This document provides an introduction to production planning and control. It defines key terms related to manufacturing systems, including the four main types of manufacturing processes: job shop, batch flow, assembly line, and continuous process. It also discusses plant layout approaches and how characteristics vary depending on the type of manufacturing process. The document aims to present the principles and components of different production planning and control approaches.
This document provides an introduction to production planning and control. It defines key terms related to manufacturing systems, including the four main types of manufacturing processes: job shop, batch flow, assembly line, and continuous process. It also discusses plant layout approaches and how characteristics vary depending on the type of manufacturing process. The document aims to present the principles and components of different production planning and control approaches.
Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
1
Introduction to Production Planning and Control
Assistant Professor Dr. Mahmoud Abbas Mahmoud Department of Production Engineering and Metallurgy University of Technology Baghdad - Iraq [email protected] [email protected]
1 Introduction
Wight [1] stated that manufacturing is "the goose that laid the golden egg". Production activities are the foundation of nation's economic system [2]. Production systems transfer, human, material, energy, machines, facilities, information, and technology into higher-valued products. The outputs of production systems are normally called "products". These products may be tangible goods, intangible services, or combination. Goods are tangible items that can be touched or held. Production systems that produce goods are often referred to as "manufacturing systems" and the production of goods is called "manufacturing" [3]. A schematic model of production system is shown in figure (1).
Figure (1) Schematic Model of a Production System Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
2 Production management responsibilities include bringing the inputs together under an acceptable production plan that effectively utilizes the material, capacity, and knowledge available in the production facility. Given a demand on the system, work is scheduled and controlled to produce desired products. Meanwhile control must be exercised over inventory, quality, and costs to ensure the ability of production system to compete. This article is devoted to give an introduction to the concept of manufacturing systems, the evolution of production planning systems, the main advanced production planning systems, and an extensive reading in the relevant literature. The aim of this is to present a theoretical study of the principles and components of the main production planning and control (PP&C) approaches, their concepts, their implementation requirements, in which environments they can be adopted, and experiences of the different countries in implementing them.
2 Concept of Manufacturing Systems and Key Terms
Manufacturing operations types are generally distinguished by the product range, product complexity and life time of the product being manufactured. The differences among the types of manufacturing processes have important implications on the choice of the production planning system. It is normal to distinguish four types of manufacturing processes namely; "job shop", "batch flow", "assembly line", and "continuous process" [4], [5]. In job shop a wide range of customized products are manufactured in low-volume according to costumer's wishes. In batch flow reasonably complex products from large products range are made in moderate-volume batches. In assembly line a small range of identical complex products is manufactured in high-volume usually on a production line consisting of single purpose machines. In continuous process the material flow is continuous. In this type the plant, equipments, and layout are Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
3 designed for certain product/s and the change of the product/s is difficult. Silver et al [5] summarized the characteristics of each type of these manufacturing processes as shown in Table (1). Usually, machines have to be given relatively fixed positions in the plant and there are two extreme approaches of the design of plant layout. The first one is "processoriented" or "functional" layout; machines with similar functions are grouped together. Often those functional groups are arranged into the order in which they are used in the typical product, so that a product moves in a constant direction through the plant during the production process. The second one is "product-oriented" or "cellular" layouts, where machines involved in a range of similar products are grouped together. This idea is also known as "Group Technology" (GT) [3], [6], [7]. In all approaches of plant layout, individual machines or the group of identical machines are called "work centers". Generally, Silver et al [5] summarized the previous remarks and gave some examples on the applications of each case in a graphical representation that is known as "product-process matrix". This matrix is shown in figure (2). Three main points can be noticed in this matrix. First, the authors have divided "assembly line" into "worker-paced" and "machine-paced" flow. Second, industries are arranged in a way in which the large and few number products are located in the top left corner, process industries products toward the bottom right corner, and assembly products in the middle. Third, there are some exceptions from the previous arrangement such as drugs and specialty chemicals, which are often considered as process industry products, are centrally located because they are produced in batches. Today, design, industrial, and manufacturing engineering departments are working together for the design of product. This type of cooperative effort is called "Concurrent Engineering" (CE) concept [8].
Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
4 Table (1) Characteristics of Manufacturing Process Types [5] Characteristics Type of Process/Industry Job Shop Batch Production Assembly Line Continuous Process Number of customers Many Many ,but fewer Less Few Number of products Many Fewer Fewer still Few Product differentiation Customized Less customized More standardized Standardized (commodities) Marketing characteristics Features of the product Quality and features Quality and features or availability/price Availability/price Families of items Little concern Some concern Some concern Primary concern Aggregation of data Difficult Less difficult Less difficult Easier Byproducts Few Few Few More Need for traceability Little Intermediate Little High Material requirements Difficult to predict More predictable Predictable Very predictable Control over suppliers Low Moderate High Very high Vertical integration None Very little Some backward, often forward Backward and forward Inventories - Raw materials Small Moderate Varies, frequent deliveries Large, continuous deliveries - WIP Large Moderate Small Very small - Finished goods None Varies High Very high QC Responsibility Direct labor Varies QC Specialists Process control Production information requirements High Varies Moderate Low Scheduling Uncertain, frequent changes Frequent expediting Often established in advance Inflexible, sequence dictated by technology Operations challenges Increasing labor and machine utilization, fast response, breaking bottlenecks Balancing stages, designing procedures, responding to diverse needs Rebalancing line, productivity improvement, adjusting staffing levels, morale Avoiding down time, timing, expansions, cost minimization End-of-period push for output Much Frequent Infrequent Non (can't do anything) Capital versus labor/material intensive Labor Labor and material Material and labor Capital Typical factory size Usually small Moderate Often large Large Level of automation Low Intermediate Low or high High Number of raw materials Often low Low High Low Bottlenecks Shifting frequently Shifting often, but predictable Certainly known and stationary Known and stationary Speed (units/day) Slow Moderate Fast Very fast Process flow No pattern A few dominant patterns Rigid flow pattern Clear and inflexible Type of equipment General purpose Combination of specialized and general purpose Specialized, low or high tech. Specialized, high tech. Flexibility of output Very Intermediate Relatively low (except some assemble to order) Low Run length Very short Moderate Long Very long Definition of capacity Fuzzy, often expressed in dollars Varies Clear, in terms of output rates Clear, expressed in physical terms Capacity addition Incremental Varies Chunks, requires rebalancing Monthly in chunks, requires synchronization Nature of maintenance As needed As needed, or preventive when idle As needed Shutdown Energy usage Low Low, but can be higher Low High Process changes required by new products Incremental Often incremental Incremental or radical Always radical
Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
5 Product mix
Process pattern Few of each; custom Low volume; many products High volume; several major products Very high volume; commodity Job shop (very jumbled flow) Aerospace Commercial printer Industrial machinery Apparel Machine tools Drugs, specialty chemicals Electrical and electronics
The manufacturing methods are typically specified in two documents. The first one is the "Bill of Materials" (BOM), which sets out the name and quantity of each part and subassembly that make up the finished items. The second is the "routing", which specifies the operations and machines involved in each process of the manufacturing of the product. These two documents are essential for production planning activities in any manufacturing organization. Generally, most manufacturing organizations carry out some stock of the various items used in manufacture as a buffer against variation in "supply" or "demand". Stocks of purchased materials are called "raw material inventory", stock of items assembled for convenience or efficiency reasons to partial completion, are called "components inventory" or "subassemblies inventory", and stocks of the end-items are called "finished goods inventory". These types of inventory are shown in figure (3).
Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
6
Figure (3) Types of Inventory in Manufacturing Organizations
All manufacturing organizations buy at least some inputs to their processes from other producers. Management decides the level of "vertical integration" by looking at all the processes performed between the acquisition of raw materials or outside services and the delivery of finished products. Vertical integration can be in two directions. "Backward integration" represents a firm's movement upstream toward the source of raw materials and parts. "Forward integration" means that the firm acquires more channels of distribution such as its own distribution centers "warehouses" and retail stores [9]. Typically, the manufacturing organizations have three categories of managerial planning activities whose names "strategic", "tactical", and Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
7 "operational" production planning [5], [10], [11]. Strategic planning is clearly of "long-range" scope planning decisions. It is a responsibility of top management so it is called "business planning". Tactical planning is a "medium-range" activity involving middle managements. Finally operational planning, which involves "short-range" actions, and it is normally executed by lower levels of management (factory operations managers). Long-range (business plans) are necessary to develop facilities and equipment, major suppliers, and production processes and become constraints on the medium-range plan. Medium-range is "aggregate plans" concerning with employment, aggregate inventory, utilities, facility modifications, and material- supply contracts. These aggregate plans impose constraints on the short-range production plans that follow. So short-range is "Master Production Schedules" (MPS) for producing finished goods or end items, which are used to derive production planning and control systems. These systems develop short-range production schedules of parts and assemblies, schedules of purchased materials, shop-floor schedules, and workforce schedules [7], [12]. Figure (4) gives an illustration of the planning activities.
3 From Informal to Formal Systems
Previously, in the craft system of manufacture, all work allocation and scheduling decisions were made by the foreman who was a craftsman of superior skill and experience. Finished items were normally made one at a time to be completed by a group of craftsmen under his command. At that time, the knowledge of the process of manufacturing was not clear, passed on by personal instruction, and seldom recorded. Thus operations management was "informal" and not efficiency-oriented. With the industrial revolution, which began in England in about 1760, came better documentation concepts and techniques were recorded, taught, and thus passed on to form a growing body of knowledge [13]. Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
8
Figure (4) Production Planning in Manufacturing Business Planning Aggregate Production Planning Master Production Scheduling Production Planning and Control Systems Planning Horizon
Description Long-Range (1-5 Years Horizon) Medium-Range (3-12 Months Horizon) Short-Range (1-90 Days Horizon) Top management make long-range plans for (1)facilitates- plant locations, layouts, size, and capacities; (2) major supplier plans and amount of vertical integrations; (3) processing plans- new production technology, new production processes, new system of automations.
Factory operations managers make plans for master production schedules -the quantity and timing of the production of finished goods and end items.
Factory operations managers make plans for (1) production schedules of parts and assemblies to be manufactured; (2) schedules of purchased materials; (3) shop floor schedulesmachine changeovers, batch movements; (4) workforce schedules. Middle management make plans for (1) employmentlayoffs, hiring, recalls, vacations, overtime, part-time employees; (2) inventories; (3) utilities; (4) facility modifications; (5) material- supply contractors. Phase I Phase II Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
9 In the late 19 th and early 20 th century, a number of innovations enabled a quantum leap in the scope and complexity of manufacturing creating the need for much more "formal" methods of manufacturing operations management. Although the idea of making product by the assembly of exchangeable parts has a long history, especially in the armaments industry [4], it was only achievable at a high cost for complex precision items that required in assembling complex products, such as automobiles. "Interchangeability" of parts helped enable "batch production" and ultimately "mass production" of machinery. This made necessary the much greater formality and precision in the "codification" of manufacturing processes and "parts specifications". In 1800 Eli Whitney was credited with the early popularization of interchangeable parts, which he achieved by "standardizing" parts and through effective "Quality Control" (QC), and in 1881 Frederick W. Taylor contributed to "personnel selection", "planning and scheduling", and "motion study" that led to the discipline of "method engineering" [14]. In addition to the title of "father of scientific management", Taylor is known as the father of "industrial engineering" [7]. The codification of manufacturing practices reduced the control of workers and foreman over the organization work and gave the responsibility for scheduling the manufacturing to specialized production control departments. The scientific study of the decision aspect of "operations management" began with the development of the "Economic Order Quantity" (EOQ) model by F.W. Harris in year 1915, which attempt to answer the question "How many parts to order / make at once?" [2]. The application of mathematical analysis to military logistics problems during world war II , going under the name of "Operations Research" (OR), led to the founding in peace time of the academic disciplines of "production and inventory management", and "production control", and professional societies such as the "American Production and Inventory Control Society" (APICS) [15]. Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
10 However, with the time manufacturing systems have been more complicated and their requirements growing due to the competition in businesses, hence, there has been a steady development in production planning and control activities to fulfill the needs of manufacturing organizations.
4 Computerizing
Before the computer was available companies took six to thirteen weeks to calculate their requirements of materials manually or with some help from tabulating equipments. They typically "ordered" once every thirteen weeks, this was called the "quarterly ordering system" [1]. Around the mid 1950's the availability of the electronic computers gave the hope that the problems of production planning and inventory control could be at last being solved. The earliest computer applications were aimed at recording inventory of parts and end items and to use the "Scientific Inventory Control" or "Statistical Inventory Control" (SIC), to help in the ordering decision for bought and manufactured parts using the "Reorder Point" (ROP) method. The ROP method treats all subassemblies and raw-material demand as "independent" of the end item demand, and signals the ordering of a predetermined order quantity when the stock of any item falls below a predetermined order point. The method generally results in large "Work-in- Process" (WIP) inventories [16]. When random access magnetic tape storage became available around 1960, the prospects for efficiently handling the complex "dependency" of demand implied in the bill of materials of a manufactured product, were greatly enhanced when a company has computerized its bills of materials, while components are ordered by ROP method. Bill of materials explosion is used to check their availability at order release time [17]. Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
11 Around that time a new technique was developed as a valid alternative to ROP and SIC approaches. This technique is known as "Material Requirement Planning" (MRP) [18].
5 Material Requirements Planning (Quick Overview)
Until the 1960's many manufacturing organizations used ROP method. Thus components were often ordered when not actually needed and so this method tended to result in very high inventory levels. Later on, the competitive of the products became tougher as the world moved toward the "economic war", and businesses began to realize that their future depended on developing a much better response to customer needs, manufacturers faced the challenges of improving the quality and reduce the time and cost of their products . In early 1970's the APICS lunched a high profile MRP education and promotional program called "MRP crusade" [19], [20]. The researchers in the field of planning realized the needs of manufacturing organizations for more efficient system for planning and control of stock to be able to compete in the market, thus MRP was developed, and within twenty years MRP technique has been changing dramatically in a stepwise progression toward "Manufacturing Resource Planning" (MRP II). The main steps in the development of MRP were:- 1. A better ordering method. 2. Priority planning. 3. Closed-loop MRP. 4. Manufacturing Resource Planning MRP II.
However, MRP II implementation is classified into four categories "ABCD classification", which has become widely used. Class "D" implementation is the lowest level of implementation and class "A" Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
12 implementation means that MRP II is running the entire activities of the business. In the 1990's, the new innovation "Enterprise Resource Planning" (ERP), which can be considered as direct extension of MRP II was coined to describe the latest development in resource planning. Nowadays, a new generation of ERP system, going under the name of (ERP II), is established [21]. The development of MRP-type systems and their functionality evolutions can be illustrated as in figure (5).
Figure (5) Development of MRP-type Systems and Their Functionality Evolutions
During the 1980's MRP faced competitions from the other "Computer Aided Production Management" (CAPM) systems, mainly the "Optimized Production Technology" (OPT), as well as the J apanese "Just-in-Time" (J IT) philosophy. Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
13 6 Optimized Production Technology
Optimized Production Technology (OPT) is a computerized production planning and scheduling tool developed by Creative Output of Milford, Connecticut, USA [22]. OPT realized that a detailed schedule and detailed shop floor feedback where only required for the "bottleneck" processes and that "non- bottleneck" processes can and should be slaved to these. Furthermore, OPT follows a set of principles called the "Theory of Constraints" (TOC) [5]. This theory is focusing attention on the capacity constraints or bottleneck parts of the operation. By identifying the location of constraints, working to remove them, then looking for next constraints an operation always focusing on the part that critically determine the pace of output [23]. A constraint is defined as anything that prevents a system from achieving high performance relative to its goal.
6.1 The Base Rules of OPT
OPT is based on a set of ten related rules*, which principally focus on managing bottleneck and non-bottleneck resources. The ten rules are as follows [23], [5]:- 1. Utilization and activation of a resource are not synonymous. There is no gain from running a non bottleneck machine if its output will only build up inventory in front of a bottleneck. 2. The level of utilization of a non-bottleneck is not determined by its own potential, but by some other constraint in the system. The utilization of a non-bottleneck is limited by the rate of the bottleneck machine.
. * They are nine rules according to Vonderembse and White [10]; Waller [22]; Vollmann et al [24]; and Shafer and Meredith [25], the 10 th rule is embedded in the 9 th rule. Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
14 3. An hour lost at the bottleneck is an hour lost for the total system. This rule parallels and extends rule number 1, and helps managers focus on all activities at the bottleneck. 4. An hour saved at a non-bottleneck is a mirage. Throughput will not increase with savings at a non-bottleneck. Therefore, managers should focus improvement efforts elsewhere. The time spent by a job at a bottleneck is compared of set-up and processing time, while the time spent at a non-bottleneck includes set-up, processing, and idle time. Reducing the set-up time at a bottleneck saves time for the entire system. But, reducing set-up time at a non-bottleneck may increase idle time. 5. The bottleneck governs the throughput and inventory in the system. Inventory should be used carefully so that the bottleneck is never face a lack of parts to process. 6. The transfer batch size should not necessarily equal the production batch size. When a large batch being run on a non-bottleneck just prior to a bottleneck then it would be desirable to get it started on part of the batch (This part called "transfer batch"), even through the non- bottleneck is still processing the reminder. The use of different sized transfer batches is called "lot streaming". 7. The production batch size should not be the same from stage to stage in the process. Lot sizes at bottlenecks should, in general, be larger than at non-bottleneck, so that less time is lost to set-ups. Of course, the small batches from the non-bottleneck need to arrive at the bottleneck in the time to be rejoined into a large batch. 8. Capacity and priority should be considered simultaneously. Because the lead time for a given batch depends on the priority given to it at a machine, and on the capacity of the machine, priority rules should be determined in conjunction with the capacity of the machine. In fact, the capacities at all constrained resources should be considered. Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
15 9. Balance flow, not capacity. The flow through the plant should equal market demand. 10. The sum of local optima is not equal to the optimum of the whole. Problems develop when supervisors at bottleneck, supervisors at non- bottlenecks, and marketing personnel all optimize for their own goals. Many supervisors try to run their equipment at full capacity, while many marketing personnel try to make bigger profits by selling more at the end of the quarter.
6.2 The Mechanism of OPT
No doubt, that the available information in the literature about the working mechanism of the OPT is very limited, but OPT produce production plans and detailed schedules using the following four basic modules [26]:- 1. Buildnet: This module creates a model of the manufacturing facility using data on work center capabilities, routings, Bill of Materials, inventories, and sales forecasts. This model is in the form of network. 2. Serve: The model of the workshop is run through an iterative process to determine bottlenecks in the system. Serve is similar to MRP in its workings, and one of its outputs is a load profile for each of the resources in the model. The most heavily utilized resource could produce a bottleneck in the system and must be examined carefully. Some times, rescheduling work from the heavily utilized machine to some other alternate to machine may produce satisfactory results. 3. Split: The network model of the shop floor is divided into two parts: critical resources and non-critical resources. The bottleneck operation and all other operations follow it in the order of manufacturing process up to the customer orders are included in the critical resources portion of the network. The remaining portion of the network includes non- critical resources. Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
16 4. Brain: The operations in the critical resource portion of the network are scheduled using module called the Brain of OPT. This module determines production and transfer lot sizes and the timing of production for each product for the bottleneck operations. Its output is fed to serve module, which then produces the entire production plan.
6.3 Weaknesses of OPT
Although, OPT attempts to overcome the weakness of the early MRP systems of taking no account of the finiteness of shop floor capacity, but practically OPT also have its own disadvantages. The main disadvantage of OPT is the concept of shifting bottlenecks. When the production volume and the mix of products are known, we can find out the bottlenecks in a system. But practically, the "aggregate planning" exercise is done at least over several months and the volume of the mix may change from one week to another. Different volumes or mixes can lead to different bottlenecks when that happen, this means that the bottleneck is shifting. It is not clear how OPT handle this dynamic situation because it relies on a clearly identified stationary bottleneck. From other side, OPT focuses on bottleneck machines and ignores others during the planning horizon. Thus, OPT provides a plan for a production system that approximates the actual production system. In order for an OPT plan to work, it is necessary to have plenty of non-bottleneck resources. When the cost of non-bottleneck resources are not small, the OPT plan may have a high cost. This restricts the usefulness of OPT for cases when non-bottleneck resources are expensive. The other weakness of OPT is that many researchers and practitioners alike have complained that the OPT software was a "black box", because its details were never published [5]. Obviously, OPT is truly difficult to understand, and in general it is not for novice [24].
Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
17 7 Just-in-Time
J ust-in-Time (J IT) approach was developed for the first time at the "Toyota Motor Company" of J apan by Taiichi Ohno and others in mid 1970's [27]. J IT is used referring to a production system in which both the movement of goods during the production and deliveries from suppliers are carefully timed so that at each step of the process the next batch arrives for processing just as the preceding batch is completed, thus the name "Just-in-time" basically means to produce the necessary units in the necessary quantities at the necessary time. So that the production of one extra piece is just as had as being one piece short. The ambition is to be able to produce a product down to one unit at a time [28], such system requires a right schedule and frequent set-ups of machines. Small quantities of everything must be produced several times a day. The system must run smoothly because any shortage has an almost immediate impact on the entire system. Obviously, J IT is a philosophy of management extending from suppliers through production to distribution systems. Hence, J IT cannot be reduced to a "formula"; every firm may apply the philosophy differently [25].
7.1 The Goals of JIT
The ultimate goal of J IT is a balanced, smooth and rapid flow of materials through the system. This can be achieved by approaching the following supporting goals first [12]. 1. Eliminate disruptions. 2. Make the system flexible. 3. Reduce set-up times and lead times. 4. Minimize inventories. 5. Eliminate waste.
Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
18 These requirements need planning with an extensive degree of accuracy and ultimate degrees of discipline in all of the facets of the production system, as it will be explained later on.
7.2 JIT and Kanban System
The term "kanban" has sometimes been used as equivalent to J IT, which certainly is not the truth. Kanban is the associated manual information and controlling system, to J IT philosophy. Kanban is a J apanese word for "card". They often use cards to signal the need for more material, hence the name kanban. The system has been modified in many facilities so that, even though it is called a kanban, the card does not exist. In some cases, an empty position on the floor is an indication that the next lot is needed, in other cases, some sort of signal, such as flag or rag is used to signify that it is time for the next batch. Figure (6) shows two of these facilities. The idea behind the kanban system is to authorize material for production only if there is a need for them. Through the use of this system, production is "pulled" through the production system; instead of "pushed" out before if is needed and then stored. In general, kanban system works in the way that, two cards are used; a "withdrawal kanban" and a "production kanban". These cards are very simple, showing only the part number and name, the work centers involved, storage location, and the container capacity. The approach is illustrated in figure (7). For example, assuming that work flows from work center number one (WC1) to WC2, and containers are used to transport the output from WC1 to WC2, where they are used as inputs. When WC2 sees that it will need more input parts, it takes an empty container and a withdrawal kanban back to WC1. There it leaves the empty container and locates a full one, which has a production kanban with it. WC2 replaces the production kanban with its withdrawal kanban, which authorizes it to remove the full container and the Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
19 withdrawal kanban. It puts the production kanban in a rack at WC1, thereby authorizing the production of another container of parts. Back at WC2, the withdrawal kanban is placed back in its rack. WC1 cannot initiate production and fill an empty container until it has a production kanban authorizing additional production. Thus, withdrawal kanban authorize the acquisition of additional material from a supplying work center and production kanban authorize a work center to make additional product.
(a)
(b) Figure (6) Two Facilities Used As a Signal in Kanban System[11] (a) The signal is an empty position on the floor. (b) The signal is a flag or marker.
Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
20
Figure (7) Kanban Process [25]
Although, the main advantage of kanban system is its simplicity but, it is not appropriate in many manufacturing environments and cannot be applicable without preparing several requirements.
7.3 The Requirements of JIT
In relevant literature such as; [3], [5], [7], [8], [12], [22], [29], [30], authors mention several conditions and supporting techniques which must first exist or to be developed to make J IT and kanban truly effective, these can be summarized in the following:- 1. Multi-skilled work force. Multi-skilled workers provide flexibility in scheduling because they are able to meet differing production demands by moving to different work centers as needed. This can be achieved only by "cross training" of workers in several production areas. Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
21 2. Customer-supplier cooperation, sole sourcing, and long term commitments. Suppliers must be able to make reliable, on time delivery of consistently good quality products and still remain flexible. To achieve this, customers and suppliers must work closely together. 3. Employee motivation and "mutual trust" between the workers and the management. J IT implementations include a strong degree of worker participation because new and heavy responsibilities are put on them. Practically, J IT requires a full "loyalty" of the workers and "with JIT, plant employs workers hearts and minds, not just their backs". 4. Extremely high levels of quality. To ensure that production will not be interrupted due to parts with poor quality. One technique to achieve high levels of quality is called "poka-yoke", which means foolproof operations. In J IT environments employees are acting as their own quality inspectors through "quality circles". Furthermore, at some J apanese plants, workers communicate with flashing lights; a system called "andon" is used to indicate when a quality problem occurs in order to stop the production line. This activity is called "quality at source". 5. Highly reliable equipments. To ensure that the system is not forced to shutdown while repair is made, one way to achieve the high levels of equipments quality is through "Total productive Maintenance" (TPM). This can be achieved by training machine operators to perform some of their own maintenance, especially preventive maintenance. By so doing, maintenance specialists can then be freed to develop higher- order skills for improved maintenance systems. 6. Well organized workplaces. In J IT environments workplaces should be well organized so the tools should be stored neatly in designated place, materials arranged neatly, and aisles kept clear of clutters. The workers should follow these activities as habit and these are done through what is called "housekeeping". Housekeeping is based on five rules which Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
22 are often referred to as the (5S) process which originated from the five J apanese words seiri (sort), seiton (straighten), seiso (sweep), seiketsu (standardize), and shitsuke (self-discipline). Housekeeping not only creates a more attractive and pleasant work atmosphere, but also improves workers morale, reduces maintenance requirements, and reduces accidents that can injure employees or damage machines. 7. Small batch sizes and low set-up times. Small batch sizes reduce average cycle stock, and provide faster feed back on quality problem. Although small batches are beneficial to operations, they have the disadvantages of increased set-up frequency. Hence, set-up times must be reduced to realize the benefits of small batch size production. In some firms, eight hour set-up times have been decreased to less than ten minutes. The goal of set-ups under ten minutes has been called "Single Minute Exchange of Dies" (SMED). 8. Group technology and manufacturing cells. Group technology clusters dissimilar machines into manufacturing cells for processing a given part or a family of similar parts having similar processing requirements. One multi-skilled operator may run several machines, which eliminate the move and queue time between operations in a given cell. Group technology is used to physically link and overlap as many operations as possible. Equipments are placed very close to each other similar to an assembly line. 9. A stable master production schedule (MPS). At Toyota, the MPS is frozen for the first month, and the entire MPS covers one year. The production schedule is exactly the same for each day of the month. This means that the same products are produced in the same quantities in the same sequence every day in the month. This will be explained in the next section. 10. High-volume, repetitive manufacturing, because this type of manufacturing is likely to be conductive to the previous requirements. Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
23 7.4 Leveled Scheduling and Mixed Modeling in JIT Environment
As noted, J IT requires high-volume, repetitive manufacturing with stable or leveled production schedule. "Heijunka" is the J apanese word for leveled scheduling so that the mix and volume of production are even over time [30]. The principle of leveled scheduling can be taken further to given mixed modeling. Hence, mixed modeling is a matter of even production in which items are produced smoothly throughout the day rather than in large batches of one item, followed by long time set-ups for producing another large batch of another item. Leveled scheduling and mixed model can be illustrated with an example. Assume three products are being produced in a plant with the following demands; every two weeks (ten working days), 500 units of product A, 400 units of product B, and 200 units of product C are required. Master production schedule for the products can be devised here, in different ways. First, the conventional approach would be to produce, in large batches, all of the requirements for each product for the two weeks. This scheduling is as shown in table (2), where all requirements of a product are produced, before changing over to start production of another product.
Table (2) Master Production Schedule (Conventional Approach) Product Day Total 1 2 3 4 5 6 7 8 9 10 A 250 250 500 B 100 100 100 100 400 C 50 50 50 50 200
The other option uses leveled scheduling, producing a mix of products in smaller lots. Because there are 1,100 units required every ten days, 110 must be made each day, on average. This reduces to 50 of A, 40 of B, and 20 of C each day. Hence, leveled scheduling will be as shown in table (3).
Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
Obviously, the principle of leveled scheduling is straightforward but the requirements to put it into practice are quite severe [30]. Now it can be noticed that the production requirements are in the ratio of; 5 of A, to 4 of B, to 2 of C, found by dividing the products production requirements by the greatest common devisor, or 10. Therefore, since J IT production strives for batch size of just one unit, so the planner could develop a production cycle consisting of eleven units; 5 of A, 4 of B, 2 of C. One possible production cycle would be to produce the three products in small batches using a sequence such as (A-A-A-A-A-B-B-B-B-C-C). Alternatively, to smooth the production of the eleven units throughout the production cycle, a sequence such as (C-A-B-A-B-C-A-B-A-B-A) might be used. It is clear that numerous other sequences are also possible. Simply, this cycle would repeat ten times each day. For this reason set-up times must be extremely reduced. It is clear that a schedule such as this is rate- based rather than batch.
7.5 JIT Implementation
Practically, J IT implementation is a very difficult task and it is a long time mission, "Toyota took more than twenty years to implement J IT" [3], [5]. Thus, the managers of any organization must understand that to achieve the "ultimate goal" of J IT; the manufacturing system must achieve the "supporting goals" Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
25 first. The later cannot be achieved without preparing the four key "building blocks" and their elements, which are shown in figure (8).
Figure (8) J IT Goals and Building Blocks [12]
References
[1]. Wight, O., "MRP II: Unlocking America's Productivity Potential" Oliver Wight Limited Publications Inc., 1983. [2]. Monks, J .G., "Operations Management; Theory and Problems" McGraw- Hill International Editions, 1987. [3]. Martinich, J .S., "Production and Operations Management: An Applied Modern Approach" J ohn Wiley and Sons Inc., 1997. Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
26 [4]. Hopp, W.J ., and Spearman, M.L., "Factory Physics: Foundations of Manufacturing Management" McGraw-Hill Inc., 2001. [5]. Silver, E.A., Pyke, D.F., and Peterson, R., "Inventory Management and Production Planning and Scheduling" J ohn Willy and Sons Inc., 1998. [6]. McLeavey, D.W., and Narasimhan, S.L., "Production Planning and Inventory Control" Allyn and Bacon Inc., 1985. [7]. Gaither, N., and Fraizer, G., "Operations Management" South-Western Thomson Learning, 2002. [8]. Bedworth, D.D., Henderson, M.R., and Wolfe, P.M., "Computer Integrated Design and Manufacturing" McGraw-Hill Inc., 1991. [9]. Krajewski, L.J , and Ritzman, L.P., "Operations Management; Processes and Value Chains" Pearson Prentice Hall, 2005. [10]. Vonderembse, M.A., and White, G.P., "Operations Management: Concepts, Methods, and Strategies" West Publishing Company, 1988. [11]. Heizer, J ., and Render, B., "Production and Operations Management: Strategic and Tactical Decisions" Prentice Hall, 1996. [12]. Stevenson, W.J ., "Production /Operations Management" Irwin /McGraw- Hill, 1999. [13]. Knod, E.M., and Schonberger, R.J ., "Operations Management: Meeting Customers Demands" McGraw-Hill/Irwin, 2001. [14]. Heizer, J ., and Render, B., "Operations Management" Prentice Hall, 2001. [15]. Newell, S., Swan, j., and Clark, P., "The Importance of User Design in the Adoption of New Information Technologies: The Example of Production and Inventory Control Systems (PICS)" International J ournal of operations and Production Management, Vol. 13, No. 2, PP. 4-22, 1993. [16]. Orlicky, J ., "Material Requirements Planning" McGraw-Hill Inc., 1975. [17]. Schonberger, R.J ., "The ROP Shortage List System" Production and Inventory Management, Vol. 21, No. 3, PP. 106-107, 1980. [18]. More, S.M., "MRP and the Least Total Cost Method of Lot-Sizing" Production and Inventory Management, Vol. 15, No.2, PP. 47-55, 1974. Introduction to Production Planning and Control Dr. Mahmoud Abbas Mahmoud
27 [19]. Browne, J ., Harden, J ., and Shivnan, J ., "Production Management System: An Integrated Perspective" Addison Wesley, 1996. [20]. Spearman, M.L., "To Pull or not to Pull: What is the Question? Part II: Making Lean Work in Your Plant" Factory Physics, Inc., (http://www.factoryphysics.net), 2002. [21]. Andreu, R., Sieber, S., and Valor, J ., "Introduction to ERP" IESE Business School. University of Navarra, Spain, (http://www.ises.edu/en/home.asp), 2003. [22]. Waller, D.L., "Operations Management: A Supply Chain Approach" International Thomson Business Press, 1999. [23]. Slack, N., Chambers, S., Harland, C. Harrisson, A., and J ohnston, R., "Operations Management" Pitman Publishing, 1998. [24]. Vollmann, T.E., Berry, W.L., and Whybark, D.C., "Manufacturing Planning and Control Systems" Richard D. Irwin Inc., 1988. [25]. Shafer, S.M., and Meredith, J .R., "Operations Management: A Process Approach with Spreadsheets" J ohn Wiley and Sons Inc., 1998. [26]. Buffa, E.S., and Sarin, R.K., "Modern Production/Operation Management" J ohn Willy and Sons Inc., 1987. [27]. Spearman, M.L., "To Pull or not to Pull: What is the Question? Part I: what is Lean?" Factory Physics, Inc., (http://www.factoryphysics.net), 2002. [28]. J ohnasson, L., and Soderberg, K., "MPC Systems and Small Companies" M.Sc. Thesis Submitted to "Vaxjo University" Sweden, 1999. [29]. Askin, R.G. and Goldberg, J .B., "Design and Analysis of Lean Production System" J ohn Wiley and Sons Inc., 2002. [30]. Slack, N., Chambers, S., and J ohnston, R., "Operations Management" Prentice Hall, 2004.