0% found this document useful (0 votes)
406 views1 page

Profit & Loss Report - Relocation of Services (Provisional Sum)

This document provides a budget for the relocation of various services during road upgrading works in Muar, Johor, Malaysia. It includes provisional sums of RM50,000 for relocating sewer pipes, RM50,000 for supporting relocated services, RM200,000 for relocating TNB electricity services, RM200,000 for relocating water pipes, and RM50,000 for relocating telecommunications services. The total budget allocated for relocating all services is RM550,000.

Uploaded by

Faiz Ahmad
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
406 views1 page

Profit & Loss Report - Relocation of Services (Provisional Sum)

This document provides a budget for the relocation of various services during road upgrading works in Muar, Johor, Malaysia. It includes provisional sums of RM50,000 for relocating sewer pipes, RM50,000 for supporting relocated services, RM200,000 for relocating TNB electricity services, RM200,000 for relocating water pipes, and RM50,000 for relocating telecommunications services. The total budget allocated for relocating all services is RM550,000.

Uploaded by

Faiz Ahmad
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

BUDGET OVERALL

ACCENTAGE SDN BHD


CADANGAN MENAIKTARAF JALAN KESANG TASEK, MUAR, JOHOR
NO KONTRAK - JKR/NEG/J/10/2002
BILL NO. 7 - RELOCATION OF SERVICES

RATIONALIZED RATE BUDGET


ITEM DESCRIPTION QTY UNIT RATE AMOUNT (RM) RATE AMOUNT (RM) PROFIT (RM)
Labour Material Machinery Total Labour Material Machinery Total

ALL QUANTITIES ARE PROVISIONAL

7.1 WORK BY STMB

7.1.1 Allow a provisional sum for relocation of all STM services


laying of cable, manhole, erection of STM poels, testing,
commissioning and reconnection to properties 1 P.S - 50,000.00 - 50,000.00 50,000.00 - 50,000.00 - 50,000.00 50,000.00 -

7.2 WORK BY TNB

7.2.1 Allow a provisional sum for relocation of all TNB services


laying of cable (underground or overhead), erection of poles,

testing and commissioning and reconnection to existing mains


properties. 1 P.S - 200,000.00 - 200,000.00 200,000.00 - 200,000.00 - 200,000.00 200,000.00 -

7.3 WORK BY SAJH

7.3.1 Allow a provisional sum for relocation of all JBA water pipes and
other services including laying of new pipes, testing,
commissioning and reconnection to existing mains and properties 1 P.S - 200,000.00 - 200,000.00 200,000.00 - 200,000.00 - 200,000.00 200,000.00 -

7.4 SEWER PIPE

7.4.1 Allow a provisional sum for relocation for sewer pipe including

manhole, laying of sewer pipe, jointing and other related works. 1 P.S - 50,000.00 - 50,000.00 50,000.00 - 50,000.00 - 50,000.00 50,000.00 -

7.5 Supporting & Housing Box Girder System for Relocated


Existing Services Including Water Pipes, Stm, TNB
Supply Cable & Other Services Existing Services
Including Water Pipes, Stm, TNB Supply Cable & Other
Services

7.5.1 To supply and construct a complete support and housing Box


Girder System for all the existing relocated services including all
M.S component, fastening, mounting, welding, painting, R.C pier
support and other necessary items leading to its complete system
1 P.S - 50,000.00 - 50,000.00 50,000.00 - 50,000.00 - 50,000.00 50,000.00 -

TOTAL CARRIED OF BILL NO.7 TO FINAL SUMMARY 550,000.00 550,000.00 -

RELOCATIONOFSERVICES - Budget Overall 1/1

You might also like