Safety Lead Time Functional Overview
Safety Lead Time Functional Overview
Contents
Introduction .................................................................................................................................................. 2 Without Safety Lead Time............................................................................................................................. 3 Setup and Process ......................................................................................................................................... 5 Setup and Process ......................................................................................................................................... 7 Dependencies and Interactions .................................................................................................................... 9 Additional Resources .................................................................................................................................... 9
Introduction
Safety lead time is the amount of time that ASCP schedules supplies in advance of the corresponding demand due dates This results in an inventory buffer during the span of the safety lead time which can hedge against demand uncertainty Use of safety lead time is an alternative to planning to safety stock target levels Not applicable to unconstrained plans and constrained (without scheduling) plans Corresponding demand due dates means due dates of the demands to which the sup plies are pegged. Safety stock target levels are considered during the middle, netting/pegging phase of ASCP planning. It is possible for some of the planned orders created during this phase to be moved in or out during the final, detailed scheduling phase of ASCP constrained planning. Therefore ASCP constrained plans are not guaranteed to follow target safety stock levels. By contrast, safety lead times are considered during the final detailed scheduling phase of ASCP planning. This mechanism can be a more reliable hedge against uncertain demand. With safety lead time, supplies are not pegged to the safety stock level Safety lead time is a soft constraint It will be violated if the supply cannot be scheduled earlier than the demand due date due to other constraints
The following table presents how supply is generated for an item with safety lead time of 2 days: Item A Demand Supply PAB 1000 1000 1000 2000 1000 Day 1 Day 2 Day 3 1000 Day 4 1000 1000 1000 1000 Day 5 Day 6 1000 1000 1000 1000 2000 1000 0 0 Day 7 Day 8 1000 Day 9 1000 Day 10
Supply of 1000 on Day 1 is generated for the demand of 1000 on Day 3, 2 day s ahead of demand because the safety lead time is equal to 2 days. Similarly supplies of 1000s on Day 2, Day 4, Day 6, and Day 7 are generated for demands of 1000s on Day 4, Day 6, Day 8 and Day 9. In this example the Average Inventory Level = 1000 and Excess Inventory = 0.
Day 5 Supply = 500 based on demand on Day 5. It is pegged to demand on Day 5. With Safety Lead Time Safety Stock Level (SSL) is calculated based on the Bucket Days = 2 (looking ahead) and Percent = 300%. Day 1: SSL = {[(Day 2 + Day 3) Demand] / 2} 300 / 100 = [(3000 + 2000) / 2] 300 / 100 = 7500 Day 2: SSL = {[(Day 3 + Day 4) Demand] / 2} 300 / 100 = [(2000 + 1000) / 2] 300 / 100 = 4500 Day 3: SSL = {[(Day 4 + Day 5) Demand] / 2} 300 / 100 = [(1000 + 2000) / 2] 300 / 100 = 4500 Day 4: SSL = {[(Day 5) Demand] / 2} 300 / 100 = [(2000) / 2] 300 / 100 = 3000 Day 5: SSL = 0 Day 1 Supply = 6000 is generated based on demands of Day 2, Day 3, and Day 4 (3000 + 2000 + 1000) since the safety lead time is equal to 3 days. This supply is pegged to demands of Day 2, Day 3, and Day 4. This supply is moved to Day 2 by the scheduling process due to capacity constraints. Day 2 Supply = 2000 is generated based on demand of Day 5 (2000). This supply is pegged to demand of Day 5. This supply is moved to Day 3 due to capacity constraints.
MSO: Use Safety Lead Time Enables ASCP to schedule supplies with respect to safety lead time
Profile Value
Description ASCP calculates and plans for safety stock directly based on the Safety Stock Percent item attribute. This is the default value. ASCP schedules supplies earlier to account for safety lead time based on the value specified in the Safety Stock Percent item attribute as the safety lead time (days).
No
Yes
You can specify Safety Stock Method and Percent in the Organization Item window: Set Safety Stock Method to MRP Planned % Value in the Percent field represents the Safety Lead Time when the profile option MSO: Use Safety Lead Time is set to Yes (example: 5% = 5/100 day) Navigation: - Inventory : Items : Organization Items : General Planning Tab
Additional Resources
For more information about Oracle Applications http://www.oracle.com/applications/home.html For more information about Education http://www.oracle.com/education/index.html For more information about Support http://www.oracle.com/support/ For Oracle Product documentation: http://www.oracle.com/technology/documentation/applications.html