By Marc Friedheim and The Post Tensioned Concrete Committee January 2013
By Marc Friedheim and The Post Tensioned Concrete Committee January 2013
Number of test
samples
1
1
4
1
1
Bara
Bar couplera
1
1
assembliesa
Prepackaged grout
1
1
aRandomly
50-1.01D(1) General
The Department rejects any unidentified prestressing steel, anchorage assemblies, or bar couplers received at
the job site or casting site.
The contractor for post-tensioned concrete must have at least one person present during all operations who is
currently certified as a PTI Level 2 Bonded PT Field Specialist. In addition to the previous certification, the
foreman for each grouting crew must be an ASBI certified grouting technician. Proof of these certifications must
accompany the grouting plan.
Cement and water grout is currently used and has the following
potential variations
HRWR agents (more bleed)
Water, must be carefully monitored
Plasticizers
Glenium 7500 (accelerates early strength)
Common prepackaged thixotropic grouts:
Masterflow 1205
Euco Cable Grout PTX
Sika Grout 300PT
Masterflow 1341
Water
tank with
overflow
Mixing
hopper
Holding hopper
with cont. feed to
pump
Superior mixing
compared to the
vane (paddle
type) mixers
Acknowledgment of
prepackged grout issues and
resolution:
Chlorides
Testing is now required to
confirm chloride ion
content
Soft Grout
Inclined tube test
Limit on filler content
(inert materials such as
limestone)
Limit on grouting
pressure
Limit on grouting speed
New PTI addendum in
March
50-1.02C Grout
Admixtures must comply with section 90, except admixtures (1) must not result in chloride ions in excess of 0.08
percent by weight of mixed grout and (2) must already be present in the prepackaged grout.
50-1.02C Grout
Mix the grout as follows:
1. Add water to the mixer followed by prepackaged grout.
2. Mix the grout with a high-shear colloidal mixer.
3. Retempering of grout is not allowed.
4. Agitate the grout continuously until the grout is pumped.
Grout must be placed within 30 min of adding the first water to the mixture.
Vents
Specify locations to prevent voids, especially at high points
More vents than currently used, larger diameter
50-1.02E Vents
Vent all ducts having a vertical duct profile change of 6 inches or more. Place vents at the following locations:
1. At the anchorage areas at both ends of the tendon.
2. At all high points.
3. At locations 4ft upstream and downstream of each high point.
4. At each low point.
5. At any location where there is a change in the cross section of the duct.
6. At any other location recommended by the Engineer.
Vents must:
1.Be at least 3/4-inch-diameter standard pipe or suitable plastic pipe.
2.Be connected to ducts using metallic or plastic structural fasteners. Plastic
components must not react with the concrete or enhance corrosion of the
prestressing steel and must be free from water soluble chlorides.
3.Be mortar tight and taped as necessary.
4.Provide a means for injection of grout through the vents and for sealing the
vents.
5. Be left open at low points in order to allow drainage of any water that may
have accumulated within the duct before grouting the duct.
Flushing
No longer allow flushing
Water will get trapped in the corrugations and act as a mechanism
for corrosion
50-1.03A(3) Ducts
Accurately place prestressing ducts. Securely fasten the ducts in place to prevent movement of the ducts during
concrete placement. Round metal ducts must be secured horizontally and vertically at a spacing not to exceed
4ft. HDPE round duct without strands must have a support spacing not to exceed 2ft. HDPE flat duct with strand
installed must have a support spacing not to exceed 2ft. HDPE flat duct without strand installed must have a
support spacing not to exceed 1ft.
Duct integrity
Pressure testing
Compressed air to remove water/debris
Torpedo to check for kinks/blockages
Purpose is to ID major leaks and fix prior to grouting
Check for cross-over
Evaluate function of vents and valves
50-1.03B Prestressing
50-1.03B(1) General
Prior to inserting strand into a duct, the duct must be pressure tested after stem and soffit concrete placement.
Pressurize ducts to 30 psi and record pressure loss for 1 minute. A loss of 50% is acceptable.
External ducts are to be pressure tested with compressed air by pressurizing to 15 psi and recording pressure
loss for 1 minute. A loss of 50% is acceptable.
After all concrete placement and just prior to inserting strand into the ducts, ducts must be cleared with the
application of compressed air into the duct to remove water or debris. After clearing the duct with compressed air,
a torpedo (or similar device) with a cross sectional area slightly smaller than the duct, must be passed through the
entire length of the duct.
50-1.03B Prestressing
50-1.03B(1) General
Installation of prestressing strand in the ducts may be by the push or pull through methods. In the pull through
method, all strands within a duct must be pulled simultaneously. In the push through method, bullets must be
attached to the leading end of each strand prior to pushing the strand through.
Pumping pressures
Cap on allowable pump pressure to prevent blowouts
Procedure for handling blockages (alternative to flushing)
7 days
20 days
40 days
Do not allow traffic or loads on the structure until 24 hours after completion of grouting.
Vertical Grouting
Alert the contractor to use a special prepackaged mix
Safety
Provide some protections for the grout plant operators
Current specs are silent on this
50-1.03B(3)(e) Safety
Personnel involved in the grouting operation must be adequately protected. They must wear NIOSH approved
Tyvek suits, full-face dual cartridge respirators, earplugs, and eye protection. They are also required to wear
gloves which are impermeable to grout. The grout plant must be arranged such that the grout plant operator is
not required to move bags of prepackaged grout more than 30 vertically in order to place grout in the mixer.
During stressing, no personnel may stand next to, behind, or above the hydraulic jack. All personnel must be
located a safe distance away from the jack and the area around the jack. The end opposite to the stressing end
must be cordoned off.