Specifications
Specifications
Technical Specifications
Bidders must state here either Comply or Not Comply against each of the individual
parameters of each Specification stating the corresponding performance parameter of
the equipment offered. Statements of Comply or Not Comply must be supported by
evidence in a Bidders Bid and cross-referenced to that evidence. Evidence shall be in
the form of manufacturers un-amended sales literature, unconditional statements of
specification and compliance issued by the manufacturer, samples, independent test
data etc., as appropriate. A statement that is not supported by evidence or is
subsequently found to be contradicted by the evidence presented will render the Bid
under evaluation liable for rejection. A statement either in the Bidders statement of
compliance or the supporting evidence that is found to be false either during Bid
evaluation, post-qualification or the execution of the Contract may be regarded as
fraudulent and render the Bidder or supplier liable for prosecution subject to the
provisions of ITB Clause 3.1(a) (ii) and/or GCC Clause 2.1(a) (ii).
SCOPE OF WORKS / Item:
NOTE IMPORTANT :
1|P age
3|P age
5|P age
OUTLINE
SPECIFICATIONS
CONSTRUCTION :
FOR
GENERAL
TWO (2) SET of clean Plans and specification shall always be kept at the
jobsite to be available to the Procuring Entity or their representative upon
his request during the construction.
7|P age
The Procuring Entity may at any time without invalidating the Contract
make changes by altering, adding to or deducting from the work as
covered by the drawings, specifications, and general scope in written
instructions. Provisions under General Conditions of the contract cover
such circumstances.
included:
1. Site Clearing: Protection and/or removal of existing structures
with the approval from the Procuring Entity and or lessor.
2. Removal of improvements above and below grade (if any)
necessary to permit construction and other work as indicated.
Procuring Entity, Lessor must be consulted prior to any
demolition. Coordination with Eton Properties Philippines
Incorporated (EPPI) Maintenance / Facilities Group & proper
investigation is to be conducted to avoid damage on existing
utilities. Rubbish shall be legally and properly disposed of. Other
items for relocation / demolition will be discussed in the Pre-Bid
Conference.
B. SITE SAFETY REQUIREMENTS:
1.
2.
9|P age
DIVISION 3: MASONRY
A. CONCRETE MASONRY UNITS
1. Masonry Units (CHB): 100mm thick for all interior walls unless
otherwise indicated. Use 400 psi for non-load bearing blocks and
700 psi for load bearing blocks where required.
a. Supplier: Allied Concrete, Rock built or Jack built
b. Where full height walls are constructed with concrete
hollow blocks, these shall extend up to the bottom of
beam or slab unless otherwise indicated on plans.
Provide stiffener columns & lintel beams as specified in
the structural drawings or as specified or as deemed
required to assure a stabilized wall due to height & other
considerations.
2. Sand: S-1, washed, clean and greenish in color.
3. Mortar: One part Portland cement and two parts sand and
water but not more than three parts sand and water.
4.
10 | P a g e
DIVISION 4: METAL
A. Stainless Steel
1.
1.
2.
per
manufacturers
DIVISION 6:
PROTECTION
THERMAL
AND
MOISTURE
WATERPROOFING
Waterproofing: Furnish all labor, materials, equipment, plant and other
facilities required to complete all waterproofing work as shown on the
drawings and herein specified. All applications shall be strictly performed by
an approved waterproofing Contractor..
All materials shall be Environmental Protection Agency (EPA) certified and
approved.
Testing: Test waterproofed area by seventy-two (72) hours and check for
any seepages.
1.
for Toilets
12 | P a g e
and
Glazing
DIVISION 8: FINISHES
Refer to Plans for location. Verify plans for other finishes not specified or
omitted herein. Sample of all materials shall be submitted to the Procuring
Entity for approval as to color and quality workmanship.
A. FLOOR FINISHES
1. Width 2100mm x 2mm thick Static Control Homogenous Vinyl
Floor Covering Roll Type by Gerflor. Offices, Hallway and other
Areas, See floor plan for Legend & Call Out Specifications as to
where to be applied. Submit sample for Procuring Entitys
approval.
15 | P a g e
16 | P a g e
a. Use standard G.I. metal Studs framing at every 600mm on center both ways. Provide standard
construction system complete with seismic bracing.
C. CEILING FINISHES
1. Acoustic Mineral Ceiling Boards: 15 mm x 600 mm x 600
mm, with 5-year warranty to withstand humidity conditions up to
at least 90F/ 90% RH without visible sag; in white color.
PLEASE SEE EXISTING It must be of the same design, brand
2. Ceiling Suspension System: ASTM C 635 (Intermediate-duty)
main beam and cross tee classification, commercial-quality
dipped galvanized steel. All exposed surfaces to be chemically
cleansed with capping in baked polyester and/or treated with
powder coat white finish. Provide seismic bracing. Submit shop
drawings for approval.
3. Gypsum Board: install Gypsum ceiling on a 400mm x 400mm
G.I. Framing Suspended Ceiling System complete with all
accessories Design as indicated on plans..
D. PAINTING WORKS
All materials shall be Environmental protection Agency (EPA) certified and
approved.
Painting Materials:
1. Submit various painting materials specification data and
sample to be used for Procuring Entitys approval.
2. All primers, thinners and putty, also waterproofing for internal
and external application shall be the same brand as the
specified material.
3. Painting materials including its application must be covered
with minimum of five- (5) year guarantee to be rendered by the
painting manufacturer.
4. Use BOYSEN or DAVIES only for all painted works.
Application:
17 | P a g e
1.
2.
3.
Interior
a.
DIVISION 9:
SPECIALTIES
Asian
1.0
GENERAL DESCRIPTION
1.1
GUARANTEE
The ELECTRICAL CONTRACTOR shall guarantee that the electrical
system is free from all grounds and defective materials and
workmanship for a period of one (1) year from the date of
acceptance of the work. All defects arising within the guarantee
period shall be reminded by the ELECTRICAL CONTRACTOR at his
own expense.
The ELECTRICAL CONTRACTOR shall indemnify and save
20 | P a g e
2.0
1.4.1
1.4.2
1.4.3
1.4.4
SCOPE OF WORK
2.1 Work Included
The work to be done under this DIVISION shall include the furnishing
of all tools, labor, equipment, fixtures and materials, each complete
and in proper working condition unless one or other is specifically
excluded or stated otherwise in these Specifications but not limited
to the following principal items of work:
2.1.1
21 | P a g e
2.1.2
2.1.3
2.1.4
2.1.5
2.1.6
3.0
PROCEDURE
3.1 Workmanship
The ELECTRICAL CONTRACTOR shall execute the work in the
most thorough, prompt and workmanlike manner and in accordance
with the plans and specifications. The installations shall be done
thru standard methods and good engineering practices.
3.2 Materials
All materials to be installed shall be brand new except as otherwise
noted on the plans or specifications. The materials shall be as
specified. No substitution of materials is allowed. Should the
ELECTRICAL CONTRACTOR find it necessary to use another
type/brand of materials instead of the specified item, he shall first
obtain approval from the PROCURING ENTITY prior to installation.
Any substituted material installed without the approval of the
PROCURING ENTITY shall be subject to replacement.
3.3
Coordination
It is the sole responsibility of the ELECTRICAL CONTRACTOR to
conduct coordination of his activities with the following:
3.3.1
3.3.2
3.3.3
3.3.4
3.4
3.6.2
3.6.3
3.6.4
3.7
Electric Power
The ELECTRICAL CONTRACTOR shall be responsible for his own
electric power needed for the execution of the job.
3.8
TEST
Conduit tests on all electrical conductors installed in the presence of
the PROCURING ENTITYs representative.
3.8.1
3.8.2
3.8.3
3.8.4
3.8.5
23 | P a g e
3.8.6
3.9
3.10 All defects found during the test shall be repaired immediately by the
ELECTRICAL CONTRACTOR.
3.11 All tools, equipment and instruments needed to conduct tests shall
be on the account of the CONTRACTOR.
4.0
4.1 Conduits
4.4.1
4.4.2
4.4.3
Installation of Conduits
a.
b.
c.
d.
e.
f.
24 | P a g e
g.
h.
i.
l.
4.2
threads.
Cut ends of conduit square with hand or power saw
and ream to remove burrs and sharp edges. Do not
use wheel cutter.
Clamps shall be galvanized malleable iron one-hole
straps, beam clamps or other approved device with
necessary bolts and expansion shields.
Trapeze hangers shall be used for parallel runs of
conduits. Install conduit clamps at end of each run
and at each elbow. Paint hangers one prime coat of
red lead or zinc chromate, and one finish coat of an
approved color. Hangers are not detailed but must be
adequate to support combined weight of conduit,
conductors and hangers. Submit shop drawings for
approval.
All underground conduits installed shall be provided
with concrete encasement at least 8cm. thick outer
face of conduit.
Wires
4.2.1
4.2.2
4.2.3
4.2.4
4.2.5
4.2.6
4.2.7
4.3 Connectors
Use solderless mechanical pressure - type lugs, copper
4.4 Insulation
All splices shall be properly insulated using 3M electrical tape.
Application of insulation tape shall be equivalent to the insulation of
the wire concerned. Use filler compound, Scotch fill at sharp edges
to provide smooth surface before taping.
4.5 Panel board & Circuit Breaker
4.5.1
25 | P a g e
NEMA type/enclosure
unless
noted, PEC rules and
regulations, circuit breaker type shall be 230V, number of
pole as required.
4.5.2
4.5.3
4.5.4
4.5.5
4.5.6
SCOPE OF WORKS
The work to be undertaken under this section shall consist of
the furnishing of all materials, labor tools, equipment and
other facilities and the satisfactory performance of all work
necessary for the complete installation, testing and operation
of the plumbing system accordance with the applicable
drawing and this section of that specifications consisting of,
but not necessarily limited to the following:
a.
b.
c.
d.
26 | P a g e
e.
l.
1.2
1.3
PSW 2.0
2.1
GENERAL
DRAWING AND SPECIFICATIONS:
2.2
PROTECTION:
The contractor shall protect all his work and materials loss,
injury or defacement. Protection of fixtures and materials shall be
provided by boards, papers and/or cloth as required and any loss,
damaged or deface material shall be replaced by the Contractor at
his own expense.
2.3
27 | P a g e
b.
IDENTIFICATION OF MATERIALS:
b.
PSW 4.0
WATER SUPPLY
a.
b.
4.1
SANITARY DRAINAGE
a.
b.
c.
d.
Cleanouts:
1.
2.
4.3
28 | P a g e
PSW 5.0
5.1
A.
substantial
hangers
and
B.
EXECUTION
GENERAL INSTALLATION OF PIPES
A.
Install pipes approximately as shown on the drawings,
as straight
and direct as possible forming right angles parallel
lines with walls and other pipes, and neatly spaced unless otherwise
indicated. Care shall be taken not to weaken the structural portions
of the building.
29 | P a g e
B.
C.
D.
E.
F.
G.
specifically approved.
H.
I.
5.2
A.
The piping shall be extended to all fixtures, outlets
and equipment. Ends of pipes and outlets shall be capped or plugged and
left ready for future connections.
B.
Branch pipe from service line may take off of main,
bottom of main, or side of main, using such cross over fittings as may be
required by structural or installation conditions.
All service pipes, valves and fittings shall be kept at
sufficient distance from other work to permit finished
covering not less than 12.7mm (1/2) from such other
work and not less than 12.7mm between finished
coverings on the different services. No water piping
shall be buried in floors until after they have been
inspected and approved.
5.3
C.
D.
E.
30 | P a g e
5.4
B.
C.
5.5
A.
B.
C.
31 | P a g e
5.6
5.7
test is
B.
C.
B.
B.
The system shall hold this water for a full thirty (30) minutes
during which time there shall be no drop more than four
inches 100mm (4).
C.
3. Intent
It is not intended that the drawings shall show every pipes,
fittings, valve and equipment. All such items whether
specifically mentioned or not, or indicated on the drawings,
shall be furnished and installed if necessary to complete the
system in accordance with the best practice of the fire
protection trade and to the satisfaction of the Procuring
Entity.
4. Site Investigation
The contractor required to visit the site and to ascertain
himself as to the local conditions and facilities that may affect
his work. He will be deemed to have done this before
preparing his proposal and any subsequent claims on the
ground of inadequate or inaccurate information will not be
entertained
5. Shop Drawings.
The Contractor shall submit to the Procuring Entity, for
approval, four (4) copies of all shop drawings of details and
connections not shown on the drawings or details or
deviations thereof but required for the work. The Contractor
33 | P a g e
34 | P a g e
SIGNS
i. Identification signs shall be provided as required by
NFPA codes or as shown on the drawing
ii. Identification signs shall have red background and
white letter sizes that are easily readable
12.0 Installation
12.1 Workmanship
12.1.1 The work throughout shall be executed in the best
and most thorough manner in accordance with NFPA
standard and to the satisfaction of the Procuring
Entity, who will jointly interpret the meaning of the
drawings and specifications and shall have power to
reject ant work and materials which in their judgment
are not in full accordance therewith
12.1.2 This Contractor shall assume unit responsibility and
shall provide the service of the qualified Engineer to
supervise the complete installation of equipment and
systems and who shall be available for conducting
the final acceptance test.
12.1.3 All equipment shall be installed in accordance with
NFPA standard and in accordance with the
manufacturers standard Certificate of Compliance
by the manufacturers representative shall be
submitted to the Procuring Entity.
12.2 Pipings Installation
12.2.1 Install pipe hanger parallel to the building line or as
shown on the drawing
12.2.2 Install essentially as shown on the drawing. Modify
as required to clear the building structure and
openings, lights, ducts, and other services
12.2.3 Install valves where it can be conveniently operated
from the floor. Valve system shall be installed upright
39 | P a g e
or horizontal only.
12.2.4 Provide adequate spacing between walls and other
pipings permit servicing of valves and other devices.
12.2.5 Provide pipes sleeves for all pipings passing
through building structures
12.2.6 Install piping to permit natural drainage by gravity
towards to control valve.
12.3 Pipe, Hanger, and Support Installation
12.3.1 All supports shall be independent of the ceiling
suspension and other system such as duct works
and other piping.
12.3.2 Sway braces shall be installed on feed mains and
cross main to avoid piping oscillations.
12.3.3 Risers shall be supported by attachment directly to
the risers or by hanger located on the horizontal
connection close to the riser.
12.3.4 Hangers or Branch lines There shall be at least 1
hanger for each sprinkler installed on the branch
lines.
12.3.5 Hangers or Cross mains There should be at least
1 hanger between 2 branch line.
12.3.6 Hanger for Risers There should be at least 1
hanger for every floor.
12.4
Painting
2.
3.
4.
5.
6.
services
7.
8.
GENERAL CONDITIONS:
41 | P a g e
Plan
and
elevation
views
of
the
Data
center(Communication Room, Monitoring Area,
Server Room), MDF, TTC rooms both horizontal and
vertical runs
Show major pathways of cable runs
Equipment closets
Location of conduit pull boxes
Wall penetrations
Location of all cable terminations
Jack numbers and outlets location should be on the
floor plan
data center
42 | P a g e
Training for the cabling (Data and Voice) shall cover SCS
administration and orientation on as-built documentation and actual setup
for 5 PPP personnel
should
be
installed,
configured
The Contractor shall warrant the cabling system against defects for
Ten (10) years for the installation and workmanship from the date of
turnover.
Cabling Warranty:
The contractor shall warrant all wireless devices for Three (3 )years
The contractor shall warrant all wireless devices for Three (3 )years
COMPONENT SPECIFICATIONS:
I. STRUCTURED CABLING SYSTEM FOR DATA CONNECTIVITY
The following components must meet or exceed the performance
requirements of ANSI/TIA/EIA-568B.2-1:
44 | P a g e
All cable runs must maintain 10 foot service loop at both end
of the cable and placed in the ceiling
rows.
Attenuation
Attenuation to Crosstalk Ratio (ACR)
Power Sum Attenuation to Crosstalk Ratio (PSACR)
Near End Crosstalk (NEXT)
Power Sum Near-End Crosstalk (PSNEXT)
Equal Level Far-End Crosstalk (ELFEXT)
Power Sum Equal Level Far-End Crosstalk
(PSELFEXT)
Return Loss
Propagation Delay
Delay Skew
Transfer Impedance
All cable runs must maintain 10 foot service loop at both end
of the cable and placed in the ceiling
46 | P a g e
Provide Cable trays under Raised Flooring at a standard 2ft x
2ft raised floor grid spacing
Attenuation
Attenuation to Crosstalk Ratio (ACR)
Power Sum Attenuation to Crosstalk Ratio (PSACR)
Near End Crosstalk (NEXT)
Power Sum Near-End Crosstalk (PSNEXT)
Equal Level Far-End Crosstalk (ELFEXT)
Power Sum Equal Level Far-End Crosstalk (PSELFEXT)
Return Loss
Propagation Delay
Delay Skew
Transfer Impedance
Termination block (connecting block with 25 pairs 110 BlockData ; 25 pairs 110 Block-Voice) from
bundles
47 | P a g e
For horizontal cable needs wall mount wiring blocks at one
end and the cabinet mount wiring blocks at the other end
ANSI/TIA/EIA-568B.3
ISO/IEC 11801
buffer units
Must follow industry standard color codes for buffer and sub-
Interconnect Panel
48 | P a g e
Patch Cord
and 5 Ghz)
49 | P a g e
1 Gigabit Ethernet
VLANs
Supports IPv6
rack
50 | P a g e
51 | P a g e
52 | P a g e
2.
Pathways (Runner grid) for electrical supply with space
provisions for data/voice cabling
2.1 Provision for cabling riser and communication line
entrance in the Data Center
Note: Structured cabling for data/voice will be installed by a qualified
provider
3.
Electrical
system
for
Data
Center,
Technical
Working/Monitoring work area , and Communications (PABX) room
4.
Wall partition and door installation for Data Center,
Communications (PABX) and Technical Working/Monitoring Rooms
4.1 Provision for physical security system installation
5.
6.
Environmental Control : Ventilation ducting and exhaust
system, cooling system, fire suppression system, Humidification system,
pre-action wet system
7.
Facility Relocation
8.
9.
WARRANTY REQUIREMENT
Installation and Workmanship Warranty:
53 | P a g e
TIA 942
rails( if needed)
grounding
materials,
Cable labeling
As-built documentation
55 | P a g e
Overhead, under-floor and wall-mount cable pathways
grounding system
Materials preparations,
management and installation
design,
distribution,
delivery,
56 | P a g e
STRINGERS
Interconnect pedestals in a 2 X 2 grid for greater stability
and to provide support for the floor panels
PEDESTALS
Base: Square base plate with not less than 16 square inches
(103 sq. mm) of bearing area.
Galvanized finished
SEISMIC BRACING
RAMPS
Ramp should
maneuvering of equipment.
have
1.8
meters
wide
for
sufficient
58 | P a g e
Electrical Runner
59 | P a g e
Wall Partition
ceiling grid
Sealing materials
60 | P a g e
Thickness: inch
FOR
TECHNICAL
WORKING
cables
Integrated power
VENTILATION REQUIREMENT
Must support the following operational parameters of the data
centers air conditioning system
Temperature: 200 C
FACILITY RELOCATION
Water sprinklers
Detectors
62 | P a g e
1 Amplifier/Mixer
20 units Wireless Delegate microphones
1 unit Wireless Chairman microphone
4 units 8-channel Wireless Receivers
1 set speaker system
2 sets wireless lapel microphones
2 units wireless microphones
DIVISION 17 FURNITURE
The Contractor shall supply, delivery and install the following items at the
new office:
17.1 Eight (8) sets of Executive Tables, Executive Chairs and Visitors Chair
for 2 DEDs and 6 Service Directors
Each set consist of the following:
* 1 - Executive Table - 25 mm Thick Table Top with legs, modesty and
shelf, MFC Wengue Finish
* 1 - Executive Chair Mesh Type with Gas Lift, Plastic Arms and Base
with Fabric Seat
* 2 - Visitors Chair Sled Type Base Fabric Chair
17.2 Seven (7) units of Executive Chairs for 1 ED, 1 DG and 5 Asst.
Directors
*Executive Chair Mesh Type with Gas Lift, Plastic Arms and Base with
Fabric Seat
17.3 Fourteen (14) units of Visitors Chairs for 1 ED, 1 DG and 5 Asst.
Directors
*Visitors Chair Sled Type Base Fabric Chair
17.4 Nineteen (19) workstations, chairs, mobile pedestals and meeting room
tables for Division Chiefs
Each set consist of the following:
*1 - Workstation see plans for details
*1 - Executive Chair Mesh Type with Gas Lift, Plastic Arms and Base
with Fabric Seat
*1 - Mobile Pedestal 3-drawer mobile pedestal. Powder coated finish w/
divider and pencil tray
*1 - Meeting table - 3 cm. thick round table top in cherry laminate w/ B.I.
Pipe spray painted finish
*2 - Visitors Chair Sled Type Base Fabric Chair
17.4 Sixty (60) chairs for Regular Staff
*Staff Chair Heavy Duty Gas Lift w/ Black Revolving Base. Mesh Back
Rest and Fabric Seat in Black Finish
17.5 One (1) lot Tables and Forty (40) Chairs for Main Conference Room
*Conference Table 25 mm Thick Table Top and Leg Panel, MFC Dark
Brown Finish with Steel Legs. (see plans for details)
*Executive Chair Mesh Type with Gas Lift, Plastic Arms and Base with
Fabric Seat
17.6 One (1) lot Tables and Twelve (12) Chairs for Conference Room 4
*Conference Table 25 mm Thick Table Top and Leg Panel, MFC Dark
Brown Finish with Steel Legs. (see plans for details)
63 | P a g e
*Executive Chair Mesh Type with Gas Lift, Plastic Arms and Base with
Fabric Seat
17.7 One Hundred Fourteen (114) Workstation Tables for Staff
*Workstation see plans for details
17.8 One (1) lot Monoblock Tables and Chairs for Employees Lounge/
Pantry
17.9 Fabrication of fixed cabinets on the following areas:
17.9.1 Library/ Press Room
17.9.2 Main Conference Room
17.9.3 Storage and Supply Room
17.9.4 Records Room
17.9.5 Serving Area
See Furniture Plan for more details.
END
64 | P a g e
65 | P a g e