AFRICA ASSOCIATION OF
QUANTITY SURVEYORS
Draft No 1 May 2014
Standard Method
of Measuring Building Work
2014
STANDARD METHOD OF MEASURING
BUILDING WORK
PREFACE
CONTENTS
GENERAL INSTRUCTIONS
Alteration work
11 Keeping excavations free of water
12
NOTE
Openings
12 Dewatering
12
Bills of quantities
Building up openings
13 Filling
12
Setting out of bills of quantities
Re-use of existing components
14 Foundation courses
12
Order of items
Work in patches
15 Compaction of surfaces
13
Order of dimensions
10 Sundries
16 Gabions and interlocking block
Net measurements
11 New doors, windows and the like
Fractional quantities
EARTHWORKS
Provisional quantities
GENERAL
Provisional sums
Method and procedure
Contingencies etc
Bulking
Preliminaries
Site clearance
EXCAVATIONS, FILLING, ETC
DEMOLITIONS
1
Method and procedure
Nature of material to be excavated
10
General
Classification of material to be excavated
10
Excavations
10
Diversion of services
11
Carting away of excavated material
11
Risk of collapse of excavations
11
ALTERATIONS
1
General
Materials arising from alterations
Barricades, screens, etc
Removals
13
17 Filter fabric
13
18 Weedkillers, insecticides, etc
13
19 Tests
13
LATERAL SUPPORT
GENERAL
SITE CLEARANCE
PRELIMINARIES
retaining structures
10 Working space
12
ii
Removal of lateral support
14
Insurance
14
Movement monitoring
14
GROUND ANCHORING
4
Descriptions
14
Establishment
14
Test anchors
15
Ground anchors
15
Waterproofing of ground anchors
15
CONCRETE CAST IN SITU PILING
Testing, re-tensioning and de-stressing
of ground anchors
10 Rock bolts and rock dowels
11 Soldiers, boarding, shotcreting, etc
15
13 Additional requirement for formwork
12 Augered piles
19
13 Driven, bored or similar tube piles
19
14 Disposal of excavated material
19
15
24
15 Projections, grooves, etc
24
16 Openings
24
REINFORCEMENT
17 Movement joints etc
24
CONCRETE
REINFORCEMENT
PLANKING, STRUTTING AND SHORING
CONCRETE, FORMWORK AND
16
13 Shoring units
16
LATERAL SUPPORT PILING
14 Lateral support piling
16
PILING
23
14 Edges, risers, ends and reveals
15
12 Planking and strutting
to slabs, beams and stairs
Classification etc
20
18 General
25
Concrete components such as
20
19 Reinforcement
25
Hollow blocks, spacing tiles and
GENERAL
20 Pre-tensioned or post-tensioned
prefabricated beams
20
reinforcement
26
Site conditions
17
Shotcrete
20
21 Tests
Nature of the work
17
Prescribed curing compounds
21
PRECAST CONCRETE
Establishment
17
Surface treatment
21
General
27
Setting up
17
Grooves, channels, mortices, etc
21
Wall linings
27
Reinforcement
17
Bedding under base plates etc
21
Slab paving
28
Exposing piles for inspection
17
Test blocks and testing
21
Copings, sills, etc
28
Cutting off etc
18
FORMWORK
Other components
28
Testing
18
10 Formwork to components such as
Joint sealants, jointing strips, etc
28
Holes, notches, etc
28
PREFABRICATED PILING
9
Precast concrete piles
21
11 Additional requirement for formwork
18
10 Steel piles
18
11 Sheet piling
18
to walls
22
12 Additional requirement for formwork
to columns
22
iii
26
MASONRY
20 Fabricated lintels
32
37 Walls and linings
35
MASONRY WORK
21 Turning pieces
32
38 Beamfilling
35
39 Facing and pointing
35
Classification etc
29
FACE BRICKWORK
Concrete filling
29
22 General
32
40 Copings, sills, etc
35
23 Face brickwork
32
41 Pitched angles
35
BRICKWORK
3
Mass brickwork and piers
29
24 Walls faced both sides
32
42 Trimming to receive plaster etc
35
Regular shaped piers
29
25 Cut face brick linings
32
43 Flues
36
Walls and linings
30
26 Fair cutting to face brickwork
33
44 Niches
36
Beamfilling
30
27 Special face bricks at angles
33
45 Turning pieces and centres
36
Vaulting
30
28 Face brick bands
33
STONEWORK OF SLATE, MARBLE,GRANITE, ETC
Lintels
30
29 Face brick copings, lintels, sills, etc
33
46 Classification etc
36
Forming toothings and bonding
30
30 Face brick arches
33
47 Ashlar walling, linings and paving
36
31 Face brick niches
34
48 Margins, skirtings, cornices, etc
37
49 Mouldings
37
10 Hacking face or raking out
joints of existing brickwork for key
30
BLOCKWORK
11 Building brickwork to a fair face
31
32 General
34
50 Columns, piers, etc
37
12 Flues
31
33 Piers and pilasters
34
51 Special features
37
13 Splayed mortar fillets in cavities
31
34 Special blocks for copings, sills,
52 Rough rebates, grooves, etc
37
14 Closing cavities
31
53 Fair edges, angles, etc
37
15 Projections and cores
31
PAVING ETC
54 Holes, notches, etc
37
16 Rough arches
31
35 Paving
55 Cramps, dowels, etc
37
17 Rough niches
31
NATURAL STONEWORK
56 Turning pieces and centres
38
18 Joint forming material in movement joints
31
RUBBLE WALLING
19 Reinforcement to brickwork
32
36 Mass and irregular rubble work
lintels, etc
34
34
MISCELLANEOUS
iv
35
57 Bagging
38
58 Quarry tiles, cement ties, fibre
cement, etc
41
15 Accessories
44
41
16 Special sheets
45
ROOF COVERINGS, CLADDINGS, ETC
17 Roof ventilators and rooflights
45
SLATES, TILES AND SHINGLES
18 Insulation
45
9
38
59 Ornamental blocks, glass blocks, etc
38
60 Hoop iron ties, cramps, etc
38
61 Air bricks etc
38
62 Fireplaces
38
63 Special features
38
WATERPROOFING
10 Waterproofing additives
General
42
FLAT SHEET METAL
Circular cutting
42
19 General
45
Eaves and verges
42
20 Circular cutting
46
Ridges, hips, closed valleys and
21 End caps, finials, etc
46
DAMP PROOF COURSE
1
General
39
WATERPROOFING
2
Classification
39
SHEET OR MEMBRANE WATERPROOFING
Joint sealants
vertical angles
42
SHEET METAL FLASHINGS, LININGS,
Purpose made tiles
43
COPINGS, ETC
Insulation
43
22 General
46
23 Flashings
46
46
THATCH
7
General
43
24 Linings, copings, etc
Sheet or membrane waterproofing
39
Ridges and apex caps
43
TIMBERWORK
Protection
40
Ornamental bands and runners
43
GENERAL
Flashing strips
40
10 Prefabricated ridges, hips, ends,
intersections, etc
TROWELLED-ON WATERPROOFING
6
Trowelled-on waterproofing
40
43
PROFILED SHEETING OF METAL,
Classification etc
47
Labours
47
Fixing
47
FIBRE-CEMENT, PLASTIC, ETC
LIQUID WATERPROOFING
7
Liquid waterproofing
40
WATERSTOPS, SEALING STRIPS, JOINT
11 General
44
12 Circular cutting
44
13 Cranks, bullnoses and curved turn-ups
44
14 Rolled edges at verges
44
SEALANTS, ETC
8
Waterstops, sealing strips, etc
40
STRUCTURAL TIMBERWORK
4
Structural timbers
48
Plate nailed timber roof truss construction
48
Floor and roof boarding
49
Eaves and verges
49
TIMBER DOORS, WINDOWS, ETC
Insets
55
Circular cutting
Doors, windows, sashes, etc
49
Edge and cover strips
55
STEELWORK
Frames etc
49
Skirtings
55
Sundry steelwork
Stairs
56
Stairs, balustrading, cat ladders, grilles,
SUNDRY JOINERY
10 Floor boarding on concrete floors
49
Nosings
56
11 Skirtings, rails, etc
50
Plastic handrails
56
12 Shelves and fittings
50
10 Polish, sealers, etc
13 Stairs
50
IRONMONGERY
14 Panelling
51
Classification
57
15 Plastic, fibre-cement, etc
51
Components such as
57
Metal shelving
57
Proprietary kitchen cupboards, lockers,
CEILINGS, PARTITIONS AND ACCESS
FLOORING
56
writing boards, seats, etc
CEILINGS
General
52
PARTITIONS
2
Partitions
62
Minor work
62
Fixing accessories to structural
timberwork
62
Ribbed floors and permanent decking
63
Floors etc formed of open grillework
or gratings
63
Skirtings etc
63
OTHER METALS
57
ACCESS FLOORING
3
Access flooring
STRUCTURAL STEELWORK
54
FLOOR COVERINGS, WALL LININGS, ETC
63
DOORS, WINDOWS, CURTAIN WALLING,
STRUCTURAL STEELWORK
53
61
gates, framework, etc
10 Aluminium, copper, lead, etc
1
61
SHOPFRONTS, ETC
Classification
58
STEEL DOOR FRAMES, DOORS, WINDOWS, ETC
General
58
11 Door frames
63
Steelwork
59
12 Doors
64
Tests
60
13 Windows etc
64
Coverings and linings
55
METALWORK
14 Fly screens and burglar screens
64
Circular cutting
55
GENERAL
15 Adjustable louvres
64
Margins, borders and turn-ups
55
16 Miscellaneous
64
Classification
61
vi
ALUMINIUM WINDOWS, DOORS, ETC
17 Windows, doors, screens, etc
64
CURTAIN WALLS, SHOPFRONTS, ETC
18 Curtain walls, shopfronts, etc
Soap dishes etc
69
16 Waste unions, traps, etc
Dividing strips, edge trims, etc
69
FRIE HOSE REELS AND FIRE FIGHTING
EQUIPMENT
PLUMBING AND DRAINAGE
65
PLASTERING
GUTTERS ETC
1
Roof gutters, rainwater pipes, etc
70
Classification
66
CHANNELS
Plaster and other in situ finishes
66
Labours on finishes
66
PIPEWORK ETC
Skirtings and stoolings
67
Pipes, pipe fittings, etc
70
Finishes to kerbs, sills, etc
67
Pipe trenches (method A)
71
Mouldings
67
Pipe trenches (method B)
72
Ornaments etc
67
Pipe insulation and protection
72
Dividing strips, edge trims, etc
67
Encasing
72
Metal lathing
67
Anchor blocks, thrust blocks, etc
72
Gulleys, grease traps, etc
73
Stormwater channels
70
Classification etc
68
10 Inspection chambers, catch pits, etc
73
Beds and backings
68
11 Soakage pits, french drains, etc
73
Tiling
68
12 Connections
73
Cutting
68
SANITARY FITTINGS, TANKS, GEYSERS, ETC
Mitred corners and special edge and
6
7
corner tiles
69
Treads, risers, sills, copings, skirtings, etc
69
Channels
17 Fire hose reels etc
73
18 Fire fighting equipment
74
SLEEVES, HOLES, ETC
TILING
73
13 Sanitary fittings etc
73
14 Tanks, geysers, etc
73
15 Taps, valves, etc
73
69
vii
19 Sleeves
74
20 Holes
74
21 Flashings
74
GENERAL
22 Testing
74
ELECTRICAL WORK
1
Classification
75
Connection to main supply
75
Main supply and equipment
75
Distribution boards, etc
75
Cables
75
Cable trenches (method A)
76
Cable trenches (method B)
76
Conduit
76
Outlet boxes, cover plates, etc
77
10 Cable trunking etc
77
11 Draw wires
77
12 Conductors
77
Pipe trenches (method B)
81
Glazing beads, gaskets, sealing, etc
86
13 Busbar systems
77
Pipe insulation and protection
81
Labours on glass
86
14 Socket outlets and light switches
77
Encasing
82
Glass louvre blades
87
15 Fittings, equipment, etc
77
Anchor blocks, thrust blocks, etc
82
Glass tops, shelves, doors, mirrors, etc
87
16 Earthing
78
10 Inspection chambers, junction boxes, etc
82
Bent glass
87
17 Lightning protection
78
DUCTWORK
Leaded and coppered lights
87
18 Holes
78
11 Ducting
82
Patent glazing
87
ELECTRONIC INSTALLATIONS
12 Diffusers, grilles, etc
83
Materials resembling glass
87
19 Communication, security and control
13 Ducting insulation and protection
83
PAINTWORK
Installations
78
GENERAL
20 Testing and commissioning
78
21 Drawings, manuals, etc
78
22 Replacement parts etc
78
MECHANICAL WORK
CONVEYING INSTALLATIONS
Classification
79
Equipment
79
PIPEWORK ETC
3
Pipes, pipe fittings, etc
79
Valves etc
80
Pipe trenches (method A)
81
88
84
Colours
88
15 Hoist, escalator and conveyor installations
84
Paintwork
88
Trusses and lattice work
89
Frames etc
89
Windows, sash doors, etc
89
OTHER MECHANICAL INSTALLATIONS
16 Material handling installations, disposal
installations, etc
85
HEATING, VENTILATION AND AIR
Classification etc
14 Lift installations
GENERAL
CONDITIONING INSTALLATIONS, ETC
17 Testing and commissioning
85
Signwriting and gilding
89
18 Drawings, manuals, etc
85
Polishing
89
19 Identification markers etc
85
PAPERHANGING
20 Replacement parts etc
85
Classification
90
21 Electrical work and work by other trades
85
Paperhanging
90
Borders and motifs
90
Hessian, canvas, etc
90
GLAZING
1
Classification etc
86
viii
EXTERNAL WORK
20 Foundation courses
LANDSCAPING
21 Compaction of natural or excavated
Contouring
91
Topsoil, compost, lime and fertilizer
91
Plant bed preparation
91
Mulch
91
Grassing, ground cover, etc
91
Trees, shrubs, etc
91
Pruning of existing trees and shrubs
92
Pitching, pebble covering, etc
92
Rockery boulders
92
10 Retaining structures
92
11 Filter fabric
92
12 Paving etc
92
13 Weedkillers, insecticides, etc
92
14 Ponds, water features, etc
92
15 Benches, tables, etc
92
16 Drainage
92
17 Irrigation systems
92
18 Effect lighting
93
93
ground surfaces
93
22 Road and parking surfacing
93
23 Channels, humps and shoulders
93
24 Channelling, kerbing, edging, etc
93
25 Road signs, crash barriers, etc
93
26 Drainage
93
27 Painting
94
FENCING
28 Fencing, posts, gates, etc
94
29 Concrete bases and kerbs
94
WASHING LINES
30 Washing lines
94
PAINTING
31 Painting
95
ROADWORK AND PARKING
19 Excavations and filling
93
ix
GENERAL INSTRUCTIONS
NOTE
This standard system has been drawn up in a tabulated format to suit the more modern way of setting out of documents
The following is to be noted: Where items are grouped together in the Item or work to be measured column those items shall not be grouped together but shall each be given
separately in the unit as shown in the Unit column, eg Concrete, Formwork and Reinforcement clause 2, concrete in Surface blindings, surface beds, surface beds cast in
panels, footings, bases, underpinning, slabs inclusive of beams and inverted beams, isolated beams, lintels, stairs inclusive of landings and beams, walls, columns, hollow block slabs,
coffered slabs, troughed slabs and gradings shall each be given separately in m
Where items may be grouped together it is specifically stated, eg Concrete, Formwork and Reinforcement clause 14, formwork to Edges, risers, ends and reveals exceeding
300mm high or wide shall be given together in m
1
Bills of quantities
This standard system has been drawn up to provide a uniform basis for measuring building work. It is the result of negotiations between the various parties to this publication
and embodies the minimum essentials of good practice
Bills of quantities shall set out the work to be done as shown on the drawings or contained in the specification in accordance with the rules laid down in this standard system.
No departure shall be made from this standard system except where no specific rule can be applied or where exceptional circumstances involving work of a different character
or particular circumstances of execution require the provision of more detailed information in order to define the nature and extent of the work. In such cases separate items shall
be given following the general principles contained herein and descriptions of such items shall provide all the information necessary for pricing
Descriptions in bills of quantities shall be complete and clear. Unless otherwise stated the radii of circular, flowing and spherical work need not be stated
Unless otherwise stated the description of each item shall be deemed to include manufacturing, conveying and delivering, unloading, storing, unpacking, hoisting, setting, fitting
and fixing in position, cutting, waste, patterns, templates, plant, temporary works, return of packings, establishment charges, profit and other obligations arising out of the
conditions of contract
Unless prescribed the method of execution of the work shall be at the discretion of the contractor
2 Setting out of bills of quantities
The bills of quantities shall be set out in the following format:
Item No
Description
Quantity
Rate
Amount
3 Order of items
The work shall be set out as far as possible in accordance with the following rules:
3.1 The work shall be divided into trades and sections of trades in the order as set out in this standard system. If necessary the work may be further divided into additional
sub-sections to facilitate cost analyses, cost reporting, etc
3.2 Ancillary work applicable to a specific trade shall be given in that trade in accordance with the principles laid down in the relevant trades
3.3 Within each trade or section thereof the order shall be mass, volume, area, length and number
3.4 Subject to the above rules, items shall be placed in their approximate order of value, the cheapest first
4
Order of dimensions
Dimensions shall as far as possible be given in the following sequence:
4.1 Horizontal at right angles to the line of sight
4.2 Horizontal parallel to the line of sight
4.3 Vertical
Net measurements
Unless otherwise stated all work shall be measured net as fixed in position. All wants shall be deducted and no allowance shall be made for waste, nor for passings and laps
except where otherwise stated. Where laps occur they shall be included in the descriptions
Each measurement shall be taken to the nearest 10mm ie 5mm and over shall be regarded as 10mm and less than 5mm shall be disregarded. This rule shall not apply to any
dimensions stated in the descriptions
Fractional quantities
Quantities shall be rounded off to the nearest whole unit. However, where the value of fractional quantities is of relative significance, quantities may be given to one decimal place
Provisional quantities
Where the quantity of any work cannot be accurately determined during preparation of the bills of quantities such work shall be described as provisional and subsequently
remeasured
Provisional sums
Separate provisional sums shall be given for each class of work
Items shall be given for profit and for attendance where required. Descriptions of attendance shall include scaffolding and other facilities to be specially provided, prescribed
protective measures, etc
Contingencies etc
Sums for contingencies, provision for contract price adjustments and other expenditure which cannot be determined during the preparation of the bills shall be given in the
summary at the end of the bills of quantities
PRELIMINARIES
Information and such requirements and restrictions of a general nature that may affect the cost of the works shall be given as items in this section eg:
1
Information concerning the bills of quantities and the availability of construction documentation
Names, addresses, telephone numbers, etc of the employer and consultants
Particulars of the contract documents
Clause headings of the relevant conditions of contract
Requirements with regard to sureties or guarantees
Identification of the site
Broad scope of the works stating inter alia overall size, height above and below ground level and number of storeys and the approximate area and height of any internal area with
a floor to ceiling height in excess of 5m
Restrictions with regard to access, area to be occupied and procedure
Restrictions on the use or disposal of materials and articles found on the site
10
Responsibility for the preservation of boundary beacons etc
11
Results of soil investigations
12
Responsibility in respect of previous contracts
13
Responsibility in respect of the management and execution of the works
14
Programming of the works and meetings
15
Samples of materials and workmanship
16
Enclosure of the works and protection of the public
17
Plant and temporary works such as roads, sheds, offices, toilets and notice boards
18
The supply of water, electricity, lighting, telephones, etc
19
Method of payment for preliminaries
20
Method of calculation for the adjustment of preliminaries
21
Method of pricing dayworks
DEMOLITIONS
Item or work to be measured
Unit
Measurement rules
DEMOLITIONS
1
Method and procedure
1
Restrictions regarding blasting and the use of jack
hammers, mechanical excavators, compactors, etc
shall be stated
General descriptions shall be given
3
4
General descriptions shall be given
Materials or components which are to remain the
property of the employer shall be so described
including storage and transport as necessary
General
2
Breaking up and removing surface concrete etc
Breaking up and removing kerbing and the like
Breaking down and removing fences, boundary
walls, etc
Demolition and removal of buildings and other
structures
no
Removal of foundations
Shall be dealt with in accordance with clause 5 of
Earthworks - Classification of material to be
excavated
Disposal of materials
Disposal of materials shall be described and where
materials are to become the property of the
contractor provision shall be made for allowing
credit
Descriptions shall be
deemed to include
Comments
ALTERATIONS
Item or work to be measured
Unit
Measurement rules
Descriptions shall be
deemed to include
Making good shall be included in the descriptions of
the relevant alteration items where expedient,
otherwise it shall be given separately in accordance
with the principles laid down in the relevant trades
Prescribed strutting and shoring shall be given in
accordance with the principles laid down in Lateral
Support
The manner of disposal of materials shall be stated
and where materials are to become the property of
the contractor provision shall be made for allowing
credit
Where materials are permitted to be re-used in new
work this shall be stated
Materials or components which are to remain the
property of the employer shall be so described
including storage and transport as necessary
Materials or components required to be set aside for
re-use shall be so described
General
Materials arising from alterations
3
4
5
6
3
Barricades, screens, etc
1
Junctions of new with
existing finishes
Strutting, shoring, etc
incidental to alterations
Prescribed temporary barricades, screens, roofs,
etc
m or
no
Alternatively prescribed temporary barricades,
screens, roofs, etc may be given in detail in
accordance with the principles laid down in the
relevant trades
Descriptions shall include ceilings, eaves, etc
Removals
2
Removal of walls, slabs and surface beds
Removal of concrete beams, columns and stairs
no
3
or m
Removal of finishes from walls, floors, ceilings, etc
Removal of roofs
no
Temporary storage of
materials or components
required to be set aside
for refixing
Comments
Removal of suspended floors, panelling, ceilings,
etc
Removal of partitions
10 Descriptions shall include doors, ironmongery,
glass, etc
Removal of doors, windows, fittings, etc
no
11 Descriptions shall include frames, ironmongery,
glass, sills, etc
12 Doors etc to be removed from walls to be
demolished shall be given separately
Removal of sanitary fittings, tanks, geysers, etc
no
13 Descriptions shall include disconnection from pipes,
traps, etc
10 Removal of pipes
9
2
11 Alternatives
no
15 Shall be given in inclusive items embodying more
than one trade as necessary
16 Alternatively alteration work may be given in detail
in accordance with the principles laid down in the
relevant trades
no
17 Descriptions shall include lintels, arches and making
good to jambs and finishes all round
no
18 Descriptions shall include bonding new to existing
work, finishes, etc
no
19 Alternatively re-use of existing components may be
given in the units as provided for in the relevant
trades
Building up openings
14 Building up openings
14 Alternatively items required to be given in cubic,
square or linear metres may be given in number and
descriptions may include making good and any
incidental new work
Openings
13 Cutting or altering openings in structures
Alteration work
12 Alteration work
Descriptions shall include skirtings, rails, cornices,
etc
Re-use of existing components
15 Re-use of existing components
Pipe fittings, valves, taps,
traps, pipe supports, etc
Work in patches
16 Work in patches
10
11
20 Work in patches, not included in the foregoing, shall
be so described
Sundries
17 Cutting through floors or ceilings for the passage of
new walls etc
21 Descriptions shall include making good to floors and
ceilings where expedient
18 Cutting through floors or ceilings for the passage of
new columns etc
no
19 Wedging up new walling to the underside of existing
structures
20 Making good to ends of walls
21 Making good to faces of walls where cross walls are
removed
22 Shall be measured only when required for the
support of existing work over
New doors, windows and the like
22 New doors, windows and the like in existing
structures, including ancillary work such as sills and
thresholds
23 Shall be given in accordance with the principles laid
down in the relevant trades
EARTHWORKS
Item or work to be measured
Unit
Measurement rules
Descriptions shall be
deemed to include
NOTE: External work of minor extent may be given in Earthworks in accordance with the principles laid down in External Work where applicable
GENERAL
1
Method and procedure
1
3
2
Restrictions regarding blasting and the use of jack
hammers, mechanical excavators, compactors, etc
shall be stated
Excavation or filling which is to be done in a
particular order or in sections, such as may be
prescribed for the removal of lateral support to
adjoining premises or for filling behind retaining
walls, shall be so described
Prescribed multiple handling of material shall be
included in the descriptions
Bulking
4
No allowance shall be made in measurements of
disposal and carting away of material for bulking
Where the value is of relative significance, the
removal of hedges etc shall be given separately in
metres or in number
The girth around the trunk 1m high above ground
level shall be stated, grouped in sizes exceeding
200mm and not exceeding 500mm girth and
thereafter in stages of 500mm
Descriptions shall state whether roots are to be
grubbed up and holes filled in, stating the method
and/or degree of compaction
SITE CLEARANCE
3
Site clearance
1
Digging up and removal of rubbish, debris,
vegetation, hedges, shrubs and trees not exceeding
200mm girth, bush, etc
Removal of larger trees and tree stumps exceeding
1m high
no
Comments
Removal of tree stumps not exceeding 1m high
no
The girth around the top of the stump shall be
stated, grouped in sizes as in measurement rule 6
above
Descriptions shall state whether roots are to be
grubbed up and holes filled in, stating the method
and/or degree of compaction
EXCAVATIONS, FILLING, ETC
4
Nature of material to be excavated
10 The nature of the material to be excavated shall be
described and if not known shall be assumed
Classification of material to be excavated
11 Excavations shall be described to be in the type of
material that is the least difficult to excavate
12 Excavations in material of a more difficult character
shall be suitably classified and given as extra over,
separating only bulk and trenches and holes and
making no separation for depths
13 Breaking up and removing concrete, brickwork, etc
encountered in excavations shall be similarly given
Excavations
14 The quantities of excavations shall be the net voids
to be formed in accordance with the drawings and
specifications and shall be not less than the
horizontal area of the bottom of the relevant
structures multiplied by the average depth from the
surface
15 Existing voids shall be deducted
16 Where undercutting is prescribed the undercut work
shall be kept separate, allowance for overbreak
being made from the bottom of the excavation at an
angle of 45 degrees
Bulk excavations, excavations for trenches and
excavations for holes
17 Separated into successive depths of 2m related to
the original or reduced ground level as the case
may be
10
Setting aside excavated
material within 100m from
the perimeter of the
excavations for use as
filling, forming excavated
surfaces to falls, slopes,
contours, etc, trimming
sides and stepping,
levelling and ramming
Removal of disused
drains, pipes, cables, etc
encountered during
excavations including
cutting and stopping off
5
6
18 No distinction being made for depths
Digging up topsoil
Diversion of services including cutting, stopping off,
etc
19 Shall be given in the relevant trades
Carting away of excavated material
8
Diversion of services
7
Open face excavation such as cutting or levelling of
sloping sites
Excavated material to be carted from the site
20 Shall be given as extra over all excavations and, if
dumped in a prescribed place, the location and
approximate distance shall be stated
21 Shall be measured to all sides of excavations
whether working space is given or not
22 The area for sloping sides shall be the mean length
multiplied by the perpendicular height
23 Separate items shall be given for bulk and
trenches and holes as well as for excavations from
ground level to not exceeding 1,5m deep and from
ground level to exceeding 1,5m deep
24 Risk of collapse shall not be measured where
prescribed support is to be measured or where the
excavated face is prescribed to be cut back to the
angle of repose
Risk of collapse of excavations
9
Risk of collapse of excavations
11
Setting aside within 100m
from the perimeter of the
excavation for use as
filling
10
Working space
10 Sides of excavations necessarily required to be
excavated back for working space ie beyond the
extent defined under clause 6 Excavations
11
Keeping excavations free of water
11 Keeping excavations free of all water other than
subterranean water
12
Item
Dewatering
12 Removal of seepage water and water from other
subterranean sources in excavations
13
28 Shall be given in accordance with the principles laid
down in the relevant trades
Filling
13 Filling of soil, stone, broken brick, etc for backfilling
to trenches, holes, etc, for filling over site, for filling
in landscape mounds, berms, etc and for filling
under floors, steps, paving, etc
29 Shall be measured to the volume after compaction,
stating the method and/or degree of compaction
30 Separate items shall be given for filling obtained
from the excavations or from specified borrow pits
or supplied by the contractor
31 The approximate distance of haulage shall be stated
if filling obtained from the excavations is hauled
more than 100m from the perimeter of the
excavations
32 Measurement rules 32 and 33 above apply
15 Subbase and base courses
33 Shall be given in accordance with clause 13 Filling
16 Stabilisation of foundation courses with lime,
cement, etc
14 Topsoil
14
25 Descriptions shall include any consequent
backfilling stating the method and/or degree of
compaction
26 Shall be grouped in successive overall depths of not
exceeding 500mm, exceeding 500mm and not
exceeding 1,5m and thereafter in stages of 1,5m
stating in each case the nature of the requirements
and the distance between the structure and the side
to be excavated back
27 Back excavations occurring in material of a more
difficult character shall be given in square metres as
extra over for each item of back excavation
Foundation courses
34 Shall be given as extra over stating the rate of
application
12
Haulage not exceeding
100m from the perimeter
of the excavations where
filling is obtained from
the excavations
Forming to falls, slopes,
contours, etc
15
Compaction of surfaces
17 Compaction of natural or excavated ground
surfaces
16
18 Retaining structures formed of filled gabion boxes
and mattresses
19 Retaining structures formed of interlocking blocks
Gabions and interlocking block retaining structures
20 Concrete foundations and trench excavations, open
face excavations and filling behind retaining
structures, filter fabric, ground anchors, etc
17
37 The area of sloping structures shall be the mean
length multiplied by the perpendicular height
38 Descriptions shall state the rate of slope and shall
include filling of blocks with garden soil, concrete,
etc
39 Shall be given separately in accordance with the
principles laid down in the relevant trades
Weedkillers, insecticides, etc
22 Treating surfaces with weedkillers, insecticides, etc
19
36 The sizes of the boxes and mattresses and the
diaphragm spacings shall be stated
Filter fabric
21 Filter fabric
18
35 Shall be measured only when the method (other
than ramming bottoms referred to under clause 6
Excavations) and/or degree of compaction is
prescribed
40 Forming V-grooves along foundation walls etc and
treating with insecticides shall be included in the
descriptions
Tests
23 Prescribed tests to determine the degree of
compaction or other properties of the ground or
filling
no
13
LATERAL SUPPORT
Item or work to be measured
Unit
Measurement rules
Descriptions shall be
deemed to include
GENERAL
1
Removal of lateral support
1
Insurance
1
Precautions to be taken and procedures to be
followed when removing lateral support shall be
given only if prescribed
In all other cases risk of collapse shall be given in
accordance with the principles laid down in
Earthworks
Insurance against claims arising from the removal
of lateral support
Shall be allowed for, either by provisional sum or by
stating the limit of the insurance cover required
Descriptions shall include the scope of the surveys
The nature of the work and the excavated faces to
be supported, any limitations affecting the ground
anchoring, the strata through which the anchors will
have to pass and the position of any cables, pipes
or other services shall be described
Item
Movement monitoring
2
3
Establishing of bench marks, pegs, etc for
prescribed movement monitoring
Item
Periodic movement surveys
no
GROUND ANCHORING
4
Descriptions
Establishment
4
Establishment of plant etc on the site
Item
Subsequent establishments for testing, retensioning or de-stressing
Item
14
Drilling
Comments
Test anchors
6
Test anchors
Ground anchors shall be given under headings
stating the working load
Classification
Lower anchorages
no
Distinction shall be made between rock anchors and
soft ground anchors
Upper anchorages
no
Descriptions shall include prescribed protection
against corrosion
Initial tensioning, initial
acceptability testing and
preparing load-extension
related graphs
Drilling
Waterproofing of ground anchors
11 Testing and re-testing of cable holes for fissures
and voids
no
12 Cement grouting of cable holes to prevent ingress
of water
kg
13 Re-drilling holes, washing out of grout and encasing
of cables
Testing, re-tensioning and de-stressing of ground anchors
no
Rock bolts and rock dowels
15 Rock bolts, expanding rock bolts, rock dowels and
soil nails
11
Descriptions shall include the working load, lower
anchorages, upper anchorages, thrust blocks and
the free length of cable
14 Testing subsequent to initial acceptability testing,
re-tensioning and de-stressing of ground anchors
10
Ground anchors
10 Free length of cable
8
no
no
10 Descriptions shall include nuts, washers, thrust
plates and grouting
Soldiers, boarding, shotcreting, etc
16 Soldiers, boarding, shotcreting, fabric
reinforcement, etc
11 Shall be given in appropriate items in accordance
with clause 12 Planking and Strutting or the
principles laid down in the relevant trades
15
17 Concrete or mortar packing behind soldiers
18 Thrust blocks
no
12 The minimum thickness shall be stated
Formwork
13 Planking and strutting required to be left in shall be
given separately
Wedges, nails, screws,
etc
PLANKING, STRUTTING AND SHORING
12
Planking and strutting
19 Planking and strutting
13
20 Timber planking, precast concrete planking and
metal or other sheeting
21 Timber strutting
22 Gum poles, logs and the like
14 The minimum diameter shall be stated
23 Tubular and solid section steel strutting
tons
15 Descriptions shall include bolting and welding
24 Bolts and clamps
tons
16 Alternatively bolts and clamps may be included with
the relevant items
25 Shoring units
no
17 Descriptions shall include sole pieces, wall plates,
etc
18 The cubic metre content per unit if in timber and the
tonnage per unit if in steel shall be stated
26 Re-use of shoring units
no
27 Timber cross bracing between shoring units
28 Steel cross bracing between shoring units
tons
Shoring units
LATERAL SUPPORT PILING
14
Lateral support piling
29 Lateral support piling
19 Shall be given in accordance with the principles laid
down in Piling
16
PILING
Item or work to be measured
Unit
Measurement rules
Descriptions shall be
deemed to include
GENERAL
1
Site conditions
1
The nature of the site with regard to contours, water
tables, high and low water levels, strata through
which piles will have to pass, etc shall be described
The nature of the work and any limitations on the
methods to be used such as piles sunk from
basement level and from any level other than
ground level shall be described
Trial piles, raking piles and piles in contact with one
another shall be given separately
Nature of the work
3
3
Establishment of plant etc on the site
Item
Subsequent establishments of plant etc for testing
Item
Setting up plant for sheet
piling
Risk of collapse of
excavations and keeping
excavations free of water
Setting up
Setting up plant at each pile position, other than
sheet piling
no
Reinforcement
4
Staging, tubing, framing,
rigs, jetting, etc
Establishment
3
5
Reinforcement
Shall be given in accordance with the principles laid
down in Concrete, Formwork and Reinforcement
Descriptions shall include excavation and backfilling
Exposing piles for inspection
5
Exposing piles for inspection
no
17
Comments
Cutting off etc
6
Cutting off piles
no
Cutting off sheet piling
Stripping back heads of concrete piles to expose
reinforcement
no
Testing
9
Testing of piles
no
PREFABRICATED PILING
9
Precast concrete piles
10 Precast concrete piles
6
7
10
11 Rock shoes
no
12 Driving
13 Dollying piles below ground level
no
14 Concrete in situ in lengthening of piles
15 Formwork to concrete in situ lengthening of piles
Separated into groups not exceeding 10m deep and
thereafter in successive depths of 5m
Shall be given in accordance with the principles laid
down in clause 9 Precast concrete piles
Moulds, joints, protection
caps, rings, handling and
pitching
Joints, protection caps,
rings, handling and
pitching
Steel piles
16 Steel piles
11
Measured for the designed length of pile before
being driven
Reinforcement may be included in the descriptions
or given separately
Sheet piling
17 Sheet piling
10 Measured for the designed height of piling before
being driven and along the length to be retained
11 Descriptions shall include shoes, laps and locking
devices
12 Sheet piling required to be left in shall be given
separately
18
18 Driving
13 Measured for the driven depth and along the length
to be retained
19 Corner piles, junction piles and other special piles
14 Shall be given as extra over sheet piling
20 Drilling
15 Separated into groups not exceeding 10m deep and
thereafter in successive depths of 5m
21 Under-reaming for enlarged feet
no
Handling, pitching,
protection caps and
extracting
Risk of collapse of
excavations and keeping
excavations free of water
Risk of collapse of
excavations and keeping
excavations free of water
Extracting tubes
CONCRETE CAST IN SITU PILING
12
13
Augered piles
22 Work in material of a more difficult character
23 Prescribed casing to prevent collapse of
excavations or to exclude subterranean water
24 Concrete
25 Additional concrete in enlarged feet
no
26 Formwork to concrete above ground level
16 Shall be given as extra over drilling
17 Shall be suitably classified and given as extra over
drilling and under-reaming
18 Measured through enlarged feet
Driven, bored or similar tube piles
27 Driving or boring
19 Measured for the depth to which tubes are sunk and
separated into groups not exceeding 10m deep and
thereafter in successive depths of 5m
14
28 Concrete
29 Expanded concrete bulbs at the bottom of piles
No
20 Measured from the top of the concrete to the depth
to which tubes are sunk
Disposal of excavated material
30 Disposal of excavated material
21 Shall be given in accordance with the principles laid
down in Earthworks
19
CONCRETE, FORMWORK AND REINFORCEMENT
Item or work to be measured
Unit
Measurement rules
Descriptions shall be
deemed to include
CONCRETE
1
Classification etc
1
2
Classified according to grade or mix
Descriptions shall not include formwork or
reinforcement unless otherwise stated
Components cast against excavated surfaces shall
be given separately
No deductions shall be made for voids not
exceeding 0,1m
No deductions shall be made for longitudinal pipes
not exceeding 200mm external diameter,
reinforcement, conduit, etc
Concrete in projections such as nibs, fins, strings,
cornices and kerbs shall be included with the
relevant components
Concrete components such as
1
Surface blindings, surface beds, surface beds cast
in panels, footings, bases, underpinning, slabs
inclusive of beams and inverted beams, isolated
beams, lintels, stairs inclusive of landings and
beams, walls, columns, hollow block slabs, coffered
slabs, troughed slabs and gradings
4
5
m
6
Closed ends
Hollow blocks, spacing tiles and prefabricated beams
2
Hollow blocks
no
Spacing tiles to soffits of solid sections
Spacing tiles to soffits of ribs
Prefabricated beams
7
8
9
3
4
Filling to irregularities
where cast against
excavated surfaces
Formwork in forming
panels in surface beds
Shaped tops
Striking off and curing
Classified in lengths not exceeding 5m and
thereafter in stages of 2,5m
Reinforcement shall be included in the descriptions
Alternatively the working load shall be stated
Shotcrete
6
Shotcrete
Additional shotcrete in thickening
10 Descriptions may include formwork where expedient
20
Comments
Prescribed curing compounds
8
Surface treatment such as wood float, steel trowel,
power float, evenly ribbed non-slip surface,
sandblasting, bush-hammering, etc
11 No distinction shall be made for different concrete
components
Curing treatment
of the finished face
of concrete other
than striking off
and curing
Surface treatment
of the finished face
of concrete other
than striking off
and curing
For testing the
quality of concrete
10 Grooves, channels and the like in tops of concrete
11 Mortices and sinkings
no
Angles, ends, etc
Formwork, chamfered
edges, etc
Bedding under base plates etc
no
Test blocks and testing
13 Test blocks and testing
no
FORMWORK
10
Grooves, channels, mortices, etc
12 Non-shrink mortar or similar grouting under base
plates etc
9
Surface treatment
9
Prescribed curing compounds
Formwork to components such as
14 Walls, columns, beams, isolated beams, wall
beams, slabs, hoods, stairs, shell construction and
sides of inverted components
12 Formwork shall be measured to net surfaces of
concrete to be supported, unless otherwise stated
13 Formwork to walls, columns and beams cast against
excavated or existing surfaces shall be given
separately
14 Formwork to sloping components shall be given
separately
15 Formwork to circular, spherical and flowing
components shall be given separately, distinction
being made for work exceeding and not exceeding
1m radius
16 No deductions shall be made for openings not
2
exceeding 3m
21
Intersections, holes for
rods, bolts, pipes and the
like, propping,
maintaining and removing
Formwork required to
support concrete at nonprescribed temporary
breaks
17 No deductions shall be made for intersections of
ends of beams with beams, columns, walls, etc
18 No deductions shall be made for intersections of
tops of columns with slabs, beams, column caps,
etc
19 Formwork to render a prescribed finish to the
concrete shall be given separately for the different
components
20 Alternatively formwork to render a prescribed finish
to the concrete surfaces may be given as extra over
rough formwork for the different components
21 Formwork required to be left in and permanent
formwork shall be given separately
11
12
Additional requirements for formwork to walls
15 Walls other than inner face of shaft walls and outer
face of walls flush with the perimeter of the concrete
structure
16 Inner face of shaft walls
17 Outer face of walls flush with the perimeter of the
concrete structure
22 Shall be separated into groups for walls not
exceeding 3,5m in height above bearing level and
thereafter for total heights above bearing level in
successive stages of 1,5m
23 Stair walls stepped over treads and risers of stairs
shall be given separately
24 Size of shaft on plan shall be given in the
description
25 Overall wall heights shall be stated in successive
stages of 5m
26 Overall wall heights shall be stated in successive
stages of 5m
Additional requirements for formwork to columns
18 Columns other than circular columns
27 Formwork to columns of different shapes shall be
given separately
28 Formwork to columns shall be separated into
groups for columns not exceeding 3,5m in height
above bearing level and thereafter for total heights
above bearing level in successive stages of 1,5m
29 Formwork to columns projecting beyond the
perimeter of the concrete structure shall be given
separately stating the projection
22
13
19 Circular columns
no
20 Column caps and bases
no
30 Descriptions may include caps and bases
31 Formwork to circular columns projecting beyond the
perimeter of the concrete structure shall be given
separately stating the projection
Additional requirements for formwork to slabs, beams and stairs
21 Soffits of solid slabs and hoods, sides and soffits of
beams and isolated beams and soffits of stairs and
landings
22 Soffits of composite hollow block slabs
38 Measurement rules 33, 34 and 36 above apply
39 Shall be measured over the flush surfaces of
adjacent solid concrete
23 Soffits of coffered slabs
40 Measurement rules 33, 34 and 36 above apply
41 Shall be measured to the full extent of the coffered
area, the widths and centres of the ribs being stated
24 Coffers
no
25 Soffits of adjacent flush surfaces of coffered slabs
42 Measurement rules 32, 33, 34 and 36 above apply
26 Soffits of troughed slabs
43 Measurement rules 33, 34 and 36 above apply
44 Shall be measured to the full extent of the troughed
area, the widths and centres of the ribs being stated
27 Troughs
28 Soffits of adjacent flush surfaces of troughed slabs
32 Formwork to soffits of solid slabs and hoods
exceeding 250mm thick shall be given separately in
stages of 250mm. No cognisance shall be taken of
the additional thickness caused by inverted beams
33 Formwork to soffits shall be separated into groups
propped to a height not exceeding 1,5m, exceeding
1,5m and not exceeding 3,5m and thereafter in
stages of 1,5m
34 Formwork to soffits of sloping components shall be
likewise categorised
35 No separation of height shall be made for formwork
to soffits of stairs and landings
36 Formwork propped off sloping or stepped surfaces
shall be given separately
37 Formwork to sides and soffits of isolated beams
propped off isolated beams below, shall be given
separately
10 Closed ends
2
45 Measurement rules 32, 33, 34 and 36 above apply
23
14
15
16
29 Troughs of composite prefabricated beam and
trough slabs
30 Bearers supporting prefabricated beams of
composite prefabricated beam and trough slabs
31 Soffits of adjacent flush surfaces of composite
prefabricated beam and trough slabs
32 Edges, risers, ends and reveals exceeding 300mm
high or wide
33 Edges, risers, ends and reveals not exceeding
300mm high or wide
46 Shall be separated into groups propped to heights
not exceeding 3,5m and thereafter in stages of 1,5m
47 Measurement rules 32, 33, 34 and 36 above apply
Edges, risers, ends and reveals
48 Shall be given together in one item
Projections, grooves, etc
34 Projections, chamfers, splayed edges, grooves,
rebates, etc
35 Raised panels, pedestals, sinkings, etc
no
51 Where applicable the formwork to the general
surfaces shall be measured past the raised panels,
pedestals, etc as if they did not exist
49 Distinction shall be made for the positions of
projections, chamfers, etc relative to the component
50 The formwork to the general surfaces shall be
measured past the projections, grooves, etc as if
they did not exist
no
52 Shall be grouped in stages of 1m
12 Stops, angles, etc
Openings
36 Openings not exceeding 2m girth
17
11 Closed ends
Movement joints etc
53 Descriptions shall include joint forming material
37 Movement joints and prescribed construction joints
exceeding 300mm high or wide
38 Movement joints and prescribed construction joints
not exceeding 300mm high or wide, rebated
movement joints and joggle construction joints
24
13 Formwork
Includes edges of
openings where
openings exceed
2m girth
REINFORCEMENT
18
General
54 Reinforcement shall be classified according to
quality
55 No separation of reinforcement shall be made for
different concrete components
56 Indented or other deformed reinforcement shall be
given separately
57 Curved reinforcement and helical reinforcement
shall be given separately
58 Reinforcement in slides shall be given separately
59 Reinforcement to be galvanised or otherwise treated
shall be given separately
60 Reinforcement shall be measured to the designed
lengths
61 Calculation of masses shall be based on the values
shown in the relevant Structural Steel Tables issued
by the South African Institute of Steel Construction
62 No allowance in the mass shall be made for rolling
margin
19
14 Bending, hooked ends
and binding wire, cover
blocks and spacers in
accordance with the
relevant SABS codes of
practice and maintaining
in position during
concreting
Reinforcement
39 Bar reinforcement
tons
40 Welded high chairs
tons
41 Mechanical splices and couplers
no
42 Rails, angles and other rolled steel sections
tons
43 Twisted plate reinforcement
44 Fabric reinforcement
63 Different diameters shall be given separately
64 Bars in lengths exceeding 13m and not exceeding
18m shall be given separately and thereafter in
stages of 1m
65 Stools manufactured from round bar shall be
included in the mass of the reinforcement
15 Preparation of bars
66 Shall be given in accordance with the principles laid
down in Structural Steelwork
67 Fabric reinforcement in cages shall be given
separately
68 No deductions shall be made for openings, wants,
2
etc not exceeding 1m
25
16 Bending to form cages
20
Pre-tensioned or post-tensioned reinforcement
45 General
21
69 The nature of the work and the general position and
accessibility of stressing anchors shall be described
70 The work shall be given under headings stating the
working load
46 Pre-tensioned and post-tensioned tendon
reinforcement
47 Prescribed couplers
no
48 Looped anchors, fanned anchors, dead anchors,
intermediate anchors and stressing anchors at ends
no
71 Tendon reinforcement shall be measured between
anchorages and descriptions shall include
sheathing, sleeves, threaded inlets and bleed pipes,
supporting chairs, marking positions of cables and
grouting or lubricating
72 Descriptions shall include corrosion protection and
sleeves
73 Descriptions shall include helical anchor
reinforcement, recesses in concrete for anchors,
holes through formwork for tendons, tensioning, retensioning, trimming ends of tendons, corrosion
protection, filling in recesses and preparing
prescribed tensioning records
Tests
49 Prescribed tests
no
26
PRECAST CONCRETE
Item or work to be measured
Unit
Measurement rules
Descriptions shall be
deemed to include
General
2
3
Classified according to grade or mix of the backing
and type of facing or finish
Work of similar design shall be suitably grouped
under headings stating the general requirements
Reinforcement may be included in the descriptions
or given separately in accordance with the principles
laid down in "Concrete, Formwork and
Reinforcement"
Bedding, jointing and pointing, finishing coats of
sealer and the like and prescribed protective
measures shall be included in the descriptions
Metal cramps, dowels, brackets, bolts, etc and
mortices and grouting shall be included in the
descriptions of the relevant precast concrete
components where expedient
Alternatively metal cramps, dowels, brackets, bolts,
etc and mortices and grouting may be given
separately in number
Wall linings
1
Wall linings
9
2
Finished edges
Circular cutting
Shall be separated into groups for slabs not
2
exceeding 0,5m on face and thereafter in
2
successive stages of 0,5m
Circular wall linings shall be given separately
measured over the finished face and stating the
radius
No deduction shall be made for openings, wants,
2
etc not exceeding 0,5m
27
Formwork
Comments
Slab paving
4
Slab paving
Finished edges
Circular cutting
Copings, sills, strings, cornices, steps and the like
Special blocks forming fair ends, rounded ends,
angles, intersections, etc
no
11 Circular work shall be given separately stating the
mean radius, distinction being made between
straight and curved lengths
12 Shall be given as extra over
Other coponents
Other coponents
no
Joint sealants, jointing strips, etc
10 Joint sealants, jointing strips, etc
10 No deductions shall be made for openings, wants,
2
etc not exceeding 0,5m
Copings, sills, etc
9
6
13 Alternatively joint sealants, jointing strips, etc may
be included in the descriptions of the relevant
precast concrete where expedient
Holes, notches, etc
11 Holes, notches, etc
no
28
MASONRY
Item or work to be measured
Unit
Measurement rules
Descriptions shall be
deemed to include
MASONRY WORK
1
Classification etc
3
4
5
2
Shall be classified according to material and quality
of the masonry unit, the bond and the composition
of the mortar
Separate items shall be given for different
components such as underpinning, mass work,
piers, projections, breasts, stacks, chimneys, walls
and linings
Portions of walling between openings shall not be
regarded as piers
Masonry work threaded over vertical reinforcement
shall be given separately
Circular work shall be given separately
Concrete filling
1
Concrete filling to hollow walls, blockwork, etc
6
7
Shall be given in accordance with the principles laid
down in Concrete, Formwork and Reinforcement
Alternatively concrete filling may be included in the
descriptions of the relevant items
BRICKWORK
3
Mass brickwork and piers
2
Mass brickwork and irregular shaped piers
No deductions shall be made for voids not
3
exceeding 0,1m
Regular shaped piers
3
Rectangular, L-shaped, X-shaped piers and the like
Alternatively regular shaped piers may be given in
metres
10 No deductions shall be made for voids not
3
exceeding 0,1m
29
3
4
Wedging, pinning,
building solid against
frames etc
Bedding of roof
coverings, wall plates,
base plates, etc
Ventilation flues through
walls for air bricks etc
Building ends of rafters,
joists, bars, pipes, bolts,
etc into or through
masonry work
Comments
Walls and linings
4
15 The skins of hollow walls shall not be measured
separately but the overall thickness and the
thickness of the individual skins shall be stated
16 Wall ties other than single wire type shall be
included in the descriptions
17 No deductions shall be made for openings and
2
recesses not exceeding 0,5m
8
9
Beamfilling
Vaulting
18 Descriptions shall include centering
Lintels
19 Shall be given separately only when the type of
brick and/or the composition of the mortar differs
from the adjoining work
Forming toothings and bonding
9
10
11 Battered walls, ie walls of uniform thickness built to
batter, shall be given separately stating the rate of
batter
12 Brickwork with battered or oversailing face on one
side shall be given separately, stating the average
thickness and the rate of slope
13 Wall ties other than single wire type shall be
included in the descriptions
14 No deductions shall be made for openings and
2
recesses not exceeding 0,5m
Lintels
8
Vaulting
7
Hollow walls
Beamfilling
6
Solid walls and linings
Forming toothings and bonding new brickwork to
existing
Hacking face or raking out joints of existing brickwork for key
10 Hacking face or raking out joints of existing
brickwork for key for finishes
30
6
7
Temporary supports to
oversailing faces
Single wire type wall ties
Hacking face or raking
out joints of new
brickwork for key for
finishes
Single wire type wall ties
Hacking face or raking
out joints of new
brickwork for key for
finishes
10 Open perpends
11
Building brickwork to a fair face
11 Building brickwork to a fair face
12
16
11 Mitres etc
22 Horizontal, vertical and raking shall be given
separately
15 Pilasters, bands, oversailing courses, cores for
mouldings and the like projecting beyond the face
of the wall
16 Cores for shields, rosettes, etc
no
23 Horizontal, vertical and raking projections shall be
given separately
Rough arches
no
24 Shall be described as extra for rough arch stating
the shape, width of soffit, span and number of rings
or depth
25 Descriptions shall include centres
no
26 Shall be measured only when not rectangular
27 Descriptions shall include closing of cavities in
hollow walls, arches, shaped backs and heads,
centres, etc
Rough niches
18 Rough niches
18
21 Horizontal, vertical and raking flues shall be given
separately
Projections and cores
17 Rough arches
17
Closing cavities
14 Brickwork in closing cavities of hollow walls
15
20 Shall be given as extra over
Splayed mortar fillets in cavities
13 Splayed mortar fillets in cavities of hollow walls
14
Flues
12 Flues and finishing smooth thereof
13
Joint forming material in movement joints
19 Joint forming material in movement joints
31
12 Angles, ends, etc
19
20
Reinforcement to brickwork
20 Steel fabric and welded reinforcement
21 Bar reinforcement
tons
28 Different diameters shall be given separately
29 Shall be grouped in lengths not exceeding 3m and
thereafter in stages of 1,5m
Fabricated lintels
22 Fabricated lintels
21
13 Building in
14 Propping
Turning pieces
23 Turning pieces to brick lintels etc
FACE BRICKWORK
22
General
30 Distinction for circular work shall be made between
work exceeding and not exceeding 2m radius
23
Face brickwork
m
25 Single skin brick walls faced both sides
26 Double skin brick walls faced both sides built in a
bond that requires headers
24 Face brickwork
24
25
31 Shall be given as extra over brickwork
32 Face brickwork to reveals and returns shall be
measured to the net area exposed and shall be
included with the general measurement of face
brickwork
33 Face brickwork to piers and pilasters shall be given
separately
34 Face brickwork to beamfilling shall be given
separately
35 Face brickwork with battered or oversailing face
shall be given separately, stating the rate of slope
Walls faced both sides
Cut face brick linings
27 Cut face brick linings to concrete etc
36 Wall ties shall be included in the descriptions
32
15 Pointing exposed tops or
soffits of battered and
oversailing work
26
27
Fair cutting to face brickwork
28 Fair raking, splay, circular and stepped cutting and
fair cut squint quoins and birdsmouth angles
29 Fair cutting and fitting around pipes
no
30 Fair cutting and fitting around joists, girders and the
like
no
31 Forming toothings and bonding new face brickwork
to existing
40 Shall be given as extra over face brickwork
16 Angles, ends, etc
41 Shall be given as extra over brickwork
42 Horizontal, vertical and raking face brick bands shall
be given separately
43 Descriptions shall include projecting or recessed
courses
17 Angles, ends, etc
44 Horizontal and raking face brick copings etc shall be
given separately
18 Angles, ends, etc
no
45 Shall be given as extra over brickwork
46 The shape, width of soffit, span and number of rings
or depth, extent of pointing and whether formed of
standard or special bricks, shall be stated
47 Descriptions shall include centres
19 Consequent cutting
Face brick copings, lintels, sills, etc
34 Face brick copings, lintels, sills, etc
30
39 Shall be measured only when cutting to irregular
profile is required. The shape and size of the joists,
girders, etc shall be stated
Face brick bands
33 Face brick bands
29
38 Shall be grouped for pipes not exceeding 100mm
external diameter and thereafter in stages of
100mm external diameter
Special face bricks at angles
32 Special face bricks at squint quoins, birdsmouth
angles, splayed or rounded angles and the like
28
37 Alternatively fair cutting may be included with the
items causing the cutting
Face brick arches
35 Face brick arches
33
31
Face brick niches
36 Face brick niches
no
48 Shall be measured only when not rectangular
49 Shall be given as extra over brickwork
50 Descriptions shall include closing of cavities in
hollow walls, arches, shaped backs and heads,
centres, etc and whether formed of standard or
special bricks
20 Consequent cutting
BLOCKWORK
32
General
37 Blockwork
33
Piers and pilasters
38 Piers and pilasters
34
51 Shall be given in accordance with the foregoing
principles and the following being applicable in
addition
52 Descriptions shall include standard complementary
blocks such as corner, three-quarter, half and
quarter blocks prescribed for the construction of
corners, reveals, ends of walls, etc and for bonding
53 Descriptions shall include corner blocks
Special blocks for copings, sills, lintels, etc
39 Special blocks for copings, sills, lintels, etc
21 Angles, ends, etc
PAVING ETC
35
Paving
40 Paving of bricks, concrete blocks, cement tiles,
quarry tiles, etc
41 Margins and borders
54 The pattern shall be stated
55 Features differing from the pattern shall be given
separately and descriptions shall include
consequent cutting
56 No deductions shall be made for openings, wants,
2
etc not exceeding 0,5m
22 Fair edges, angles, ends,
etc
34
42 Circular cutting
43 Steps, kerbs, channels, etc
57 Measured only when not included with the items
causing the cutting
23 Angles, ends, etc
NATURAL STONEWORK
RUBBLE WALLING
36
Mass and irregular rubble work
44 Mass and irregular rubble work
37
58 No deductions shall be made for voids not
3
exceeding 0,1m
59 No deductions shall be made for openings and
2
recesses not exceeding 0,5m
Beamfilling
46 Beamfilling
39
Walls and linings
45 Walls and linings
38
Facing and pointing
47 Facing and pointing
40
Copings, sills, etc
48 Copings, sills, lintels, arches and the like which
differ from the general work
41
61 Alternatively copings, sills, lintels, arches and the
like which differ from the general work may be given
in number
Pitched angles
49 Pitched angles
42
60 Facing and pointing shall be included in the
descriptions of the relevant rubble work when
practicable. When not practicable facing and
pointing shall be given separately in square meters,
no distinction being made for different elements
62 Descriptions shall state whether pitched from one or
both faces
Trimming to receive plaster etc
50 Trimming to receive plaster etc
35
24 Angles, fair ends, etc
43
Flues
51 Flues and finishing smooth thereof
44
Niches
52 Niches
45
no
Turning pieces and centres
53 Turning pieces to lintels etc
54 Centres to arches
no
STONEWORK OF SLATE, MARBLE, GRANITE, ETC
46
Classification etc
63 Shall be classified according to the nature of the
work such as ashlar walling, linings, paving, plinths,
arches, etc
64 Circular work, circular sunk work, spherical work
and spherical sunk work shall be given separately,
the radius being stated
65 Labours shall be included in the descriptions of the
relevant work when practicable. When not
practicable labours shall be given separately
66 Descriptions shall state the type of dressing and
distinction shall be made for sunk labours
47
Ashlar walling, linings and paving
55 Ashlar walling, linings and paving
56 Circular cutting
67 Shall be measured over the exposed surface and
separated into groups for stones not exceeding
2
0,5m on face and thereafter in successive stages
2
of 0,5m
68 No deductions shall be made for openings and
2
recesses not exceeding 0,5m
36
48
49
50
Margins, skirtings, cornices, etc
57 Margins, skirtings, cornices, copings, sills, kerbs,
steps, etc
58 Special stones in angles, returned ends, apexes,
etc
no
59 Mouldings
60 Stoped ends, mitres, etc
no
54
no
Rough rebates, grooves, etc
m
25 Stops, mitres, etc
Fair edges, angles, etc
64 Fair edges, rounded angles, chamfers, splays,
rebates, flutes, throats, etc
65 Stoped ends, mitres, etc
no
Holes, notches, etc
66 Holes, notches, etc
55
no
Special features
63 Rough rebates, grooves, chases, joggle joints, etc
53
71 Shall be measured to the mean length
72 Descriptions shall state the girth, width and
projection
Columns, piers, etc
62 Stones in arches, surrounds, etc and in features
which differ in material or finish from the general
work
52
70 Shall be given as extra over
Mouldings
61 Columns, piers, lintels, etc and single stone sills,
steps, thresholds, etc
51
69 Shall be measured to the mean length
no
Cramps, dowels, etc
67 Metal cramps, dowels, ties, etc and mortices and
grouting
73 Shall be included in the descriptions of the relevant
stonework where expedient
74 Alternatively metal cramps, dowels, ties, etc may be
given separately
37
56
Turning pieces and centres
68 Turning pieces to lintels etc
69 Centres to arches
no
MISCELLANEOUS
57
58
Bagging
70 Bagging walls
71 Bagging ceilings
Quarry tiles, cement tiles, fibre-cement, etc
72 Sills, copings, etc of quarry tiles, cement tiles, fibrecement and the like
59
75 May be given in this trade when appropriate in
accordance with the foregoing principles
Ornamental blocks, glass blocks, etc
73 Decorative screen walling and grilles of ornamental
blocks, glass blocks, etc
60
Hoop iron ties, cramps, etc
74 Hoop iron ties between concrete and masonry
work, roof ties, cramps to frames, etc
61
no
Fireplaces
76 Fireplaces
63
no
Air bricks etc
75 Air bricks, chimney pots, etc
62
76 Shall be given in accordance with the foregoing
principles
no
77 Alternatively fireplaces may be given in detail in
accordance with the foregoing principles
Special features
77 Circular columns, entasised columns, moulded
panels, etc
no
38
WATERPROOFING
Item or work to be measured
Unit
Measurement rules
Descriptions shall be
deemed to include
DAMP PROOF COURSE
1
General
1
Damp proof course
No distinction shall be made for horizontal, vertical,
in hollow walls, under sills, etc
Shall be classified according to the nature of the
work and be given under appropriate headings such
as to underground structures, roofs, walls, facades,
miscellaneous waterproofing, etc
Waterproofing to floors and roofs shall be given in
the following categories:
3.1 Flat not exceeding 25 degrees from the
horizontal
3.2 Sloping exceeding 25 degrees from the
horizontal stating the pitch
No deductions shall be made for openings, wants,
2
etc not exceeding 0,5m
Waterproofing in turn-ups and turn-downs not
exceeding 300mm girth shall be included in the
general areas
Preparatory work, priming coats, adhesives, etc and
paper, felt, plastic and other underlays shall be
included in the descriptions
Work to circular surfaces shall be given separately,
distinction being made between circular and
spherical work
WATERPROOFING
2
Classification
SHEET OR MEMBRANE WATERPROOFING
3
Sheet or membrane waterproofing
2
Waterproofing to floors, roofs, balconies, showers,
inverted beams, box gutters, channels, ducts, etc
4
5
Waterproofing in turn-ups and turn-downs
exceeding 300mm girth
39
1
2
Dressing generally
Dressing around pipes
and into outlets and
channels
Comments
4
5
6
4
Additional membranes, gussets, collars, etc around
pipes and into outlets etc
no
Waterproofing to sumps, catchpits, etc
no
Angles etc
Angles etc
Labours such as fair,
rounded and chamfered
edges, trowel cuts,
arrises, rounded external
angles, etc
Angles etc
Joints
Protection
7
Additional membranes, fillets and sealing at turnups and turn-downs
Paint, crushed stone layer, tiling, etc
Flashing strips
8
Flashing strips
TROWELLED-ON WATERPROOFING
6
Trowelled-on waterproofing
9
Waterproofing to floors, roofs, balconies, walls,
showers, inverted beams, box gutters, channels,
ducts, etc
10 Waterproofing in turn-ups and turn-downs
8
m
Shall be given in accordance with the foregoing
principles with the following being applicable in
addition:
8.1 In circular work distinction shall be made
between work exceeding and not exceeding
300mm radius
9 The average height shall be stated
10 Fillets shall be included in the descriptions
LIQUID WATERPROOFING
7
Liquid waterproofing
11 Liquid waterproofing brushed or sprayed on
WATERSTOPS, SEALING STRIPS, JOINT SEALANTS, ETC
8
Waterstops, sealing strips, etc
12 Waterstops
13 Angles and intersections to waterstops
no
40
Rubber and other
proprietary
waterstops in
expansion joints
etc
14 Sealing strips etc
Joints, angles,
intersections, etc
Polyolefin and
other proprietary
sealing strips over
expansion joints
etc
Resilient sealants
to expansion joints
etc
Joint sealants
15 Joint sealants
10
11 Sealants to joints in top surfaces, vertical surfaces
and soffits shall be given separately
Waterproofing additives
16 Waterproofing additives to concrete, plaster and the
like
12 Shall be included in the appropriate items in the
relevant trades
41
ROOF COVERINGS, CLADDINGS, ETC
Item or work to be measured
Unit
Measurement rules
Descriptions shall be
deemed to include
SLATES, TILES AND SHINGLES
1
General
1
Roof coverings and side and soffit claddings
2
3
4
5
2
Circular cutting
2
Shall be given in the following categories:
1.1 Roof coverings with pitches not exceeding
25 degrees
1.2 Roof coverings with pitches exceeding
25 degrees stating the pitch
1.3 Side claddings
1.4 Soffit claddings
1.5 Roof coverings and side and soffit claddings
to dormers, turrets, etc
Circular, spherical and conical work shall be given
separately stating the radius
No deductions shall be made for openings, wants
2
etc not exceeding 0,5m
Battens, underlays and fixing accessories shall be
included in the descriptions
Alternatively battens may be given in Timberwork
Circular cutting
Eaves and verges
3
Undercloak course and any bedding and pointing
Double eaves course
Verge capping tiles
Shall be given as extra over and descriptions shall
include fixing clips and tilting fillets
Descriptions shall include soakers and additional
battens
Ridges, hips, closed valleys and vertical angles
6
Ridges, hips, closed valleys and vertical angles
42
One-and-a-half width
slates, tiles or shingles at
verges
Holes for fixing and
notches
Comments
Purpose made tiles
7
Purpose made tiles to ends and to intersections
between ridges and hips, ventilation tiles, etc
Shall be given as extra over
Descriptions shall include supporting wires and
fixing accessories
no
Insulation
8
Insulation
10 No deductions shall be made for openings, wants,
2
etc not exceeding 0,5m
11 Distinction shall be made between general roof
slopes and dormers, turrets, etc
12 Thatch incorporating a spread layer to exposed
soffit shall be given separately
13 Battens, fixing rods, binding twine, fire retardant
underlays or interlays and fireproofing treatment
shall be included in the descriptions
THATCH
7
General
9
Roof coverings and side and soffit claddings
Dressing to hips, valleys,
eaves, verges and top
edges
Ends, intersections, etc
Ends, intersections, etc
Ridges and apex caps
10 Ridges
11 Apex caps
no
Ornamental bands and runners
12 Ornamental bands and runners
10
Prefabricated ridges, hips, ends, intersections, etc
13 Ridges and hips
14 Ends, intersections, etc
no
14 Shall be given as extra over
43
PROFILED SHEETING OF METAL, FIBRE-CEMENT, PLASTIC, ETC
11
General
15 Roof coverings and side and soffit claddings
12
6
7
Holes for fixing and
notches
Forming drips and turnups to troughs of
troughed metal roof
covering
20 Shall be given as extra over stating the angle and,
where appropriate, the radius
Rolled edges at verges
18 Rolled edges at verges
15
15 Shall be measured net on the undeveloped surface
area and shall be given in the following categories:
15.1 Roof coverings with pitches not exceeding
25 degrees
15.2 Roof coverings with pitches exceeding 25
degrees stating the pitch
15.3 Side claddings
15.4 Soffit claddings
15.5 Roof coverings and side and soffit
claddings to dormers, turrets, etc
16 Roof coverings in single sheets exceeding 13m
shall be given separately
17 Circular work shall be given separately stating the
radius
18 No deductions shall be made for openings, wants
2
etc not exceeding 0,5m
19 Fixing accessories, sealing strips to laps and seam
stitching shall be included in the descriptions
Cranks, bullnoses and curved turn-ups
17 Cranks, bullnoses and curved turn-ups
14
Circular cutting
16 Circular cutting
13
Accessories
19 Accessories such as closers, ridge and hip
coverings, flashings, etc
20 End caps, finials, etc
no
44
Holes for fixing, notches,
ends, angles and
intersections
16
17
Special sheets
21 Ventilator sheets, sheets with flanges for pipes, etc
no
22 Panels of translucent sheeting and isolated
translucent sheets
22 Shall be given as extra over the sheeting in which
they occur
23 Alternatively panels and sheets may be given in
number
Roof ventilators and rooflights
23 Roof ventilators and rooflights
18
21 Shall be given as extra over the sheeting in which
they occur
no
24 Alternatively ventilators and rooflights may be given
in metres in which case ends, corners, etc shall be
given in number as extra over
Insulation
24 Insulation
25 Descriptions shall include supporting wires and
fixing accessories
26 Shall be measured net on the undeveloped surface
area and shall be separated in the following
categories:
26.1 Roof coverings with pitches not exceeding
25 degrees
26.2 Roof coverings with pitches exceeding 25
degrees stating the pitch
26.3 Side claddings
26.4 Soffit claddings
26.5 Roof coverings and side and soffit
claddings to dormers, turrets, etc
27 Circular, spherical and conical work shall be given
separately stating the radius
28 Turn-ups and turn-downs shall be added to the
general areas
29 No deductions shall be made for openings, wants
2
etc not exceeding 0,5m
FLAT SHEET METAL
19
General
25 Roof coverings and side and soffit claddings
45
Angles, bending,
dressing, bossing,
wedging, holes for fixing
and notches
30 Laps, seams, welts, clips, tacks, soldered dots,
riveting, soldering, brazing, burning and nailing shall
be included in the descriptions stating the extent of
the laps and the type of seam, welt, etc
20
Circular cutting
26 Circular cutting
21
End caps, finials, etc
27 End caps, finials, etc
no
SHEET METAL FLASHINGS, LININGS, COPINGS, ETC
22
General
31 Laps, seams, welts, clips, tacks, soldered dots,
riveting, soldering, brazing, burning and nailing shall
be included in the descriptions stating the extent of
the laps and the type of seam, welt, etc
28 Circular cutting
23
24
10 Angles, bending,
dressing, bossing,
wedging, holes for fixing
and notches
32 Alternatively circular cutting may be included in the
descriptions
Flashings
2
29 Flashings
30 Flashings around pipes through roof coverings etc
no
33 Alternatively flashings may be given in metres
34 Stepped cover flashings to roof pitches exceeding
25 degrees shall be given separately stating the
pitch
35 Alternatively flashings may be included with the
relevant items of roof coverings and side claddings
11 Ends, angles and
intersections
36 Shall be grouped for pipes not exceeding 100mm
external diameter and thereafter in stages of
100mm
Linings, copings, etc
31 Linings to valleys and gutters, copings and the like
37 Alternatively linings etc may be given in metres
46
12 Ends, angles and
intersections
TIMBERWORK
Item or work to be measured
Unit
Measurement rules
Descriptions shall be
deemed to include
GENERAL
1
Classification etc
1
Timber
1
2
3
4
5
2
2
Labours
3
4
Protective surface treatment such as creosote
Shall be classified according to species and quality
Any required pre-treatment such as kiln drying and
impregnation and any required pre-selection shall
be stated
Sawn and wrought timbers shall be given separately
stating the finished size
Timber described as wrought shall be deemed to be
wrought on all faces
Wrought faces on sawn timbers shall be included in
the descriptions of linear items but may be given in
square metres where expedient
Circular work shall be given separately stating the
radius and where necessary, stating which faces
are circular
Circular cutting, rounded angles, rebates, grooves,
chamfers, moulded edges, etc
Rounded corners, scribed ends, shaped ends, etc
no
Labours shall however be included in the
descriptions of timber which is given linear
Mitres, intersections,
splay cut ends, stops, etc
Nails, screws, plugs,
adhesives, holes, sinking,
etc
Fixing
5
Fixing timberwork
8
9
The method of fixing shall be stated
Holes and tapping of metalwork for the fixing of
timber may be included in the descriptions of the
relevant timberwork or included with the relevant
metalwork
10 Descriptions shall include pelleting
47
Comments
STRUCTURAL TIMBERWORK
4
Structural timbers
6
Structural timbers
Wrought ends and wrought and shaped ends of
sawn timber
no
Timber connectors such as split rings and toothed
rings
no
Shaped laminated timbers such as portal frames,
arches, etc
no
8
9
5
11 Shall be measured to net lengths as fixed
12 Laminated timbers required to be in single lengths
exceeding 13m and not exceeding 18m shall be
given separately and thereafter in stages of 1m.
Structural timbers, other than laminated timbers,
required to be in single lengths, shall be given in the
following categories:
12.1 Lengths not exceeding 2,4m
12.2 Lengths exceeding 2,4m and not exceeding
3,9m
12.3 Lengths exceeding 3,9m and not exceeding
6,6m
12.4 Lengths exceeding 6,6m
13 Members of roof trusses may be grouped together
but wall plates, bearers, bracing, joists, purlins,
battens, fillets, trimmers and the like shall be given
separately
3
4
Joints in the length
Holes, splay cut ends and
mitres
Grooves for split rings
Splay cut ends, mitres,
jointing, wrought and
shaped ends,
connections, bolts, cleats,
gussets and timber
connectors
Plate nailed timber roof truss construction
10 Plate nailed timber roof trusses
no
11 Valleys and hips
sets
12 Wall plates, purlins, bracing, etc
14 Shall be given in accordance with clause 4
Structural timbers
48
13 Alternative
15 Alternatively plate nailed timber roof truss
construction may be given as an item in which case
descriptions shall include wall plates, purlins,
bracing, etc
Floor and roof boarding
14 Floor, roof and weather boarding, boarding to tank
stands, gutter boarding and the like
15 Nosings and edge strips
16 Trapdoors
no
16 No deductions shall be made for openings, wants,
2
etc not exceeding 0,5m
Notches and holes
Mitres and intersections
Mitres and intersections
17 Shall be given as extra over and descriptions shall
include trimmers, margins, cover strips, etc
Eaves and verges
17 Eaves soffit covering
18 Fascias, barge boards, etc
18 Shall be given in accordance with the principles laid
down in Ceilings, Partitions and Access Flooring
m
19 Jointing strips shall be included in the descriptions
TIMBER DOORS, WINDOWS, ETC
8
Doors, windows, sashes, etc
19 Doors, windows, sashes, fanlights, fly screens and
shutters
no
20 Descriptions shall include weatherboards, glazing
beads, fixing beads, edge strips, etc
21 Descriptions of cased frames with sashes shall
include pulleys, cords, counter weights and spring
balances
Frames etc
20 Frames, mullions, transoms, posts, linings, cover
strips, beads, etc
22 Framed work shall be given separately
23 Alternatively frames for doors and windows may be
given in number
24 Descriptions shall Include rounded angles, rebates,
grooves, chamfers, moulded edges, etc
10 Mitres and intersections
25 No deductions shall be made for openings, wants,
2
etc not exceeding 0,5m
11 Notches and holes
SUNDRY JOINERY
10
Floor boarding on concrete floors
21 Floor boarding
22 Fixing strips
26 Descriptions shall include fixing clips, anchors, etc
49
11
Skirtings, rails, etc
23 Skirtings, dado rails, picture rails, etc
12
27 Skirtings stepped over treads and risers of stairs
shall be given separately
Shelves and fittings
2
24 Shelves, divisions, sides, tops and the like
25 Edge strips and veneered or thermosetting plastic
edges applied after manufacture
26 Thermosetting plastic laminate boards with formed
edges
no
27 Standards, rails, cover strips, beads, skirtings, etc
to fittings
12 Housing, notches and
holes
13 Mitres and intersections
31 Framed work shall be given separately
28 Fittings
13
28 Solid timber exceeding 300mm wide shall be given
separately
29 No deductions shall be made for openings, wants,
2
etc not exceeding 0,1m
30 Descriptions shall include edge strips applied during
manufacture
32 Shall be measured in detail under headings and
given in accordance with the foregoing principles
and when of similar design shall be suitably
grouped stating the general requirements and the
number
33 Alternatively fittings may be given in number
29 Doors, drawers, cash bowls and the like
no
30 Notice boards, keyboards, blackboards,
duckboards, etc
no
34 Timber guides and runners shall be included in the
descriptions of the drawers
35 Alternatively notice boards, keyboards, blackboards,
duckboards, etc may be measured in detail and
given in accordance with the foregoing principles
Stairs
31 General
36 Stairs of similar design shall be suitably grouped
under headings stating the general requirements
2
32 Flooring to landings
33 Treads and risers
34 Brackets, housed ends, returned ends, rounded
ends, quadrant ends, curtail ends, etc
no
37 Descriptions shall include blocking pieces
50
14 Mitres and intersections
14
15
35 Winders
no
36 Bearers, stringers, apron linings, cappings,
handrails, etc
38 Wreathed work shall be so described
39 Continuous handrails shall be so described and
descriptions shall include heading joints
37 Bends, ramps, knees, wreaths, scrolled ends, etc
no
40 Shall be given as extra over
38 Balusters and newels
no
41 Descriptions shall include framing and housing
42 Balusters and newels framed or housed on rake
shall be given separately
15 Mitres and intersections
Panelling
39 Panelling
40 Acoustic and vermin-proof linings, fabric backings,
etc
41 Grounds
42 Skirtings, plinths, cappings, bolection moulds, cover
strips, beads, edge strips and surrounds
43 Posts, pilasters, pediments, canopies, etc
no
43 Descriptions shall state whether panels are to be
matched
44 Framed panelling shall be suitably grouped for
panels of different widths and descriptions shall
state the height and the number of panels to the
height and shall include fixing beads etc
45 Spandrel panelling shall be given separately
46 No deductions shall be made for openings, wants,
2
etc not exceeding 0,1m
47 No allowance shall be made in the measurement of
boarded panelling for laps and tongues and net
widths of boards shall be stated
48 Alternatively acoustic and vermin-proof linings,
fabric backings, etc may be included in the
descriptions of the panelling
49 Alternatively grounds may be included in the
descriptions of the panelling
Plastic, fibre-cement, etc
44 Plastic, fibre-cement, etc
16 Notches and holes
50 Plastic, fibre-cement and other processed materials
shall be given in accordance with the foregoing
principles
51
17 Mitres and intersections
CEILINGS, PARTITIONS AND ACCESS FLOORING
Item or work to be measured
Unit
Measurement rules
Descriptions shall be
deemed to include
CEILINGS
1
General
2
3
4
5
6
7
1
Ceilings
Circular cutting
Flush margins and borders not exceeding 1,2m
wide of material differing from the general ceiling
material
Ceilings shall be given under headings separating
nailed-up and suspended ceilings, distinction being
made between horizontal, sloping and vertical
ceilings
No deductions shall be made for openings, wants,
2
etc not exceeding 0,5m
Brandering shall be included in the descriptions of
nailed-up ceilings. When brandering is not to a
regular pattern it shall be given separately in metres
Circular work shall be given separately stating the
mean radius
Proprietary support systems for suspended ceilings
shall be included in the descriptions of the ceilings
5.1
When the support system is not to a regular
pattern it shall be given separately, in which
case brandering or bearers shall be given in
metres and hangers in number
5.2
A general description of the supporting
structure from which ceilings are suspended
shall be given
5.3
Separate items shall be given for ceilings
etc suspended not exceeding 1m below
suspension level and thereafter in
successive stages of 1m
Cover strips, jointing strips, etc shall be included in
the descriptions
Plastering shall be included in the descriptions
Shall be given in groups in successive widths of
300mm
52
Notches and holes
Comments
Bulkheads in ceilings which occur at a level or
plane differing from the general ceiling level or
plane, of which no horizontal, vertical or sloping
dimension exceed 1,2m
Dimensions of all faces shall be given in the
description
10 Alternatively, when linear measurement is not
practicable, bulkheads shall be given in detail in
appropriate items
Fire barriers and the like
11 Alternatively, when linear measurement is not
practicable, fire barriers and the like shall be given
in detail in appropriate items
Trapdoors
no
12 Shall be given as extra over ceilings, bulkheads, etc
Cornices
Openings for light fittings, mechanical diffusers, etc
no
Insulation materials such as fibreglass and slagwool
13 Shall be given as extra over ceilings, bulkheads, etc
Trimmers
Mitres and intersections
Additional trimmers,
hangers, etc
Notches and holes other
than in glass
Cleats, screws, bolts,
plates, etc
14 Stating whether in panels such as between roof
timbers etc
PARTITIONS
2
Partitions
10 Partitions
11 Notches and holes in glass
no
12 Ends, intersections, openings, doors and frames,
special panels, etc
no
13 Partitions (alternative)
15 Descriptions shall include finishes
16 Alternatively finishes may be given in appropriate
items in accordance with the principles laid down in
the relevant trades
17 Shall be given as extra over
18 Descriptions shall include ironmongery and finishes
19 Alternatively ironmongery and finishes may be given
in appropriate items in accordance with the
principles laid down in the relevant trades
20 When linear measurement is not practicable,
partitions shall be measured in detail in which case
boards, glass, etc shall be given in square metres,
standards, rails, mullions, transoms, skirtings,
cornices, cappings, beads, etc in metres and
panels, doors, fanlights, borrowed lights and frames
in number
21 Ironmongery and finishes shall be given in
accordance with the principles laid down in the
relevant trades
53
7
8
Notches and holes other
than in glass
Mitres, intersections,
cleats, screws, bolts,
plates, etc
14 Circular cutting
15 Insulation materials such as fibreglass and slagwool
if not included with panels etc
16 Access flooring
17 Ventilation grille panels, strengthened panels, etc
no
24 Shall be given as extra over
18 Junctions against walls, columns, etc
25 Circular junctions shall be given separately
19 Movement joints
20 Dividers and fire barriers below access flooring
21 Holes and outlets through floor panels and dividers
no
22 Lifting tools
no
ACCESS FLOORING
3
Access flooring
22 Descriptions shall include panels, support system,
coverings, etc
23 No deductions shall be made for openings, wants,
2
etc not exceeding 0,5m
54
Lifting and replacing
panels for work executed
under floors by others
10 Additional pedestals and
other support members
FLOOR COVERINGS, WALL LININGS, ETC
Item or work to be measured
Unit
Measurement rules
Coverings and linings
1
Wood block, wood mosaic, thermoplastic, vinyl,
linoleum, rubber, cork, carpeting and other similar
coverings and linings
1
m
2
3
4
5
6
7
Margins, borders and turn-ups not exceeding
500mm wide or high
Circular work may include circular cutting to
surrounding work where expedient
Mitres etc
Circular work may include circular cutting to
surrounding work where expedient
Mitres etc
Mitres etc
Mitres etc
Insets
m or
no
Edge and cover strips
5
Insets
4
Circular cutting
Margins, borders and turn-ups
3
No deductions shall be made for openings, wants,
2
etc not exceeding 0,5m
Preparatory work, priming coats and adhesives shall
be included in the descriptions
Descriptions shall include welding of plastic or
rubber
Descriptions shall include underfelt for carpeting
Linings to reveals etc shall be included in the
general areas
Work to circular surfaces shall be given separately
Dished flooring shall be given separately
Circular cutting
2
Descriptions shall be
deemed to include
Edge and cover strips
Skirtings
6
Skirtings of vinyl etc
10 Skirtings stepped over treads and risers of stairs
shall be given separately
55
Comments
Stairs
Covering to treads and risers
Combined tread and riser coverings
Mitres etc
Mitres etc
Running joints, bends,
wreaths, mitres, closed
ends, etc
Nosings
Plastic handrails
10 Plastic handrails
10
11 Covering to winding stairs shall be given separately
Nosings
9
Polish, sealers, etc
11 Polish, sealers, etc
12 Alternatively polish, sealers, etc may be included in
the descriptions
56
IRONMONGERY
Item or work to be measured
Unit
Measurement rules
Descriptions shall be
deemed to include
Classification etc
Components such as
1
2
Continuous hinges, tracks, channels, rods, rails,
bars, etc
Hinges, locks, handles, catches, hooks, towel rails,
grab rails, etc, sets of floor spring hinges, sets of
sliding gear for doors, cording sets, etc
no
Locks
no
3
4
Descriptions shall include keys
En suite locks and master keys shall each be
given separately
Metal shelving shall be measured in detail with
shelving, wall bands, standards and rails given in
metres or in number and shelf brackets, foot pieces
and the like in number
Alternatively metal shelving may be given in number
as a unit including all components
Metal shelving
4
Metal shelving, wall bands, standards and rails
6
4
Ironmongery fixed to timber, metalwork, brickwork,
etc shall be given separately
Preparation of metal doors and frames to receive
ironmongery shall be included with the doors and
frames or given separately in "Metalwork" as
prescribed
Proprietary kitchen cupboards, lockers, writing boards, seats, etc
5
Proprietary kitchen cupboards, lockers, writing
boards, seats, etc of metal, timber or other material
no
57
Screws, plugs, etc and
the preparation of timber,
metalwork, brickwork, etc
Comments
STRUCTURAL STEELWORK
Item or work to be measured
Unit
Measurement rules
Descriptions shall be
deemed to include
STRUCTURAL STEELWORK
1
Classification
1
2
4
5
Steelwork shall be classified according to the
quality and composition
Structures of similar nature and design shall be
suitably grouped under headings stating the
general requirements
Circular work shall be given separately stating the
mean radius and where necessary which faces are
circular
Work required to be prepared or painted before
delivery shall be so described
Work required to be galvanised, metal sprayed,
epoxy coated or otherwise treated or finished shall
be so described
Work specifically required to be treated or finished
before or after manufacture or assembly or after
delivery to the site shall be so described
General
7
Steelwork shall be measured to the designed sizes
of components
8 The calculation of masses shall be in accordance
with Structural Steel Tables issued by the South
African Institute of Steel Construction
9 No allowance shall be made in the mass for rolling
margin, rivets, black bolts, nuts, washers, distance
pieces, packings, additional material in welding,
decorative or protective treatment nor for temporary
constructional aids
10 Welding, holes, black bolts, nuts, washers, rivets,
bolting and riveting integral with structural
steelwork shall be included in the descriptions of
the relevant work
58
Scribed ends
Comments
11 Rolled sections in single lengths exceeding 13m
and not exceeding 18m shall be given separately
and thereafter in stages of 1m
3
Steelwork
1
Columns, beams and other members
tons
Compound and latticed columns, beams and other
members
tons
12 Shall be given separately classified according to
cross-sectional size
13 Shall be so described stating the cross-sectional
size of the main components
Caps, bases and connections
Roof trusses
tons
15 Shall be given in one item for each truss or each
group of similar trusses stating for each item the
number of trusses, shape, overall size, construction
and type of components (flats, angles, tees, tubes,
etc)
16 The cross-sectional size of components of a truss
need not be stated
Purlins, girts, wind bracing, sag rods, etc
tons
17 Shall be given separately stating the type of
components (flats, angles, tees, tubes, etc)
18 Connections shall be included in the descriptions of
the relevant members and their mass shall be
added to the mass thereof
19 The cross-sectional size of components need not
be stated
Roof gutters, rainwater pipes, etc integral with
structural steelwork
tons
Stairs, balustrading, handrails, cat ladders, flooring,
etc integral with structural steelwork
tons
Circular cutting
Bends and machined ends
no
14 Shall be included in the descriptions of the relevant
members, no distinction being made for size or
shape and their mass shall be added to the mass
thereof
20 Shall be given in suitable inclusive items
21 Shall be given in suitable inclusive items stating for
each item the construction, type of components
(flats, angles, tees, tubes, etc) and the number
where relevant
22 The cross-sectional size of components need not
be stated
59
Angles, stopped ends,
outlets, offsets, shoes, etc
10 High tensile bolts and high strength friction grip
bolts including nuts and washers
tons
11 Ragbolts, expanding bolts, anchor bolts, machined
bolts, etc
no
12 Patent handrails, patent clips and other items
integral with structural steelwork not marketed in
tons
m or
no
23 Shall be given separately under the relevant
headings
24 Descriptions shall include nuts and washers,
25 Distinction shall be made for those requiring to be
embedded in tops, sides or soffits of concrete
Tests
13 Tests
Item
60
METALWORK
Item or work to be measured
Unit
Measurement rules
GENERAL
1
Classification etc
1
2
3
4
Metalwork shall be classified according to type,
quality and composition of the metal
Circular work shall be given separately stating the
mean radius and, where necessary, which faces are
circular
Work required to be prepared or painted before
delivery to the site shall be so described
Work required to be galvanised, chromium plated,
anodized, metal sprayed, epoxy coated, stove
enamelled, vitreous enamelled or otherwise treated
or finished shall be so described
Work specifically required to be treated or finished
before or after manufacture or assembly or after
delivery to the site shall be so described
Welding, brazing, soldering, holes, bolting, rivets
and riveting shall be included in the descriptions of
the relevant work
Circular cutting
1
Circular cutting
STEELWORK
3
Sundry steelwork
2
Rolled or drawn solid sections
kg
7
8
Shall be measured to the designed sizes of
components
Calculation of masses shall be in accordance with
the Structural Steel Tables issued by the South
African Institute of Steel Construction
No allowance shall be made in the mass for rolling
margin, rivets, additional material in welding,
decorative or protective treatment nor for temporary
constructional aids
61
Descriptions shall be
deemed to include
Comments
10 The cross-sectional size of components shall be
given
Tubular work generally
Tubular columns
no
Screwed and socketed piping
Sheeting, wire mesh, screening, expanded metal,
gratings and the like
Bolts including nuts and washers
kg
Ragbolts, expanding bolts, anchor bolts, etc
no
Stairs, balustrading, cat ladders, grilles, gates,
framework, etc
10 Fanged, rounded, scribed, closed and scrolled
ends, intersections, bends, wreaths, etc
13 No deductions shall be made for openings, wants,
2
etc not exceeding 0,5m
Holes and notches
Running joints
14 Descriptions shall include nuts and washers
15 Distinction shall be made for those requiring to be
embedded in tops, sides or soffits of concrete
kg or
m or
no
16 Shall be given in inclusive items stating for each
item the construction and the cross-sectional size of
components and the number where relevant
17 Alternatively when inclusive items are not
practicable, work of similar design shall be suitably
grouped under headings stating the general
requirements in which case separate items shall be
given for the different components stating crosssectional sizes
18 Shall be given as extra over
no
Minor work
11 Brackets, anchors, etc
12 Shall be given in accordance with the principles laid
down in Plumbing and Drainage
Stairs, balustrading, cat ladders, grilles, gates, framework, etc
9
11 Descriptions shall include cap and base plates
kg or
no
19 When given in kilograms the number shall be stated
and when given in number the mass shall be stated
where significant
Fixing accessories to structural timberwork
12 Black bolts, high tensile bolts, etc including nuts
and washers
kg
13 Ragbolts, expanding bolts, anchor bolts, etc
no
20 Distinction shall be made for those requiring to be
embedded in tops, sides or soffits of concrete
62
Ribbed floors and permanent decking
14 Ribbed floors and permanent decking
15 Closed ends to ribs
21 Shall be measured net on the plane or undeveloped
surface area
22 No deductions shall be made for openings, wants,
2
etc not exceeding 0,5m
23 If in banded panels the sizes of the panels shall be
stated
24 No deductions shall be made for openings, wants,
2
etc not exceeding 0,5m
Floors etc formed of open grillework or gratings
16 Floors etc formed of open grillework or gratings
17 Stair treads
no
Skirtings etc
18 Skirtings, picture rails, copings, etc
25 Skirtings stepped over treads and risers of stairs
shall be given separately
19 Corner pieces, end caps, switch sockets, etc
no
26 Shall be given as extra over
OTHER METALS
10
Aluminium, copper, lead, etc
20 Metalwork
27 Metalwork of aluminium, copper, lead, zinc,
stainless steel, brass, bronze, etc shall be given in
accordance with the foregoing principles
28 Solid sections of metals not marketed in kilograms
shall be given in metres or in number
DOORS, WINDOWS, CURTAIN WALLING, SHOPFRONTS, ETC
STEEL DOOR FRAMES, DOORS, WINDOWS, ETC
11
Door frames
21 Pressed steel door frames
no
29 The size of the door, fanlight, sidelight, etc shall be
stated
30 Ironmongery normally supplied by the
manufacturers of the frames shall be included in the
descriptions
63
Running joints and mitres
31 Preparation for ironmongery to be fitted or
accommodated shall be included in the descriptions
or given separately in number
12
Doors
22 Pressed steel doors
13
no
33 Ironmongery and attached burglar bars shall be
included in the descriptions
34 Components of coupled windows and doors may be
given separately, in which case coupling mullions
and transoms shall be given either in metres or in
number
35 Sub-frames, sills, surrounds, sliding gear, etc may
be included in the descriptions or given separately
in metres or in number
36 Steel and other panels, fixed steel louvres and fixed
louvre shoes may be included in the descriptions or
given separately in number
Fly screens and burglar screens
24 Fly screens and burglar screens
15
32 Descriptions shall include frames and ironmongery
Windows etc
23 Windows, doors, etc of rolled sections
14
no
no
Adjustable louvres
25 Adjustable louvre insert units
16
37 Descriptions shall include glass louvres
Miscellaneous
26 Strongroom doors, roller shutters, collapsible gates,
roof lights, pavement lights, fireplace units, stoves,
etc
no
ALUMINIUM WINDOWS, DOORS, ETC
17
Windows, doors, screens, etc
27 Windows, doors, fly screens, burglar screens,
adjustable louvre insert units, etc
38 Shall be given in accordance with the principles laid
down in sub-section Steel door frames, doors,
windows, etc but descriptions shall include glass
and other panels and sealing of windows, doors, etc
against adjoining work
64
Mitres etc
CURTAIN WALLS, SHOPFRONTS, ETC
18
Curtain walls, shopfronts, etc
28 General
39 Curtain walls, shopfronts, etc shall be suitably
grouped under headings stating the general
requirements
40 Separate items shall be given for the different
components
29 Components such as heads, sills, transoms and
mullions
m or
no
41 Waterproofing and sealing components, insulation
between different metals and electrical bonding
shall be included in the descriptions
30 Windows, doors, fanlights, grilles, panels, glass, etc
no
42 Descriptions shall include ironmongery and finishes
43 Alternatively timberwork, ironmongery, glass,
painting and other integral work may be measured
separately and given in appropriate items in
accordance with the principles laid down in the
relevant trades
31 Insulating material such as fibreglass and slagwool
not included with panels etc
32 Cladding to structural steel components and to
columns, beams, etc
33 Alternative
Mitres, intersections,
cleats, screws, bolts,
plates, etc
Mitres, intersections,
cleats, screws, bolts,
plates, etc
44 Measurement rule 41 above applies
45 Where practicable curtain walls, shopfronts, etc may
be given in number in which case descriptions shall
include all components, windows, doors, fanlights,
grilles, panels, glass, insulation, etc as well as
cladding to structural steel components, columns,
beams, etc
46 Measurement rule 41 above applies
65
PLASTERING
Item or work to be measured
Unit
Measurement rules
Classification etc
1
2
Shall be classified according to composition,
texture, and preparatory work
Patterned, sloping, weathered, troughed, ribbed and
coffered work, work to falls or to falls and currents,
work incorporating heating or similar equipment and
2
work in sunk or raised panels not exceeding 2m
shall be given separately
Work to circular surfaces shall be given separately,
distinction being made between circular and
spherical work
Plaster and other in situ finishes
1
Finishes to elements such as floors and landings,
treads and risers of stairs, walls inclusive of flush
columns and beams, columns, ceilings and beams
4
m
5
6
Descriptions shall be
deemed to include
Finishes to narrow widths not exceeding 300mm
wide except to treads and risers of stairs,
columns, beams, troughed, ribbed and coffered
work and that in the flush face caused by
projections and openings
Finishes shall be measured over the net area to be
covered
No deductions shall be made for openings, wants,
2
etc not exceeding 0,5m
Reedings to treads shall be included in the
descriptions
1
2
Curing
Labours such as fair,
rounded and chamfered
edges, trowel cuts,
throats, V-joints and
angles
Outlets, angles, stopped
ends, etc
Shall be described as narrow widths and no
distinction shall be made for different components
Labours on finishes
3
Labours generally
Reedings
Forming channels
66
Comments
Skirtings and stoolings
6
Skirtings
Stoolings
no
Finishes to kerbs, sills, copings, nibs, surrounds
and the like
Mouldings
Ends, mitres, etc
Mitres etc
Laps and holes
9 The girth, width and projection shall be stated
10 Descriptions shall include ends, mitres and
intersections when the girth does not exceed
300mm
no
11 Enrichments
no
Ornaments etc
no
Dividing strips, edge trims, etc
13 Dividing strips, edge trims, etc
Mitres etc
10 Ends, mitres and intersections when the girth of the
moulding exceeds 300mm
12 Ornaments, air gratings, etc
8
Mouldings
9
Skirtings stepped over treads and risers of stairs
shall be given separately
Finishes to kerbs, sills, etc
8
Metal lathing
14 Metal lathing and the like to receive in situ finishes
67
TILING
Item or work to be measured
Unit
Measurement rules
Classification etc
1
2
3
Beds and backings
5
6
Beds and backings shall be included in the
descriptions
When tiling is prescribed to be fixed with adhesive
the beds and backings shall be given separately in
Plastering
Beds and backings incorporating heating or similar
equipment shall be so described
Tiling
2
Tiling shall be classified according to type, size,
preparatory work, method of fixing, etc
Tiling laid to a pattern shall be so described
Tiling to falls or to falls and currents and tiling in
2
isolated panels not exceeding 1m shall be given
separately
Work to circular surfaces shall be given separately,
distinction being made between work exceeding and
not exceeding 300mm radius and also between
circular and spherical work
Beds and backings
1
Descriptions shall be
deemed to include
Tiling to elements such as floors and landings, walls
inclusive of flush columns and beams, columns,
ceilings and beams
Tiling to narrow widths not exceeding 300mm wide
except to columns, beams and that in the flush
face caused by projections and openings
8
9
m
Shall be measured over the net area to be covered
No deductions shall be made for openings, wants,
2
etc not exceeding 0,1m
10 Shall be described as narrow widths and no
distinction shall be made for different components
m
Cutting
4
Circular cutting
Fair exposed cutting and fitting around pipes,
balusters and the like
no
11 Shall be grouped for pipes not exceeding 100mm
external diameter and thereafter in stages of
100mm external diameter
68
Pointing fair exposed
edges
Comments
Mitred corners and special edge and corner tiles
6
Mitred corners
Special edge and corner tiles
Treads, risers, sills, copings, skirtings, etc
8
9
Treads, risers, sills, copings, skirtings, bands,
margins, beads, mouldings and the like
13 Skirtings etc stepped over treads and risers of stairs
shall be given separately
End tiles and external and internal angle tiles
no
14 Shall be given as extra over
Mitres etc
Forming recesses etc
Mitres etc
Channels
10 Scum and block channels
11 Fair ends, stopped ends, intersections, angles and
outlets
no
15 Shall be given as extra over
Soap dishes etc
12 Soap dishes, foot rests, toilet paper holders, access
panels and the like
12 Shall be given as extra over, no distinction being
made for different components
no
Dividing strips, edge trims, etc
13 Dividing strips, edge trims, etc
69
PLUMBING AND DRAINAGE
Item or work to be measured
Unit
Measurement rules
Descriptions shall be
deemed to include
GUTTERS ETC
1
Roof gutters, rainwater pipes, etc
1
Roof gutters, rainwater pipes, etc
Angles, stopped ends, outlets, offsets, shoes, etc
no
Weep pipes, spreaders, gargoyles, rainwater
heads, etc
no
Shall be given as extra over
Jointing
Short lengths, nipples and
running joints such as
sockets, collars, couplers,
etc
Bending, jointing pipes of
differing materials and
jointing pipes to taps,
valves, traps, etc
Pipe supports such as
clips, saddles, holderbats,
hangers, etc
Holes for pipes and
cutting and fitting around
pipes unless otherwise
stated in the relevant
trades
CHANNELS
2
Stormwater channels
4
Stormwater channels
Descriptions shall include earthworks, formwork and
finishes
Angles, intersections, ends, etc
no
Shall be given together as extra over
Short isolated channels
no
Pipes and pipe fittings which are wrapped, coated or
lined in the course of manufacture shall be so
described
The method of jointing shall be stated
No distinction shall be made between pipes fixed
vertically, horizontally or to falls nor between pipes
fixed to different elements, cast in, built in, etc
Pipes chased in and pipes suspended exceeding
1m below suspension level shall be given
separately
Pipework in ground shall be given separately and
descriptions may include pipe trenches in
accordance with clause 5 Pipe trenches (method
B)
PIPEWORK ETC
3
Pipes, pipe fittings, etc
7
Pipes
5
6
70
Comments
Welded joints
no
Flanges on pipes and gasket and bolt sets
no
10 Alternatively, where expedient flanges on pipes and
gasket and bolt sets may be included in the
descriptions of the piping
10 Prescribed purpose made pipe supports
11 Shall be given separately in accordance with the
principles laid down in the relevant trades
11 Service pipes and flexible connecting pipes
no
12 Descriptions shall include connectors
12 Pipe fittings
no
13 Shall be given as extra over
14 Fittings to pipes not exceeding 30mm internal
diameter shall be given together for each diameter
of pipe
15 Fittings to pipes exceeding 30mm internal diameter
shall be given separately for each diameter of pipe
and for each type of fitting such as bushes, bends,
tees, junctions, unions, etc
16 Flanges on pipe fittings shall be included in the
descriptions of the fittings
13 Adaptors or similar pipe fittings at joints between
pipes of differing materials and at connections of
pipes to taps, valves, traps, etc
Alternatively, where expedient welded joints may be
included in the descriptions of the piping
17 Shall be given in accordance with the principles laid
down for pipe fittings
14 Pipe closers which are prescribed to be measured
on site and cut to exact length
no
15 Prescribed tests of welded joints
no
18 Shall be given as extra over the pipe in which they
occur
Pipe trenches (method A)
16 Pipe trenches
19 Shall be given in accordance with the principles laid
down in "Earthworks
20 Where no width of excavation is prescribed it shall
be calculated as follows:
Trenches not exceeding 1m deep shall be taken of
such width as to provide a clearance of 300mm on
each side of the pipe or group of pipes. The width
of the trench shall be increased by 100mm for
each successive depth of 1m to a maximum width
which provides a clearance of 500mm on each
side of the pipe or group of pipes
71
Any additional excavation
and backfilling necessary
at joints, risk of collapse
of excavations and
keeping excavations free
of water
17 Bedding under and filling around pipes comprising
sand, crushed stone, concrete, etc
5
Pipe trenches (method B)
18 Pipe trenches
22 Where expedient pipe trenches may be included in
the descriptions of the pipe or group of pipes and
separated into successive total depths in increments
of 1m, in which case descriptions shall include
excavation, bedding, backfilling, compaction and
disposal of surplus material
23 Excavations in material of a more difficult character
shall be suitably classified and given in cubic metres
as extra over, in which case the width of the
excavations shall be determined as described in
clause 4 Pipe trenches (method A)
Any additional excavation
and backfilling necessary
at joints, risk of collapse
of excavations and
keeping excavations free
of water
Pipe insulation and protection
19 Insulating and protective wrappings, coatings and
linings to pipes
20 Insulation etc around fittings, valves, etc to pipes
not exceeding 30mm internal diameter
no
21 Insulation etc around fittings, valves, etc to pipes
exceeding 30mm internal diameter
no
24 Internal diameter of the pipe shall be stated
25 Shall be given together as extra over for each
diameter of pipe
26 Shall be given separately as extra over for each
diameter of pipe and for each type of fitting, valve,
etc
Encasing
22 Concrete encasing to pipes
21 No deduction shall be made for pipes not exceeding
200mm external diameter
27 Alternatively encasing may be given in cubic metres
in which case no deduction shall be made for pipes
not exceeding 200mm external diameter
Anchor blocks, thrust blocks, etc
23 Concrete anchor blocks, thrust blocks, etc
28 Shall be given in accordance with the principles laid
down in "Concrete, Formwork and Reinforcement
29 Alternatively blocks may be given in number in
which case descriptions shall include formwork and
reinforcement
72
Formwork
Other than those
applied in the
course of
manufacture
Gulleys, grease traps, etc
24 Gulleys, grease traps, intercepting traps, etc
10
no
Inspection chambers, catch pits, etc
25 Inspection chambers, catch pits, junction boxes,
valve boxes, septic tanks, conservancy tanks, etc
11
Soakage pits, french drains, etc
26 Soakage pits, french drains, etc
12
30 Shall be given in accordance with the principles laid
down in the relevant trades
31 Alternatively inspection chambers, catch pits, etc
may be given in number
no
32 Alternatively soakage pits, french drains, etc may be
given in accordance with the principles laid down in
the relevant trades
Connections
27 Connections of new to existing pipes
no
28 Connections to services of the local authority
Item
9
33 Shall be allowed for by provisional sum
SANITARY FITTINGS, TANKS, GEYSERS, ETC
13
Sanitary fittings etc
29 Sanitary fittings
14
Tanks, geysers, etc
30 Tanks, geysers, boilers, heat pumps, incinerators,
etc
15
no
Taps, valves, etc
31 Taps, valves, shower roses, meters, etc
16
no
no
Waste unions, traps, etc
32 Waste unions, traps, etc
no
FIRE HOSE REELS AND FIRE FIGHTING EQUIPMENT
17
Fire hose reels etc
33 Fire hose reels, booster connections, hydrants,
pressure gauges, etc
no
73
Necessary fittings
18
Fire fighting equipment
34 Fire fighting equipment such as extinguishers,
blankets, buckets, etc
no
SLEEVES, HOLES, ETC
19
Sleeves
35 Sleeves through slabs, beams, walls, etc
20
no
Holes
36 Holes for pipes and cutting and fitting around pipes
21
34 Shall be given together grouped for pipes not
exceeding 100mm external diameter and thereafter
in stages of 100mm, separated in successive
lengths of 250mm
35 Shall be given in the relevant trades where stated
Flashings
37 Flashings around pipes through roof coverings
36 Shall be given in Roof Coverings, Claddings, etc
GENERAL
22
Testing
38 Prescribed testing
Item
37 Various systems shall be kept separate
74
ELECTRICAL WORK
Item or work to be measured
Unit
Measurement rules
Descriptions shall be
deemed to include
ELECTRICAL WORK
1
Classification
Connection to main supply
Item
Shall be allowed for by provisional sum
Given under headings and classified according to
type
Descriptions shall include busbars, jumpers, neutral
bars, internal wiring and connections, space for
future equipment blanking and the like
Main supply and equipment
2
3
Classified according to the nature of the installation
such as high tension supply, low tension supply, low
tension distribution, general lighting and power,
uninterrupted power supply, external lighting, etc
Connection to main supply
1
Generators, transformers, mini-substations, low
tension distribution cubicles, switchgear, etc
no
Poles, cross arms, insulators, street lights,
brackets, stays, struts, other equipment and bases
no
Distribution boards etc
4
Distribution boards, switch boards, meter boards
and the like
no
4
Equipment such as isolators, circuit breakers, earth
leakage units, transformers, time switches, surge
protectors and measuring instruments
Alternatively equipment may be included in the
board description
Classified according to size and method of
installation
Identification markers,
labels, legend cards, etc
Allowance for snaking
Glands and allowance for
making off
no
Cables
6
Cables
Cable terminations and prescribed running joints
no
Protection such as slabs and metal sheeting and
warning devices such as PVC marker tapes
75
Comments
9
6
Cable route markers
no
Cable trenches (method A)
10 Cable trenches
Shall be given in accordance with the principles laid
down in "Earthworks
Where no width of excavation is prescribed it shall
be calculated as follows:
Trenches not exceeding 1m deep shall be taken of
such width as to provide a clearance of 300mm on
each side of the cable or group of cables. The
width of the trench shall be increased by 100mm
for each successive depth of 1m to a maximum
width which provides a clearance of 500mm on
each side of the cable or group of cables
Risk of collapse of
excavations and keeping
excavations free of water
Where expedient cable trenches may be included in
the description of the cable or group of cables and
separated into successive total depths in increments
of 1m, in which case descriptions shall include
excavation, bedding, backfilling, compaction and
disposal of surplus material
10 Excavations in material of a more difficult character
shall be suitably classified and given in cubic metres
as extra over, in which case the width of the
excavations shall be determined as described in
clause 6 Cable trenches (method A)
Risk of collapse of
excavations and keeping
excavations free of water
11 No distinction shall be made between conduit fixed
vertically or horizontally
12 No distinction shall be made between conduit fixed
to different elements, cast in, chased in, built in, etc
Bending, threading,
jointing, short lengths,
couplings, bends, tees,
saddles, draw boxes and
the like
Holes for conduit and
cutting and fitting around
conduit unless otherwise
stated in the relevant
trades
7
8
11 Bedding under and filling around cables comprising
sand etc
7
Cable trenches (method B)
12 Cable trenches
Conduit
13 Conduit
76
14 Flexible conduit
9
10
11
13
14
15 Switch, socket and other outlet boxes
no
13 No distinction shall be made for number of entries
16 Cover plates, dome covers, ball and socket covers
and the like
no
14 Alternatively cover plates etc may be included in the
descriptions of the outlet boxes
Connectors
Locknuts and bushes
Cable trunking etc
17 Cable trunking, cable trays and ladders, floor and
skirting trunking, lighting channels, etc
18 Fittings to cable trunking etc such as angles,
stopped ends, junctions and outlets
no
19 Suspension rods, fixing brackets, cable clamps and
short lengths of channel for cable trunking fixing
no
10 Forming holes for conduit
entries or fittings
15 Alternatively suspension rods etc may be included
in the descriptions of the trunking etc
Draw wires
m
16 Alternatively draw wires may be included in the
descriptions of the conduit
Conductors
21 Bare and insulated conductors in conduit etc
22 Open wired conductors
17 Descriptions shall include bobbins, cleats, clips and
binding wire
11 Allowance for additional
length at connections
Busbar systems
23 Busbars
24 Fittings etc such as elbows, tees, crosses, end
covers, feed units, tap-off boxes and fixing brackets
no
18 Alternatively fixing brackets may be included in the
descriptions of the busbars
no
19 Descriptions shall include cover plates
Socket outlets and light switches
25 Socket outlets and light switches
15
Outlet boxes, cover plates, etc
20 Draw wires required to be left in
12
no
Fittings, equipment, etc
26 Luminaires, bells, telephones, speakers, geysers,
stoves, heaters, clocks, thermostats, starters,
motors, stand-by equipment, battery chargers,
control panels, etc
20 Lamps shall be included with the relevant luminaires
21 Alternatively lamps may be given separately in
number
no
77
12 Mounting plates,
brackets, connectors, etc
16
17
Earthing
27 Earthing the system
Item
28 Prescribed earth resistivity tests
Item
Lightning protection
29 Conductors of tape, wire and the like
18
30 Short coupling lengths such as between roofs and
eaves gutters and from down conductors to earth
terminals
no
31 Air and earth terminals
no
13 Bending and jointing
14 Jointing and excavation
Holes
32 Holes for conduit and cutting and fitting around
conduit etc
22 Shall be given in the relevant trades where stated
ELECTRONIC INSTALLATIONS
19
Communication, security and control installations
33 Installations such as telecommunication, public
address, closed circuit television, data
transmission, access control, security, fire
detection, building management systems, etc
23 Shall be given in accordance with the foregoing
principles
GENERAL
20
Testing and commissioning
34 Testing and commissioning the installation
21
Drawings, manuals, etc
35 Provision of as-built drawings, manuals, operative
training, etc
22
Item
Item
Replacement parts etc
36 Replacement parts, tool kits, etc
no
78
MECHANICAL WORK
Item or work to be measured
Unit
Measurement rules
Descriptions shall be
deemed to include
HEATING, VENTILATION AND AIR CONDITIONING INSTALLATIONS, ETC
1
Classification
1
Classified according to the nature of the installation
such as heating, ventilation, air conditioning, fire
protection, boiler, gas, refrigeration, compressed air,
etc
Descriptions shall include pipework, ductwork and
electrical work integral with the item of equipment,
paint or other finishes, accessories where
expedient, assembling and jointing together of
components and jointing to pipes, ducts and the like
Pipes and pipe fittings which are wrapped, coated or
lined in the course of manufacture shall be so
described
Pipework prescribed to be temporarily fixed in
position, dismantled for plating or other finishing and
subsequently refixed shall be so described
Pipework to be executed in prescribed cut lengths
shall be given separately
The method of jointing shall be stated
No distinction shall be made between pipes fixed
vertically, horizontally or to falls, nor between pipes
fixed to different elements, cast in, built in, etc
Pipes chased in and pipes suspended exceeding
1m below suspension level shall be given
separately
Pipework in ground shall be given separately and
descriptions may include pipe trenches in accordance with clause 6 Pipe trenches (method B)
Equipment
1
Items of equipment such as chillers, air handling
units, fans, air conditioning units, motors, pumps,
boilers, tanks, compressors, etc
no
PIPEWORK ETC
3
Pipes, pipe fittings, etc
2
Pipes
5
6
7
79
Short lengths, nipples and
running joints such as
sockets, collars, couplers,
etc
Bending pipes, jointing
pipes of differing
materials and jointing
pipes to taps, valves,
traps, etc
Pipe supports such as
clips, saddles, holderbats,
hangers, etc
Holes for pipes and
cutting and fitting around
pipes unless otherwise
stated in the relevant
trades
Comments
Welded joints
no
10 Alternatively, where expedient welded joints may be
included in the descriptions of the piping
Flanges on pipes and gasket and bolt sets
no
11 Alternatively, where expedient flanges on pipes and
gasket and bolt sets may be included in the
descriptions of the piping
Prescribed purpose-made pipe supports
Service pipes and flexible connecting pipes
no
13 Descriptions shall include connectors
Pipe fittings
no
14 Shall be given as extra over
15 Fittings to pipes not exceeding 60mm internal
diameter shall be given together for each diameter
of pipe
16 Fittings to pipes exceeding 60mm internal diameter
shall be given separately for each diameter of pipe
and for each type of fitting such as bushes, bends,
tees, junctions, unions, etc
17 Flanges on pipe fittings shall be included in the
descriptions of the fittings
Adaptors or similar pipe fittings at joints between
pipes of differing materials and at connections of
pipes to taps, valves, traps, etc
Pipe closers which are prescribed to be measured
on site and cut to exact length
10 Prescribed tests of welded joints
4
12 Shall be given separately in accordance with the
principles laid down in the relevant trades
18 Shall be given in accordance with the principles laid
down for pipe fittings
no
19 Shall be given as extra over the pipe in which they
occur
no
Valves etc
11 Valves, meters, pressure gauges, strainers,
sprinkler heads, etc
no
80
Pipe trenches (method A)
12 Pipe trenches
13 Bedding under and filling around pipes comprising
sand, crushed stone, concrete, etc
6
20 Shall be given in accordance with the principles laid
down in "Earthworks
21 Where no width of excavation is prescribed it shall
be calculated as follows:
Trenches not exceeding 1m deep shall be taken of
such width as to provide a clearance of 300mm on
each side of the pipe or group of pipes. The width
of the trench shall be increased by 100mm for each
successive depth of 1m to a maximum width which
provides a clearance of 500mm on each side of the
pipe or group of pipes
m
Any additional excavation
and backfilling necessary
at joints, risk of collapse
of excavations and
keeping excavations free
of water
Any additional excavation
and backfilling necessary
at joints, risk of collapse
of excavations and
keeping excavations free
of water
22 No deduction shall be made for pipes not exceeding
200mm external diameter
Pipe trenches (method B)
14 Pipe trenches
23 Where expedient pipe trenches may be included in
the descriptions of the pipe or group of pipes and
separated into successive total depths in increments
of 1m, in which case descriptions shall include
excavation, bedding, backfilling, compaction and
disposal of surplus material
24 Excavations in material of a more difficult character
shall be suitably classified and given in cubic metres
as extra over, in which case the width of the
excavations shall be determined as described in
clause 5 Pipe trenches (method A)"
Pipe insulation and protection
15 Insulating and protective wrappings, coatings and
linings to pipes
25 Internal diameter of pipe shall be stated
16 Insulation etc around fittings, valves, etc to pipes
not exceeding 60mm intrnal diameter
no
17 Insulation etc around fittings, valves, etc to pipes
exceeding 60mm internal diameter
no
26 Shall be given together as extra over for each
diameter of pipe
27 Shall be given separately as extra over for each
diameter of pipe and for each type of fitting, valve,
etc
81
Other than those
applied in the
course of
manufacture
Encasing
18 Concrete encasing to pipes
28 Alternatively encasing may be given in cubic metres
in which case no deductions shall be made for pipes
not exceeding 200mm external diameter
Formwork
Jointing
Anchor blocks, thrust blocks, etc
19 Concrete anchor blocks, thrust blocks, etc
10
29 Shall be given in accordance with the principles laid
down in "Concrete, Formwork and Reinforcement
30 Alternatively blocks may be given in number in
which case descriptions shall include formwork and
reinforcement
Inspection chambers, junction boxes, etc
20 Inspection chambers, junction boxes, etc
31 Shall be given in accordance with the principles laid
down in the relevant trades
32 Alternatively inspection chambers, catch pits, etc
may be given in number
DUCTWORK ETC
11
Ducting
21 Rectangular low pressure galvanised sheet metal
ducting
33 Shall be measured over ducting fittings and grouped
according to size in the following categories:
33.1 Width or height not exceeding 750mm and
sum of two adjacent sides not exceeding
1,15m
33.2 Width or height not exceeding 750mm and
sum of two adjacent sides exceeding 1,15m
33.3 Width or height exceeding 750mm and not
exceeding 1,35m
33.4 Width or height exceeding 1,35m and not
exceeding 2,1m
33.5 Width or height exceeding 2,1m
34 Where an in-line reduction in size of ducting occurs,
the larger size shall be measured over the full length
of the fitting
35 No distinction shall be made between ducting fixed
vertically, horizontally or raking nor between ducting
fixed to different elements
82
36 Separate items shall be given for ducting
suspended not exceeding 1m below suspension
level and thereafter in successive stages of 1m
measured from the underside of the ducting. A
general description of the supporting structure from
which ducting is suspended shall be given
37 Ducting to a curve shall be given separately stating
the mean radius
38 Supports shall be included in the descriptions of
ducting or may be given separately in accordance
with the principles laid down in the relevant trades
12
22 Rectangular ducting other than low pressure
galvanised sheet metal ducting and round ducting
23 Ducting fittings
24 Flexible ducting
Jointing
no
41 Shall be given as extra over
42 Reducers, radius bends, square bends,
transformations, spigots, branches and tees shall be
given together for each category or size of ducting
43 All other ducting fittings shall be given separately for
each category or size of ducting and for each type
of fitting
44 Stopped ends shall be given separately for each
category or size of ducting
10 Forming openings and
jointing to ducting
no
45 Shall be grouped for ducting not exceeding 1,5m
girth and thereafter in successive girths of 1,5m
46 Descriptions shall include connectors
11 Jointing
47 Shall be measured to the external or internal
surface of the ducting
48 Alternatively wrappings etc may be included in the
descriptions of the ducting
12 Working around ducting
fittings
Diffusers, grilles, etc
25 Diffusers, grilles, attenuators, dampers, filters, etc
13
39 Shall be measured over ducting fittings
40 Measurement rules 34 to 38 above apply
no
Ducting insulation and protection
26 Insulating and protective wrappings, coatings and
linings to ducting
83
CONVEYING INSTALLATIONS
14
Lift installations
49 Lift installations shall be suitably grouped under
headings stating whether it comprises a single lift or
a bank of lifts
15
27 Cars
no
50 Descriptions shall include frames, guides,
enclosures, base, car doors, door opening devices,
locking and safety devices, inspection doors, sills,
internal finishes, fittings such as handrails, mirrors,
etc and lighting and ventilation requirements
28 Landing entrances
no
51 Descriptions shall include frames, sills, landing
doors, door opening devices, locking and safety
devices, etc
29 Power units
no
52 Descriptions shall include supports, sheaves, sound
reducing material, switching equipment, etc
30 Support work in lift shafts comprising guide rails,
brackets, plates, buffers, supports, sheave beams,
etc
Item
31 Ropes comprising cables, clamps, etc
Item
32 Counterweights comprising frames, guides,
compensation, etc
Item
33 Governors and safety gears
Item
34 Operation and control system comprising car
operator panels, car position and direction
indicators, landing position and direction indicators,
call buttons, lanterns and gongs, load weighing
devices, intercommunication, detectors, wiring, etc
Item
35 Temporary use of lifts comprising temporary
enclosures, protection, finishes, etc, refurbishment,
completion and re-commissioning
Item
Hoist, escalator and conveyor installations
36 Hoist, escalator and conveyor installations
53 Shall be given in accordance with the principles laid
down in clause 14 Lift installations
84
OTHER MECHANICAL INSTALLATIONS
16
Material handling installations, disposal installations, etc
37 Installations such as material handling, refuse
disposal, waste compaction, incineration, etc
54 Shall be given in accordance with the foregoing
principles
GENERAL
17
Testing and commissioning
38 Testing and commissioning
18
55 Descriptions shall include details of any prescribed
tests and requirements such as provision of
instruments and appliances, performance logging,
fuel, power, water, etc
Drawings, manuals, etc
39 Provision of as-built drawings, manuals, operative
training, etc
19
Item
Item
Identification markers etc
40 Identification markers, direction indicators, labels,
legend cards, etc
20
Replacement parts etc
41 Replacement parts, tool kits, etc
21
13 Identification markers,
direction indicators,
labels, legend cards, etc
no
Electrical work and work by other trades
42 Electrical work and work by other trades integral
with mechanical installations
56 Shall be given in accordance with the principles laid
down in the relevant trades
85
GLAZING
Item or work to be measured
Unit
Measurement rules
Classification etc
1
2
3
4
Descriptions shall be
deemed to include
Glass
Glass in shapes which are not rectangular
Glass shall be classified according to type, quality,
thickness and size
Descriptions of glass shall state the method of
glazing and the material of the frames to receive the
glass
Descriptions of glass in beaded frames shall state
the method by which beads are fixed
Glass shall be grouped according to size in the
following categories:
2
4.1 Not exceeding 0,1m
2
2
4.2 Exceeding 0,1m and not exceeding 0,5m
2
2
4.3 Exceeding 0,5m and not exceeding 2m
2
4.4 Thereafter in stages of 2m
Glazing beads, gaskets, sealing, etc
3
Glazing beads
Glazing gaskets, cover beading and the like
Moulded corners to gaskets
no
Sealing of joints in panes with silicone
Glazing beads shall be given separately in the
relevant trades
1
Shall be given as extra over
Descriptions shall include designs
Labours on glass
7
Grounding, sandblasting, embossing or brilliant
cutting to panes
no
Labours to edges such as bevelled or polished
Holes, finger grips, etc
no
86
Mitres
Comments
Glass louvre blades
10 Glass louvre blades
Descriptions shall include labours to edges, holes,
finger grips, screws, clips, etc
no
10 Descriptions shall state the shape and average size
of panes and method of fixing and shall include
cames, saddle bars, etc
Patent glazing
14 Patent glazing
no
Leaded and coppered lights
13 Panels of leaded or coppered lights
Descriptions shall include labours to edges
Bent glass
12 Panes of bent glass
Glass tops, shelves, doors, mirrors, etc
11 Glass tops, shelves, doors, mirrors, etc
no
11 Descriptions shall include all components forming
an integral part of the glazing system
12 Alternatively when inclusive numbered items are not
practicable, patent glazing may be given in detail in
which case glass shall be given in square metres
grouped according to size in the categories provided
for in clause 1 Classification etc. Glazing bars,
glazing wings, head and sill members, dividers, etc
shall be given in metres and stops, fixing saddles
and the like shall be given in number. Descriptions
shall include cleats, bolts, plates and other
incidentals
Materials resembling glass
15 Materials resembling glass such as acrylic,
polycarbonate, etc
13 Shall be given in accordance with the foregoing
principles
87
PAINTWORK
Item or work to be measured
Unit
Measurement rules
Classification etc
1
Paintwork shall be classified according to the
specification of the paint, preparatory work and the
material to be painted such as plaster, concrete,
brick, wood or metal, distinction being made
between floated and textured plaster surfaces and
smooth and rough concrete surfaces
Separate items shall be given for paintwork on
different components, except where they can be
suitably grouped as general surfaces
Paintwork on columns, beams, ribs, hoods and fins
shall be included with painting walls or ceilings as
the case may be
Colours
4
5
6
Descriptions shall be
deemed to include
Paintwork shall be clasified in the different colour
groups White, Pastel, Deep and Transparent
(in accordance with the Natural Colour System
(NCS) adopted by the SA National Standards)
Paintwork in one colour group may be given as
extra over paintwork in another colour group
No further distinction shall be made for colour
except for the following:
5.1
Paintwork on mouldings and bands picked
out in colours differing from the surrounding
paintwork, which shall be given separately
5.2
Paintwork on walls, ceilings, etc to patterns
in more than one colour, which shall be
given separately as in patterned multicolours
Paintwork
1
Paintwork generally
No deductions shall be made for openings, wants,
2
etc not exceeding 0,5m
88
Cutting in of edges
Comments
Paintwork on profiled surfaces
Paintwork on gates, grilles, burglar screens,
balustrades, etc
Paintwork not exceeding 300mm wide or girth and
not adjoining similarly painted work
Painted lines
4
5
4
Paintwork on members of trusses and lattice work
Paintwork on frames etc
Paintwork on windows, sash doors, fanlights,
louvred units, etc
11 Shall be measured over the full flat area of both
sides
12 Painting cottage pane windows etc and windows
with burglar bars, steel louvers, etc shall be given
separately
Signwriting and gilding
9
Shall be measured over the full flat area of both
sides
10 Alternatively paintwork may be given in detail in
accordance with the principles laid down for
paintwork not exceeding 300mm wide or girth and
not adjoining similarly painted work
Windows, sash doors, etc
8
Frames etc
7
May be measured over the flat area stating that the
work has been measured on flat
Trusses and lattice work
6
Letters, numerals, figures, motifs and punctuation
marks
no
13 Shall be given together in one item, distinction being
made for height and style only
Polishing
10 Polishing
14 Polishing shall be given in accordance with the
foregoing principles
89
PAPERHANGING
Item or work to be measured
Measurement rules
Descriptions shall be
deemed to include
Classification
1
Paperhanging shall be classified according to the
type of material, preparatory work and the nature of
the surfaces to be prepared
No deductions shall be made for openings, wants,
2
etc not exceeding 0,5m
Matching
Mitres and intersections
Paperhanging
1
Unit
Paperhanging to elements such as walls inclusive
of columns and ceilings inclusive of beams
Borders and motifs
2
Border and panel strips
Descriptions shall include cutting to profile
Motifs
no
Descriptions shall include cutting to profile
Shall be given in accordance with the foregoing
principles
Hessian, canvas, etc
4
Hessian, canvas and other similar fabrics fixed to
wall or ceiling surfaces
90
Comments
EXTERNAL WORK
Item or work to be measured
Unit
Measurement rules
Descriptions shall be
deemed to include
NOTE: External work of minor extent may be given in Earthworks under suitable headings
LANDSCAPING
1
Contouring etc
1
Excavating, filling, digging up and removing topsoil,
etc shall be given in accordance with the principles
laid down in Earthworks
Topsoil shall be given in accordance with the
principles laid down Earthworks
Topsoil and compost to plant boxes shall be given
separately
Topsoil, compost, lime and fertilizer
1
Topsoil and compost
3
2
3
Spreading and mixing
Cultivating plant bed surfaces
Mulch
Watering, mowing,
trimming edges,
maintaining and
protection
no
Excavation, planting,
backfilling, damming
around and maintaining in
position
Watering, pruning,
maintaining and
protection
Grassing, ground cover, etc
5
Mulch
4
kg
Plant bed preparation
3
Lime and fertilizer
Grassing, ground cover, herbaceous plants, etc
Trees, shrubs, etc
6
Trees, shrubs, bulbs and plants
Removing and repositioning of existing trees
no
91
Comments
Pruning of existing trees and shrubs
8
Pitching, pebble covering, etc
Rockery boulders
10 Rockery boulders
10
no
Pitching, pebble covering, etc
9
Pruning of existing trees and shrubs
no
Shall be given in accordance with the principles laid
down in the relevant trades
Shall be given in accordance with the principles laid
down in the relevant trades
Shall be given under suitable headings in
accordance with the principles laid down in the
relevant trades
Shall be given in accordance with the principles laid
down in Plumbing and Drainage
Shall be given in accordance with the principles laid
down in the relevant trades
Paving etc
13 Paving etc
13
Filter fabric
12 Filter fabric
12
Shall be suitably grouped
Retaining structures
11 Retaining structures formed of filled gabion boxes
and mattresses, concrete, precast concrete,
interlocking blocks, masonry, etc
11
Weedkillers, insecticides, etc
14 Treating surfaces with weedkillers, insecticides, etc
m
14
Ponds, water features, etc
15 Ponds, water features, etc formed of concrete,
precast concrete, masonry, etc
15
Benches, tables, etc
16 Benches, tables, etc
16
Drainage
17 Drainage
17
no
Irrigation systems
18 Irrigation systems
92
18
Effect lighting
19 Effect lighting
10 Shall be given in accordance with the principles laid
down in Electrical Work
ROADWORK AND PARKING
19
Excavations and filling
20 Excavations and filling
20
11 Shall be given in accordance with the principles laid
down in Earthworks
Foundation courses
21 Sub-base and base courses
12 Shall be given in accordance with the principles laid
down in Earthworks
22 Stabilisation of foundation courses with lime,
cement, etc
21
Compaction of natural or excavated ground surfaces
23 Compaction of natural or excavated ground
surfaces
22
23
24 Road and parking surfacing of gravel, concrete,
tarmacadam, blocks, etc
25 Movement joints
Road and parking surfacing
Channels, humps and shoulders
26 Channels, humps and shoulders formed in road
surfacing
24
14 Shall be given as extra over
15 Circular channelling, kerbing or edging shall be
given separately, distinction being made between
work exceeding and not exceeding 4m radius
Road signs, crash barriers, etc
28 Road signs, crash barriers, etc
26
m or
no
Channelling, kerbing, edging, etc
27 Channelling, kerbing, edging, etc of concrete, brick,
stone and the like
25
13 No deductions shall be made for openings, wants,
2
etc not exceeding 1m
16 Shall be given in accordance with the principles laid
down in the relevant trades
Drainage
29 Drainage
17 Shall be given in accordance with the principles laid
down in Plumbing and Drainage
93
Angles, ends, etc
27
Painting
30 Painted lines and letters and painting of signs and
posts
18 Shall be given in accordance with the principles laid
down in Paintwork
FENCING
28
29
Fencing, posts, gates, etc
31 Fencing
32 Posts and stays differing from those included in the
descriptions
no
33 Gates
no
Holes, binding wire,
screws, nails, etc
26 Descriptions shall include hinges, latches, stops,
runners, etc
Holes, binding wire,
screws, nails, etc
27 Shall be included in the descriptions or may be
given in number
Earthworks, formwork, etc
19 The height above ground level or other base shall
be stated
20 Descriptions shall include site clearance and the
preparation of ground
21 Descriptions shall include bolts and straining eye
bolts
22 Posts and stays which occur at regular intervals
may be included in the descriptions or may be given
separately in number. Descriptions shall include
caps, base plates, arms or brackets for overhang,
pointing and driving
23 Fencing to a curve shall be given separately stating
whether straight or circular between posts
24 If circular between posts the radius shall be stated
25 Shall be given separately as extra over
Concrete bases and kerbs
34 Bases to posts and stays
35 Kerbs
WASHING LINES
30
Washing lines
36 Washing lines
no
28 Alternatively washing lines may be given in detail in
accordance with the foregoing principles
94
PAINTING
31
Painting
37 Painting fencing, washing lines, etc
29 Painting shall be included in the descriptions
30 Alternatively painting may be given separately in
accordance with the principles laid down in
Paintwork
95