In Figure 4, the Project Definition is created by the project manager; approved by the project
sponsor, functional manager and the Steering Committee; and reviewed by the project team. The
Business Requirements are created by the project team; reviewed by the project manager and
the functional manager; and approved by the project sponsor and Steering Committee.
Informed - These people need to be kept in the picture. They need updates on the
progress but they do not need to be formally consulted, nor do they contribute directly to
the task.
Input Required - Those who should be consulted as work is prepared, i.e. the driving input.
Notify Those who need to be notified about some aspect of the task, such as the
completion of the task. Those who are impacted by the project, are provided status, are
informed of decisions, and with whom there is one-way communication (informational
only).
Provides Input Those who should be consulted as work is prepared in order to provide
information.
Support These are resources allocated to Responsible in order to assist in completing the
task.
Verifier - Those who check whether the product meets the acceptance criteria set forth in
the product description.
The following participation types may be used in a Responsibility Matrix for decision-making
roles. The same type name may have slightly different definitions.