Critical Path Method
Critical Path Method
The critical path method (CPM) is an algorithm for scheduling a set of project activities.
History
The critical path method (CPM) is a project modeling technique developed in the late 1950s
by Morgan R. Walker of DuPontand James E. Kelley, Jr. of Remington Rand. Kelley and
Walker related their memories of the development of CPM in 1989. Kelley attributed the term
"critical path" to the developers of the Program Evaluation and Review Technique which was
developed at about the same time by Booz Allen Hamilton and the U.S. Navy. The
precursors of what came to be known as Critical Path were developed and put into practice
by DuPont between 1940 and 1943 and contributed to the success of the Manhattan Project.
CPM is commonly used with all forms of projects, including construction, aerospace and
defense, software development, research projects, product development, engineering, and
plant maintenance, among others. Any project with interdependent activities can apply this
method of mathematical analysis. Although the original CPM program and approach is no
longer used, the term is generally applied to any approach used to analyze a project network
logic diagram.
Basic technique
he essential technique for using CPM is to construct a model of the project that includes the
following:
1. A list of all activities required to complete the project (typically categorized within
a work breakdown structure),
2. The time (duration) that each activity will take to complete,
3. The dependencies between the activities and,
4. Logical end points such as milestones or deliverable items.
Using these values, CPM calculates the longest path of planned activities to logical end
points or to the end of the project, and the earliest and latest that each activity can start and
finish without making the project longer. This process determines which activities are
"critical" (i.e., on the longest path) and which have "total float" (i.e., can be delayed without
making the project longer). In project management, a critical path is the sequence of project
network activities which add up to the longest overall duration. This determines the shortest
time possible to complete the project. Any delay of an activity on the critical path directly
impacts the planned project completion date (i.e. there is no float on the critical path). A
project can have several, parallel, near critical paths. An additional parallel path through the
network with the total durations shorter than the critical path is called a sub-critical or non-
critical path.
CPM analysis tools allow a user to select a logical end point in a project and quickly identify
its longest series of dependent activities (its longest path). These tools can display the critical
path (and near critical path activities if desired) as a cascading waterfall that flows from the
project's start (or current status date) to the selected logical end point.
Although the activity-on-arrow diagram ("PERT Chart") is still used in a few places, it has
generally been superseded by the activity-on-node diagram, where each activity is shown as
a box or node and the arrows represent the logical relationships going from predecessor to
successor as shown here in the "Activity-on-node diagram".
Activity-on-node diagram showing critical path schedule, along with total float and critical path drag
computations
In this diagram, Activities A, B, C, D, and E comprise the critical or longest path, while
Activities F, G, and H are off the critical path with floats of 15 days, 5 days, and 20 days
respectively. Whereas activities that are off the critical path have float and are therefore not
delaying completion of the project, those on the critical path will usually have critical path
drag, i.e., they delay project completion. The drag of a critical path activity can be computed
using the following formula:
1. If a critical path activity has nothing in parallel, its drag is equal to its duration. Thus A
and E have drags of 10 days and 20 days respectively.
2. If a critical path activity has another activity in parallel, its drag is equal to whichever
is less: its duration or the total float of the parallel activity with the least total float.
Thus since B and C are both parallel to F (float of 15) and H (float of 20), B has a
duration of 20 and drag of 15 (equal to F's float), while C has a duration of only 5
days and thus drag of only 5. Activity D, with a duration of 10 days, is parallel to G
(float of 5) and H (float of 20) and therefore its drag is equal to 5, the float of G.
These results, including the drag computations, allow managers to prioritize activities for the
effective management of project completion, and to shorten the planned critical path of a
project by pruning critical path activities, by "fast tracking" (i.e., performing more activities in
parallel), and/or by "crashing the critical path" (i.e., shortening the durations of critical path
activities by adding resources).
Crash duration
"Crash duration" is a term referring to the shortest possible time for which an activity can be
scheduled. It is achieved by shifting more resources towards the completion of that activity,
resulting in decreased time spent and often a reduced quality of work, as the premium is set
on speed. Crash duration is typically modeled as a linear relationship between cost and
activity duration, however in many cases a convex function or a step function is more
applicable.
Expansion
Originally, the critical path method considered only logical dependencies between terminal
elements. Since then, it has been expanded to allow for the inclusion of resources related to
each activity, through processes called activity-based resource assignments and resource
leveling. A resource-leveled schedule may include delays due to resource bottlenecks (i.e.,
unavailability of a resource at the required time), and may cause a previously shorter path to
become the longest or most "resource critical" path. A related concept is called the critical
chain, which attempts to protect activity and project durations from unforeseen delays due to
resource constraints.
Since project schedules change on a regular basis, CPM allows continuous monitoring of the
schedule, which allows the project manager to track the critical activities, and alerts the
project manager to the possibility that non-critical activities may be delayed beyond their total
float, thus creating a new critical path and delaying project completion. In addition, the
method can easily incorporate the concepts of stochastic predictions, using the program
evaluation and review technique (PERT) and event chain methodology.
Currently, there are several software solutions available in industry that use the CPM method
of scheduling, see list of project management software. The method currently used by most
project management software is based on a manual calculation approach developed by
Fondahl of Stanford University.
Flexibility
A schedule generated using critical path techniques often is not realised precisely, as
estimations are used to calculate times: if one mistake is made, the results of the analysis
may change. This could cause an upset in the implementation of a project if the estimates
are blindly believed, and if changes are not addressed promptly. However, the structure of
critical path analysis is such that the variance from the original schedule caused by any
change can be measured, and its impact either ameliorated or adjusted for. Indeed, an
important element of project postmortem analysis is the As Built Critical Path (ABCP), which
analyzes the specific causes and impacts of changes between the planned schedule and
eventual schedule as actually implemented.