Construction of Contiguous Bored Pile Wall: Open-Cut & Bottom-Up Construction Method
Construction of Contiguous Bored Pile Wall: Open-Cut & Bottom-Up Construction Method
Excavation &
04 . Construction
of Underground Structure
While noise, dust and other inconveniences are inevitable during construction, LTA will
Base Slab
The underground Rapid Transit System (RTS) stations and cut-and-cover tunnels are typically constructed by the open-cut and bottom-up method. In this method, the earth is excavated to the required depth with retaining walls and struts supporting the soil at the sides. Upon the completion of excavation to the required depth, the base slab of the underground structure is cast at the bottom-most level, followed by the side walls. Casting of concrete progresses upwards, level by level till the roof of the structure is completed. Ground is then backfilled and reinstated.
Formation Level
The soil is excavated to the next strut level and the second level strut is installed. It continues till the excavation reaches the final depth or formation level. The number of strut levels depends on the excavation depth.
At formation level, the reinforced concrete slab or base slab is constructed, followed by the removal of the lowest level strut and the side walls are constructed.
05 . Construction
of Underground Structure
Roof Slab
06 . Backfilling &
Reinstated Road Backfill
Reinstatement
The next level of slab is constructed, followed by the removal of the strut near to that slab level. This process progresses upwards till the roof slab is constructed.
After the roof slab is completed, the soil is backfilled to the first strut level before the first level strut is removed. This is followed by completely backfilling the top of the underground structure. If the retaining wall is a diaphragm wall or a bored pile wall, the top 2 metres of the wall will be removed. If it is a sheet pile wall, the sheet piles will be extracted.
Side Wall
01 . Installation of
Retaining Wall
Retaining Wall
02 . Excavation &
First Level Strut
If you have any suggestions or feedback, please call our Customer Service Line: 1800 CALL LTA 1800 2255 582
October 2004
The underground retaining wall is installed before excavation commences. The retaining wall can be a concrete diaphragm wall, a concrete bored pile wall or a steel sheet pile wall; depending on the site condition, soil type and the excavation depth.
The soil is excavated to the first strut level. The first level strut is installed before the excavation proceeds further.
Safety Measures
The Land Transport Authority (LTA) accords top priority to safety. Professional Engineers (PE) and Qualified Persons (QP) are engaged to carry out stringent checks on the temporary structures to ensure that they are installed correctly and safely before the excavation can proceed from one level to the next level. In addition, our engineers monitor the various stress and strain gauges installed on the temporary structures on a regular basis so as to be sure that the stresses fall within acceptable limits set by the design engineers. Likewise, instruments are extensively installed in the vicinity of the construction site to monitor vibrations, ground movements etc. This is so that the engineers are always in the know of the impact of the construction on the surrounding buildings and structures, thereby ensuring that they are safe.
Inconveniences
Noise and vibrations are generated when the casing is driven in and extracted from the ground by the vibro-hammer. Noise is also generated during the augering process. We will therefore try our best to schedule the work such that it creates minimal disruption to the public.
01 .
02 .
Installation of Casing
VibroHammer
03 .
Augering of Borehole
04 .
05 .
Concreting of Borehole
06 .
Extraction of Casing
VibroHammer
07 .
Repetition of Process
Wooden Peg
Auger
Steel Cage
Cross-Section View
Casing
Cross-Section View
Casing
Cross-Section View
Casing
Casing
Design Depth
Bentonite Slurry
Design Depth
Design Depth
Concrete
Design Depth
Concrete
Design Depth
Wooden pegs are used to mark out the center position of each bored pile. The gap between two bored piles is typically between 100 to 200 millimetres.
The vibro-hammer drives a casing into the ground, leaving about 1 metre length of the casing protruding from the ground.
The auger, a drilling tool, cuts and removes the soil within the casing to form a borehole. The soil surrounding the borehole is supported by the casing. If the casing is not long enough to reach the required depth in the ground, bentonite slurry is used to support the soil below the casing.
The crane lifts up the steel cage and places it within the borehole.
Steps 2 - 6 are repeated till the entire length of the contiguous bored pile wall construction is completed.