The document describes a project to install a LAB (linear alkylbenzene) plant. The plant will convert paraffins to olefins using a PACOL (paraffin conversion to olefin) unit and then alkylate benzene with the olefins using an HF (hydrofluoric acid) alkylation unit. Key units include a paraffin pretreatment system, PACOL reactor, HF alkylation reactor, and storage tanks. The plant aims to produce LAB, which is used to make detergents, from raw materials like paraffins, benzene, and catalysts like palladium and hydrofluoric acid.
The document describes a project to install a LAB (linear alkylbenzene) plant. The plant will convert paraffins to olefins using a PACOL (paraffin conversion to olefin) unit and then alkylate benzene with the olefins using an HF (hydrofluoric acid) alkylation unit. Key units include a paraffin pretreatment system, PACOL reactor, HF alkylation reactor, and storage tanks. The plant aims to produce LAB, which is used to make detergents, from raw materials like paraffins, benzene, and catalysts like palladium and hydrofluoric acid.
LAB project Environmental Impact Assessment March 2002
Section 3: Project description 1 of 42
SECTION 3
PROJECT DESCRIPTION LAB project Environmental Impact Assessment March 2002 Section 3: Project description 2 of 42
Section Summary
3.1 SITE LOCATION 4 3.2 PLANT DESCRIPTION 5 3.2.1 PLANT HISTORY 5 3.2.2 PROCESS DESCRIPTION 6 3.2.2.1 Paraffin Conversion to Olefin (PACOL) 7 3.2.2.2 Linear Detergent Alkylate Process (LAB) 9 3.2.2.3 Treatment of Gases 10 3.2.2.4 Treatment of Liquids 12 3.2.2.5 Treatment of Wastes 13 3.2.3 PLANT UNITS DESCRIPTION 13 3.2.3.1 Process Units Installed in the Process Area 14 3.2.3.2 Facilities installed outside the Process Area 15 3.3.3 MATERIALS, SUBSTANCES AND RESOURCES INPUT / OUTPUT 19 3.3.3.1 Raw materials and resources input 19 3.3.3.2 Products output 21 3.3.4 Emissions to the environment and resources use 22 3.3.4.1 Emissions 22 3.3.4.1 Resources use 27 3.4 YARD PHASE 29 3.5 PROJECT RELIABILITY AND SAFETY SYSTEMS 30 3.6 SAFETY CRITERIA AND SAFETY MEASURES ADOPTED IN ORDER TO PREVENT INCIDENTS 34 3.7 PLANT MAINTENANCE AND AVAILABILITY 37 3.8 ADVERSE IMPACTS PREVENTION AND MITIGATION AND MEASURES 38 LAB project Environmental Impact Assessment March 2002 Section 3: Project description 3 of 42
ANNEXES TO SECTION 3 III.1 Block diagrams III.2 General lay-out III.3 Material Safety Data Sheets III.4 General lay-out with air emission sources localization III.5 General lay-out with waste water sewerage III.6 HAZOP Analysis Report
LAB project Environmental Impact Assessment March 2002 Section 3: Project description 4 of 42
3.1 Site location LAB site is located in South-West part of Syria, about 25 km south of Damascus (see figures 4.1, 4.3), not very far from political borders with Lebanon (about 50 km North- West), Israel (about 70 km West), Jordan (about 80-90 km South). It has a coastline of about 183 km in length. LAB site is located in the Province of Damascus Countryside, in the territory pertaining to the Municipality of Deir Ali village, which is also the principal inhabited centre near the site. The area is a plain upland one, about 700m above sea level, with rocky desert features. An important road, the highway connecting Damascus to Daraa (near Jordan border) is present at a minimum distance of about 400 m from LAB site. For more detail about territorial context and environmental component status refer to sec.4. LAB project Environmental Impact Assessment March 2002 Section 3: Project description 5 of 42
3.2 Plant description
3.2.1 Plant history The Proponent has purchased an existing LAB plant in Yambol City (Bulgaria) in order to have it dismantled, reconditioned and re-assembled in Syria. The Plant, described more in detail in the following, includes the process units and the relevant facilities. The Plants process units basic design and license were provided by UOP, while the detailed engineering was originally made in Bulgaria where the previous LAB project was done. The main equipment, machinery, instrumentation, accessories were originally manufactured / sourced in Bulgaria and Western Europe. The Bulgaria plant construction started in 1984 but was never brought to completion, as works were stopped in 1991 and the plant was therefore never put into operation. During the dismantling activities, performed between 2000 and 2001, an UOP survey has been carried out to assess the general conditions of the Bulgarian Plants equipment (mainly vessel, columns and heat exchangers). The original Bulgarian Plants engineering documentation, was completely re-ordered, checked and classified. All available process area, basic & detail engineering documentation, equipment drawings, have been collected to the Site from Ballestra offices, properly packed and marked by Ballestra. Ballestra has provided the Basic design engineering documents for off sites units (tank farm and utilities units), which includes the following documents: P&I drawings, equipment specifications, instrument specifications, lay out. The detail engineering documents for off sites units (utilities and tank farm units) have been provided by two third Companies. INCO, a Turkish engineering company, provided piping and structures detailed documents, while ELTECH, an Italian one, provided all the electric and instruments specifications and diagrams. The construction drawings of the new equipment has been provided directly by the relevant constructors. During the re-erection works Ballestra is supervising all the activities: a dedicated Ballestra Site Manager is continuously present at Site in order to give instructions LAB project Environmental Impact Assessment March 2002 Section 3: Project description 6 of 42
when necessary, to assist and to report to the Project Manager, issue the project status reports and to collect all information to all parties in this project.
3.2.2 Process description The HF Detergent Alkylation Process is a catalytic process to alkylate benzene with linear olefins to form linear alkylbenzene. The linear alkylbenzenes produced from the C 10 -C 13 linear olefins are useful detergent intermediates and can be readily sulfonated to yield linear alkylbenzene sulfonates. These compounds constitute the active ingredients of many household detergents. The process is based on two main reactions: paraffin dehydrogenation and conversion to olefins (PACOL) benzene alkylation with linear olefins, in order to obtain Linear Alkyl Benzene (LAB). The principal raw materials are paraffins and benzene, the principal product is Linear Alkyl Benzene. By-products are light gases (hydrogen, light hydrocarbons), alkylate polymers and heavy alkylates. Catalysts are used in both reactions: Palladium on Alumina pellets in Pacol unit and Hydrofluoric Acid in the Alkylation unit. The following flow diagram (Fig.3.1, see also Annex III.1) shows main process blocks: - Paraffin pre-treatment (Oxygen stripping unit) - Paraffin conversion to olefins (PACOL unit) - Benzene alkylation with linear olefins (HF alkylation unit) - Raw materials, products and by-products storage (Tank farm) In order to provide heat for reagents (to reach reaction temperature) and for vapor production in the distillation columns, a Hot oil unit and a specific charge heater in Pacol unit are present. Fuel oil is the main fuel, but also a low quantity of process by products from PACOL unit (light ends) and from Lab unit (heavy polymers) are burnt. In the following sections process and plant units are described in more detail. . Fig. 3.1: Global Block Diagram 4175 n-paraffins C10 - C13 175 4175 n-Paraffins Light-end from PACOL Light ends 50 Recycle n-paraffins Hydrogen n-paraffins + 125 1675 n-olefins Benzene 35150 75 Alkyl. Polymers LAB 5000 Heavy alkylates 425 Hot oil unit Raw material & products storage Tank Farm Paraffin dehydrogenation Pacol unit Oxygen stripper unit 31325 Olefins alkylation HF alkylation unit = Flowrate (kg/h) AHMAD DAABOUL & SONS Co. FOR DETERGENTS LAB project -- Environmental Impact Assessment Section 3: Project description March 2002 Figure Ballestra P : \ \ 0 1 5 0 9 i \ f i g u r e \ p r o g e t t u a l e . c d r LAB project Environmental Impact Assessment March 2002 Section 3: Project description 7 of 42
3.2.2.1 Paraffin Conversion to Olefin (PACOL) Introduction The UOP Pacol Process (paraffin conversion to olefins) is very similar in flow scheme and process equipment to many other hydrogen recycle reaction systems which utilize a fixed catalyst bed (like platforming). In the next figure PACOL flow diagram is shown. Feed Section The feed to the Pacol process unit consists of both fresh and recycle paraffin streams. The recycle paraffin stream comes from the top of the paraffin column of the UOP Detergent Alkylation process unit (see point A in the Fig.3.2). The recycle paraffin stream and the fresh paraffin stream are first sent upflow through two alumina treaters operated in series (B). The purpose of the alumina treaters is to remove combined fluorides from the recycle paraffin stream coming from the detergent alkylation unit. Fluorides are a poison to the Pacol catalyst. The alumina treaters are two carbon steel vessels, which contain activated alumina resting on crushed limestone support material. The mixed liquid feed, after the treaters, is sent to the combined feed/effluent exchanger (C). Reactor Section The liquid feed is mixed with recycle hydrogen gas from the recycle gas compressor after entering the combined feed exchanger. The combined feed is preheated in this exchanger by exchanging heat with the reactor effluent. The reactor effluent passes through the exchanger where it is cooled as the combined feed is preheated. The combined feed is heated to reaction temperature by the charge heater (D). The Pacol charge heater is designed to operate on either fuel gas and/or fuel oil. From the charge heater the hot combined feed is sent directly to the Pacol reactor (E) where the following reaction takes place. R1 R1 C C R1 C H C H H H R1 H H
A B C D E H F G 4175 31325 5217 35500 5217 125 50 35375 35150 175 40717 Paraffins from oxygen stripper Paraffins from alkylation Alumina treater Paraffin purification Hydrogen Compressor Dehydrogenation reactor Feed fired heater Paraffin & Hydrogen Heat recovery 40717 40717 40717 Light hydrocarbon stripper Paraffin - Olefins condensation Hydrogen to furnace Light gas to furnace Light liquid to storage Parffin & oleofin to alkylation Fig. 3.2: PACOL Unit Block Diagram = Flowrate (kg/h) AHMAD DAABOUL & SONS Co. FOR DETERGENTS LAB project -- Environmental Impact Assessment Section 3: Project description March 2002 Figure Ballestra P : \ \ 0 1 5 0 9 i \ f i g u r e \ p r o g e t t u a l e . c d r LAB project Environmental Impact Assessment March 2002 Section 3: Project description 8 of 42
The reactor product flows back to the combined feed exchanger. The Pacol unit is operated with only one reactor in service at a time, but has two reactor vessels. While one reactor remains in operation, the other reactor with deactivated catalyst is unloaded and reloaded with fresh catalyst. The reactor section also contains a second heater which is provided so that one of the reactors loaded with fresh catalyst (Pd on alumina pellets) can be heated while the other reactor is still producing olefins. The heater is a simple all-radiant type with combination gas and fuel oil burners. Separator Section After passing through the combined feed exchanger (C), the reactor product is sent to the reactor products condenser (F). This condenser is used to condense the vaporized product stream, which is then separated in the product separator. The purpose of the product separator is to provide means for the cooled reactor effluent to separate into the liquid product and the hydrogen-rich recycle gas. If there is an excess of pressure, it will open the control valve to flare. The liquid from the product separator is sent to the Pacol stripper (G). Recycle gas is taken directly off the top of the product separator to the recycle gas coalescer and then to the suction of the recycle gas compressor (H). Much of the entrained liquid and condensation mist that could end up in the recycle gas is designed to be removed by the recycle gas coalescer. The coalescer consists of three separate compartments and two liquid boots to collect the liquid. The recycle hydrogen is sent to the inlet of the combined feed/effluent exchanger (C). Fractionation Section The stripper column (G) is necessary to remove all of the light ends formed by cracking reactions in the reactor. Stripper overhead vapors are cooled in the stripper overhead condenser and separated into a gas and liquid phase in the stripper receiver. Stripper off-gas is sent to fuel gas or to the flare if the pressure is high. The column bottoms, paraffins and olefins, are pumped to the detergent alkylation unit (next unit). As much heat as possible is normally recovered from the bottoms stream by passing it through a heat exchanger where the recycle paraffin stream is heated on its way to the paraffin alumina treaters. LAB project Environmental Impact Assessment March 2002 Section 3: Project description 9 of 42
3.2.2.2 Linear Detergent Alkylate Process (LAB) Reactor System The HF Detergent Alkylation Process is a catalytic process to alkylate benzene with linear olefins in the presence of an HF acid catalyst, to form linear alkylbenzene
According to the following block diagram (Fig.3.3), the reaction is carried out in a two stage mixer-settler system (H). The reagents are first mixed and then cooled. The liquid proceeds upflow in the first stage alkylation mixer and the outlet is sent to the first stage settler where the acid and hydrocarbon phases separate. The hydrocarbon phase from the first stage settler enters the second stage alkylation mixer and the hydrocarbon effluent from the second stage settler goes to the HF stripper (I). The acid phase is pumped back to the mixer stages. HF Regenerator The main purpose of the HF regenerator (L) is to remove the heavy unsaturated material (alkylate polymers) contained in the hydrofluoric acid. After separation from the HF and neutralization (M), the polymers go to the fuel oil circuit where they are mixed with the fuel oil that is burnt in the two heaters, Pacol Charge and Hot oil heater. HF Stripper The hydrocarbon phase from the second stage settler (H) is fed onto the top tray of the HF stripper (I) where the HF dissolved in the hydrocarbon phase is stripped out. The bottoms liquid leaving the column is virtually free of HF. It does contain organic fluorides, however, which may decompose and form HF again when exposed to high temperatures. The HF stripper is heated by means of a hot oil reboiler. If the HF stripper is ever allowed to cool down because of an emergency, acid that goes to the bottom of the column can be recirculated to the reboiler so that acid going forward to the benzene column is minimized. HF alkylation: 2nd stage Benzene from storage Paraffins + olefin from PACOL Benzene recycle Liquid HF Heavy polym. to furnace Recycled paraffins to PACOL LAB to storage Heavy alkylated to storage Benzene recycle LAB + Heavy alkylates H Q H I N O P L M A 1675 35150 15700 50850 3600 47250 50775 3525 43205 75 75 36750 5425 425 5000 32325 6455 7570 Benzene dryer HF stripper column HF regeneration HF alkylation: 1st stage Paraffin distillation Benzene distillation HF neutralization LAB distillation Fig. 3.3: HF Alkylation Unit Block Diagram = Flowrate (kg/h) AHMAD DAABOUL & SONS Co. FOR DETERGENTS LAB project -- Environmental Impact Assessment Section 3: Project description March 2002 Figure Ballestra P : \ \ 0 1 5 0 9 i \ f i g u r e \ p r o g e t t u a l e . c d r LAB project Environmental Impact Assessment March 2002 Section 3: Project description 10 of 42
Benzene Column The HF stripper bottoms are fed to the benzene column (N) where benzene is separated from the heavier hydrocarbons and recycled to the hydrocarbon feed cooler inlet. The benzene drag stream leaving the unit from the overhead of the benzene column is treated with solid KOH in the benzene KOH treater for removal of traces of free acid that may have been carried through from the HF stripper. Paraffin Column The bottoms from the benzene column go to the paraffin column (O). The net n- paraffins from the overhead accumulator go to the Pacol feed surge drum being alumina treated in route to remove the combined fluorides. The bottoms of the paraffin column is pumped to the rerun column. Alkylate Rerun Column The final split between detergent range alkylate and heavy alkylate is performed under vacuum in the alkylate rerun column (P). The LAB product normally goes to one of the product day tanks. Typically of the feed to the column 5-10% is taken off as bottoms (heavy alkylate). Benzene Stripper The high volatility of water dissolved in hydrocarbons is used in this column (Q) to obtain water-free benzene in the column bottoms which also removes any dissolved oxygen or noncondensibles in the benzene or off spec feeds.
3.2.2.3 Treatment of Gases Non-Acidic Gases The non-acidic hydrocarbon gases from process vents and relief valves discharge will be sent to the flare, while all acid vents and relief valves are piped to a separate acid relief system (see Fig.3.4). Acid Relief System Acid relief and vent gases first flow to a liquid knockout drum while the acid contaminated drain liquid goes to the liquid recovery drum to remove all liquid possible. The liquid from the knockout drum is educted using the neutralization Gases NON ACID GASES Flare ACID GASES ACID DRAIN Neutralized gases Liquid Knock-out drum Liquid recovery drum Liquid Alkylation reactor Neutralizing pits API separator Relief gas scrubber CAF sludge 2 Hydro-carbons Fig. 3.4: Gas Treatment Block Diagram AHMAD DAABOUL & SONS Co. FOR DETERGENTS LAB project -- Environmental Impact Assessment Section 3: Project description March 2002 Figure Ballestra P : \ \ 0 1 5 0 9 i \ f i g u r e \ p r o g e t t u a l e . c d r LAB project Environmental Impact Assessment March 2002 Section 3: Project description 11 of 42
eductor to the relief gas scrubber hydrocarbon skimming and neutralization section. Normally, liquid from the pressurized liquid recovery drum is recovered to the reactor section via the fresh acid pump while the liquid from the liquid knockout drum is sent to the relief gas scrubber since in the latter case contamination by KOH is considered possible. The acidic gases from the liquid recovery drum go to the liquid knockout drum and the acid gases from the liquid knockout drum then pass to the scrubbing section of the relief gas scrubber (RGS) where they are neutralized by countercurrent contact with a solution of KOH. The neutralized gases from the overhead of the relief gas scrubber go to the non-acid relief header and on to the flare. Hydrocarbons entering the relief gas scrubber overflow the baffle on the hydrocarbon end and accumulate as indicated by a level instrument and high level alarm. Occasionally it may be necessary to pump hydrocarbon out of the RGS for which the KOH transfer pumps are used with the discharge sending the hydrocarbon to the oily water separator. The neutralization of HF in the RGS works by the following acid-base reaction: HF + KOH =============> KF + H 2 O The KOH solution is continuously circulated by the KOH circulating pump to the top of the scrubber. The KOH circulation pumps are set up with the down pump connected to an uninterruptable power supply with an auto start system such that in the case of low flow of circulating KOH the spare pump automatically starts to assure continuous neutralization circulation. The KOH solution is normally maintained between 7 and 10 wt-% KOH and between 0 and 3% KF. In order to maintain the circulating KOH percent KOH high and percent KF low, a regeneration system is necessary for the circulating KOH. The KOH regeneration takes place by the following reaction: 2KF + Ca(OH) 2 =========> 2KOH + CaF 2
The insoluble calcium fluoride is transferred into one of the neutralizing pits. Obnoxious Fumes and Odors The only process area from which potentially fumes could originate would be the unit's neutralizing basins (see 3.2.2.4). To prevent the discharge of these gases to the surroundings, the neutralizing basins are tightly covered and equipped with small vent scrubbers, one for each of the two basins. LAB project Environmental Impact Assessment March 2002 Section 3: Project description 12 of 42
3.2.2.4 Treatment of Liquids Process Waste Water Effluent Sewers Plant areas (process area, tank farm, utilities excluded nitrogen production, air compressing, water tanks) are provided with concrete paving in order to collect possible liquid spills. Three separate sewer systems are provided: - one for non acid possibly oily water streams, - one for possible acid containing water streams - one for white waters (rain from areas external to possibly contaminated areas, water discharge from cooling towers and from raw water demineralization unit). Sanitary waste water from buildings will be collected to a septic tank, from which clean water will be sent to white water sewerage. Settling tank sludge will be periodically drained and correctly disposed. The non-acid possibly oily effluents are directed to the oil separators as they represent an essentially HF-free stream. Possible HF-containing water streams are directed to the acid sewers and are collected in the neutralizing basins. These potential acid containing streams include rainwater runoff from the curbed acid area, wash water, heavy hydrocarbons, and possibly spent neutralizing media which may contain HF. In the neutralizing basin, lime is used to convert any HF or traces of other soluble fluoride compounds in the water to calcium fluoride. Calcium fluoride is highly inert and has an extremely low solubility in water. Operation of the neutralizing basin is such that once the calcium fluoride is formed, it is permitted to settle. Once the level in a chamber has risen, the clear, essentially fluoride-free water is drained from the neutralizing basin to the sump from which the sump pump pumps it to the white water sewerage. Neutralizing Basin The neutralizing basin consists of two parallel pits. The two parallel pits will be alternately operated. Since there are only a few surface drains directed to the pit, inlet flow will normally be very small, or no flow at all, except when acid equipment is being drained, CBM LAB project Environmental Impact Assessment March 2002 Section 3: Project description 13 of 42
(Constant Boiling Mixture, an azeotrope HF-water coming from HF regeneration column bottom) is being neutralized, or there is a rainstorm. After settling, the effluent from the first pit is drained by opening the outlet valve to the sump from which it is pumped away.
3.2.2.5 Treatment of Wastes Process Treating Waste Solids These wastes originate when process streams are defluorinated over activated alumina. Over a period of time, the alumina loses the ability to defluorinate the process streams. At this time, the alumina is considered "spent" and it is then replaced with fresh alumina. Spent alumina is recovered by the Suppliers. Miscellaneous Solid Waste Porous materials such as wiping cloths, wood, pipe coverings and packings, which have been suspected of coming into contact with HF, are placed in specially provided disposal cans for removal. These wastes may originate during normal unit operation or during a maintenance period and will be disposed in approved landfill. CaF 2 sludge Calcium fluoride originates from acid liquid neutralization with lime (see 3.2.2.4). Periodically a vacuum truck will be used to remove calcium fluoride sludge from neutralization pits for subsequent disposal in an approved landfill. Daaboul is evaluating the possibility of CaF2 recovery fro industrial use. 3.2.3 Plant units description The Plants battery limits are marked in the General Lay-Out (Annex III.2) and in the following Fig.3.5. Plant area is divided into two main parts: the process area; the off-site area (outside the process area) Process units and auxiliary systems are located in the process area. The off-site facilities (Tank Farm unit and utilities units) are located outside the process area (with the exception of the Steam boiler unit) and connected to the process units through an interconnecting system. With reference to the attached General layout, the overall LAB Plant is composed of: P A R K I N G T R U C K P R O C E S S A R E A A U X I L I A R Y
P L A N T S T A N K
F A R M F L A R E C O M P R E S S O R S N 2
P R O D U C T I O N C O O L I N G T O W E R F I R E
F I G H T I N G P O W E R
U N I T S O F F I C E E N T R A N C E C O N T R O L
R O O M / L A B O R A T O R I E S 0 2 5
M e t r i Fig. 3.5: General lay-out AHMAD DAABOUL & SONS Co. FOR DETERGENTS LAB project -- Environmental Impact Assessment Section 3: Project description March 2002 Figure Ballestra P : \ \ 0 1 5 0 9 i \ f i g u r e \ p r o g e t t u a l e . c d r LAB project Environmental Impact Assessment March 2002 Section 3: Project description 14 of 42
Process units installed in the process area . Other units installed in the process area. Tank Farm unit located out-side the process area. Utilities units located out-side the process areas (with the exception of steam boiler unit). 3.2.3.1 Process Units Installed in the Process Area PACOL This unit (marked 01 on the General Layout) is used for the dehydrogenation reaction of N-paraffins converted to N-olefins. This process unit includes: two high working temperature Pacol reactors with relevant heat exchangers; two large hydrogen compressors; two process furnaces; one distillation column; two alumina treater fixed bed reactors with relevant heat exchangers.
N-paraffin oxygen stripper This unit is used to remove some oxygenated-dirty compounds from N-paraffins feedstock, before feeding the n-paraffins to the Pacol Unit. This unit is mainly composed by one distillation column with relevant ancillaries. The unit is installed near the Pacol unit.
Alkylation This unit is used for alkylation of mono-olefins produced in the Pacol unit and includes also: HF reaction system using two large alkylation stages in series based mixer- settlers UOP technology; LAB project Environmental Impact Assessment March 2002 Section 3: Project description 15 of 42
the HF unloading system from tankers, to an intermediate storage tank; a safety guard (marked 06) located close to HF unloading station. an HF vent scrubber which is used to eliminate the HF vapor present in the organic vents. the LAB daily storage and off spec storage section with relevant ancillaries. a series of distillation columns, with relevant ancillaries, used for HF, Benzene, paraffin and LAB distillation operations.
Other units installed in the Process Area Hot oil system (marked 02): is used as the heat source for the column reboilers of the plant. This unit is mainly composed by the Hot oil furnace, hot oil pumping station, hot oil expansion vessel.
3.2.3.2 Facilities installed outside the Process Area The off-site facilities include the following systems, each one complete with relevant piping, control panels, local instrumentation etc. Compressed and instrument air This unit (marked 17) is composed of: N.2 reciprocating compressors (one in stand-by) one/two air-drying system, heat-less type. Three plant air storage vessels. Nitrogen production and storage This unit (marked 10) is composed by a Nitrogen production package (PSA unit), three low pressure nitrogen storage vessels, one nitrogen compressor and two high pressure nitrogen storage cylinders (horizontal vessels). Steam generation unit This unit (marked 20) is composed by a package containing the demi water production unit and the medium pressure steam boiler unit. As above reported, this unit is located near the hot oil heater, in the process area. LAB project Environmental Impact Assessment March 2002 Section 3: Project description 16 of 42
Cooling water system This unit (marked 16) is composed of: Cooling towers package (wet cooling type) with relevant chemicals dosing system N 3 cooling water feeding pumps (one stand-by) fed from a water concrete basin. Main storage tanks Tanks for raw material, products, by-products and fuel oil will be installed near the process units. The tank farm (marked 19) is installed close to the process Plant and is composed of the following storage tanks: N-paraffins: n two tanks 2000 m 3 each. LAB: n two tanks 2000 m 3 each. Benzene: n two floating roof 1000 m 3 each. Fuel oil / Diesel oil: n two 500 m 3 each. Light pacol & off spec benzene tank: 100 m 3 . KOH solution storage tank: 300 m 3 . Heavy alkylate storage tank: 300 m 3 . The supply of such products to the factory is made by tank-trucks. Six nitrogen Tanks was recovered from Bulgaria: these tanks will be reused in Syria as follow: three tanks for 10 barg plant air storage; three tanks for low pressure nitrogen storage.
Power production unit Power distribution (marked 28) includes four diesel units. During the design phase assumed that the power availability for LAB plant of 100%.
LAB project Environmental Impact Assessment March 2002 Section 3: Project description 17 of 42
Pumping station The pumping station (marked 18) is located close to main storage tanks, and composed of: Loading / unloading / transfer pumps; loading/unloading hoses for tank trucks. Fire fighting water and foam liquid system This unit (marked 15) is composed of : One fire fighting water new thank, 2000 m 3 of capacity. N 5 fire-fighting water pumps, installed near the fire fighting water tank. Liquid foam system composed by two (see par.3.5 for more detail) foam storage vessels and several foam pumps. Fire-fighting equipment (Hydrants, detectors, etc.). Flare The blow down / flare unit (marked 08) is completed with its accessories (knock out drum + pump). This unit will be located as far as possible from the process area and the tank farm area. Electric power distribution sytem The electric power distribution system is composed of the following main items: Medium voltage switchboard 6000 V, to feed the two hot oil pumps (350 kW each) and the two hydrogen compressors (1050 kW each) N 3 transformers 6000/400 V. Each transformer can feed the overall plat. Power center (L.V. switch-gear-for 400 V power distribution) Motor control centers for all electrical users of the process Plant Local Power Boards (for utilities/off site facilities pumps and instrument air production) Plant control system The control room and the control cabinets room (marked 09 and 11) based on commercial DCS or PLC systems is composed of: LAB project Environmental Impact Assessment March 2002 Section 3: Project description 18 of 42
DCS or PLC cabinets. The control cabinets are located in two control buildings: one near the cooling water unit, the second near the control room Barrier cabinets + Marshalling panels, (for interface with instruments). N 1 instrument control panel, installed in the control room. N 1 operator station, located in the control room composed by four operator console. N 2 printers. The software for the whole control system will be developed by the DCS / PLC provider Company. Interconnecting System The interconnecting system for all the above units and systems is realized by pipe racks which incorporate all pipes (process pipes, utilities pipes) and cable trays for instruments and electric distribution. The pipe rack structures are organized in the following system: Main pipe-rack inside the process area. The main piping connecting the units in the process area runs on a pipe rack with 3 main branches, where cable trays (for instruments and electric cables) are also located. All piping and cable trays running on this pipe rack are part of the Plant. Rack between the tank farm / pumping station and the process area. This pipe rack supports all lines required for the tank farm unit, the relevant utilities necessary to the tank farm, the blow-down piping, all cable trays necessary for the instruments and electric cables. Connection between flare and process area. A gas blow down line is installed to connect the process area to the flare unit and it is complete with relevant piping supports. Connections between process area and cooling water/fire fighting. These connections are running underground. LAB project Environmental Impact Assessment March 2002 Section 3: Project description 19 of 42
3.3.3 Materials, substances and resources input / output
3.3.3.1 Raw materials and resources input In the following tables raw material consumption for process units and for utilities is reported:
Raw materials input in process units Materials Consumption (Tons/year) n-Paraffins C10-C13 33.400 Benzene 13.400 Hydrofluoric acid 25 Activated Alumina pellets About 76,200 kg at start-up, periodically recovered Pacol catalyst 8 m3 at start-up, periodically recovered
Resources input in utilities Resources Consumption (Tons/year) Fuel oil 17600 Diesel oil 5600 LPG 250 Water 192000 m3/year
LAB project Environmental Impact Assessment March 2002 Section 3: Project description 20 of 42
Material flow IN
WHAT FROM WHERE NOTES Paraffins Iran 5 Trucks/day Europe (via Latakia/Tartus) Ships / Trucks HF India 1 Trucks/year Europe (via Latakia/Tartus) Ships / Trucks Benzene Europe / USA (via Latakia/Tartus) Ships / 2 Trucks/day KOH (Dry) Turkey Trucks H 2 (for start up) SYRIA (around Damascus) Trucks Pacol catalyst USA (via Latakia/Tartus) Ships / Trucks Allumina Europe / USA (via Latakia/Tartus) Ships / Trucks Fuel oil SIRYA (refineries) 3 Trucks/day Diesel Oil 1 Trucks/day LPG SIRYA (refineries) 10 Trucks/year N 2 Self produced --- Other chemicals SYRIA (near Damascus) Trucks
In Annex III.3 material safety data sheet for substances used in major quantity in the plant and for more hazardous ones are reported.
LAB project Environmental Impact Assessment March 2002 Section 3: Project description 21 of 42
3.3.3.2 Products output In the following table product output from LAB site is reported: Substance (tons/year) LAB 40000 Heavy alkylates 3400 Light end from Pacol 1400 Material flow OUT WHAT TO WHERE NOTES LAB DAABOUL sulfonation plant located in AL KISWAH, south Damascus, 12 km from LAB plant 8,000 t/y Trucks 2 sulfonation plants located around Damascus 14,000 t/y Trucks Jordan, Lebanon, Turkey, South Arabia 19,000 t/y Trucks
6 Trucks/day Light alkylates Partly burnt in the heater, partly commercialized 1 Trucks/week Heavy alkylates Partly burnt in the heater, partly commercialised (Daaboul is evaluating a suitable use, a plant/factory that can use it) 4 Trucks/week CaF2 sludge Daaboul is evaluating a suitable use for fluorides (a plant/factory that can use it) 1 Trucks/every 2 months Exhausted Pacol catalyst Sent to UK where platinum is recovered and sent to USA for producing new catalyst Ships (via Latakia/Tartus) and trucks Exhausted alumina Sent to Europe for regeneration Ships (via Latakia/Tartus) and trucks Waste water In the interim phase, before treatment plant construction, sent to Damascus waste water plant 15-20 Trucks/day
3 WATER BALANCE (m /h) 1 Vapour to furnaces Raw water from wells Cooling towers Steam generator Service stations Buildings 8 8 Vapour to atmosphere Blowdown water 3 Blowdown water 2 Oily water 1 Waste water contaminated with HF 1 Waste organic water 16 6 1 1 24 Organic sewer Api separator Acid sewer Neutralization basin White water sewer Fig. 3.6: Water Balance AHMAD DAABOUL & SONS Co. FOR DETERGENTS LAB project -- Environmental Impact Assessment Section 3: Project description March 2002 Figure Ballestra P : \ \ 0 1 5 0 9 i \ f i g u r e \ p r o g e t t u a l e . c d r LAB project Environmental Impact Assessment March 2002 Section 3: Project description 22 of 42
3.3.4 Emissions to the environment and resources use 3.3.4.1 Emissions Emissions to the environment can be summarized as follows. AIR EMISSIONS - Air emissions are due to: - fuel combustion (mainly fuel oil) in Hot oil unit and Pacol charge heaters; - fuel combustion (fuel oil) in steam boiler burners; - fuel combustion (diesel oil) in power generators; - waste gases and LPG combustion in flare and heater pilots (LPG); - organic substances evaporation losses from tanks; - water evaporation losses from cooling tower. Emission sources localization is shown in the following figure (see also General Lay- out with air emission sources localization in Annex III.4); significant emission points and their emission values are listed in the following tables. SO2 and NOx emission values have been evaluated on the base of 1% sulphur fuel oil, which will be used in LAB plant, as far as possible considering its availability in Syria. Air emissions will be monitored, when the plant will be running. If problems should arise in NOx emission values respecting, substitution of the existing burners with Low- NOx ones, will be evaluated. LAB project Environmental Impact Assessment March 2002
Section 3: Project description 23 of 42
N Description Characteristic
Concentrations (mg/Nm 3 )
Flow rate (tons/year) a
Frequency Height (m) Diameter (m) Flow rate (Nm 3 /h)
a Service factor: 8.000 hour/year LAB project Environmental Impact Assessment March 2002
Section 3: Project description 24 of 42
Air pollutants emission from storage tanks
Emission source Description Tank Hydrocarbon vapors Mean storage Vapor Total emission / year identification type released temperature (C) MW (Kilograms)
Legend CFX = vertical cylindrical with conical fixed roof CFL = vertical cylindrical with conical fixed roof and internal floating roof negligible = less than 2 kilograms/year
LAB project Environmental Impact Assessment March 2002 Section 3: Project description Page 25 of 42
WATER DISCHARGES - Waste water discharges are due to: - cooling tower blowdown; - raw water demineralisation unit blowdown; - service stations (washing areas where contamination by hydrocarbon or hydrofluoric acid cannot be excluded); - building services. In Annex III.5 a general lay-out with sewage systems is reported. Site water balance is reported In the following table and in the following Fig.3.6: Use Input (m 3 /h) Output (m 3 /h) Liquid Vapour Cooling tower losses (evaporation+liquid blowdown) 16 8 8 Steam generator losses 6 5 1 Potentially contaminated areas wash waters 1 1 --- Building services 1 1 --- Total 24 15 9
Waste water will respect limit values indicated by Syrian guidelines for discharge in public sewage systems (see also par.2.2.2.1 in Sec.2). Industrial waste water from companies located around Damascus are typically piped or trucked to the municipal waste water treatment plant. Daaboul LABs original permit was based on this. Due to the amounts of waste water to be trucked (up to 15 cubic meters per hour), the distance of the transport (30-40 Kilometres), as well as relative low contamination level of the waste water it was in early February 2002 decided to design and build a full waste water treatment plant on-site. The waste water treated in the on-site plant will comply with World Bank guidelines and will be used for irrigation of new green areas within Daabouls own premises, and/or for outside irrigations projects according to permits obtained. The design and construction of the waste water treatment plant is delayed according to the LAB plant implementation schedule and it might, in an interim period during the commissioning, be necessary to use the municipal waste water treatment system. LAB project Environmental Impact Assessment March 2002 Section 3: Project description Page 26 of 42
WASTE PRODUCTION - Waste materials production is due to: - acid waters neutralization in neutralization pits and CaF2 sludge production; - exhausted Pacol catalyst - exhausted alumina catalyst. At the moment Daaboul is evaluating the possibility of CaF2 recovery for industrial use. Exhausted catalysts will be sent to suppliers for rigeneration/recovery:
WHAT TO WHERE HOW Exhausted Pacol catalyst Sent to UK where, platinum is recovered and sent to USA for producing new catalyst Ships (via Latakia/Tartus) and trucks Exhausted alumina Sent to Europe for regeneration Ships (via Latakia/Tartus) and trucks Other solid wastes, mainly form maintenance activities, will be disposed in an approved landfill. NOISE EMISSION Noise emission is mainly due to noisy units running (mainly power production units, compressors, furnaces). The most noisy units are the power generators, which are located inside a building. Noise level inside the building is approximately 117 dB(A), outside the building level the expected noise is approximately 90 dB(A). For the other noisy units, a value of 85 dB(A) have been considered as noise pressure level at a distance of 1 m (data assumed also in other studies for similar equipment).
LAB project Environmental Impact Assessment March 2002 Section 3: Project description Page 27 of 42
3.3.4.1 Resources use Resources uses can be summarized as follows. WATER USE Water is needed mainly to compensate water discharges and vapor emission (see previous points in 3.3.3.1). The only available source of water in the area is underground water. Five wells are present in LAB site. Water estimated consumption is about 24 m 3 /hour, approximately equivalent to 190000 m 3 /year. FUEL CONSUMPTION Fuel consumption is necessary in order to guarantee heat supply in different process steps and electric energy supply to the site. -Fuel consumption is due to combustion in: - Hot oil unit and other process heaters (mainly fuel oil); - Power generation units (Diesel oil) - flare (LPG and other waste gas). In order to minimize gaseous emissions (above all SO2 emissions), low sulphur (1%) fuel oil will be chosen, as far as possible a . Air emissions in 3.3.4.1 have been calculated considering 1% sulphur fuel oil. An internal hydrocarbon recovery is performed in different process steps (see previous process description in section and data in section 3.3.3.1). By products such as: - Light gaseous ends from Pacol - Hydrogen - Alkylate polymers are recovered in order to be burnt in Hot oil and other process heaters. Fuel consumption data are reported in previous point 3.3.3.1.
a In Syria low sulphur distillates are not currently commercialised. LAB project Environmental Impact Assessment March 2002 Section 3: Project description Page 28 of 42
LAND USE LAB site covers a rectangular area, 160m large x 318m long, of about 50,800m 2 . Process area will be paved, in order to avoid soil contamination due to incidental leakage of hazardous materials.
LAB project Environmental Impact Assessment March 2002 Section 3: Project description Page 29 of 42
3.4 Yard phase Construction works are in progress; INCO International (Sultanate of Oman) has been encharged to carry on the works; some features of the works in progress are given in the following: 1- Employed personal for construction activities is 135 totally, 12 of them are technical staff and 102 are workers. Administration personal are 11. 2- Workers and administrative personal live in different dormitories which are furnished with similar commodities. 3- A car is used for services between Damascus and site in case of an emergencya minibus is used for links to Damascus. 4- Two type of machinery are used in the yard 1 ST ) Construction machines for erection works (like one lifting crane-mobiles, lifting cap mobile cranes, forklits and so on) 2 nd ) Supplementary machinery and equipment (like automatic pipe cutting machines, Flange re-facing machines, Acetylene cutting torches and so on) 5- Transport activities in site for material movements are done by tractors and mobile cranes. The other vehicle traffic is only for servicing personal to work places, like measuring & mapping staff and for in coming trucks from outside for supplying material/and other consumables. 6- Water is supplied from wells. Drinking water is supplied from out of site by filling a daily tank. Energy supply for work and social life is derived from 350 KVA gen/set which runs continuously. 7- Waste water comes out only from living places; it is collected by means of a short sewage system in a waste-water basin (about 150m capacity) periodically drained by sewage tankers.The distance between basin and dormitory buildings is about 50 m. 8- Waste resulted from working and human activities (for example waste from restaurant) are collected in barrels which their top are closed. These are taken away by a truck which collects hard-waste-a company car working under authority of municipality. 9- In the areas and during activities with high noise personnel is provided with ear protecting head wears and if necessary eyes protection goggles. There are no night shifts and consequently no noise emission. In the following Fig.3.7 a program of the building activities and the fraction of realized ones are reported. I D T a s k
N a m e D u r a t i o n S t a r t F i n i s h %
C o m p l e t e A p r i l J u l y O c t o b e r J a n u a r y A p r i l J u l y O c t o b e r M o b i l i z a t i o n 1 2 8 23456789 1 0 1 1 1 2 1 3 1 4 1 5 1 6 1 7 1 8 1 9 2 0 2 1 2 2 2 3 2 4 2 5 2 6 2 7 2 9 D a a b o u l
S i t e
M o b .
&
W a r e h o u s e P r o j e c t / W a r e h o u s e
S e t t l e m e n P r o j e c t / D e s i g n
W o r k s M a i n t e n a n c e
&
O v e r h a u l i n g
W . P r o c e s s
A r e a
E r e c t i o n
W o r k s S l e e l
S t r u c t u r e
M o d .
&
E r e c t i o n P i p i n g
W o r k s E r e c t i o n
o f
T a n k
f a r m E l e c t r i c a l
&
I n s t r u m e n t a t i o n
W o r k s T e s l i n g
o f
P i p e s I n s u l a t i o n
W o r k s P a l n t i n g
W o r k s F i r e
a l a r m
S y s t e m
I n s t a l l a t i o n P r e - C o m m i s s i o n i n g 4 9
d a y s 1 6 4
d a y s 1 7 0
d a y s 1 4 1
d a y s 1 8 5
d a y s 1 9 5
d a y s 1 6 3
d a y s 1 9 5
d a y s 1 3 0
d a y s 2 1 6
d a y s 3 0 4
d a y s 1 2 8
d a y s 3 4 8
d a y s 6 4
d a y s 2 2
d a y s F r i
1 5 / 0 6 / 0 1 M o n
1 8 / 0 6 / 0 1 M o n
1 8 / 0 6 / 0 1 M o n
1 8 / 0 6 / 0 1 M o n
1 8 / 0 6 / 0 1 M o n
0 2 / 0 7 / 0 1 T u e
1 9 / 0 5 / 0 1 M o n
0 3 / 0 9 / 0 1 M o n
0 1 / 1 0 / 0 1 M o n
0 3 / 1 2 / 0 1 M o n
0 3 / 0 9 / 0 1 W e d
0 1 / 0 5 / 0 2 W e d
0 1 / 0 8 / 0 2 T h u
0 1 / 0 6 / 0 2 T u e
0 1 / 1 0 / 0 2 W e d
2 2 / 0 8 / 0 1 T h u
3 1 / 0 1 / 0 2 F r i
0 8 / 0 2 / 0 2 M o n
3 1 / 1 2 / 0 1 F r i
0 1 / 0 3 / 0 2 F r i
2 9 / 0 3 / 0 2 T h u
3 1 / 0 1 / 0 2 F r i
3 1 / 0 5 / 0 2 F r i
2 9 / 0 3 / 0 2 M o n
3 0 / 0 9 / 0 2 T h u
3 1 / 1 0 / 0 2 F r i
2 5 / 1 0 / 0 2 F r i
2 9 / 1 1 / 0 2 T u e
2 9 / 1 0 / 0 2 W e d
3 0 / 1 0 / 0 2 1 0 0
% 5 1
% 1 9
% 3 5
% 3 5
% 5 2
% 8 3
% 1 0
% 5
% 0
% 5
% 0
% 2 0
% 0
% 0
% 1 0 0
% 5 1
% 1 9
% 3 5
% 3 5
% 5 2
% 8 3
% 1 0
% 5
% 0
% 5
% 0
% 0
% 0
% 2 0
% Fig. 3.7: Project Calendar with percent of realized activities AHMAD DAABOUL & SONS Co. FOR DETERGENTS LAB project -- Environmental Impact Assessment Section 3: Project description March 2002 Figure Ballestra P : \ \ 0 1 5 0 9 i \ f i g u r e \ p r o g e t t u a l e . c d r LAB project Environmental Impact Assessment March 2002 Section 3: Project description Page 30 of 42
3.5 Project reliability and safety systems PROJECT RELIABILITY The adopted technology is very well known and several large industrial plants are in operation since many years in different countries. The HF technology is still the most applied to produce LAB (almost 80% of the total LAB worldwide produced). The biggest plant of this type in the world is now operating in Augusta, Sicily (Italy), with 150,000 tons/year LAB production capacity.
FIRE FIGHTING SYSTEM The LAB production plant site is protected against accidental fire with a series of properly sized equipment which are able first to detect possible inflammable gas mixture presence or fire presence and then to guarantee water sprinkling/distribution for at least 2 hours in the area involved. The system is composed of the following equipment: 1. A LEL (lower explosive level) monitoring network for main flammable hydrocarbons, generating an alarm in control room in case of limit exceeding; 2. A UV (Ultra Violet type) flame detectors network, which is able to generate an alarm in control room; 3. A sprinkler based cooling system for critical equipment, activated from remote position (control room); 4. A fire fighting water storage tank 200T1, having an operating capacity of 2000 m3; 5. Four lead pumps (200 P10 / P11 / P12 / P13) having a capacity of 180 m3/h; 6. One jockey-pressure maintenance pump (200 P14), having a capacity of 20 m3/h; 7. Two foaming agent storage vessels, each one having a capacity of 40 m3; 8. Four foam pumps (200 P21 / P22 / P23 / P24); 9. One foam jockey pump (200 P25); 10. A piping network to deliver fire water, divided into three main loops; 11. A piping network to deliver foaming liquid, divided into three main loops; 12. A series of local hydrant; 13. A series of swinging monitor, located both at ground level and above steel structure; 14. A foam distribution network for storage tanks containing flammable liquids; LAB project Environmental Impact Assessment March 2002 Section 3: Project description Page 31 of 42
Each equipment or particular device will be further described in the following part of this document. Concerning monitoring system, refers to the distribution lay-out in which location of detection points is indicated, dwg. Nr. 3A65.85.014 (2 sheets): a) LEL detectors have been installed around and inside the process area (PACOL unit, Hot oil generation and HF Alkylation) to identify possible leaks of flammable liquids or gases. These detectors are of catalytic type and are able to generate an alarm in case hydrocarbons concentration, in mixture with ambient air, exceeds 50 % of the lower explosive level. In this way operators are timely advised in order to proceed in eliminating leak cause and prevent dangerous behaviours from safety point of view. All these points are marked on the lay-out as MX-sensor. b) In case an explosion or a fire potential source cannot be avoided, UV flame detectors allow fire source identification and start up of the appropriate emergency procedure. These detectors respond to flaming fires emitting light in the ultraviolet portion of the spectrum. UV detectors can respond to a fire condition in less than 10 milliseconds. The monitoring system described may be defined as a preventive measure against potential damages due to fire events. A further measure to limit fire events or damages is represented by the sprinkler cooling system. For this system, refers to the lay-out drawing Nr. 3A65.60.002. c) 15 deluge valves have been installed to feed a sprinkler system for an equal number of critical equipment or group of them. These valves can be operated from a remote control room. An effective cooling may result in an additional safety measure. Actually, fluids circulating through them, due to particular temperature or pressure conditions, may generate dangerous mixture in case of external release. Another reason for protecting these equipment is that keeping them cool, even in case of a fire event, it is always possible to have the availability of their cooling power or blanketing action. The 15 groups are resumed here below : 1. Oxygen stripper bottom pumps 390 P2 A/B 2. Fuel oil circulating pumps 900 P3 A/B LAB project Environmental Impact Assessment March 2002 Section 3: Project description Page 32 of 42
3. Reactor product condenser 350 E2 4. Stripper Condenser 350 E4 5. Reactor charge pumps 350 P1 A/B, Stripper overhead receiver pumps 350 P4 A/B and Stripper bottom pumps 350 P5 A/B 6. Oxygen stripper overhead condenser 390 E8 7. (void) 8. Benzene make-up pumps 450 P2 A/B 9. Benzene stripper overhead pumps 450 P3 A/B and Benzene column overhead pumps 450 P8 A/B 10. Benzene column condenser 450 E12 11. Rerun column overhead and bottom pumps 450 P12 A/B, 450 P13 A/B 12. Flush pumps 450 P11 A/B 13. Paraffin column overhead and bottom pumps 450 P10 A/B, 450 P9 A/B 14. Paraffin column overhead cooler 450 E16 15. Off spec transfer pumps 450 P16 A/B 16. Nitrogen high pressure buffer tanks, 200 V106 / V107 An external cooling with sprayed water is also guaranteed for the Benzene stripper column 450 V2, the Benzene column 450 V12, the Paraffin column 450 V15 and the HF acid storage drum 450 V18. Moreover all the storage tanks for flammable hydrocarbons are provided with toric cooling water distributors, to ensure walls cooling in case of external fire. Water could also be used to maintain mild wall temperature during summer and consequently avoid massive hydrocarbons evaporation. d) Fire fighting water and foam distribution network are indicated in the lay-out drawings Nr. 3A65.60.003 (for process area) and 3A65.60.004 (for tank farm). A storage tank for fire fighting water with a capacity of 2000 m3, 200 T1 has been foreseen to guarantee a sufficient supply during a fire emergency involving most critical hydrocarbons hold-up release. In case of flame detection, after first attempt to limit fire extension, the lead pumps (200 P10 / P11 / P12 / P13) are automatically and in sequence started up according to user (hydrants or monitors) requirement. A jockey pump is used to maintain the pressure in the network, in order to guarantee water instantaneous availability on demand. An adequate pressure level in the network represents also a necessary condition for safe working of sprinkler and foaming systems. Fire fighting distribution network has been laid underground and divided into LAB project Environmental Impact Assessment March 2002 Section 3: Project description Page 33 of 42
three main loops: Pacol and Hot oil process area, HF alkylation process area and tank farm. Every point of the network has the same the pressure level. Each loop may be blocked to satisfy water greater demand in the area interested by fire emergency. Isolating pits have been provided on loop borders; a blocking manual valve for water and foaming agent may be operated in every pit. A pit with gate valves for water and foaming agent is also present where hydrant or monitors have been placed. Swinging monitors have been distributed around and inside the process area, at ground level and mounted on steel structure. Each monitor can be operated from remote and safe position (according to wind prevailing directions) by means of joystick control panels.
A particular foam distribution system allows to mix air, fire water and foaming agent and feed produced foam inside every storage tank containing flammable liquids. Foaming agent is stored into two vessels, 200 T2 / T3 having a capacity of 40 m3 each one. Foaming agent is then pumped into the distribution network according to the same logic system as fire water (4 main load pump + 1 jockey pump that maintain pressure level). Foam is poured on liquid surface to prevent air/hydrocarbons contact and consequently flames development.
LAB project Environmental Impact Assessment March 2002 Section 3: Project description Page 34 of 42
3.6 Safety criteria and safety measures adopted in order to prevent incidents HazOp analysis for the Daaboul LAB plant (see complete report in Annex III.6) allowed the definition of a set of recommendations for the improvement of plant safety. Descriptions and details of all recommendation are included in Attachment #1 to Annex III.6. Following a short summary with indication of main issues is provided. ISOLATION AND PUMPING OUT Isolation and pumping out of acid circuit of alkylation unit was not foreseen in original U.O.P. project. The new project has introduced on/off valves and procedures to pump out the acid mixture in case of emergency. This will allow reducing duration of an accidental release. On/off remotely activated valves will to be designed as failure hold, so that in case of lack of energy or instrumental air, they will keep the position. In the event of emergency a dedicated logic circuit will operate the valves in order to close main acid circuit and open the lines to the storage vessel. A reliable trip logic system that foresees feed pumps stop before on/off valves shut down will be installed. HF LEAKAGE DETECTION Video cameras have been selected as means for HF leakage detection. The installation of a suitable number of video cameras (at least 4) will cover the entire acid area in all possible directions. FLAMMABLE GAS DETECTION A review of flammable gas detectors location will be done, so that they will cover not only pumps but also areas in which hot flammable fluids are processed and therefore might be released, particularly in correspondence of flanged joints. Besides, they will be placed in order to detect the possible cloud directed towards potential ignition sources (furnaces, hot oil heat exchangers). LAB project Environmental Impact Assessment March 2002 Section 3: Project description Page 35 of 42
FIRE DETECTORS Review of fire detectors location is required. They should cover mainly pumps and equipment that process liquids above their autoignition point (with particular regards to paraffines). For other areas, positioning should take into consideration the slope of the paved area that might force the pool to pool. FIRE PROOFING Fire proofing of skirts and saddles will be done in PACOL unit and in distillation and purification section of alkylation unit. Light fire proofing application along the horizontal metallic structures will be realized, especially for the areas subjected to a higher fire risk (PACOL unit and distillation and purification section of alkylation unit). FIRE FIGHTING The benzene stripper, V2, the benzene column, V12 and paraffine column V15 are protected with water sprinklers. Reference for dimensioning will be international standards (such as NFPA 15). Position of water sprinklers will be optimized. PAVING AND SEWER SYSTEM All the equipment containing HF are located on a paved area; leakages and rainfalls in the area will be collected to Acid sewer and to the neutralization pits. All equipment containing hydrocarbons are located on a paved area connected to oily sewer and to the oily separator. The paved area of alkylation unit will be divided form the rest of the acid section in order to separate fire risk from toxic risk. In this sense a curb between heat exchanger E7 and E9, directed N-S, will be built. Paved area of the distillation and purification section of PACOL unit (positioned immediately North of PACOL process area main pipe rack) will be adequately sloped in order to collect the leakages (and potential fire) far from process pipe rack. The paved areas of the Hydrocarbon processing plant sections will be divided into smaller areas with a suitable slope towards the wells, in order to collect potential LAB project Environmental Impact Assessment March 2002 Section 3: Project description Page 36 of 42
leakages. TANK FARM Storage tank containment dikes will be dimensioned to contain the hold up of the largest tank. Each benzene storage tank will be positioned in a single dike. CONTROL ROOM Control room will be pressurized. Toxic gas detectors will be put in the air intake duct with alarm in control room; air re-circulation inside control room must be provided. WIND DIRECTION MONITORING Wind direction is fundamental for emergency management due to toxic gas release. Wind cones visible from all parts of the plant will be provided. An anemometric station in control room is also foreseen. CONTROL SYSTEMS Redundancy in control and alarm systems in critical equipment will be realized. Minimum set of measures that will be implemented is following detailed: Redundancy of the minimum flow trip of the paraffine flush for acid and benzene pumps seals. Redundancies of minimum flow trip for caustic solution recycle in the neutralization section of alkylation unit. Installation of high temperature trip on the outlet line of the furnace, with shut- off of the furnace in the PACOL unit. DRAINAGE A spring loaded (dead man type) valve as second manual valve on draining lines, in order to avoid liquid spills during drainage operations, will be installed. SHUT-OFF VALVES Installation of on/off valve, fire safe type, on the bottom line of the vessels containing large hold up of hot flammable substances, is in project., as a minimum, for vessel 350 V1A/B and 350 V2. FIREDAMP STEAM Toroidal vapour ejectors will be installed in correspondence to flanged joints of the LAB project Environmental Impact Assessment March 2002 Section 3: Project description Page 37 of 42
furnaces heat exchangers in the PACOL unit. LOADING/UNLOADING A nitrogen system to recover the pressure in the mobile tanker during unloading operations will be provided. Volumetric counters for the indication of total amount loaded into the mobile tanker (with particular concern to LAB, heavy hydrocarbons and light pacolate) will be installed. Availability of a earthing plier in each of the loading/unloading bay is required; to be associated to the consent of relevant pump start up. For LPG station, the logic consent will be directed also to the opening of an independent on/off valve on the inlet line of the storage vessel. 3.7 Plant maintenance and availability On the base of previous experiences, a general stop of the plant for maintenance is foreseen every 2-3 years. The actual maintenance frequency will depend on the results of the implementation of an inspection program, whose contents are to be developed and defined in detail before plant starting. Inspection program will describe the typology and frequency of controls, with particular attention to control of lines and equipment containing acid liquid or gases, in order to verify possible corrosion effects reducing material thickness. In Operating Manuals a list of critical lines and equipment and detailed procedures for their control will be present. The general maintenance will be committed to specialized external companies, managed by the internal responsible for maintenance. Everyday maintenance interventions (like catalysts substitutions, instrument cleaning and so on) for which actual plant stop is not required, will be made by internal maintenance staff.
LAB project Environmental Impact Assessment March 2002 Section 3: Project description Page 38 of 42
3.8 Adverse impacts prevention and mitigation and measures In the previous paragraphs a series of prevention and mitigation measures (mainly technical measures), have been described. In section 5, other prevention measures (mainly management measures) will be described, concerning safety and environment management system. Hereafter a short synthesis is reported. SAFETY The project has been analysed with HazOp methodology and main issues outcoming from analysis has been identified and described in par.3.6. HazOp recommendations are finalized to increase plant reliability and to reduce the potential consequences of an incident. Daaboul Lab will implement all recommendations from HazOp, and will use the HazOp results for accident probability and consequence calculations. All accidents with probability higher than 10 -6 will be included in the emergency Response Plan. For hygiene and safety operation a training program for personnel is in elaboration (see also sec.6). All the necessary personal protective equipment will be available for operative personnel, who will be trained on its use. ENVIRONMENT Soil contamination is prevented by the presence of pavements in process areas (see 3.6), that will collect eventual leakage. Storage tank containment dikes will be dimensioned in order to contain the hold up of the largest tank. Air emissions are mainly due to fuel oil combustion in furnaces. Air pollutant emission will be limited by choice of low sulphur (1%) fuel oil, as far as possible considering its availability in Syria. Benzene emissions from storage tanks is limited adopting an internal floating roof with external fixed roof. Benzene concentration monitoring in different points inside the plant and at its fence is foreseen (see also section 6). Particular care will be given in the management system to water use and saving. In waste water sewerage, separation between possibly acid contaminated liquids and possibly oily contaminated liquids is foreseen. Two different treatments are provided: a neutralization treatment, for acid liquids, and an oil separation, for oily liquids. LAB project Environmental Impact Assessment March 2002 Section 3: Project description Page 39 of 42
As already evidenced (3.3.4.1 page 25) a full waste water treatment will be built, so that waste water will be usable for irrigation purposes. Noise emissions from power generators (which are the most noisy equipments) is limited by a closed building. PREPAREDNESS AND RESPONSE TO EMERGENCY In par.3.5 fire fighting system has been described. An emergency plan will be defined before plant start up. A group of internal operator will be trained for fire fighting and first aid. Appropriate training for emergency behaviour will be provided for all personnel (see section 6).
3.9 Examined Alternatives SITE ALTERNATIVES LAB localization in present site was identified after examining and eliminating another site choice. The previous site is situated next to existing Daaboul Sulfonation plant (final destination of LAB). The advantages of this site was the good integration between the existing and the new plant. However, the previous choice was not good for two main reasons, evidenced by Ballestra technicians: the site was too near to inhabited centres and next to a big supermarket; the site morphology was not good for a chemical plant (it was not perfectly plain, giving rise to a much more complex project and to difficulties in trucks access and movements). LAB site final choice is good for: distance from towns (Deir Ali is 1.5 km distant) the almost desertic features of the area.
PROJECT ALTERNATIVES As already mentioned, HF technology, adopted in Syria plant, is very well known and LAB project Environmental Impact Assessment March 2002 Section 3: Project description Page 40 of 42
several large industrial plants are in operation since many years in different countries. The HF technology is still the most applied to produce LAB (almost 80% of the total LAB worldwide produced). Two other different technologies are currently available in order to produce LAB: -AlCl 3 technology -Detal process technology. AlCl 3 technology is very similar to HF technology. AlCl 3 is much less hazardous than HF, but, being used in aqueous solution, is highly corrosive, giving rise to many maintenance problems; moreover a recovery of the catalyst used is not possible and large quantities of Aluminum Hydroxide are produced (it could be used as flocculant agent, after appropriate treatment). Detal process technology is a state of the art process for the manufacture of detergent alkylate that uses a solid heterogeneous catalyst to produce Linear Alkylbenzene by the direct alkylation of benzene and Linear olefins. This technology has the fundamental advantage of eliminating HF or AlCl 3 corrosive liquids. The choice of HF technology for Syria plant was essentially due to the chance of recovering an existing not operating plant with a high production capacity. This choice permits to completely satisfy Daaboul sulfonation plant LAB needs and to provide more LAB in the Arabic market, substituting a significant quantity (about 20,000 tons/year) currently purchased from external far Countries.
LAB project Environmental Impact Assessment March 2002 Section 3: Project description Page 41 of 42
Environmental Factor/ Component Main Project Interference with Environment Note Air emissions from fuel oil combustion. (Hot oil unit, Pacol charge heaters, steam boiler burners, power generators). Minor contributions due LPG and waste gases combustion in flare. Minor contributions from traffic from and towards the site (about 15-20 trucks/day). Principal emissions concernes : SO2 472 tons/year 1,700 mg/Nm 3
Nox 142 tons/year 460 mg/Nm 3
CO 28 tons/year 50 mg/Nm 3 (*)
PTS 18 tons/year 100 mg/Nm 3 (**).
Air Organic substances evaporation losses from tanks Fuel oil 170 kg/year Diesel oil 70 kg/year Paraffins 500 kg/year Benzene 820 kg/year Off-specific 350 kg/year Groundwater use mainly for cooling towers and demineralisation operations (evaporation and blowdown losses).
24 m 3 /hour - 190,000 m 3 /year
Water Appropriate waste water treatment will be performed in the site, in order to recover water for irrigation (in an interim period it might be necessary to use the municipal waste water plant). 15 m 3 /hour - 120,000 m 3 /year Treated waste water will comply to WorldBank reference values and will be use for irrigation. Waste production Calcium Fluoride sludge production (from neutralization basins). It could be recovered in external factories. Exhausted catalysts can be completely recovered by the Suppliers. 10 35 m 3 /month Noise Noise emissions from some equipments (compressors, furnaces, power generators). Minor contributions from traffic from and towards the site (about 15-20 trucks/day). Higher emission values (pressure levels at 1 m distance): 90 dB(A) for power generators (outside their closed building) 85 dB(A) for the other equipments. (*) : 25 mg/Nm 3 for power generators (**) : 2 mg/Nm 3 for power generators
LAB project Environmental Impact Assessment March 2002 Section 3: Project description Page 42 of 42
Environmental Factor/ Component Main Project Interference with Environment Note Land use Soil and Subsoil Occupation of about 50,800 m 2 . Incidental leakages are collected by pavements and sewer networks in process area. In tankfarm, paved dikes and curbs are provided for incidental leakages containment. --- Landscape The plant is a greenfield one. Highest elevation is 56 meters (stack). Flora and Fauna, Ecosystems The site area is a rocky debris one. No vegetal associations or fauna species are present. ---