Process Flow Map
Process Flow Map
SM
PHASE 5 CONSTRUCTION
Mobilize and manage the construction forces and perform other activities including procurement necessary to construct the facility in accordance with the construction documents.
PHASE 6 START-UP
Perform commissioning and operating activities required to achieve design performance levels.
PHASE 7 CLOSEOUT
Perform regulatory, contractual, archival and Jacobs required activities to close the project in an orderly fashion.
OBJECTIVES
KEY ACTIVITIES
Ongoing activities: Progress Reports, Client Expectations, CSIPS, Client Surveys, Quality Audits and Measurements, Cost and Schedule Control, TIC Trending, Execution & Reporting of Jacobs VEPS/Innovation, Jacobs Value Plus, Lessons Learned 1. 2. 3. 4. 5. Identify business opportunity Assess market Identify and evaluate options Obtain key supplier input Analyze risk and impacts (sociological, technological, economic, political, environmental) 6. Initiate Project Execution Strategy 7. Identify Gate Keeper 1. Select team and align to project objectives 2. Confirm preferred concepts, Design Basis and scope with client 3. Complete alternative analyses and testing studies 4. Develop concept(s) into preliminary scope documents 5. Identify regulatory and permitting requirements 6. Initiate environmental impact assessment 7. Conduct constructability and safety reviews, and initiate modular studies 8. Initiate Project Execution Plan including work sharing and modular opportunities, PQP 9. Identify long lead/critical equipment 10. Initiate geotechnical studies 1. Align team to project objectives 2. Confirm project objectives: scope, cost, schedule, etc. 3. Translate project concept into preliminary engineering and design documents 4. Conduct design reviews for constructability, safety, maintainability and operability 5. Finalize purchase order and contract terms and conditions 6. Prepare to procure critical and long lead equipment/materials 7. Prepare applications for necessary permits/licenses 8. Finalize modular application plans 9. Gate Keeper freezes scope 1. Align team to project objectives 2. Initiate change management 3. Procure, expedite, and inspect equipment and materials 4. Manage vendor data 5. Develop and issue construction documents (IFC) 6. Coordinate internal and external interfaces 7. Conduct design reviews (constructability, safety, maintainability, operability, etc.) and incorporate into the design 8. Obtain regulatory authority approval (e.g. FDA, environmental) 1. Align team to project objectives 2. Procure construction equipment, materials and construction services 3. Develop detailed, integrated project schedule 4. Manage construction site safety and environmental programs 5. Review submittals 6. Coordinate site activities 7. Manage QA/QC program 8. Manage labor relations program 9. Construct facilities in accordance with contract requirements 10. Continue change management 11. Red line construction documents 12. Achieve construction turn over 13. Provide technical support 1. Select and align team to project objectives 2. Coordinate inspections by regulatory authorities 3. Plan sequential testing and start-up of completed facilities 4. Assist with operator training 5. Record changes to construction documents 6. Continue change management 7. Complete Pre-startup Safety Review 8. Provide technical support 1. Conduct Lessons Learned sessions and compile for total project 2. Close purchase order and contract accounts 3. Assemble and archive project files 4. Return all client assets 5. Resolve any claims or disputes 6. Resolve any warranty issues 7. Obtain final acceptance certificate and final payment 8. Prepare project benchmarking data and feed back into system 9. Prepare final cost accounting 10. Conduct Operability Assessment
PHASE OVERLAPS
Opportunity Analysis Conceptual Design Project Definition Detailed Design/Procurement Construction Start-up Closeout
Close-out may occur at the end of any phase
KEY DELIVERABLES
1. Project Objectives 2. Phase 1 Report: - Market Study - Definition & Evaluation of Options -Alternative Analysis & Test Study Plan for Developmental Projects - Regulatory and Permitting Requirements Evaluation - Order-of-Magnitude Cost Estimate
(+50% to -30%)
1. 2. 3. 4. 5. 6. 7.
- Economic Analysis - Risk Analysis - Project Execution Strategy - Milestone Schedule 3. Recommendations for Path Forward
Updated Project Objectives Project Execution Plan Project Procedures Process Description Process Design Guide & Criteria Design Safety & Environmental Plan Preliminary Site Plan & Plot Plan, PFDs, H&M Balance, Prelim. Building Sizes, Material Selection for Equipment and Pipe, Equipment List with Process Design Data, Long Lead / Critical Path Equipment Data Sheets, Preliminary Motor List Control Systems Philosophy Utility Summary & Infrastructure Requirements Level II EPC Schedule Study Estimate (+30% to -20%) Overall Economic Analysis Phase 2 Report Recommendations for Path Forward Catalyst & License Agreement
1. 2. 3. 4. 5. 6.
Copyright 2005 by Jacobs Engineering Group Inc. All rights reserved. The contents of this document are proprietary and produced for the exclusive benefit of Jacobs Engineering Group Inc. and its affiliated companies. No part of this document may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without the prior written approval of Jacobs Engineering Group Inc. The current applicable version of this publication resides on Jacobs' Intranet. All copies are considered to be uncontrolled.
Updated Project Objectives Updated Project Execution Plan Updated Project Procedures Updated Process Description Design Basis Site & Plot Plans, Equipment Location Plans, Preliminary Piping Layout Model (All lines on P&IDs), PFDs & H&M Balance (IFD), Material Selection Diagrams, Process & Utility P&IDs (IFD), Building Plans & Elevations, Equipment List & Data Sheets, Line Lists, Tie-in List, Fire Protection Rqmnts (for est.), Electrical Single Lines, Motor List, Area Classes, Control Systems Index & Specifications for Special Instrument or Control Rqmnts, Geotechnical Report. Requests for Quotes & Bid/Bid Tab (Maj. Eq.) Purchase Requisitions (Maj. Eq.) Appropriate Regulatory and Permitting Documents Resource Loaded EPC Schedule Budget/Control Estimate (+10% to - 5%) Updated Economic Analysis Phase 3 Report (If Req.) Recommendations for Path Forward
Updated Project Objectives Updated Project Execution Plan Updated Project Procedures Request for Quotes & Bids/Bid Analysis Purchase Order Documentation Construction Documents (IFC) Control Systems Programs/ Software Appropriate Permit Applications Detailed, Resource Loaded Construction Schedule Project Data Books Change Control Documents Vendor Data Subcontract Technical Documents and Packages
Procurement/Contract Documents Updated Project Execution Plan Updated Project Procedures Construction Permits Safety Program and Documentation Updated Construction Schedule Constructed Facility QA/QC and Check-out/Completion Documentation Red Line Documentation (AsBuilts) Change Control Documents Turnover of Spare/Change Parts Turnover Documentation
1. Commissioning/Start-up Plan and Procedure 2. Start-up Schedule 3. Operating, Maintenance and Training Manuals 4. Record Documentation (Completed As-Builts) 5. Pre-start-up Safety Review Report 6. Facility Operating at Specifications 7. Performance Plan and Test Documents
1. 2. 3. 4. 5. 6. 7. 8. 9. 10.
Closeout Plan Project Closure Notice Final Project Report Project Completion Report Lessons Learned Warranty File Archive Log Final Acceptance Documents Final Invoice Benchmarking Data
Note: See Glossary following CPI CrossFunctional Maps for explanation of abbreviations and definitions.
Rev. No. 2 Page: 1 of 2 Rev. Date: June 1, 2005 Approved by: B. Herrington
SM
Phase 1
Opportunity Analysis
Phase 2
Conceptual Design
Phase 3
Project Definition
Phase 4
Detail Design / Procurement
Client Expectations (V-1), Client Surveys (V-2), Project Execution Planning (V-5), Interactive Planning (V-6), Lessons Learned (V-7), Team Alignment (V-8), Owner's Objectives (V-10), Value Plus (V-12)
Waste Minimization (V-20) Process Reliability Modeling (V-17) Process Simplification (V-18) Predictive Maintenance (V-16) Energy Optimization (V-15) Design to Capacity (V-4) Class of Plant (V-13) Customized Standards & Specifications (V-14) Operability & Maintainability Change Management (V-22)
PFD Development
Constructability Validated
Note: JVEPSSM V-1, V-2, V-5 through V-8, V-10 and V-12 continue through project closure, as applicable. Constructability (V-3), PDS Modeling (V-21) & Change Management (V-22) continue through Phase 5, Construction, as applicable.
Rev. No. 2 Page: 2 of 2 Rev. Date: June 1, 2005 Approved by: B. Herrington
JSTEPS
SM
CLIENT
Opportunity Evaluation Initiated Business Objectives Client Expectations Established Team Alignment Lessons Learned Review Identify Gate Keeper 1-2 V19 Business Objectives Client Information Phase I - Plan - Budget - Schedule - Deliverables Options Identified Technology Selection Initiated List of Options Options Analyzed & Screened Selected Options Developed
V5
Evaluation Completed & Execution Strategy Developed Sociological Technological Economic Political Environmental
Proceed ? 1-9 No
Selected Options
Drawings Documents
1-3
1-4
1-5
1-7
DESIGN DISCIPLINES
Market Study Definition & Evaluation of Options Alternative Analysis & Test Study Plan Regulatory & Permitting Evaluation Order of Magnitude Cost Estimate Economic Analysis Risk Analysis Project Execution Strategy Milestone Schedule
1-8
SUPPLY MANAGEMENT
CONSTRUCTION
V2
OTHERS (INTERNAL)
M1 M2 M5
SUPPLIERS
OTHERS (EXTERNAL)
KEY:
See Glossary for explanation of terms; and definitions of Standard Operating Procedures, Value Enhancing PracticesSM, and Measures.
V3
M2
Measurement
Task(s)
Decision
Involvement
Rev. No. 2 Page: 1 of 16 Rev. Date: June 1, 2005 Approved by: B. Herrington
JSTEPS
SM
CLIENT
From Phase 1 Task 1-9 Phase Initiated Authorization P100 P131 P202 Alternative Analysis Completed Technology Licensing Market Study Pilot Plant Testing Economics
V19
Concepts Developed, Simulated, Screened & Selected Technology Selection Relative Economic Evaluation
V1 V5 V6 V7 V8 V10 V13
Select Team Strategy/Kick Off Meetings Client Project Execution Plan Expectations - Project Objectives Updated Class of Plant Project Execution Phase 2: - Budget and Schedule Planning - Deliverables List Interactive - Project Procedures Planning Team Alignment Phase 1 Data and Plant Data Validation Lessons Learned DS&E Plans Developed 2-1 2-3 DS&E Plan P201 P350
V19
Ongoing: Cost Mgt. Cost Trending Value Plus Schedule Mgt. Reports Lessons Lrnd.
Selected Concepts - Process - Technology - Layouts Economic Evaluation Conceptual Design Prepared
Preliminary Documents: Site Plan Plot Plan Preliminary Building Sizes PFDs Material Selection for Equipment and Pipe H&M Balance Equipment List Motor List Control System Philosophy Utility Summary Infrastructure Requirements Catalyst/Chemicals Summary
2-2
Process Design Guide & Criteria Class of Plant Capacity Product Site Design Criteria/Data
2-6
DESIGN DISCIPLINES
SUPPLY MANAGEMENT
Request for Proposals
CONSTRUCTION
Discipline Designs Design to Capacity Process Simplification Completed Initiate Process Reliability Modeling Modular Studies and Constructability Initiated Energy Optimization Waste Minimization Commissioning / Start-Up Plan Initiated 2-7
P203 P204
V2
OTHERS (INTERNAL)
Safety
Safety
M1 M2 M5
SUPPLIERS
OTHERS (EXTERNAL)
KEY:
See Glossary for explanation of terms; and definitions of Standard Operating Procedures, Value Enhancing PracticesSM, and Measures.
V3
M2
Measurement
Task(s)
Decision
Involvement
Rev. No. 2 Page: 2 of 16 Rev. Date: June 1, 2005 Approved by: B. Herrington
JSTEPS
SM
CLIENT
V20 Regulatory and Permitting Requirements Identified Environmental Impact Assessment Initiated V5 V6 V14 Project Execution Plan & Procedures Developed Project Schedule Developed - Interactive Planning Receipt of Client Specifications Customized Standards & Specifications Initiated Preliminary Project Site & Labor Studies Developed Study Estimate Basis Project Execution Plan Project Procedures Project Schedule Study Cost Estimate (+30% to -20%) Prepared - IPA FEL Assessment or - PDRI
Proceed ? 2-18
Yes
Ongoing: Cost Mgt. Cost Trending Value Plus Schedule Mgt. Reports Lessons Lrnd.
Stop or Recycle
V9 M4
P132
Project Execution Plan Corporate / Business Goals Project Objectives Scope of Work Risk Management Plan Organization Plan Milestone Schedule Contracting Plan JVEPSM Plan Constructability Plan Design Management Plan Supply Management Plan Construction Mgmt Plan Startup Management Plan Environmental Plan Cost Management Plan Schedule Management Plan Project Quality Plan Safety Management Plan Information Management Plan Special Factors Management Plan Reference Only 2-17 Quality Accounting P310
2-12 Reviews Held for: Constructability Design For Safety Design Documents Operability Maintainability Commissioning/ Start-Up P201 P203 P350 Phase 2 Technical Documents
2-15
2-16
V3
DESIGN DISCIPLINES
P100 P131
SUPPLY MANAGEMENT
CONSTRUCTION
OTHERS (INTERNAL)
Safety 2-13
SUPPLIERS
OTHERS (EXTERNAL)
Information Reviewed 2-14 See Glossary for explanation of terms; and definitions of Standard Operating Procedures, Value Enhancing PracticesSM, and Measures. Process Industries P202 Standard Operating Procedure Jacobs Value Enhancing PracticeSM
KEY:
V3
M2
Measurement
Task(s)
Decision
Involvement
Rev. No. 2 Page: 3 of 16 Rev. Date: June 1, 2005 Approved by: B. Herrington
JSTEPS
SM
CLIENT
Permit Package P100 P134 P203 P204 P205 P207 V11 Value Engineering P&IDs Reviewed Plot Plans Reviewed Rev. B P&IDs & Plot Plans V3 V5 V21 Reviews Held For: - Safety - Process Hazard - Operability - Constructability - Maintainability -Reliability -Commissioning Preliminary 3D Model Internal Review for Major Equipment Layout/Piping Cursory Stress Analysis for Critical Equipment Completed P100 P201 P350
Authorization
P100 P131 P202 P310 Major Equip. Defined Design Basis Updated Preliminary Process Design Completed Discipline Design Specification Defined Initiate CAE Activities Process Reliability Modeling Completed 3-4
DESIGN DISCIPLINES
V1 V5 V6 V7 V8 V10
SUPPLY MANAGEMENT
Phase Initiated Strategy/Kick Off Meetings Client Expectations Project Execution Planning Interactive Planning Team Alignment Phase 2 Data & Plant Data Lessons Learned Commissioning / Start-Up Planning
P100 P134 P203 P204 P205 P207 Preliminary Process Design Rev. A P&IDs and Plot Plan
Phase 3 Design Documents Site Plan Plot Plan Preliminary Piping Layouts of All Lines on P&IDs (One-Line 3D Modeled on Sketches) Building Plans & Elevations PFDs Material Selection Diagrams H&M Balance Process & Utility P&IDs, (Rev. C IFD) Equipment List Data Sheets & Specifications for Equipment Line List Tie-in List
Ongoing: Cost Mgt. Cost Trending Value Plus Schedule Mgt. Reports Lessons Lrnd.
To Phase 3 Task 3-11 Review Comments 3-9 Electrical Single Lines Motor List Area Classification Control System Index & Specifications for Special Instruments or Control Requirements Fire Protection Requirements for Estimate Geotechnical Report Hydraulic Study Process Control Scheme Updated Project Execution Plan
Project Execution Plan - Updated Project Objectives Phase 3: - Budget - Schedule - Estimate Plan - Deliverables List - Project Procedures
3-5
P401
CONSTRUCTION
Request for Bids
V2 M1 M2 M5 M12
OTHERS (INTERNAL)
Safety
Process License
SUPPLIERS
3-1
OTHERS (EXTERNAL)
KEY:
See Glossary for explanation of terms; and definitions of Standard Operating Procedures, Value Enhancing PracticesSM, and Measures.
V3
M2
Measurement
Task(s)
Decision
Involvement
Rev. No. 2 Page: 4 of 16 Rev. Date: June 1, 2005 Approved by: B. Herrington
JSTEPS
SM
CLIENT
Funding Requested 3-18 M3 M6 M13 M10 V7 V12 Report Recommendations Preliminary Engineering Phase Report Completed 3-16
Ongoing: Cost Trending Cost Mgt. Value Plus Schedule Mgt. Reports Lessons Lrnd.
No
Phase 3 Design Documents IFD Project Execution Plan Basis of Estimate and MTOs Completed
Stop or Recycle
V6 V9 V22
M4 Quantities
DESIGN DISCIPLINES
From Phase 3 Task 3-9 3-11 Critical Equipment/ Materials Bids and Alliance Quotes Requested 3-12
SUPPLY MANAGEMENT
P401 P402
Definitive Cost Estimate (+10% to - 5%) Completed PDRI or IPA FEL Assessment Process Risk, Cost & Schedule Risk Analysis Completed Project Schedule Develope d - Interactive Planning Scope Frozen Change Management Initiated Commissioning / Start-Up Plan Updated
Project Execution Plan Corporate / Business Goals Project Objectives Scope of Work Risk Management Plan Organization Plan Milestone Schedule Contracting Plan JVEPSM Plan Constructability Plan Design Management Plan Supply Management Plan Construction Mgmt Plan Startup Management Plan Environmental Plan Cost Management Plan Schedule Management Plan Project Quality Plan Safety Management Plan Information Management Plan Special Factors Management Plan
P131 P132 P134 P403 Budget Cost Estimate Updated Basis of Estimate Updated Economic Analysis Resource Loaded EPC Project Schedule
CONSTRUCTION
3-17 Reference Only V2 Ongoing Activities Client Survey Audits Accounting Quality Accounting P310 P320
OTHERS (INTERNAL)
Major/Long Lead Equipment Bids/ Alliance Quotes
M1 M2 M5 M12
SUPPLIERS
Preliminary Applications
OTHERS (EXTERNAL)
Preliminary Environmental Applications Evaluated 3-15 See Glossary for explanation of terms; and definitions of Standard Operating Procedures, Value Enhancing PracticesSM, and Measures. Process Industries P202 Standard Operating Procedure Jacobs Value Enhancing PracticeSM
To Phase 4 Task 4 - 14
KEY:
V3
M2
Measurement
Task(s)
Decision
Involvement
Rev. No. 2 Page: 5 of 16 Rev. Date: June 1, 2005 Approved by: B. Herrington
JSTEPS
SM
CLIENT
Authorization
Project Execution Plan - Updated Project Objectives Turnover Systems List Phase 4: - Budget - Schedule - Deliverables List - Project Procedures
Reviews Completed: Discipline Design Design For Safety - HAZOP 3D Model Reviews Operations & Maintenance Commissioning / Start-Up
Permit Package
Detailed Design Input Finalized 4-2 4-9 IFD Technical Documents Equipment/Material Requisitions
DESIGN DISCIPLINES
V1 V5 V6 V7 V8 V10
Discipline Detailed Design Completed Equipment / Materials Requisitions Prepared and Bids Requested 4-10 P204 P205 P401 P403 P401 Vendor Data V21 Equipment/ Materials Purchased 4-5 Vendor Data Expedited and Obtained 4-7
To Phase 4 Task 4-19 Construction Documents Approved Vendor Data Control System Software
M8
SUPPLY MANAGEMENT
4-3
P202 P407
CONSTRUCTION
Constructability Recommendations
V2
OTHERS (INTERNAL)
Safety
Vendor Data
SUPPLIERS
Bids
OTHERS (EXTERNAL)
Environmental and Building Permit Applications Approved by Regulatory Authorities 4-15 See Glossary for explanation of terms; and definitions of Standard Operating Procedures, Value Enhancing PracticesSM, and Measures. Process Industries P202 Standard Operating Procedure Jacobs Value Enhancing PracticeSM
Permits
KEY:
V3
M2
Measurement
Task(s)
Decision
Involvement
Rev. No. 2 Page: 6 of 16 Rev. Date: June 1, 2005 Approved by: B. Herrington
JSTEPS
SM
CLIENT
Ongoing: Cost Mgt. Change Mgt. Value Plus Schedule Mgt. Reports Lessons Lrnd.
P500 Construction Documents Approved Vendor Data Control System Software From Phase 4 Task 4-10 Construction Readiness Reviews Subcontract Technical Documents Prepared & Packages Assembled
DESIGN DISCIPLINES
4-20
SUPPLY MANAGEMENT
P407 P408
Project Execution Plan Corporate / Business Goals Project Objectives Scope of Work Risk Management Plan Organization Plan Milestone Schedule Contracting Plan JVEPSM Plan Constructability Plan Design Management Plan Supply Management Plan Construction Management Plan Startup Management Plan Environmental Plan Cost Management Plan Schedule Management Plan Project Quality Plan Safety Management Plan Information Management Plan Special Factors Management Plan
CONSTRUCTION
Construction Documents Vendor Data Control System Software
V2
OTHERS (INTERNAL)
M1 M2 M5 M12
Safety 4-18
SUPPLIERS
OTHERS (EXTERNAL)
Reference Only
KEY:
See Glossary for explanation of terms; and definitions of Standard Operating Procedures, Value Enhancing PracticesSM, and Measures.
V3
M2
Measurement
Task(s)
Decision
Involvement
Rev. No. 2 Page: 7 of 16 Rev. Date: June 1, 2005 Approved by: B. Herrington
PHASE 5 Construction
From Phase 3 Task 3-19
JSTEPS
SM
CLIENT
Authorization
Ongoing: Cost Mgt. Change Mgt. Value Plus Schedule Mgt. Reports Lessons Lrnd. QA/QC Safety Mgt. Rework
DESIGN DISCIPLINES
V1 V5 V6 V7 V8 V10
SUPPLY MANAGEMENT
CONSTRUCTION
Phase Initiated Kick Off Meetings Client Expectations Project Execution Planning Construction Readiness Review Interactive Planning Team Alignment Phase 5 Input Data Validation Lessons Learned Permit Applications Completed Commissioning / Start-Up Plan Updated
P131 P500 P100 P131 P202 P500 From Phase 4 Task 4-18 Requisitions Contract Packages P403 P405 P405 P401 Construction Subcontracts and Bids Requested Construction Contracts Awarded From Phase 4 Task 4-10 5-2 Requests for Bids 5-4 Bids Construction Contracts To Phase 6 Task 6-2 Integrated Construction Schedule Prepared Start-up Sequence Finalized Vendor Schedule for Construction and Start-up Finalized Contractor Design Completed Field Materials & Equipment Procured Site Preparation Initiated Turn Over Packages Prepared P401 P407 P408 P409 P500
P202
Construction Documents Vendor Data Control System Programs Site Set Up & Mobilized Site Safety Plan Initiated
OTHERS (INTERNAL)
Safety Project Execution Plan Safety Program QA/QC Plan Schedule Budget Project Procedures Mobilization Plan Staffing Plan Construction Equipment Plan Subcontract Plan Labor Relations Program Vendor Support Plan for Construction and Start-up
Safety
P350 P500
Safety 5-10
Contractor Schedules Resources Infrastructure 5-5 Construction Start Notified Permits Awarded Regulatory Authorities 5-7 Regulatory Authorities Permits 5-6 5-9
SUPPLIERS
5-1 Quality Accounting P310 P320
V2
OTHERS (EXTERNAL)
M1 M2 M5 M12
KEY:
See Glossary for explanation of terms; and definitions of Standard Operating Procedures, Value Enhancing PracticesSM, and Measures.
V3
M2
Measurement
Task(s)
Decision
Involvement
Rev. No. 2 Page: 8 of 16 Rev. Date: June 1, 2005 Approved by: B. Herrington
JSTEPS
SM
CLIENT
Project Execution Plan Corporate / Business Goals Project Objectives Scope of Work Risk Management Plan Organization Plan Milestone Schedule Contracting Plan JVEPSM Plan Constructability Plan Design Mgmt Plan Supply Mgmt Plan Construction Mgmt Plan Startup Mgmt Plan Environmental Plan Cost Mgmt Plan Schedule Mgmt Plan Project Quality Plan Safety Mgmt Plan Information Mgmt Plan Special Factors Mgmt Plan
Ongoing: Cost Mgt. Change Mgt. Value Plus Schedule Mgt. Reports Lessons Lrnd. QA/QC Safety Mgt. Rework
No
Yes
DESIGN DISCIPLINES
Reference Only
SUPPLY MANAGEMENT
CONSTRUCTION
Turn Over Packages M8 M9 Constructed Facility M9 Quality Accounting P310 P320 Construction Check-out Completed by Package or System Demobilization Initiated
Recycle Packages
V2
OTHERS (INTERNAL)
From Phase 5 Task 5-9 From Phase 4 Task 4-16 From Phase 5 Task 5-5
Facility Constructed
P500 P501
M1 M2 M5 M12
Facility or System Mechanically Completed Spare and Change Parts Assembled Facility or system care, custody and control presented to client
P500
SUPPLIERS
OTHERS (EXTERNAL)
Permits
Regulatory Authorities
KEY:
See Glossary for explanation of terms; and definitions of Standard Operating Procedures, Value Enhancing PracticesSM, and Measures.
V3
M2
Measurement
Task(s)
Decision
Involvement
Rev. No. 2 Page: 9 of 16 Rev. Date: June 1, 2005 Approved by: B. Herrington
PHASE 6 Start-up
JSTEPS
SM
CLIENT
V7 V22 Authorization M3 M6 M10 Red Line Construction Documents Project Data Books
Ongoing: Cost Mgt. Change Mgt. Schedule Mgt. Reports Lessons Lrnd.
P202 Commissioning/Start-up Plan Performance Plan Performance Test Docs Safety Action Plan Operating Plan Training, Operation and Maintenance Manuals Updated Construction Documents (As-Builts) Documents Prepared
From Phase 5 Task 5-12 Start-up Phase Initiated Kick Off Meetings Client Expectations Project Execution Planning Team Alignment Prior Phase Data Validation Lessons Learned Commissioning / Start-Up Planning From Phase 4 Task 4-19
Updated Construction Document Mark-ups To Phase 6 Task 6-7 Facility Precommissioning Completed Engineering Check-out Completed Construction Turnover Certificates Mechanically Complete Facility From Phase 5 Task 5-15 Precommissioned Facility Facility Commissioned Facility Start-up Completed
DESIGN DISCIPLINES
V1 V5 V7 V8 V10
Staffing Plan Start-up Program Start-up Schedule Safety Program Budget Start-up Schedule To Phase 5 Task 5-6
SUPPLY MANAGEMENT
CONSTRUCTION
OTHERS (INTERNAL)
Safety
Safety
M1 M2 M5
Safety
Safety
SUPPLIERS
6-1 6-2 6-5 6-6 6-6
OTHERS (EXTERNAL)
KEY:
See Glossary for explanation of terms; and definitions of Standard Operating Procedures, Value Enhancing PracticesSM, and Measures.
V3
M2
Measurement
Task(s)
Decision
Involvement
Rev. No. 2 Page: 10 of 16 Rev. Date: June 1, 2005 Approved by: B. Herrington
JSTEPS
SM
CLIENT
Ongoing: Cost Mgt. Change Mgt. Schedule Mgt. Reports Lessons Lrnd.
Acceptance Documentation
Record Documents
DESIGN DISCIPLINES
P202
SUPPLY MANAGEMENT
CONSTRUCTION
V2
OTHERS (INTERNAL)
M1 M2 M5
SUPPLIERS
OTHERS (EXTERNAL)
KEY:
See Glossary for explanation of terms; and definitions of Standard Operating Procedures, Value Enhancing PracticesSM, and Measures.
V3
M2
Measurement
Task(s)
Decision
Involvement
Rev. No. 2 Page: 11 of 16 Rev. Date: June 1, 2005 Approved by: B. Herrington
PHASE 7 Closeout
JSTEPS
Lessons Learned Final Client Survey
SM
CLIENT
Receipt
Data Assembly & Compilation Completed 7-4 Record Documents From Phase 6 Task 6-7
P100 P202
M2 V2 V7
From Phase 6 Task 6-9 Acceptance Documentation P100 P310 Procurement & Contract Records
DESIGN DISCIPLINES
Prior Phase Completions
SUPPLY MANAGEMENT
Lessons Learned
Final EPC Survey Obtained Lessons Learned Conducted Lessons Learned Compiled From All Phases
CONSTRUCTION
OTHERS (INTERNAL)
Safety
Accounting
IS
SUPPLIERS
7-1
OTHERS (EXTERNAL)
KEY:
See Glossary for explanation of terms; and definitions of Standard Operating Procedures, Value Enhancing PracticesSM, and Measures.
V3
M2
Measurement
Task(s)
Decision
Involvement
Rev. No. 2 Page: 12 of 16 Rev. Date: June 1, 2005 Approved by: B. Herrington
JSTEPS
ABBREVIATIONS
CCC cGMP CII CPI CSIP DS&E E EU FEL H&M HAZOP IFC IFD IPA Care, Custody and Control Current Good Manufacturing Practices Construction Industry Institute Chemical Process Industries Client Satisfaction Improvement Plan Design Safety and Environmental Environmental European Union Front End Loading Heat and Material Hazard and Operability Issue for Construction Issue for Design Independent Project Analysis IS MOC MTO P&ID PDRI PFD PI-SOP PSSR PQP QA/QC RFI S VIP VEP
SM
SM
PI-SOP PI-SOP-100 PI-SOP-110 PI-SOP-111 PI-SOP-120 PI-SOP-130 PI-SOP-131 PI-SOP-132 PI-SOP-133 PI-SOP-134 PI-SOP-135 PI-SOP-201 PI-SOP-202 PI-SOP-203 PI-SOP-204 PI-SOP-205 PI-SOP-206 PI-SOP-207 PI-SOP-208 PI-SOP-300 PI-SOP-310 PI-SOP-311 PI-SOP-320 PI-SOP-350 PI-SOP-401
NAME Project Management and Execution Business Risk Identification and Management Project Risk Identification and Management Multi-Office Project Execution & Planning Project Control Plan and Work Breakdown Structure Planning and Scheduling Estimating Cost Management Change Management Performance Measurement Design for Safety Document Management & Control Deliverable Verification Preparation of Specifications Engineering Requisitions cGMP Review/Consultation Computer Aided Design Control of Engineering Software Region/LOB Quality System Requirements Client Surveys Management Review of Quality System Project Audits HS&E Program Project Supply Management Procedure Inquiry Requisitions and Inquiry Documents Bid Opening, Evaluation and Award Administration and Closeout of Agreement for Equipment and Materials Administration and Closeout of Agreement for Services Field Materials Management Expediting Supplier Surveillance and Inspection Transportation Field Services Field Inspection and Testing
(JVEPs )
Value Plus Class of Plant Quality Customized Standards/Specs Energy Optimization Predictive Maintenance Process Reliability Modeling Process Simplification Technology Selection Waste Minimization 3D CAD Change Management
V-12 V-13* V-14* V-15* V-16* V-17* V-18* V-19* V-20* V-21* V-22
FUNCTIONS
CLIENT PROJECT MANAGEMENT/ SERVICES PROCESS ENGINEERING/ ENVIRONMENTAL DESIGN DISCIPLINES All client functions including management, engineering, operations, maintenance, etc. Project management, project engineering, estimating, scheduling, and cost engineering The process and environmental group(s) All detailed design functions including architectural production, civil, structural, mechanical, HVAC/FP, piping, electrical, and control systems Purchasing, subcontracts, expediting, and inspection Construction forces including constructibility, construction management and field staff; and craft personnel and labor on direct hire projects Internal Jacobs functions not mentioned above such as sales, safety, environmental, regulatory compliance, validation, information systems, accounting, human resources, quality and legal All suppliers including equipment vendors, subcontractors, and consultants Organizations outside Jacobs, other than suppliers, such as regulatory bodies, generally differentiated by not being paid for their services
MEASURES
M-1 M-2 M-3 M-4 M-5 M-6 M-7 Accounts Receivable Client Survey Cost PDRI Project Gross Margin Productivity Project Performance Total of amounts due and payable by an owner that have not been paid See Client Survey in Definitions Measures of budgeted, actual and forecast cost for engineering, construction and total installed cost, as appropriate See PDRI in Definitions The difference between the direct costs of the project and the revenues deriving from it to Jacobs The ratio of earned work hours to spent work hours for either home office or field activities The projects ability to meet established project objectives for items such as product quality, capacity, time to full production, efficiency, etc. Home office or field work that has to be re-performed (redone) due to client change, designer change, vendor change, constructor change, designer error, vendor error, or constructor error. The number of E1, OSHA recordable and other incidents in the home office and field versus the number of hours worked Measures of performance against an agreed project schedule including forecast days early or late, percent complete versus scheduled, etc. The number of agreed, scheduled milestones met versus the number of milestones scheduled to have been met Measure of a projects compliance with its applicable SOPs as defined in its quality plan See Value Plus in Definitions
PI-SOP-402 PI-SOP-403 PI-SOP-404 PI-SOP-405 PI-SOP-406 PI-SOP-407 PI-SOP-408 PI-SOP-409 PI-SOP-500 PI-SOP-501
OTHERS (INTERNAL)
M-8
Rework
M-9 M-10
Safety Schedule
Rev. No. 2 Page: 13 of 16 Rev. Date: June 1, 2005 Approved by: B. Herrington
JSTEPS
SM
Area Classification
Basis of Estimate
Benchmarking Data
Beneficial Occupancy
Bid
Construction Documents
Construction Industry Institute. An organization of owners, contractors and academia whose mission is to improve the safety, quality, schedule, and cost effectiveness of the capital investment process through research and implementation support. Agreement or contract that grants to a licensee the right to use a catalyst and/or technology under specific terms and conditions including compensation.
Engineering Check-out
Contract Package
Document from a building regulatory agency that certifies a facility has been inspected, has no violations and meets the regulatory requirements and codes for occupancy for its intended purpose. Process of controlling the scope of a project against a defined baseline by only allowing a change after it has been formally approved, taking into account its benefit to the project outcome, and its impact on cost and schedule. IPA VIP that established what quality facility is needed to meet business objectives. It adjusts reliability, expandability, automation, life of facility, etc. to recognize goals.
Cost Trending
Client Expectations A proactive approach to identify, collect, and address client expectations, concerns, (V-1) past issues and soft issues that can adversely or positively affect a clients perception to our performance and attitude toward Jacobs Engineering. Client Survey (V-2) Close-Out Plan PI-SOP-310 process to obtain both a numerical rating and a narrative evaluation of a clients satisfaction with our performance against standard headings. Plan to perform all of those activities necessary to properly complete a project in accordance with the contract, SOPs, law, and other considerations. Analysis, conducted by knowledgeable professionals, to ensure that a facility design meets the regulatory requirements applicable to its structure type, occupancy type, building siting, building size, set backs, etc.
Critical Equipment
Facility Started-up
Facility(ies) Feedstock
Code Analysis
Design Development
Rev. No. 2 Page: 14 of 16 Rev. Date: June 1, 2005 Approved by: B. Herrington
JSTEPS
SM
Milestone Schedule
O&M Documentation
Formal review led by the client to confirm that the constructed facility is ready to startup safely and to confirm that: 1) the unit has been designed and constructed in accordance with design specifications, 2) proper safety, maintenance and emergency procedures have been instituted, 3) appropriate training of personnel has been completed and 4) appropriate documentation has been updated. US law (OSHA 1910) requires that the review be held before the start-up of certain classes of new or modified facility. Also called Pre-Start-Up Change Management Review. PI-SOPs are standard operating procedures issued jointly by the Northern, Southern, and Western Regions to implement the GSOPs. A simulation technique to examine operability targets for a facility. The objective is to determine the most economical sizing, spacing, and storage conditions that meet operability goals while minimizing cost. Typically, specialized computer software and/or a consultant are necessary (IPA VIP). Disciplined analytical method for reducing investment of operating costs by combining or making unnecessary one or more chemical or physical processing steps (IPA VIP). Clear statement of the project goals, drivers, and constraints that will enable the project management team to maintain its focus and make responsible decisions; including capital cost permitted, completion milestones required, cash-flow constraints, new technology application and purpose, environmental goals and operational considerations. Simulation studies to optimize a design based on chosen optimization parameters using a computer based model of the process. Compilation of information prepared for the plant at the end of a project. Contents vary with owner, industry and contract but can include calculations, drawings and specifications, test data, vendor drawings and manuals. They can be electronic (CD). Overall plan for performing a defined scope of work including all necessary elements such as goals and objectives, scope of work, organization, schedule, and plans for risk management, contracting, design, material management, construction, start-up, quality, safety, etc. Request for Information. A request from the construction entity for additional information, clarification or direction to enable construction to proceed. Return on Investment. A financial method to compare the monetary outcome of the project against the owners expectations and against investing the required capital in a different opportunity. Construction documents updated to reflect changes made or errors found during construction and start-up. Construction documents marked up during construction to reflect the manner in which the project was actually constructed. Changes can result from errors, measurements being field determined, or as-found conditions being other than expected. Any and all legal and regulatory restrictions and constraints that may impact the project including those related to air and water emissions and quality, land usage, building code compliance, resource conservation, existing pollution including those of EPA, OSHA, FDA, Building Codes.
Occupancy
IFC
Opportunity Option
IFD
IPA
Jacobs System to Ensure SM Project Success Jacobs Value Enhancing SM Practices Labor Relations Program
A document used to initiate and monitor effective resolution of observations, suggestions, or nonconformances arising from the performance evaluation process. Plan to demonstrate the performance of the project in accordance with its design objectives. Includes organization, contractor/supplier participation, duration of demonstration tests, production rates and specifications, verification methods. Operation of the facility for a predetermined period of time under specified conditions to demonstrate that it can achieve its design objective product quantity and quality. Frequently the basis for final acceptance of equipment and final payments to vendors. Documentation to be completed prior to, during and subsequent to performance tests as part of the performance plan to provide a formal record of the plant performance during the tests. Permits issued by authorities having jurisdiction over various aspects of the project construction which are required before some or all of the construction may commence. Examples include certain environmental permits, provisional use permits, and building (structural, electrical, plumbing, etc.) permits A scaled drawing showing an overall unit within a facility with all major equipment, structures and building. Activities performed after mechanical completion in preparation for introducing feedstock into the plant and putting it into full operation. Precommissioning includes activities such as putting electrical, compressed air and plant water systems into operation, filling reactors with catalyst, running systems with no load or simulating operations with water, drying out refractory vessel linings, etc. An approach to maintaining a facility whereby equipment is monitored and repairs are made before failure. Typically, such an approach requires adding various measurement devices to evaluate operating characteristics.
Performance Test
RFI
Line of Business
ROI
Permits
Plot Plan
Precommissioning
MTO
Master Plan
Rev. No. 2 Page: 15 of 16 Rev. Date: June 1, 2005 Approved by: B. Herrington
JSTEPS
SM
Supplier
Risk Analysis
Preliminary Engineering Task 3-6 completed by Process Engineering and Design Disciplines with involvement by Client and Materials Management.
CLIENT
Work process task(s) or activities identified by noun and past tense verb combination.
Room Requirements
Output from task 3-2 and input to task 3-6. Fac Schematic Drawings Schematic Design Estimate Completed 3-3 Estimate
Room Schedule
Safety File
File containing all of the relevant health and safety characteristics of the project, updated throughout the project, which becomes the owners formal record on project completion. Also known as the Health and Safety File. Training, Operations and Maintenance Program employed to define the organization, procedures and methods that will be Manuals employed to ensure the safe execution of work. Turnover Package Chemical, unit operations and equipment variables, how they scale-up, and boundaries. Drawing that schematically depicts the major elements of an electrical power distribution system including typically transformers, feeders, switchgear, motor control centers, motors and other significant loads. A scaled drawing showing the overall facility. This will normally include all operating units, administrative buildings and locations of all access into the plant. Safety program tailored for a specific site Major categories to be considered when evaluating the feasibility of a project opportunity for an owner. Includes review of regulatory agency issues; public acceptance issues; capital, operating, and other cost issues (including ROI, IRR, sensitivity and other cost analyses); trans-national, federal, national and local governmental issues; as well as environmental impact of proposed development. Spare and interchangeable parts for project equipment that are provided under the contract. Estimate produced during Phase 2, Conceptual Design, based on early documentation, typically having an accuracy of +30% to 20%.
PROJECT MANAGEMENT
Package containing the documentation, such as inspection, test, reports that needs to be completed prior to turning over all or an element of the project to the owner.
Turn-over Systems List List of the systems to be separately handed over to the owner. Updated Construction Documents VEP VIP Construction documents revised to incorporate changes made or required during construction. See Jacobs Value Enhancing Practices
SM
Major Equip. Defined Design Basis Updated Preliminary Process Design Completed Schematic Design Completed 3-2
Fac
Site Plan
DESIGN DISCIPLINES
Preliminary Process Design Major/Long Lead Equipment Specs/ Data Sheets Major/Long Lead Equipment Bids Requested 3-4 P401
PhB Fac
Value Improving Practices. A term coined by IPA for a practice which has been statistically demonstrated to improve project performance and outcome. VEPs . Best practices identified by CII and IPA that, when used consistently and collectively, significantly increase the value of the project. A disciplined method of functional analysis used during design, often employing an internal or external consultant, aimed at eliminating or modifying items that do not contribute to meeting business needs. An organized system to recognize and report value added provided by the Project Team. It promotes a cultural change to increase value awareness by recording all value adding concepts and uses a wall chart to advertise progress towards goal. Total Value Added includes operational savings, capital avoidance, EPC savings, and other savings. Also known as EPCM Initiative Savings. Drawings, documents, manuals and other information provided by suppliers of equipment and materials under purchase orders including design drawings, installation instructions, maintenance manuals and operating instructions. File containing documentation of and relating to warranties provided by suppliers. A disciplined approach used during design to minimize the production of waste products. Such an approach might add additional equipment or examine alternate process technologies that have lower waste side-streams (IPA VIP)
SM
SUPPLY MANAGEMENT
Line of Business exception for Pharma-Bio and Facilities which call this task Design Development.
Vendor Data
Dashed lines on a task box indicate that functional group does not participate.
Rev. No. 2 Page: 16 of 16 Rev. Date: June 1, 2005 Approved by: B. Herrington