Bridge Constraints
Bridge Constraints
ABSTRACT
This bridge is 2.000 m long and 140m high due to environmental
requirements. Strict economical restrictions led to a bridge design that
could be constructed in 36 months. The bridge has 14 spans of
40+3x70+150+5x250+150+2x70+40 m. The deck has a very large 24.0 m
wide, variable depth single-box cross section. The central part of the main
span was designed with H-35 lightweight concrete whereas high
performance H-75 concrete was used at the piers. The main 250 m spans
are to be built by the balanced cantilever method. The piers are very high,
up to 125 m, with a hollow box cross section at the bottom and two shafts
at the top, all made of high performance H-75 concrete
1. DESIGN CONSTRAINTS
1.1 Functional and layout constraints
The plan layout of the bridge is straight in almost its entire length; in
elevation it has a constant slope of -1.25% except at abutments.
The freeway's cross section includes two roadways, each of which
houses two 3.50m lanes for traffic, interior and exterior hard
shoulders (1.0m and 2.50m wide respectively) as well as double rigid
barriers. Both roadways are separated 2.0m (measured between the
inside edges of the interior shoulders). Transversely, the cross
section has a 2% crown, which changes towards the abutments to a
2% camber.
1.2 Constructive constraints
Constructive constraints are of great importance in the case of this
structure, due to the high altitude at which the road crosses the
valley. This situation leaves cantilevered construction coupled with
self-propelling formwork as the only choice. Current self-propelling
formwork systems have a maximum span of 70-80m, therefore only
Pgina 1
F H E C O R J Ingenieros Consultores
the side spans may be built using this method. During the
cantilevered construction of the main 250m spans, the deck must be
fixed at the piers; in some cases it will be permanently fixed and in
others only during construction.
The decks' height limits lightweight concrete strength to 35 N/mm,
since at the present time stronger concretes cannot be pumped to
such heights.
Pgina 2
F H E C O R J Ingenieros Consultores
The deck will be built using both high performance and lightweight
concrete, lightweight concrete for the overhangs and the central
portions of the cantilever spans, and high performance concrete for
the box girder at the piers and in the 40 and 70m spans. This aspect
will be more thoroughly discussed in the next chapter, construction
process.
Prestressing in the 40 and 70m spans consists of 5 or 6 tendons per
web which are put in tension at the end of each stage. This is
reinforced with additional prestressing along the bottom slab once
the deck is complete. Prestressing in the cantilevered spans serves
two purposes; tendons in the top slab are needed to ensure that the
Pgina 3
F H E C O R J Ingenieros Consultores
There are two types of piers, the first type (corresponding to the
side spans, piers 1 to 4 and 11 to 13) have a hollow rectangular cross
section of 7.5 x 3.0m with 0.30m thick walls, and heights ranging
between 9.5 and 46.3m. The deck is supported at these piers by POT
bearings, which allow displacement along the longitudinal axis.
The second type of piers (piers 5 to 10) is required to fix the deck
during the balanced cantilever construction process whilst
remaining flexible with respect to longitudinal displacements; their
height ranges from 59.2 to 124.8m. Each of them consists of two
hollow rectangular shafts, with a 9.0m axis-to-axis longitudinal
separation at the top which 50m bellow is reduced to 5.0m; from
that point to the pier foundation both shafts become a single
vertical shaft.
Shaft dimensions at the top are 8.50x3.0m, 0.25m thick in the
transverse direction and 0.35m thick in the longitudinal direction.
The shafts have a 1/66 slope in the transverse direction and a 1/166
slope in the longitudinal direction. Piers 6 to 9 are fixed to the deck,
piers 5 and 10 however are hinged to increase their flexibility with
regard to longitudinal displacements. During construction they will
be fixed to the deck using reinforcement bars.
The deck is supported at the abutments by a pair of 9.0m long,
2.30m wide walls reaching to the wall which contains the
embankment. This design follows the need to absorb the decks'
longitudinal displacements, (mainly due to rheological and thermal
loadings), whilst also housing both the expansion joint and the
Pgina 4
F H E C O R J Ingenieros Consultores
damper system. These elements are very large due to the fact that
the deck has no intermediate joints along its 1980m length.
Piled foundations have been used both at the piers and at the
abutments, with 1.80m diameter piles. Foundations for piers 1 to 4
and 11 to 13 consist of 9 piles with a 14 x 14m variable depth pile cap.
Piles 5 to 10 comprise 49 piles each, with a two-way prestressed pile
cap 36 x 36m wide and variable (3 to 8m) depth. Abutment
foundations consist of 6 piles each, with a variable geometry pile cap
3m deep.
3. CONSTRUCTION PROCESS
Construction will proceed as follows:
Foundation construction
Pier and abutment construction. Piers will be built using
travelling formwork.
Deck construction. Work on spans built using self-propelling
formwork and cantilever spans may proceed simultaneously.
The side spans (built on self-propelling formwork) will be
constructed in two stages, firstly the 9.5m wide box girder with
high performance H-75 concrete and then the 7.25m long
overhangs with HL-35 lightweight concrete.
Pgina 5
F H E C O R J Ingenieros Consultores
Balanced cantilever spans will also be built in two stages, the first
stage is to be built with 14.7m wide dowels, with ribs and overhangs
being built in a second stage. Dowels from the pierhead to 9 are of
high performance H-75 concrete, whilst dowels 10 to closure are to
be built with HL-35 lightweight concrete.
In spans 5 and 11, a 12.2m gap will remain between the portion built
on the self-propelling formwork and the cantilever. This portion will
be finished using formwork suspended from the edges of the
cantilever and the adjoining 70m span. It will be built entirely with
HL-35 lightweight concrete in two stages, using the same detailing
Pgina 6
F H E C O R J Ingenieros Consultores
as in the side spans. Once the curing of the concrete is complete the
tendons in the lower slab will be put into tension, thus completing
the structure.
F H E C O R J Ingenieros Consultores
yzx
F H E C O R J Ingenieros Consultores
Pgina 9