Project Management Plan Contents and Templates
Project Management Plan Contents and Templates
For
-
<CUSTOMER> -
Revision 1.0
Date 2014
Page ii
Table of Contents
1. Overview ................................................................................................................... 3
1.1. Project Purpose, Objectives, and Success Criteria ............................................ 3
1.2. Project Deliverables ........................................................................................... 3
1.3. Assumptions, Dependencies, and Constraints .................................................. 3
2. Project Organization ................................................................................................ 5
2.1. Team Structure .................................................................................................. 5
2.2. Roles and Responsibilities ................................................................................. 6
3. Managerial Process Plans ....................................................................................... 7
3.1. Staffing Plan ...................................................................................................... 7
3.2. End User Training Plan ...................................................................................... 8
3.3. Detailed Monitoring Plan .................................................................................... 9
3.4. Communication and Reporting Plan .................................................................. 9
3.5. Risk Management Plan .................................................................................... 12
3.6. Issue Resolution Plan ...................................................................................... 12
3.7. Project Close-Out Plan .................................................................................... 13
Appendix A Project Plan ....................................................................................... 16
Appendix B Detailed Monitoring Plan.................................................................... 17
Appendix C Change Request Form ...................................................................... 18
Appendix D Risk and Issue Management Templates ........................................... 19
Appendix E Progress Reporting Template ............................................................ 21
Appendix F Meeting Minutes Template................................................................. 24
ii
Page 3
1. Overview
The Company Intro in Brief
Deliverable
Project Preparation
ABC Execution
Validation & Acceptance
Testing
Post Execution Activities
Recipients
Delivery
Date
Delivery
Method
Comments
Task
Id
16
51
63
68
Page 4
<CUSTOMER> shall provide proper working space and other resources to <VENDOR> team.
<CUSTOMER> shall provide timely response to information request and required approvals to
go-forward from <VENDOR> within 3 business days.
<CUSTOMER> shall provide the personnel / executive support and access as reasonably
requested by <VENDOR> to meet the identified timelines for this project
<CUSTOMER> shall ensure participation of its staff in the coordination meetings to ensure quick
decision making and timely approvals to avoid any project delays.
Any delay / operational hindrance in providing information and/or sign-off shall consequently
result in delay in the overall project and should not be included in the time line. This may have
material affect on the contract executed by <VENDOR> and <CUSTOMER>.
There shall be adequate involvement from IT and Business Management for interviews,
facilitation sessions, and project guidance and the involvement of key IT-Business liaisons to
gather the information required to perform the assignment.
<CUSTOMER> shall provide access to any work previously performed on related projects that
could be of use to <VENDOR> such as presentations, project schedules, BPR and business
plans, etc.
<CUSTOMER> shall provide access to documentation of processes and manuals, related
performance measures and any current state reports/studies.
<CUSTOMER> shall assign a full-time project manager to this project to assist with data
gathering, interviews and any other reasonable assistance required for this project
<CUSTOMER> project management office shall arrange the time and place with the interviewers
as per the project plan
<VENDOR> shall deploy its people in accordance with the project plan/Staffing Plan (2.3)
<CUSTOMER> will provide balances as of Mar-31 2014 for go-live activities.
Oracle System will go-live in April. <CUSTOMER> will run parallel system till Jun-30 2014 and
from Jul-01 2014 legacy system will be shutdown.
Dependencies
<VENDOR> team will be dependent on <CUSTOMER> team for information and the decisions
where needed.
<VENDOR> team deliverables will be dependent on <CUSTOMER> response i.e. document
acceptance / signoff.
Constraints
Page 5
2. Project Organization
2.1. Team Structure
Page 6
Page 7
Sr.
#
Resource Name
1
2
3
4
5
6
7
8
9
10
11
Role
Senior Solution
Architect/Manager
Project manager
Track Lead SCM
SCM Consultant
SCM Consultant
SCM Consultant
Track Lead Financials
Financials Consultant
Financials Consultant
DBA/System
Administrator
Developer
Cell #
Utilization Days
40%
35%
80%
30%
100%
70%
80%
100%
100%
24
21
49
18
61
43
49
61
61
20%
100%
12
61
<CUSTOMER> Team
Sr.
#
1
2
3
4
5
6
7
8
9
10
Resource Name
Role
Project Manager
Manager IT Infrastructure
Financials Support
SCM Support
Project Lead
Financials User
Financials User
Financials User
SCM User
SCM User
Cell #
Page 8
Activity
User Training (Financials & SCM)
Duration
5 days
Start Date
18-Mar-13
End Date
24-Mar-13
Page 9
Written request with clear definition of change following the agreed upon process in place will be
initiated by the respective stakeholder
Duly approved by project manager / or authorized representatives from each party Impact
analysis to be conducted by <VENDOR> Project Manager and concerned team (this must include
impact upon Scope, Schedule, Budget and Quality)
Review and approval/rejection of the request based on the Impact Analysis by <VENDOR> team
All changes will be recorded along with serial number
If changes are rejected, reason of rejection and its consequences shall be recorded. If changes are
accepted, Project Plan shall be amended in order to accommodate the approved change.
Escalation Procedure
The following escalation procedure will be followed to:
1. Level 1: If an issue is not resolved to the satisfaction of <CUSTOMER>, it will be escalated to the
<VENDOR> Project Manager by the <CUSTOMER> Project Manager.
2. Level 2: If an issue cannot be mutually resolved between the <VENDOR> Project Manager and
the <CUSTOMER> Project Manager, it will be raised to the level of Project Director for
<VENDOR>.
3. Level 3: If an issue cannot be resolved by the <VENDOR> Project Director, it will be escalated to
the <VENDOR> Country Manager and <CUSTOMER> CEO
Acceptance Procedure
Deliverable Acceptance Procedure
The following procedure will be followed on the submission of deliverable materials:
All Deliverable Materials submitted to <CUSTOMER> by <VENDOR> will be signed off by
<CUSTOMER> within three working days from the date of submission. If we did not receive any
comments / feedback, it is deemed as accepted. Once observation is rectified it will be
considered approved.
Unless written comments or objections are provided for any of the Deliverable Materials within the
same duration by <CUSTOMER>, such documents will be deemed to have been signed off and
accepted.
Where written comments are received by <VENDOR> within the stipulated timeframe, the
<VENDOR> Project Manager shall agree with the <CUSTOMER> Project Manager what
corrective actions need to be taken in order for the Deliverable to be deemed acceptable and
Page 10
subject to the agreed changes the <CUSTOMER> team will accept the Deliverable on resubmittal. intervention
Reporting Plan
Each <VENDOR> Track-lead will submit a weekly progress report to the <VENDOR> Project Manager
using the Progress Status Report template shown in Appendix E: Progress Reporting Template
This report will record the:
Status of work performed during the last weeks;
Planned activities that were not achieved;
Planned activities for the coming weeks
Key issues currently being faced and the actions required to resolve these issues;
Progress according to milestones; and Key meetings attended.
Communication Plan
Following is the communication plan that would be used by both team to monitor and control the progress
of the project and ensure timely delivery of project deliverables:
Type of
Communication
Status Report
Communication
Schedule
Weekly
Typical
Communication
Mechanism
Team meeting
Members Meeting
Email and Personal
meetings
Responsible
team member
Project Managers
Project Director
Project Director
Project Review
Face to face
Recipient
Who Initiates
10
Page 11
Members
Role
CEO
CFO
CIO
<CUSTOMER> Project Manager
< VENDOR> Project Manager
<CUCTOMER> Power User
<VENDOR> Project Director
11
Page 12
Risks are formally identified by the project management team at the start of the project. Risk is
recorded in the Risk/Issue Record Form and listed on the Risk Register. During each subsequent
fortnightly project management meeting, the project management team will meet to review the
effectiveness of the management of the known risks, to identify any new risks and agree the
actions required to mitigate all risks.
At any stage during the course of the project, a project team member can identify a new risk.
Following discussion with the project manager, the identifier may be requested to define the risk
using the Risk/Issue Record Form presented in Appendix D: Risk and Issue Management
Templates
This must be immediately forwarded to the Team Project Manager.
The Project Manager will register the risk on the Risk and Issue Register and assign the next
sequential number to the Risk Record Form.
Risks will be formally discussed by the <CUSTOMER> and <VENDOR> project managers at
each fortnightly project management meeting or more frequently if necessary. During this meeting
each risk will be prioritized by assessing the:
1. Probability of the risk becoming an issue
2. Impact on the success of the project, should the risk become an issue.
Priority H
Priority M
Priority L
Will not require immediate or urgent action at this stage, but will still require
monitoring
Mitigating actions will be agreed by the Project Management Team, assigning a responsible person and a
target date for completing the action. The <VENDOR> Project Manager will record the assigned actions
and their status on the Agreed Action List
The <VENDOR> Project Manager will distribute the Agreed Action List to all project participants
following the project management meeting. Each person assigned a responsibility for performing
a risk mitigating action (the responsible person) will be required to complete the action before
the target completion date and communicate the status back to the Accountable person.
The responsible person will verify that the action has been completed, and will ensure that the
Agreed Action List is updated before the next project management meeting.
The Project Managers will review the risks listed within the Risk & Issue Register and Agreed Action List
on a fortnightly basis to ensure that risks are being managed and that agreed actions have been
completed.
An issue can be noticed by any project team member or stakeholder external to the core project
team. All issues must be communicated immediately to the Project Management Team using the
Risk/Issue Report Form presented in Appendix D: Risk and Issue Management Templates
The <VENDOR> Project Manager will review the issue and assign it the next available serial
number in the Risk and Issue Register and will update the register with the details of the issue.
The Project Managers will meet fortnightly to formally review the project issues, or on an ad-hoc
basis depending on the nature and severity of the issue. During these discussions, they will
prioritize each issue as follows:
Priority H
12
Priority L
Will not require immediate or urgent action at this stage, but will still
require monitoring
Page 13
Based on the priority of the issue, the project managers will agree on actions that need to be
taken and assign accountability and target completion dates to each action.
The <VENDOR> project manager will update the Action List and distribute to all project team
members following the fortnightly meeting, or issue specific actions on an ad-hoc basis as
necessary.
Each person assigned a responsibility for performing an action (the responsible person) will be
required to complete the action before the target completion date and communicate the status
back to the accountable person.
The person accountable will verify that the action has been completed, and will ensure that the
Agreed Action List and Issue Register are updated before the next project management meeting.
These updates will include capturing:
Change to the status of the action
Change to the status or priority of an issue
The date the issue was closed and the nature of the resolution
The Project Managers will review the Risk and Issue Register and Agreed Action List on a fortnightly
basis to ensure that risks are being managed and that agreed actions have been completed.
<CUSTOMER> Responsibilities
<VENDOR> will provide a Project Closure Report to the <CUSTOMER> team as a result of this activity.
13
Page 14
14
Page 15
Revision History
Name
Date
Dec-14 2014
Version
1.0
15
Page 16
16
Page 17
17
Page 18
Completed on (date):
Change Title:
Source:
Status:
Raised, Under Review,
Under Analysis, Closed
Priority:
H/M/L
Change Analysis
Prepared by:
Prepared on:
Estimated Cost
Change decision:
Implement, Postpone, Reject
Decided by:
Date:
Justification:
Implementation assigned to:
18
Page 19
Risk or Issue?
Risk ID:
Risk Title
Priority
Assigned by
Project Manager
Assigned by Project
Manager
H,M or L
Background
Describe the background to the risk or issue
Risk Description
Probability
High
Moderate
Low
Impact on 7 Keys
Y/N
Stakeholders
Y/N
Business Benefit
Y/N
Work Schedule
Y/N
Team
Y/N
Moderate
Scope
Y/N
Low
Risk Mitigation
Y/N
Other
Y/N
ID
Propose what should be / is being done to mitigate the risk or resolve the issue,
indicating the date before which it should be completed
Impact
High
Date
2
Risk Control Record
Track:
Raised by:
Date:
Accepted by:
Date:
Closed by:
Date:
Additional
Comments:
19
Risk /
Issue
ID
Page 20
Date
Raised
Assigned
to
Target
Complete
Revise
d Date
Probability
Impact
Status
Date
Closed
Priority
1
2
3
4
5
ID
Description of
Action
Track
Raise
d by
Responsible
Date
Raise
d
Current
Status
Date
Closed
Risk /
Issue
Priority
Comments
Days
Overdue
1
2
3
4
5
20
Page 21
Distribution List
Tasks Completed/Started
* Key, P: prepared, D: Delivered or Conducted, A:
Approved, NR: Not required
Status
P
Project Management
Oracle Financials
Technical
21
Page 22
Responsibility
/ Comments
Project Management
Financials
Supply Chain
Technical
Issues Identified
Issues Register
Impact
Status
Resolution
Baseline
Date
Current
Planned
Date
Actual Date
Current
Status
22
Page 23
SL.
NO. Track
Process Area
Meeting/
Workshop
Date
Meeting /
Workshop
Status
1
2
3
23
Page 24
Time:
Track:
Participants:
<CUSTOMER> Participants
Name
Role
<VENDOR> Participants
Name
Role
Objectives:
Meeting Agenda:
Item
1
2
3
Topic
Start Time
Duration
End Time:
24
Page 25
Meeting Minutes
No
1
2
3
Responsibility
Agreed Actions:
No.
1
2
3
Description of Action
Responsibility
Completion Date
Other Notes:
Attachments:
25