Chilled Water Optimization
Chilled Water Optimization
How Chilled Water Optimization makes Cogeneration More Effective with a Better Payback
By
Post Sandy
Challenge our industry Resiliency Answer Micro Grid - CHP Island mode operation
CHP Implementation
CHP Limitation
High electric to thermal demand during summer limits CHP operation. Decreasing the summer electric demand allows best operational scenario for CHP.
ELECTRICAL OUTPUT 29.7%
INPUT 100%
CHP Selection
Reduction in power consumption in summer allows the selection of smaller CHP units with low minimum thermal output optimal in summer
It allows the better unit selection with more operating hours and more energy savings resulting in good payback.
Chilled Water Optimization is a necessary step for CHP operation.
1. Power requirements for Chilled water system establish peak summer demand 2. I have yet to see an efficient chilled water system
Brain
(Building End-Users)
Heart
(Variable Volume Primary Pump)
Local consultant recommended Installing 3,000 tons of additional capacity We were called in for peer review Our review indicated that the cooling load was only 8,800 tons Reengineering the plant we regain the capacity and reduced PEAK Power
I observed major valves partially closed all over Balancing is a crime for any dynamic hydraulic system Partially closed valves eats up pump energy for no reason
Distribution Observations
Use of Building Pumping Unnecessary, Removed 130 pumps from the buildings. Power reduction 1.1 megawatt
Pressure Wasted by Closing valve Pressure Increased Removed 130 pumps from the buildings
by pump
FM
DISTRIBUTION
FM
SECONDARY PUMPS
CH-6
PRIMARY PUMPS
P
CH-1 CH-2
CH-7
DECOUPLER
CH-3
CH-4
MIN BYPASS
Primary-Constant Speed
Primary/Secondary Variable
Poor Design
Oversized Pumps causing valves to throttle at 60%. Flow above 4000 GPM through the de-coupler.
Generation
Utilization
Division of Responsibility
Building connections: Chilled water pressure being utilized improperly at buildings. Valve OPEN
Valve CLOSED Variable Primary Pumping User Buildings
CHILLERS
Farthest Building
Division of Responsibility
Building connections: Chilled water pressure being utilized improperly at buildings. Chilled water flowing through non-operating pump.
Pressure drop:10psi Head Loss: 23 ft At peak load flow of 46,000 GPM, additional power required for Pumps at Chiller Plant is
kW
After
3 Pumps Removed
8 Pumps Removed
7 Pumps Removed
3 Pumps Removed
Modifications
Performed comprehensive hydraulic analysis and identified flow restrictions and pump deficiencies, enabling further capacity increase by 2000 tons.
REDUCED DEMAND AND CONSUMPTION AND ENERGY COST BY 20%
11,750
Demand (KW)
Now peak cooling day demand is met by 4 chillers compared to six prior to modification 650 kW demand savings
11,500
11,250
11,000
10,750
10,500
10,250
10,000 8 9 10 11 12 13 14 15 16 17 18 19 20
Time of Day
DP Ce m
Refrigerant mass flow:
200 m RE
RE: Refrigerant effect increases as T increases. Mass flow rate decreases with increase in T Hence compressor power decreases with increase in T. Low T reduces chiller capacity and more chillers need to be operated.
August 2012
February 2013
December 2012
Base Case
Month Cooling Load (Tons) 73,253 434,587 2,366,054 2,035,622 3,439,051 4,078,799 5,617,310 4,075,679 3,999,653 2,134,784 1,401,126 1,529,842 31,185,761 Total Chiller Total CHPW Power Power (kWH) (kWh) 42,481 242,603 1,170,524 1,006,826 1,703,912 2,006,957 2,807,070 2,097,100 1,963,882 1,071,904 732,718 785,992 15,631,968 5,583 30,942 136,124 114,011 207,288 228,190 315,648 227,470 231,896 108,340 66,521 85,692 1,757,704 CW Pump CT Fan Power Power (kWH) (kWH) 16,023 83,880 259,735 225,773 333,584 350,618 440,303 361,732 354,066 222,158 173,286 200,029 3,021,188 4,522 11,545 54,696 83,751 157,903 224,666 291,414 245,651 193,669 76,515 49,594 5,886 1,399,813 Cost ($)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
$3,430 $18,449 $81,054 $71,518 $120,134 $140,522 $192,722 $146,598 $137,176 $73,946 $51,106 $53,880 $1,090,534
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
$3,208 $17,284 $77,447 $68,382 $115,501 $135,652 $186,606 $141,574 $132,258 $70,860 $48,699 $51,102 $1,048,573
Summary: How to get power reduction and get your system in shape
1. Keep operating logs; have logs reviewed by an expert
2. Dont be afraid of change; use state-of-the-art technology 3. Interchange operating personal between plant and buildings, or cross training 4. Provide System training to operators 5. Convert HVAC controls to process controls
OAT: 45
Temp: 58
Operators Training
Training the operators for systems operation yields maximum plant savings. Systems knowledge eliminates the fear of operation thus eliminating redundant system/product operations. Empowers operators to take knowledgeable decisions during plant operation.
We will review documents and provide a report on the health of your system and opportunities for system optimization at NO COST to you
Achievements
Association of Energy Engineers (AEE) Region I Energy Engineer of the Year: Oct. 2011
Thank You
Hemant Mehta, P.E. President