Interconnection Handbook v1 2
Interconnection Handbook v1 2
This handbook is intended to provide a convenient description of ERCOTs generator interconnection process for current and potential ERCOT Market Participants. It is not 1
intended to, and shall not be read to, create any rule or standard. While reasonable efforts have been made to ensure accuracy, this handbook may, from time to time, be found to conflict with the ERCOT Protocols, Market Guides, and Other Binding Documents (OBDs). In the event of such conflict, the ERCOT Protocols, Market Guides, and/or Other Binding Documents (OBDs) shall control.
ERCOT disclaims any representation or guarantee concerning the source, originality, accuracy, completeness or reliability of any statement, information, data, finding, interpretation, advice, or opinion as contained in this document.
Description of Changes Original Document Draft Editing and reduction of scope Editing and Addition of Description of Changes/Table of Contents Replacing details of each process with checklist in appendix and other edits Editing, make Figure 2 and 3 consistent with Planning Guide, changes to Appendices G and H, updated TOC Editing for simplicity & clarity
Author Al Garcia John Adams W. Rickerson John Adams Paul Tan Eric Adams/John Adams Art Deller, Bill Blevins, John Adams Ed Geer, Art Deller, Patrick Coon Woody Rickerson John Adams John Adams John Adams
0.7
11/26/2012
0.8
11/30/2012
Editing and cleanup initial draft Add planning model requirements, commercial operation requirements, corrections & Initial Issue Clarify SCADA Point plan, Generation checkout, fate of projects if FIS scope not agreed to within 60 days. Incorporate recommendations of QMWG to clarify
TABLE OF CONTENTS
TABLE OF CONTENTS ................................................................................................................................. 4 Document Maintenance Process .............................................................................................................. 6 Generation Interconnection Process ........................................................................................................ 7 Stage 1: How to Begin: Interconnection studies and project development .................................... 10 Step 1 GINR and Screening Study .................................................................................................. 10 Step 2: Full Interconnection Study (FIS) ......................................................................................... 11 Step 3 Negotiation of Interconnection Agreement .................................................................... 15 Protocol Compliance Review ......................................................................................................... 16 Stage 2: Registration and Modeling .................................................................................................. 17 Stage 3: Synchronizing, Commissioning, and Commercial Operations ............................................. 23 APPENDIX A: NEW GENERATION COMMISSIONING CHECKLIST ............................................................. 26 APPENDIX B: SUBCATEGORIES OF GENERATORS .................................................................................... 38 APPENDIX C: LIST OF ERCOT FORMS FOR INTERCONNECTION PROCESS ............................................... 39 APPENDIX D: GUIDE TO PROTOCOL AND OTHER BINDING DOCUMENTS .............................................. 40 APPENDIX E: SCREENING STUDY CHECKLIST ........................................................................................... 41 APPENDIX F: RESOURCE ASSESSMENT ANALYST CHECKLIST UPON RECEIPT OF IA FROM TSP .............. 43 APPENDIX G: SSR STUDY GRID SIDE SCREENING STUDY ...................................................................... 46 APPENDIX H: FIS SCOPE MEETING CHECKLIST ........................................................................................ 47 APPENDIX I: FIS MANAGEMENT PROCESS CHECKLIST ............................................................................ 49 APPENDIX J: PROJECT PROTOCOL REVIEW CHECKLIST ........................................................................... 52 APPENDIX K: ERCOT NOTICE FOR COMMISSIONING PLAN ..................................................................... 53 APPENDIX L: MODELING REQUIREMENTS FOR SYNCHRONIZATION WITH THE GRID ............................ 55
Acronyms and Abbreviations Acronym ECS TDSP AR ESI ID FIS GC GEN Map GINR GINR Coordinator IE Market Guides ME MRD NM NOIE NOMCR OA OPS OS PED POI PUCT QSE RARF RARI RE RIRE RSOC SCADA SCED SGIA SMOG SSR TSP/TDSPRA USA Definition ERCOT Client Services Transmission and/or Distribution Service Provider Authorized Representative Electronic Service Identifier Full Interconnection Study Grid Coordination Generation meter mapping data package Generation Interconnection or Change Request The ERCOT Resource Adequacy analyst who owns the GINR database and coordinates engineering access Interconnecting Entity The set of ERCOT documents binding upon market participants, including ERCOT Protocols, Planning Guides, Operating guides, etc. Meter Engineering Model Ready Date Network Modeling Non-Opt In Entity Network Operations Model Change Request Operations Analysis Operations Support Outage Scheduling Proposed Energization Date Point of Interconnect Public Utility Commission of Texas Qualified Scheduling Entity Resource Asset Registration Form Resource Adequacy Resource Integration Resource Entity Resource Integration Resource Entity Resource Outage Submittal Contact Supervisory Control And Data Acquisition Security Constrained Economic Dispatch Standard Generation Interconnection Agreement (commonly referred to as IA) Settlement Metering Operating Guides Sub-Synchronous Resonance Transmission and/or Distribution Service Provider Resource Adequacy User Security Administrator
In Stage 1, ERCOT accepts a request for interconnection studies and conducts a series of studies to evaluate the proposed resources effect on the system. If the proposed resource adds 10 Megawatts or more generation at the proposed point of interconnect, a Generation Interconnection or Change Request (GINR) application must be submitted along with applicable data and fees. Screening study completion and a notice to proceed from the interconnecting entity (IE) sets into motion the Interconnect Studies process. Once sub-synchronous resonance (SSR) and FIS studies are complete, an Interconnection Agreement (IA) may be reached. Upon completion of an Interconnection Agreement (IA), generator data sufficient to update the ERCOT planning cases shall be requested by ERCOT, and supplied by the Interconnecting Entity (ID). Stage 1 requirements are thoroughly documented in ERCOT planning guides section 5, available at: http://www.ercot.com/mktrules/guides/planning/index. Registration of the new Generation Resource and associated Resource Entity may commence during Stage 1 upon ERCOT receiving notice of commitment. In Stage 2, ERCOT models the new generation resource in future planning base cases, which it then makes available to the Transmission Service Providers (TSPs). In this stage, the Interconnecting Entity (IE) transitions to the Resource Entity (RE). Once registered, the RE must update the Resource Asset Registration Form (RARF). Also in Stage 2, ERCOT models the new resource node and builds a new network operations model to reflect changes. ERCOT requires the installation of telemetry points and the creation of a (SCADA) plan to establish real-time communication and control between ERCOT and QSE. In Stage 2, ERCOT also establishes ERCOT Polled Settlement (EPS) meter communication which allows gathering of real-time data for settlements. In Stage 3, ERCOT approves the Generation Resources Commissioning Plan, Request to Commission Point of Interconnection, Request for Initial Synchronization, and Request to Begin Commercial Operation described in the New Generator Commissioning Checklist (Appendix A). ERCOT acceptance of Reactive Power maximum leading and lagging capability tests, AVR test, and PFR test are required for ERCOT approval to begin commercial operation.
Public Utility Commission Substantive Rules 25.198 governs the interconnection of facilities to transmission service in Texas, and Substantive rule 25.109 governs the certification, licensing, and registration of generators. These rules may be found on the PUCT public website, and a guide to certification and licensing may be found at http://www.puc.texas.gov/industry/electric/business/pgc/Pgc.aspx ERCOT protocol section 1.6.5 identifies additional requirements binding market participants and describing the Standard Generation Interconnection Agreement. ERCOT protocols are available at http://www.ercot.com/content/mktrules/nprotocols. ERCOT planning guides section 5 provides further details governing ERCOT staff, and are available at: http://www.ercot.com/mktrules/guides/planning/index Interconnecting Distributed Generation (voltages below 60-kV) is described in PUCT substantive Rule 25.211, and is not discussed in this document.
Screening Study GINR (SSR if required) Request 90 Day Limit (FEE) 45 day target
Negotiation IE provides ERCOT Of resource data Assess Interconnection sufficient for standards Agreement Planning 60 day limit 180 day limit Models
Stage 1
Stage 2
Proposed Model Ready Energization Date (MRD) Date (PED) identified identified
RE submits RARF
EPS meter QSE Pts design list received proposal from from QSE based TSP on Scada Plan
Stage 3
SCADA Confirmed
Key Processes Generation Interconnection or Change Request (GINR) application process Pre-RARF provided to ERCOT ERCOT Screening Study Decision to proceed to Full Interconnection Study (FIS) FIS assigned to a TSP Negotiation of FIS study scope/pricing Complete RARF provided to ERCOT/TSP FIS FIS Acceptance by ERCOT Decision to proceed with and execute Standard Generation Interconnection Agreement (SGIA)
5-60
SGIA signed Project Development Resource Registration and Modeling Commissioning, Final Testing, Commercial Operations TOTAL
Up to 180 TSP must submit the executed SGIA to ERCOT within 10 business days. ERCOT has 60 days after receipt of the SGIA to review and comment on the projects adherence to binding requirements. Currently undetermined. ERCOT will take measures to increase transparency regarding timeline 120 to 180 60 to 120 270 minimum1 1028 typical2
Figure 3-Key Process Duration and Deadlines
GINR Cancellation
Minimum estimate 285 = 5 application + 45 Screening + 0 decision FIS + 40 FIS + 0 decision SGIA + 0 SGIA + 0 project dev. + 120 registration/modeling + 60 Test/commissioning 2 Typical estimate = 20 application + 45 screening + 30 decision FIS + 500 FIS + 11 decision SGIA + 62 SGIA + 180 project development + 120 registration/modeling + 60 test/commissioning
These forms may be obtained by download at http://www.ercot.com/services/rq/re/newgensteps.html. Once completed, these forms are submitted to ERCOT by email as distinct file attachments to [email protected] with e-mail subject Generation Interconnection or Change Request. Upon ERCOTs receipt of this initial package, the project will be assigned a unique GINR project tracking number. Project details such as Interconnecting Entity (IE), MW capacity, and site name are then entered into the GINR database. This initiates the interconnection application process. During this initial stage, the developer or group of developers is referred to as the Interconnecting Entity (IE) by ERCOT protocols and binding documents. The IE is responsible for submitting the entire application, including the abbreviated (preliminary) RARF data as described in the guide3. The IE will
The Resource Asset Registration Form (RARF) has entries describing the characteristics of the resource. Screening studies may be completed with an abbreviated set of information. Instructions for what information MUST be filled out in each step are posted at http://www.ercot.com/services/rq/re/newgen-steps.html under the link Screening Study/Full Interconnection Study Guides (.zip). Start with Gen_Form_Guide_locked.xls Note that the pre-RARF is the same document as the RARF. Instructions for the pre-RARF simply allow incomplete submissions.
10
also declare its proposed initial commissioning date (COD) and the proposed Point of Interconnect (POI). In addition to providing the informational forms, the IE must pay an ERCOT Security Screening Study fee. The Security Screening Study fee will be determined by the capacity of the proposed resource. A $5,000 fee will be assessed for projects less than or equal to 150-MW. A $7,000 fee will be assessed for projects greater than 150-MW. This fee is non-refundable. The Screening Study will be completed by ERCOT in a maximum of 90-days. This study identifies steady state transmission constraints at the proposed generator interconnection point which will require transmission improvements to allow full output. Screening Study 1. The Interconnecting Entity (IE) initiates the Screening Study process by requesting a study through the Generation Interconnect or Change Request (GINR) email at [email protected]. The GINR coordinator creates an entry for the project in the GINR database, assigning the project its GINR identification code. IE also submits the initial data needed to model the resource. 2. In accordance with Planning Guides, ERCOT has 90-days to complete the Screening Study. ERCOT strives for a 45-day response. 3. The Screening Study is assigned to a Resource Integration engineer. This engineer notifies the IE of the assignment, and will be the main point of contact for the IE through Stage 1 of the interconnection process, which takes the project through the ERCOT review of Protocol requirements. A checklist describing the steps taken by ERCOT in the screening study is included in Appendix E. As a part of each screening study, the ERCOT engineer will review the point of interconnection for possible SSR risk as follows. Screening Study: SSR Risk Grid Screen A sub-synchronous resonance screen is performed by a Resource Integration engineer if the engineer determines, through a visual evaluation of the proposed resources location, that any set of five single or double-circuit contingencies can make the proposed generation interconnection connect in series to a series-compensated transmission line. Appendix G contains a checklist for performing this SSR screening study. 4 Upon completion of the Screening Study, the Interconnecting Entity (IE) has 180-days to notify ERCOT in writing of its intention to pursue the project by proceeding to the Full Interconnection Study (FIS). After 180-days, the results of the Screening Study will expire, and the GINR will be cancelled. Any further action on the project will require a new GINR application, including the payment of a fee for a new study.
11
The FIS is a set of 4 to 6 studies conducted by the TSP under an agreement with the Interconnecting Entity (IE). These studies always include: 1. 2. 3. 4. Steady state and transfer analysis Short-circuit and breaker duty review Dynamic and transient stability analysis Facility study
Two further studies may be required: 5. An SSR Study may be required based upon the results of the SSR screening analysis. 6. An Economic Study will be required if the estimated cost of transmission improvements exceeds 25million dollars. FIS Scope Meeting The Interconnecting Entity initiates the Full Interconnection Study (FIS) scope meeting process by submitting to a GINR coordinator, through email to [email protected] the following: 1. 2. 3. 4. Written notice to proceed with FIS Resource Integration form Payment of Stability Modeling fee Proof of Site Control
This request may take place even before the Screening Study is completed if requested by the IE. When FIS studies are quested by the IE, the ERCOT GINR coordinator notifies the engineer who performed the original Screening Study for this project, and enters the request date into the GINR database. The assigned engineer organizes a scoping meeting with the TSP and IE in attendance. A checklist for the scoping meeting is included in the Appendix H. The FIS scoping meeting defines the scope of work for the Full Interconnection Studies. ERCOT will facilitate this interaction, and an ERCOT representative will either attend the initial meeting in person or participate via phone. It is the responsibility of the TSP and the IE to reach an agreement on the scope of the studies within 60-days. If the TSP and the IE cannot reach an agreement the GINR will be terminated. Before this termination takes place, the ERCOT engineer will attempt to mediate an agreement. To initiate Full Interconnection Studies, the IE will pay ERCOT a stability modeling fee. Full Interconnection Study (FIS) If requested by the RE, the FIS process may begin prior to completion of the Screening Study. But ERCOT discourages this practice. ERCOT conducts the screening study, but the interconnecting TSP conducts the FIS. The FIS proceeds as follows: 12
1. Once an FIS scope agreement has been reached between the IE and the TSP, and the ERCOT RI Engineer has approved the scope, the TSP proceeds with the studies. 2. After FIS scope agreement, ERCOT Protocol section 1.3.1.2 allows publication of the following information, which will be included in the next public report (Reliability & Operations Subcommittee planning report - ROS report): a. Project INR Number b. Facility nameplate capacity c. Facility fuel type d. County where facility is located 3. ERCOT verifies the pre-RARF data requirements per the Screening Study/Full Interconnection Study Guides for information needed for FIS has been received by ERCOT and forwarded to the TSP performing the FIS studies if necessary. FIS Study descriptions 1. Steady State Analysis- This analysis is created from the most recently approved Steady State Working Group power flow base case for the interconnection year. It will identify transmission facilities which may have a limiting impact on resource output. The TSP shall perform contingency analysis sufficient to demonstrate existing or planned transmission capacity in the area meets ERCOT Market guides and NERC transmission criteria following installation of the proposed resource. If insufficient transmission capability exists to interconnect the proposed resource without congestion, the analysis will propose facility improvements which can accommodate the proposal without limitation. Specifically: a. Pre-contingency flows below normal rating or a RAP in place (Operating Guide 3.7.2) b. Credible Single Contingencies as defined in the Planning Guides shall not result in i. Cascading or uncontrolled Outages ii. Instability of Generation Resources iii. Interruption of service to firm demand or generation other than that isolated by the Credible Single Contingency. c. Demonstrate proposed addition will not result in violation of NERC TPL standards. 2. Short Circuit Study - The FIS agreement shall specify locations where available short-circuit fault duty will be identified, calculated, and documented. If any of the required transmission system improvements associated with the GINR result in violations of the TSP short circuit criteria, the TSP shall plan and identify facilities to address those violations. . The initial short-circuit base case transmission configuration shall be the System Protection Working Group base case for the resources first planned year of commercial service.
13
3. Dynamic and Transient Stability Analysis- The interconnecting TSP shall perform these studies examining the proposed units response to transient events on the ERCOT transmission grid including local transmission faults and the expected normal and delayed clearing of faults. All existing or publicly committed resources in the area shall be modeled at full net output. The initial stability study base case transmission configuration shall be the Dynamic Working Group base case for the resources first planned year of commercial service. Transient Stability Studies will analyze the performance of the proposed Generation Resource and the ERCOT system. Studies must meet NERC requirements. 4. Facilities Study- This study provides details and estimated cost of the facility requirements for the direct interconnection of the proposed Generation Resource project to the TSP. The Facilities Study includes conceptual design descriptions, construction milestones, and detailed cost estimates for all direct interconnection-related transmission and substation facilities proposed to be installed in accordance with the findings and recommendations of the other FIS studies. 5. SSR study - If the ERCOT Screening Study determines that a detailed study is required; this study shall also be included in the scope of the FIS. 6. Economic Study - This study is required only if the ERCOT screening study or Full Interconnection Studies (typically steady state analysis) identify transmission upgrades expected to cost more than $25 million. If facilities cost is estimated as exceeding the $25 million threshold, notification from the TSP to ERCOT that an Economic Study will be required (email to [email protected]) must take place within ten days of estimating the facilities cost. This notification shall contain a description of the proposed interconnection facilities; information necessary to modify a power flow case to include these facilities, and any other information available to the TSP required to model the proposed generation resource and estimate cost/benefit of the proposed facilities. This study is performed by ERCOT and does not require a financial contribution from the IE. These reports are typically available within 30 days of request, but there is not a binding timing requirement.
The FIS process is complete upon ERCOT approval of the last report submitted by the TSP to ERCOT. ERCOT shall approve or request revisions to this report within 10-days. ERCOT provides each of these reports to all TSPs for review via mailing list TRANSMISSION [email protected]. If revisions are requested, the 10-day clock for approval resets. ERCOT is not a party to the FIS contract. The cost and responsibility for completing each internal phase of the FIS lies with the IE and the TSP. Currently, there is no hard time limit for completion of the FIS. However, the IE is required to update ERCOT any time there are changes to the proposed system design during the FIS process, and the IE must provide an affidavit every September and October that the RARF is correct. The IE is required to conduct new studies if the capacity increases by more than 20%, or if the proposed resource specifications are revised making the existing studies invalid. A checklist for ERCOT actions in coordinating the FIS studies is included in Appendix I. 14
15
16
5 6
Registration must take place at least 130 days prior to the Commercial Operation Date (COD). When this document was written, PUCT requirements for registration were contained in rule 25.109 Registration of Power Generation Companies and Self-Generators
Market Information System (MIS) access. The process, which usually takes 10 to 15-days, is composed of the following key components: 1. Registration as a Resource Entity a. Submission of Resource Entity (RE) Application for Registration b. Designation of a Qualified Scheduling Entity (QSE) c. Issuance of ERCOT Digital Certificates d. Initial submission of a Resource Asset Registration Form (RARF) 2. Execution of a binding Standard Form Market Participant Agreement 3. Submission of a Decision Making Entity (DME) or Managed Capacity Declaration Form The RE Application for Registration form has 3 critical subcomponents: 1. Basic Entity Information - Each registering RE needs to provide basic company information that allows ERCOT to enter the entity into the Registration systems and populate ERCOT systems with necessary information. This information includes legal company name, Dun & Bradstreet DUNS number, address and company officers.
2. Designation of a Qualified Scheduling Entity (QSE) - Each new Resource Entity (RE) must designate a QSE to be associated with the new generation resource. This QSE will work with the RE during the commissioning and final steps of the interconnection process. The QSE will be responsible for scheduling and directing ERCOT dispatches to the generation resource. For an overview and more information on QSEs and QSE qualification, see the QSE Qualification Guide.
3. Designation of a User Security Administrator (USA), an Authorized Representative (AR), and a Resource Outage Submittal Contact (ROSC) - Every RE must identify these key personnel, as they will be the primary contacts for a variety of ERCOT- related market and system activities. Designation of a User Security Administrator (USA) permits ERCOT to issue the RE with digital certificates that allows it to interact with ERCOT systems to submit and receive information. This includes important communication tools such as resource outage scheduling and access to ERCOTs Market Information System (MIS). After the submission of the RE application, ERCOT will send the RE a Standard Form Market Participant Agreement to be executed. The Standard Form Market Participant agreement legally binds the RE as Market Participant to comply with ERCOT protocols and all applicable binding documents. This agreement established the legal framework for an MP to operate in the ERCOT market. In addition to the Registration Form the RE will also be required to complete the Resource Asset Registration Form (RARF) for each All-Inclusive Generation Resource being registered. The RARF is the foundational dataintake document for ERCOT systems. It is a package of forms and spreadsheets that facilitates the assembly of operational parameters and data about a generation resource. When a RARF is submitted to ERCOT it goes through two phases of validation. The first step of validation is an automated process targeted for completion within 3 (three) days of RARF receipt. The second phase of RARF validation involves an engineer attempting to integrate the data into the ERCOT models, and is normally completed within 5 (five) additional days. Completion of the RARF is typically an iterative process, and sufficient time for multiple iterations should be allowed. As part ERCOT Public Page 18 of 60
of the RARF, the RE will indicate its Proposed Energization Date (PED), which will dictate the timeframe for the rest of the interconnection process. The PED must be a point in time when all physical transmission infrastructure, the Point of Interconnect (POI), and the modeling for the generator will be in place and functioning as indicated in the RARF form. The process for submission of modeling information must be complete more than 90 days prior to the 1st of the month in which the resource expects to energize. (In accordance with protocol 3.10.1 Time Line for Network Operations Model Changes) After ERCOT approval, the resource may be energized in preparation for synchronization with the ERCOT grid. Complementary to the RE Form is the Managed Capacity Declaration Form. This form identifies for ERCOT the Decision Making Entity (DME) with authority over the generation resource. The DME is defined as the agent with authority over the generation resource, including the authority to put the resource into the market and offer the unit. This measure ensures competitiveness in ERCOTs deregulated electricity market after initial registration of the RE and submission of the completed and accepted RARF the interconnection process shifts to a ~130 day countdown leading to the proposed energization date (PED). Within 15-days of receiving a valid7 and complete RARF and the Proposed Energization Date (PED), ERCOT Client Services (ECS) will confirm the Model Ready Date8 (MRD) for adding the new All-Inclusive Generation Resource to the Network Operations Model. A Note about the RARF The RARF is used by ERCOT to collect definitive information about a generation resource. Information from the RARF is pulled into many of ERCOTs internal systems. It is a critical component of ERCOTs ability to accurately model and coordinate generation resources in the grid. Accuracy and completeness of the information contained in the RARF is essential. During the interconnection process, the RARF is an evolving document. In the first phasepreFIS and FIS studiesthe IE will submit an abbreviated version of the RARF which is used in planning and evaluation of the impact of the resource on ERCOT grid. After the IA is signed and all other criteria is met for inclusion into the Planning Models in accordance with section 6.9 of the Planning Guides, additional data must be submitted as outlined in the Screening Study/Full Interconnection Study Guides tab Spreadsheet Map for tabs Needed for Planning Models. During the RE registration process, the new RE must submit a completed RARF document which is needed for inclusion of the resource into the Network Operations Model. During the interconnection (stage 1) process, it is likely that the details in the RARF may be incomplete or change as the RE completes the requirements to begin commercial operations. This will require further updates and could require revised FIS studies. It is critical that the RE continually update the RARF document to reflect any such changes. The RARF submission process is automated and ECS automatically audits RARF documents for errors and completion. Failure to update the RARF can lead to delays in commissioning.
7
Note that validation of the Resource Asset Registration Form (RARF) usually takes several submission/ERCOT review and resubmission cycles. 8 Model Ready Date (MRD) is the date that generator parameters are loaded into the ERCOT energy management and market systems, allowing the proposed generator to be recognized by ERCOT operations systems. Protocols call for the parameters required for this load be provided 90 days prior to the MRD. Note that the MRD does not load data into the lodestar system which is required for settlements.
ERCOT Public
Page 19 of 60
Step 2: Modeling, Metering, and Telemetry The final technical phase of the interconnection process begins once the organizational structure and resource data have been received by ERCOT via the RE registration process. In this step, the logical and system structure for dispatching, metering, and communicating with the new generator will be established and verified prior to being loaded into the ERCOT Network Operations Model. This model is updated on a scheduled basis, with a set model load date calendar9. On the model load date, ERCOT systems will link together the following key components: 1. Metering and Meter Data Acquisition System (MDAS) 2. ERCOT market settlement information and pricing location 3. Supervisory Control And Data Acquisition (SCADA) and Inter-Control Center Communication Protocol (ICCP) communication points 4. QSE and RE relationship and contact information Establishing these links requires coordination between all involved MPs and internal ERCOT departments. ERCOT Client Services maintains a coordination log as a reference for this process. Appendix C also provides a list and links for how to submit this data to ERCOT. Figure 4 outlines the normal successful timeline with respect to the Proposed Energization Date (PED). Refer to Appendix L for further details. The responsibility for these submissions is shared between the TSP, RE, and QSE.
Days Prior to PED 130-days 130-days Days Prior to PED 45-days 35-days
Process
TSP Network Model Data
Process
QSE Points list & Commissioning Plan EMS Database load for QSE (if needed)
RE Registration
Submit Resource Asset Registration for target Model Ready Date (MRD)
EPS Cutover Form EMS Database Load for RE New Generation Part 1 Checklist Submitted Date POI is cleared to energize
The model load calendar is located on the ERCOT website at: http://www.ercot.com/gridinfo/transmission/opsys-change-schedule.html
ERCOT Public
Page 20 of 60
1. Model data through the Network Operations Model Change Request (NOMCR) process a. The TSP is responsible for submitting network modeling information to ERCOT for equipment it owns through the NOMCR process. More details about this process are available in the Network Operations Modeling and Expectations Guide 2. Metering plan EPS Design Proposal The design of EPS equipment and a one-line diagram of the TSPs interconnection and the generator site topology. This plan is reviewed and approved by ERCOTs Meter Engineering (ME) group. The ME group will also conduct a site certification review after energization. For more details about metering and technical requirements refer to the Settlement Metering Operating Guide 3. Meter Data Acquisition Form Verification of meter telemetry and communication with ERCOT meter polling systems. 4. EPS Cutover Form Submitted 15-days before meters are officially cut-over to ERCOTs systems, this will occur at the same day as the model load date. QSE must submit: 1. Outage Schedule In the final stage of the interconnection process before energization, on the Model Ready Date (MRD) the new resource will become live in ERCOT systems. To ensure that the generator is not dispatched by ERCOT, the QSE must submit an outage through the outage scheduler. This outage status will be updated throughout the final verification and testing phases. 2. SCADA plan The SCADA plan is generated by ERCOTs operations group and is a guide for what resource and interconnection telemetry points are needed for ERCOT to oversee the grid. This plan is built in collaboration with the QSE and ERCOTs Energy and Market Management Systems (EMMS). The process begins with the RE or QSE coordinating a SCADA plan for the proposed unit from ERCOT via their client representative. ERCOT will provide a point list of proposed SCADA points and their definition for the QSE and RE to review and begin implementing. 3. ICCP Points list This list is a final update of the communication and telemetry points agreed upon between ERCOT and the QSE. 4. Verifiable Costs Verifiable Cost encompasses data that represents the actual start-up and minimum energy at Low Sustainable Limit (LSL) applied in economic commitment and deployment in accordance with ERCOT Protocol Section 5.6.1, Verifiable Cost.
RE must submit: 1. Model data through the ERCOT-prescribed process applicable to Resource Entities o The RE is responsible for submitting network modeling information to ERCOT for equipment it owns through the ERCOT-prescribed process applicable to Resource Entities. 2. GEN Map package verification The GEN map package is compiled by ERCOT and includes the final version of the how the resource node
ERCOT Public
Page 21 of 60
and metering will be mapped. The All-Inclusive Generation Resource must be modeled in the Network Operations Model before this process can be completed. The RE will verify this information with ECS. 3. Updated RARF document If at any point the parameters of the All-Inclusive Generation Resource that are documented on the RARF are changed, the RE must submit an updated RARF. All these data submissions and verifications are designed to take effect on the Model Ready Date (MRD). On this day, with submission of the EPS Cutover form, all telemetry and metering with ERCOT will be fully functional and the resource will appear in the ERCOT Network Operations Model. At this point, the All-Inclusive Generation Resource is modeled such that it can be dispatched, scheduled, and settled in ERCOT market systems. However, it will not be permitted to energize until a final round of technical verifications. These final verifications are captured in the last step, Stage 3: ERCOTs New Generation Commissioning Checklist (Appendix A)
ERCOT Public
Page 22 of 60
Client Service Rep. acquires ERCOT EMS one-line diagram (Genmap) from ERCOT modeling group
Reviews SCADA plan and ERCOT One-line with IE and resolves questions
Client Rep
Respond to questions & get agreement on SCADA plan Agreement on ICCP points?/ Scada plan?
Approve Energization
Yes
Interconnecting Entity
Yes
Submit New Generation Commissioning Checklist Part ! For approval to energize Energize
KEY
Normal flow solid line Single arrowhead: one way abnormal flow dashed line Double arrowhead:bidirectional
Process
Document
Decision
10
ERCOTs determination that a Generation Resource meets the requirements for energization, synchronization or commercial operations should not be construed as a waiver of ERCOTs right to require compliance with any operational standard, even if the non-compliance with that standard could have been identified when the determination was made.
ERCOT Public
Page 23 of 60
At least 30-days before submittal of PART 1 of this checklist, the Resource Entity and its QSE are to submit a commissioning plan, detailing how the facility will be operated during testing of generation and systems while supporting grid security in accordance with ERCOT Protocols. ERCOT will review the commissioning plan and provide feedback on compliance with operational standards as well as possible operational limitations during commissioning of the new generation facility. Approval of PART 2 of the checklist is contingent on completion of the commissioning plan review. This system operations procedure verifies critical communication points and generation security measures before allowing energization, synchronization, or commercial operations. This checklist process is coordinated by the ECS group, but all final approvals are made by ERCOTs Operations Support Engineering (OE). In all cases, the checklist sections must be submitted 10-days before the milestone dates. The responsibilities and milestones of the checklist process are as follows: 1. Checklist Part 1 Request to Commission Point of Interconnection Submitted by the RE Resource cleared to Energize 2. Checklist Part 2 Request for Initial Synchronization Submitted by the QSE Resource cleared to Synchronize 3. Checklist Part 3 Request to Begin Commercial Operations Submitted by the RE Resource cleared to begin Commercial Operations
New Generator Commissioning Checklists Part 1 (energization & back-feed) & Part 2 (initial synchronization) are used to verify that the QSE and RE have established the appropriate network operational modeling, communications with ERCOT, and that they are in compliance with the SCADA plan and ICCP points that were established in the registration process. Upon receipt of the checklists, ERCOT uses them while verifying the AllInclusive Generation Resource is communicating data to ERCOT systems with the proper frequency and correct values. The steps and required coordination with ERCOT to energize and synchronize are described in detail in the checklist document in Appendix A. Checklist part 3 (request to begin commercial operation) requires a final stage of coordination with ERCOT before the resource will be approved to begin commercial operations. The All-Inclusive Generation Resource will provide ERCOTs Operations Analysis (OA) group performance testing results of the resources maximum lagging and leading reactive capability, Automatic Voltage Regulator (AVR) test results, and Primary Frequency Response (PFR) test results. This is ERCOTs final verification that the Resource can demonstrate the requirements for voltage support and frequency response specified in the protocols. The Checklist 3 test/document must be submitted at least 7-days prior to the desired commercial operation date. ERCOT recommends submission 20 to 30 days prior to the desired commercial operation date to avoid delays.
ERCOT Public
Page 24 of 60
The Reactive Capability, AVR, and Governor performance Tests The Reactive Power Capability, AVR and Governor Performance tests are the final step before approval to begin commercial operations. Remember, Part 3 of the New Generator Commissioning Checklist must be submitted at least 7-days before the proposed commercial operations date. These tests are described in the ERCOT Operating Guides sections 2.2.5 (AVR), 2.2.7 (Turbine governors), and 3.3.2.2 3.3.2.3(Reactive testing).
Normally, the Reactive Power Capability test may be performed with minimal coordination with ERCOT as described in section 3.3.2.2 of the ERCOT Operating Guides. (Available at http://www.ercot.com/mktrules/guides/noperating/lib) If assistance of other reactive resources is needed to exercise the full reactive capability, a Coordinated Reactive test as described in the Operating Guides may be utilized. Both coordinated and non-coordinated tests meet ERCOTs commissioning requirements for approval to begin commercial operation. Although ERCOT operating guides recommend maximum leading reactive tests be performed in low load months, and maximum lagging reactive tests be performed in high load months, this is often not possible for initial operation. Testing shall be attempted for both leading and lagging performance. If a resource repeatedly attempts to perform testing including an attempted coordinated test, and is unable to succeed due to external system conditions, ERCOT may recognize the need to delay testing and provide written documentation of this recognition to the resource entity. Completion of checklist Part 2 allows an RE and its associated QSE to participate in the ERCOT energy market, be dispatched by Security Constrained Economic Dispatch SCED, and be available for Reliability Unit Commitment (RUC). Note, however, that the process for qualifying to provide Ancillary Services (AS) to ERCOT is separate and is typically determined at some point after beginning commercial operations depending on the Resource and the desire to provide those services. AS qualification is described in the QSE Qualification Guide.
ERCOT Public
Page 25 of 60
Purpose
This checklist is intended to coordinate the energization, synchronization, and commercial operation of new Generation Resources in accordance with the ERCOT Protocols and Operating Guides, including ERCOT Protocols 3.10.6, 3.10.7.2, 3.15, 6.5.5.2, and 16.5, ERCOT Planning Guide 5.7.1 (4)(d), and ERCOT Operating Guides Sections 2.2.5, 2.2.6, 2.2.7, 3.2.1, 3.3, 7.1.2., 7.3. In the event of any conflict between the Protocols or Operating Guides and this checklist, the Protocols or Operating Guides shall take precedence. ERCOTs determination that a Generation Resource meets the requirements for energization, synchronization or commercial operations should not be construed as a waiver of ERCOTs right to require compliance with any operational standard, even if the non-compliance with that standard could have been identified when the determination was made.
2.
ERCOT Public
Page 26 of 60
3.2.2 Day of Synchronization On the day of the planned initial synchronization, the QSE must re-confirm the intended synchronization with the Shift Supervisor via telephone. The Generation Resource must be started up in Test mode. Maximum capability and MVAR testing for the new unit will be planned in accordance with ERCOT Operating Guide.
ERCOT Public
Page 27 of 60
3.3 Commercial Operations After synchronization of the Generation Resource, the QSE and Resource Entity may submit a request to begin commercial operation upon completing requirements of Section 3.15(3) of the Protocols (PART 3 of the Checklist). The request should be submitted at least 10 business days before the intended date of commercial operations. However, commercial operations may begin before the expiration of 10 business days upon verification that the Generation Resource is in compliance with the Reactive Power capability requirements. Upon approval of the request for commercial operations, ERCOT will consider the Generation Resource available for economic and reliability dispatch. The QSE shall update the COP and telemetry to indicate non-testing operations.
ERCOT Public
Page 28 of 60
Primary contact for Station Commissioning (Contacts may be REs Agent): Primary Contact Name: Primary Contact Telephone Number: Primary Contact E-mail Address:
Gen Site Name: Load Zone: Special Protection Scheme (SPS) Yes No
No
Identify the QSE/TDSP responsible for sending ERCOT station telemetry: QSE: QSE primary contact (may be QSEs Agent): Name: Telephone Number: E-mail Address: TDSP: TDSP primary telemetry contact: Name: Telephone Number: E-mail Address:
The QSE and Resource Entity are required to comply with the ERCOT Protocols and Operating Guides from the moment the interconnection becomes operational. The Resource Entity confirms that the following requirements have been met: [Submit PART 1 with copy of current Commissioning Plan] The Generation Resource is in the ERCOT Control Area. Station telemetry to QSE and TDSP from the facilitys Point of Interconnection is in place and operational as of (date), as required under ERCOT Operating Guide Section. 7.3 Telemetry and the ERCOT Nodal ICCP Communication Handbook. Enter specific comments about status of station telemetry in comment box on telemetry checklist below. The QSE is capable of communicating the Resources Point of Interconnection information to ERCOT in the manner specified in Operating Guides Section 7.3, Telemetry, and Protocols Section 6.5.5.2, Operational Data Requirements, and any other information required by Section 3.10.7.5, Telemetry Criteria. Instructions for ERCOT to escalate telemetry quality issues with QSE/RE during commissioning: ERCOT Public Page 29 of 60
Station Telemetry
Data Frequency Mode Reference/Comments Protocol Section 6.5.5.2, Operational Data Requirements. (High side Typical TSP telemetry point; Low side typical QSE telemetry point) 10 sec ICCP RE Comment: Protocol Section 6.5.5.2, Operational Data Requirements. (Typical QSE telemetry point) 10 sec ICCP RE Comment: Protocol Section 3.15, Voltage Support. May be supplied by the TDSP (Typical TDSP telemetry point) or Low Side voltage with appropriate transformer model may be substituted (Typical QSE telemetry point). 10 sec ICCP RE Comment: Protocol Section 6.5.5.2, Operational Data Requirements.(Typical QSE telemetry point) 10 sec ICCP RE Comment:
ERCOT Public
Page 30 of 60
By signing below I attest that information provided on this form (PART 1) is true, correct and complete, and that any substantial changes in such information will promptly be provided to the Electric Reliability Council of Texas (ERCOT). Signature:
(RE Authorized Representative)
Printed Name:
(RE Authorized Representative)
Date Signed:
ERCOT Public
Page 31 of 60
Primary and back-up contact personnel for Initial Synchronization (may be QSEs Agent): Primary for Initial Synchronization Contact Name: Primary Contact Telephone Number: Primary Contact E-mail Address: Back-Up Contact Name: Back-Up Contact Telephone Number: Back-Up Contact E-mail Address:
*If the unit is Split Metered: Identify the QSE responsible for coordinating the start-up testing: Identify all of the QSEs that are sharing this unit: Projected Commercial Operation Date (unit available for market and/or reliability commitment):
The QSE and Resource Entity are required to comply with the ERCOT Protocols and Operating Guides from the moment the interconnection becomes operational. The QSE will comply with procedures for new unit start-up testing, with initial synchronization schedule communicated to ERCOT Shift Supervisor. The QSE confirms that the following requirements have been met: Telemetry from the facility (station and generation) is in place and operational as of (date) to QSE and TDSP (Optional). Enter specific comments about status of telemetry in QSE comment box on telemetry checklist on next page. QSE telemetry is being provided to ERCOT ISO (This information is summarized in PART 2 QSE New Generator Telemetry Checklist and is provided to assist Market Participants in identifying the telemetry required under ERCOT Operating Guide Section 7.3 Telemetry and ERCOT Nodal ICCP Communication Handbook). Instructions for ERCOT to raise telemetry quality issues with QSE/RE during commissioning: QSE confirms voice and data communications with the Generation Resource, ERCOT, and TDSP (Optional) ERCOT Operating Guide No. 3.2, 7.1.2. Comments:
ERCOT Public
Page 32 of 60
ERCOT Public
Page 33 of 60
Generating Unit gross and net MVar output Switching Device status other than reported in PART 1 Breaker status other than reported in PART 1 Generating Unit High Sustainable Limit Generating Unit Low Sustainable Limit Generating Unit Automatic Voltage Regulator status
Protocol Section 6.5.5.2, Operational Data Requirements. 10 sec ICCP QSE Comment:
Protocol Section 6.5.5.2, Operational Data Requirements 10 sec ICCP QSE Comment: Protocol Section 6.5.5.2, Operational Data Requirements. 10 sec ICCP QSE Comment: Protocol Section 6.5.5.2, Operational Data Requirements. 10 sec ICCP QSE Comment: Protocol Section 3.15.3, QSE Responsibilities Related to Voltage Support. Applies to units required to provide VSS. 10 sec ICCP QSE Comment: Protocol Section 3.15.3, QSE Responsibilities Related to Voltage Support. Applies to units required to provide VSS. 10 sec ICCP QSE Comment: Protocol Section 6.5.5.2, Operational Data Requirements as specified in ICCP Communications Handbook. As Specified ICCP QSE Comment:
ERCOT Public
Page 34 of 60
Additional Wind Resource Data Wind Speed (Miles per Hour) Wind Direction (Degrees) Temperature (Celsius) Barometric Pressure (Millibars)
Frequency (sec) 10 10 10 10
Protocol Reference
6.5.7.1.13 (1) (d) 4.2.2 (1) (implied) 4.2.2 (1) (implied) 4.2.2 (1) (implied) 4.2.2 (1) (implied)
By signing below I attest that information provided on this form (PART 2) is true, correct and complete, and that any substantial changes in such information will promptly be provided to the Electric Reliability Council of Texas (ERCOT). Signature:
(QSE Authorized Representative)
Printed Name:
(QSE Authorized Representative)
Date Signed:
ERCOT Public
Page 35 of 60
RE Name: QSE Name: Date of Notice: Gen Site Name: Gen Unit Code(s): Proposed Commercial Operation Date*:
* Actual date contingent on completion of requirements and approval from ERCOT.
In accordance with Protocols Section 3.15(3), Voltage Support, adequate reactive capability has been demonstrated by either performance test or engineering study, as checked below. If system conditions do not allow for a test to be completed ERCOT may at its discretion grant an extension.
Reactive performance test submitted and approved by ERCOT. Comment: Engineering study submitted with this notice. Comment:
I understand that ERCOT must provide confirmation that this Resource has demonstrated adequate reactive capability before commercial operations may begin.
By signing below I attest that information provided on this form (PART 3) is true, correct and complete, and that any substantial changes in such information will be provided to the Electric Reliability Council of Texas (ERCOT) in a timely manner.
RE Signature:
(RE Authorized Representative)
Printed Name:
(RE Authorized Representative)
ERCOT Public
Page 36 of 60
ERCOT Public
Page 37 of 60
Combined Cycle Generation Resource Intermittent Renewable Resource (IRR) Quick Start Generation Resource (QSGR) Split Generation Resource
Outage Schedule QSE ICCP Points List New Generation Checklist, Part 1 New Generation Checklist, Part 2 Net Dependable Capability and Reactive Capability (NDCRC New Generation Checklist, Part 3
MIS System MIS System New Gen Checklist New Gen Checklist MIS System New Gen Checklist
References
Planning Guide Section 5 Planning Guide Section 5.2 Planning Guide Section 5.3 Planning Guide Section 5.4.1 Planning Guide Section 5.4.2 Planning Guide Section 5.4.8 Planning Guide Section 5.5 Planning Guide Section 5.5 Protocol Sections 2, 3, 16 Nodal Operating Guides Sections 2, 3, 5, 7 Protocol Section 16.5.2 Other Binding Documents Protocol Section 10 Settlement Metering Operations Guide Nodal Operating Guide Sections 2, 3, 7 Nodal Operating Guide Sections 7 Nodal ICCP Communication Handbook Protocols Section 3.1 Protocols Section 3.14 Protocols Section 22 Attachment
Increase nearby dispatchable thermal generation to 100% output and nearby wind to 80% output if in the West and 95% output if in the Coast. Dispatchable exc ludes Mothball, Private Use Network, Hydro, Nuclear, Equivalent, and Blackstart, as these are not normally available for dispatch. Engineer inspects the NON_MB_GENS subsystem list and removes any units which are nearby the interconnection study area. The increase in nearby generation is couter-balanced by scaling down generators in subsystem NON_MB_GENS. If the slack bus is in the study vicinity, the Engineer changes it to a distant generator. All changes are noted in the report.
(5) If the project is in the South or West zone, the project may be affected by nearby wind patterns. The engineer will thus create a second case for study, a high wind case, (6) Engineer lists the identified equipment overloaded in study case(s). (9) Engineer adds the proposed generator to the study case with capacity indicated by the Interconnection Request and engineer sets the Qmin Qmax reactive power limits to fixed quantities corresponding to 0.95 power factor capability. (10) Using AC Transfer Limit Analysis, RI Engineer examines base case and N-1 contingency limitations for the proposed generators. Engineer identifies Max transfer limit and limiting contingency and element for each scenario. Engineer documents these results in the report using the report template. (11) If flows on transmission equipment are >100% of the equipment rating with the study generator injecting at 120% of capability, the RI Engineer identifies and models appropriate transmission upgrades or additions as necessary to allow injection without limit violations. Equipment rating upgrades will be applied using industry standard available conductor and facility ratings. The RI engineer reruns the study to confirm the overloads are resolved. (12) The engineer notes the list of applied upgrades or reconfigurations in the report. (13) Reviewing a map, RI Engineer determines if any set of 5 single or double circuit contingencies on the same towers can make the proposed generator interconnection connect in a series to a series-compensated transmission line. (13a) If so, engineer performs a Sub Synchronous grid side screening study. (15) If additional Point of Interconnection will be studied, repeat all steps for additional POI.
ERCOT Public
Page 41 of 60
ERCOT Public
Page 42 of 60
o VRT requirements may be met by the performance of the generators; by installing additional reactive equipment behind the POI; or by a combination of generator performance and additional equipment behind the POI. VRT requirements may be met by equipment outside the POI if documented in the SGIA. Confirm AVR is included in the design, and it will be operated in voltage control mode. Protocol section (3.15.3 & 3.15 [5]) Confirm unit can respond to changes in the voltage profile. Protocol Section 3.15 Confirm reactive capability is based upon the ability to deliver to the HIGH side of the step-up transformer. Protocol section (3.15 [3]) The Resource Integration Engineer evaluates the information provided by TSP, cites evidence sources that back up the decision, formulates a protocol compliance review letter to the Interconnecting Entity, and scans a copy of results to the project folder. Resource Integration Engineer then sends letter to Legal Department for review. Upon authorization from Legal Department, the engineer sends the letter to the interconnecting TSP and IE. Engineer copies ERCOT Client Services (Ed Geer or Account Rep, if designated already) on the email. Engineer also notifies RI Manager of checklist completion and of the results. If the RI Engine ers decision was negative, or not enough information, TSP is directed to send information necessary to the same engineer. In case of not enough information RI Engineer must specify which changes need to be made. Engineer updates the GINR database the day the letter is sent to the TSP and IE, entering the date in the appropriate field, and saves a copy of the IA review letter in the project folder. If the engineers decision was Insufficient information at this time or Not meeting standards, engineer repeats steps 7 through 11 as needed until all requirements are met, at which time, engineer updates the GINR database with the date of IA approval.
ERCOT Public
Page 44 of 60
ERCOT Public
Page 45 of 60
Phase 2- Conversion using ETran Setup ETran parameters for a hybrid Pi model. Use the .etr file for Etran settings. Convert the base case selected will be converted into .psc format using ETran software
Phase 3 PSCAD run Read the ETran converted electromagnetic model of the area into PSCAD. Create the frequency injection model from the point of turbine connection, and the Graph model in PSCAD. Run a simulation of current injections at different frequencies, and model the frequency/impudence characteristic of the grid for base case conditions. Create scenarios based on the credible planning contingencies as per NERC standard TPL-005 contingencies. Plot Resistance(R) and Reactance(X) are plotted under these conditions. (To prepare for the next contingency, system adjustments may be made, including changes to generation, uses of the transmission system if necessary to make a credible case under contingencies) Once all possible ERCOT credible contingencies have been studied, create a scenario in which the connection of the POI is radial with that of series compensation. To prepare for the next contingency, system adjustments may be made, including changes to generation, uses of the transmission system if necessary to make a credible case under contingencies Prepare a report, in which R and X of the system are observed over the range of frequencies and observed for zero crossings of R and/or dips in X at certain frequencies is graphed.
The general selection of applicable contingencies for studies is outlined in the ERCOT Planning Guides section 4. Contingencies and performance are identified in the ERCOT ISO System Planning methodology, ESP-METHOD-03 System Planning Contingency Identification.
This can happen even before the Screening Study is completed. GINR coordinator notifies, via email, the RI Engineer who performed the original Screening Study for this project. The RI Engineer enters the request date into the GINR database. If the original Engineer (performed the screening study) is not available, GINR coordinator informs RI Manager so he can assign the FIS Scoping meeting duties to another RI Engineer. RI Engineers notifies IE whether it has provided all necessary information as part of the FIS application. o If information is not sufficient, RI engineer instructs IE to provide it promptly. o IF the information is not forthcoming after ten days, RI Engineer must contact IE via email and phone to request missing information. o If sufficient information not provided within 20-days the RI engineer turns problem over to Manager. Once the information is provided, the RI Engineer determines if ERCOT has already completed a Screening Study for the project. o If it has not, then Engineer notifies IE that a Screening Study must be performed concurrently, and that the IE must request a screening study with accompanying fees. Information provided by IE will be used for both studies. o RI engineer allows 10-days for a screening study to be requested. If a screening study is not requested the engineer sends an email to the IE notifying it that if a request for screening study is not received within 30-days with accompanying fee and request the FIS request will be canceled. o If a screening study request is not received within 35-days, a study cancelation notice is sent by the RI engineer and the project canceled. The RI Engineer selects the lead Transmission Service Provider (TSP) to deal with the Interconnecting Entity (IE), within five days of getting the notice from the IE to proceed with a Full Interconnection Study (FIS), as indicated in Planning Guide 5.4.2.1 (1). This selection is based on the analysis of the most likely point of interconnection. RI Engineer contacts the TSP, and all other TSPs through the Transmission Owners Generation Interconnection list, to schedule a FIS scope meeting with IE. If ERCOT has already conducted a Screening Study, RI Engineer checks GINR database to determine if the Screening Study is over 180-days old. If it is, RI Engineer notifies IE that the FIS cannot be conducted because the deadline has passed, and that IE needs to apply for new GINR.
ERCOT Public
Page 48 of 60
ERCOT Public
IF the RI Engineer receives an SSR study as a part of the FIS scope, the date it was received is entered into the SSR StudyReceived field of the GINR database. IF an SSR study is required, when the SSR study is complete, the RI engineer sends the SSR study report to the TSP resource integration group for comments within 10-days. The RI engineer will save the SSR study report in the study folder. Page 50 of 60
ERCOT Public
Once all individual studies in the FIS have been accepted, the FIS is deemed complete. The RI engineer enters the date into the FIS_approved field of the GINR database. After the FIS is completed, the TSP and IE have 180-days to sign an IA, per ERCOT Planning Guide, 5.4.8 (5). The GINR coordinator will check the database for project status and keep the RI Manager updated with a weekly report of project status showing all projects with a completed FIS, detailing how many days it has been since that FIS was completed. If the resource has been registered, the ERCOT Client Services department receives updated RARF information from the IE as a result of the FIS process. The ECS Account Manager loads the updated information into the RARF Planning Hub. If the resource has not been registered, the ERCOT engineer receives the updated RARF data and stores it in the project folder on SystemPlanning/GenInterconnect.
ERCOT Public
Page 51 of 60
ERCOT Public
Page 52 of 60
Frequency Range Above 59.4 Hz Above 58.4 Hz up to And including 59.4 Hz Above 58.0 Hz up to And including 58.4 Hz Above 57.5 Hz up to And including 58.0 Hz 57.5 Hz or below
Delay to Trip No automatic tripping (Continuous operation) Not less than 9 minutes Not less than 30 seconds Not less than 2 seconds No time delay required
Additional documentation that supports the information requested in bullets A, B, C, and D above is encouraged. Please note which technical documents referenced in the commissioning plan were already provided to ERCOT during the engineering design study in accordance with Protocol Section 16.5 (3).
ERCOT Public
Page 54 of 60
Page 55 of 60
ERCOT Public
Page 56 of 60
Page 57 of 60
Page 58 of 60
ERCOT Public
Page 59 of 60
ERCOT Public
Page 60 of 60