AS9100C Checklists
AS9100C Checklists
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
4. Quality Management System
Developed By:
Art Baldwin
Page 1 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
4.2.1 General:
b) A Quality manual?
Developed By:
Art Baldwin
Page 2 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
a) Identification?
b) Storage?
c) Retrieval?
d) Protection?
e) Retention Time?
f) Disposition?
Developed By:
Art Baldwin
Page 3 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
5. Management Responsibility
Developed By:
Art Baldwin
Page 4 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
5.4 Planning:
Developed By:
Art Baldwin
Page 5 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
5.6.1 General:
a) Results of audits?
b) Customer Feedback?
Developed By:
Art Baldwin
Page 6 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
6. Resource Management
6.2.1 General:
Developed By:
Art Baldwin
Page 7 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
6.3 Infrastructure:
c) Supporting Services?
7. Product Realization
Developed By:
Art Baldwin
Page 8 of 79
AS 9100C: 2009
Quality Management System
Contractor:
Audit Checklist Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 9 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
b) Configuration identification?
e) Configuration audits?
Developed By:
Art Baldwin
Page 10 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 11 of 79
AS 9100C: 2009
Quality Management System
Contractor:
Audit Checklist Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 12 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 13 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 14 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 15 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
7.4 Purchasing:
Developed By:
Art Baldwin
Page 16 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
53
Developed By:
Art Baldwin
Page 17 of 79
AS 9100C: 2009
Quality Management System
Contractor:
Audit Checklist Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
h) Retention of records?
Developed By:
Art Baldwin
Page 18 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 19 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Developed By:
Art Baldwin
Page 20 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
d) Special processes?
Developed By:
Art Baldwin
Page 21 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Developed By:
Art Baldwin
Page 22 of 79
AS 9100C: 2009
Quality Management System
Contractor:
Audit Checklist Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
e) Re-validation, if required?
Developed By:
Art Baldwin
Page 23 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Developed By:
Art Baldwin
Page 24 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 25 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
a) Identification?
b) Handling?
c) Packaging?
d) Storage?
e) Protection?
a) Cleaning?
a) Equipment type?
Developed By:
Art Baldwin
Page 26 of 79
AS 9100C: 2009
Quality Management System
Contractor:
Audit Checklist Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
b) Unique identification?
86
c) Location?
d) Frequency of checks?
e) Verification/check method?
f) Acceptance criteria?
a) Test hardware?
b) Test software?
d) Plotters?
a) Calibration?
b) Inspection?
c) Measurement?
d) Testing?
Developed By:
Art Baldwin
Page 27 of 79
AS 9100C: 2009
Quality Management System
Contractor:
Audit Checklist Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
8.1 General:
Developed By:
Art Baldwin
Page 28 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
2) Process capability
measurements?
4) Design of experiments?
c) Inspection?
a) Product conformity?
c) Customer complaints?
Developed By:
Art Baldwin
Page 29 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 30 of 79
AS 9100C: 2009
Quality Management System
Contractor:
Audit Checklist Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 31 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Developed By:
Art Baldwin
Page 32 of 79
AS 9100C: 2009
Quality Management System
Contractor:
Audit Checklist Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 33 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Developed By:
Art Baldwin
Page 34 of 79
AS 9100C: 2009
Quality Management System
Contractor:
Audit Checklist Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 35 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
a) Customer satisfaction?
d) Adequacy of suppliers/subcontractors?
Developed By:
Art Baldwin
Page 36 of 79
AS 9100C: 2009
Quality Management System
Contractor:
Audit Checklist Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 37 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 38 of 79
AS 9100C: 2009
Quality Management System
Audit Checklist
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Notes & Comments
Developed By:
Art Baldwin
Page 39 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Contractor:
Chapter 4 - General Requirements Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
4. Quality Management System
4.2.1 General:
b) A Quality manual?
Developed By:
Art Baldwin
Page 40 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 4 - General Requirements
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 41 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 4 - General Requirements
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
a) Identification?
b) Storage?
c) Retrieval?
d) Protection?
e) Retention Time?
f) Disposition?
Developed By:
Art Baldwin
Page 42 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 4 - General Requirements
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Notes & Comments
Developed By:
Art Baldwin
Page 43 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 5 - Management Systems
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
5. Management Responsibility
Developed By:
Art Baldwin
Page 44 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 5 - Management Systems
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
5.4 Planning:
Developed By:
Art Baldwin
Page 45 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 5 - Management Systems
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
5.6.1 General:
a) Results of audits?
b) Customer Feedback?
Developed By:
Art Baldwin
Page 46 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 5 - Management Systems
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 47 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 5 - Management Systems
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Notes & Comments
Developed By:
Art Baldwin
Page 48 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 6 - Resource Management
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
6. Resource Management
6.2.1 General:
Developed By:
Art Baldwin
Page 49 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 6 - Resource Management
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
6.3 Infrastructure:
c) Supporting Services?
Developed By:
Art Baldwin
Page 50 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 6 - Resource Management
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Notes & Comments
Developed By:
Art Baldwin
Page 51 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 7 - Risk, Design, Production, and Supplier Processes
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
7. Product Realization
Developed By:
Art Baldwin
Page 52 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 7 - Risk, Design, Production, and Supplier Processes
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
b) Configuration identification?
e) Configuration audits?
Developed By:
Art Baldwin
Page 53 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 7 - Risk, Design, Production, and Supplier Processes
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 54 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 7 - Risk, Design, Production, and Supplier Processes
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 55 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 7 - Risk, Design, Production, and Supplier Processes
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 56 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 7 - Risk, Design, Production, and Supplier Processes
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 57 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 7 - Risk, Design, Production, and Supplier Processes
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 58 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 7 - Risk, Design, Production, and Supplier Processes
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
7.4 Purchasing:
Developed By:
Art Baldwin
Page 59 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 7 - Risk, Design, Production, and Supplier Processes
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 60 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 7 - Risk, Design, Production, and Supplier Processes
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
h) Retention of records?
Developed By:
Art Baldwin
Page 61 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 7 - Risk, Design, Production, and Supplier Processes
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 62 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 7 - Risk, Design, Production, and Supplier Processes
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
d) Special processes?
Developed By:
Art Baldwin
Page 63 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 7 - Risk, Design, Production, and Supplier Processes
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 64 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 7 - Risk, Design, Production, and Supplier Processes
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
e) Re-validation, if required?
Developed By:
Art Baldwin
Page 65 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 7 - Risk, Design, Production, and Supplier Processes
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
a) Identification?
b) Handling?
c) Packaging?
d) Storage?
e) Protection?
Developed By:
Art Baldwin
Page 66 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 7 - Risk, Design, Production, and Supplier Processes
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
a) Cleaning?
a) Equipment type?
b) Unique identification?
c) Location?
d) Frequency of checks?
e) Verification/check method?
f) Acceptance criteria?
Developed By:
Art Baldwin
Page 67 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 7 - Risk, Design, Production, and Supplier Processes
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
a) Test hardware?
b) Test software?
d) Plotters?
a) Calibration?
b) Inspection?
c) Measurement?
d) Testing?
Developed By:
Art Baldwin
Page 68 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 7 - Risk, Design, Production, and Supplier Processes
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 69 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 7 - Risk, Design, Production, and Supplier Processes
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Notes & Comments
Developed By:
Art Baldwin
Page 70 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 8 - Measurement / Internal Audits / Corrective Action
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
8. Measurement, Analysis, and
Improvement
8.1 General:
2) Process capability
measurements?
4) Design of experiments?
c) Inspection?
Developed By:
Art Baldwin
Page 71 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 8 - Measurement / Internal Audits / Corrective Action
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
a) Product conformity?
c) Customer complaints?
Developed By:
Art Baldwin
Page 72 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 8 - Measurement / Internal Audits / Corrective Action
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 73 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 8 - Measurement / Internal Audits / Corrective Action
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 74 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 8 - Measurement / Internal Audits / Corrective Action
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 75 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 8 - Measurement / Internal Audits / Corrective Action
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
a) Customer satisfaction?
Developed By:
Art Baldwin
Page 76 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 8 - Measurement / Internal Audits / Corrective Action
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
d) Adequacy of suppliers/subcontractors?
Developed By:
Art Baldwin
Page 77 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 8 - Measurement / Internal Audits / Corrective Action
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Number Question Process/Procedure Reference Comments
Developed By:
Art Baldwin
Page 78 of 79
AS 9100C: 2009
Audit Checklist - Quality Management System
Chapter 8 - Measurement / Internal Audits / Corrective Action
Contractor: Date:
AS9100C Audit Checklist Program PLAS Code:
Notes & Comments
Developed By:
Art Baldwin
Page 79 of 79