For confirming the specifications and performances of an electrical transformer it has to go through numbers of testing procedures. Some tests are done at manufacturer premises before delivering the transformer. Mainly two types of transformer testing are done at manufacturer premises - type test of transformer and routine test of transformer. In addition to that some transformer tests are also carried out at the consumer site before commissioning and also periodically in regular & emergency basis throughout its service life. Tests done at Factory Type Tests Routine Tests Special Tests Tests done at Site Pre Commissioning Tests Periodic/Condition Monitoring Tests Emergency Tests
Transformer vector group test Measurement of impedance voltage/short circuit impedance (principal tap) and load loss (Short circuit test) Measurement of no load loss and current (Open circuit test) Measurement of insulation resistance Dielectric tests of transformer Tests on on-load tap-changer Oil pressure test on transformer to check against leakages past joints and gaskets. That means Routine tests of transformer include all the type tests except temperature rise and vacuum tests. The oil pressure test on transformer to check against leakages past joints and gaskets is included. Special Tests of transformer include Dielectric Tests Measurement of zero-sequence impedance of three-phase transformers Short-Circuit Test Measurement of acoustic noise level Measurement of the harmonics of the no-load current Measurement of the power taken by the fans and oil pumps Tests on bought out components / accessories such as buchhloz relay, temperature indicators, pressure relief devices, oil preservation system etc.
There are different methods for measuring of transformer winding, likewise Current voltage method of measurement of winding resistance. Bridge method of measurement of winding resistance. Kelvin bridge method of Measuring Winding Resistance. Measuring winding resistance by Automatic Winding Resistance Measurement Kit. NB: - Transformer winding resistance measurement shall be carried out at each tap.
4) Measure the voltage in two other HV terminals in respect of neutral terminal. 5) Repeat the test for each of the three phases. In case of auto transformer, magnetic balance test of transformer should be repeated for IV winding also. There are three limbs side by side in a core of transformer. One phase winding is wound in one limb. The voltage induced in different phases depends upon the respective position of the limb in the core. The voltage induced in different phases of transformer in respect to neutral terminals given in the table below.
LEFT SIDE PHASE AN VOLTAGE APPLIED AT LEFT SIDE PHASE VOLTAGE APPLIED AT CENTRAL PHASE VOLTAGE APPLIED AT RIGHT SIDE PHASE 230 V 115 V 50 V
transformers. 3) Measure the supply voltage and electric current in each phase. 4) Now repeat the magnetizing current test of transformertest with keeping tap changer in normal position. 5) And repeat the test with keeping the tap at highest position. Generally there are two similar higher readings on two outer limb phases on transformer core and one lower reading on the centre limb phase, in case of three phase transformers. An agreement to within 30 % of the measured exciting current with the previous test is usually considered satisfactory. If the measured exciting current value is 50 times higher than the value measured during factory test, there is likelihood of a fault in the winding which needs further analysis. Caution: This magnetizing current test of transformer is to be carried out before DC resistance measurement.
Insulation resistance test of transformer is essential type test. This test is carried out to ensure the healthiness of over all insulation system of an electrical power transformer.
Oil temperature should be noted at the time of insulation resistance test of transformer. Since the IR value of transformer insulating oil may vary with temperature. IR values to be recorded at intervals of 15 seconds, 1 minute and 10 minutes. . With the duration of application of voltage, IR value increases. The increase in IR is an indication of dryness of insulation. Absorption Coefficient = 1 minute value/ 15 secs. value. Polarization Index = 10 minutes value / 1 minute value
The induced voltage test of transformer is intended to check the inter turn and line end insulation as well as main insulation to earth and between windings 1) Keep the primary winding of transformer open circuited. 2) Apply three phase voltage to the secondary winding. The applied voltage should be twice of rated voltage of secondary winding in magnitude and frequency. 3) The duration of the test shall be 60 second. 4) The test shall start with a voltage lower than 1/3 the full test voltage, and it shall be quickly increased up to desired value. The test is successful if no break down occurs at full test voltage during test.