System Description-ParkddHyatt - 1

The document describes the HVAC system for the Park Hyatt Hotel. The system includes central chillers, cooling towers, air handling units, fan coil units, and cassette units to condition various areas of the hotel. A direct digital control building management system monitors and controls the HVAC equipment and maintains temperature and humidity setpoints throughout the building. The basement levels contain plant equipment while upper floors utilize air handling units, fan coils, and other units to condition guest rooms, offices, restaurants, and other spaces.

Uploaded by

Syed Shahbaz
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
167 views9 pages

System Description-ParkddHyatt - 1

The document describes the HVAC system for the Park Hyatt Hotel. The system includes central chillers, cooling towers, air handling units, fan coil units, and cassette units to condition various areas of the hotel. A direct digital control building management system monitors and controls the HVAC equipment and maintains temperature and humidity setpoints throughout the building. The basement levels contain plant equipment while upper floors utilize air handling units, fan coils, and other units to condition guest rooms, offices, restaurants, and other spaces.

Uploaded by

Syed Shahbaz
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 9

PARK HYATT HOTEL HVAC SYSTEM HVAC SYSTEM DESCRIPTION

1.0 General

The Air conditioning system is designed in such a way that the air conditioned space is maintain 23 1 deg. C Db temperature & Rh not exceeding 555% for All smoke free lobbies, Car parking areas, all toilets and all pantry rooms. The smoke free lobbies ventilation system shall operate during the fire mode only. The chilled water system is designed to supply the chilled water at a temp of 7 deg C inlet 12 deg C Out let to the AHUs and FCUs. The Chillers shall operate to meet the overall building load requirement throughout the day. Chiller operation shall be by a combination of chiller optimization and sequencing. The cooled air supplied by AHUs , CSUs , FCUs and Cassette Type Units to the areas served by them shall ensure the inside conditions of 23 Deg C 1 Deg C Dry Bulb Temperature (DBT) with RH not more than 60 %. The cooled and dehumidified air (supply air) shall be conveyed to the air conditioned areas through Galvanized Sheet Steel (GSS) ducting and distributed to the air conditioned areas through supply air diffusers. The air handling and air distribution system shall be a constant Air volume (CAV) system. The GSS ducting, diffusers, AHUs and the associated control system shall be designed, erected, and commissioned by us to ensure that the air conditioned space is maintained at the temperature and humidity levels specified above. The return air from the air conditioned areas is brought back to the AHU room using the false ceiling void (space available between the false ceiling and roof) by means of return air diffusers and grilles. Fire dampers and volume control dampers shall be provided at all necessary locations. Volume control dampers shall be provided at all branch and sub branch ducts from individual main and sub main ducts whether shown on drawing or not to facilitate proper air balancing. Fire dampers of proper rating shall be provided wherever duct penetrates a fire.
i

PARK HYATT HOTEL HVAC SYSTEM


The building shall be provided with a Direct Digital control (DDC) integrated building management system (IBMS). The BMS shall be designed for remote operation, control, and monitoring of the ACMV system and equipment including Pumps, Chiller s, Cooling towers ,AHUs, Valves, Dampers and all mechanical ventilation fans, etc. Performance of the HVAC system shall be demonstrated by ETA prior to the commissioning of the BMS system in the manual mode. The HVAC contractor (ETA) shall interface with BMS contractor for installation of devices and successful commissioning of the system. The chiller internal parameters shall be provided to the BMS system through industry standard BAC net / Modbus TRU protocol. We have installed motorized on / off butterfly valves with limit switches for on / off status. Actuator shall accept remote on / off command from BMS system. The on / off status shall be furnished as NO contacts. The motorized valves and Thermostats will be supplied by BMS Vendor.
2.0

PLANT ROOM @B4 Level:

The Chilled water plant consists of 2 nos Water cooled Centrifugal chillers of 750 TR and 2 nos Water cooled Hermetic screw chillers of 350 TR(stand by) capacities each located at the Plant room of the Service Floor (B4). All the chillers are connected by common chilled water header. The Feeder panel for the Water cooled chillers is located at the Same Floor. The chilled water circulation system located in the B4 Floor, Plant Room consists of primary pumps to circulate water through chiller and secondary pumps for further circulation to the load i.e., air handling units,CSUS,Cassett units and fan coil units and back. There are 5 nos of primary chilled water pumps (4W + 1S), one pump each catering to each chiller. The secondary chilled water system consists of 4 nos secondary chilled water pumps (3W + 1S). Condenser water pumps (4W + 1S) one pump each catering to each chiller and also of 4 nos. Cooling towers (4W), Two CT each catering to each chiller (750 TR) located at 1st Guest Floor Terrace Level.

ii

PARK HYATT HOTEL HVAC SYSTEM


Primary pump sets and Cooling towers shall be controlled through BMS system. Secondary pump sets shall be controlled by variable frequency drives sensing the pressure differential in the distribution loop. Depending on the load the 2 way valve of AHU and Other equipments regulate the water flow to the coil and this causes an increase in line pressure. Sensing the increased pressure differential the pressure transmitter will send a signal to the secondary pump controller which in turn controls the speed of motor through VFD thus saving power. The excess water from the secondary circuit goes back to the primary circuit through the bypass pipe line. In the Primary system we have also installed air separator and Degasser for purge the air and gases from the system. For Pressurization of chilled water we have provided pressurization tank with 1w+1s pump set with Tank at Terrace Level. The entire chilled water system is provided with balancing valves at various locations to balance the load properly. 2.2 i) The air conditioning and ventilation system of different floors are described hereunder: Basement Floor (B5):

Pump room ventilation is provided through 1 no exhaust fans located at the Basement-4 Level. ii) Basement Floor (B4): Forced ventilation is provided through Dual Speed 6 nos Axial flow fans, (3No.s with VFD & other 3Nos with S/D starter) and 23 nos Jet fans located at the Same Floor by extracting the air of the car parking area at basement. All the fans in normal condition will work as per the PPM Level in the Fire mode all fans will work in High speed through fire alarm system and also 3nos of Exhaust fans serving to Electrical room and Fire pump rooms. Air-conditioning is provided for Plant room, Electrical room and UPS rooms
iii

PARK HYATT HOTEL HVAC SYSTEM


3 nos. of Fresh air fans are located in the Same Floor Serving to B4 to Lobby M Level of the Building Staircases to provide pressurized ventilation in the Staircase. This Pressurization system will work through the Building fire alarm system. iii) Basement Floor (B3):

Forced ventilation is provided through Dual Speed 6 nos axial flow fans (3No.s with VFD & other 3Nos with S/D starter) and 23 nos of Jet fans located at the Same Floor by extracting the air of the car parking area at basement. All the fans in normal condition will work as per the PPM Level in the Fire mode all fans will work in High speed through fire alarm system. Ventilation is provided for STP Area through 1 nos exhaust air fan and 1no.s Fresh air fan. Apart from that 3 nos. of Fresh air fans each are located in the Same Floor Serving to B4 to Lobby M Level of the Building Staircases to provide pressurized ventilation in the Staircase. This Pressurization system will work through the Building fire alarm system. iv) Basement Floor (B2):

Forced ventilation is provided through Dual Speed 6 nos axial flow fans (3No.s with VFD & other 3Nos with S/D starter) and 23 nos of Jet fans located at the Same Floor by extracting the air of the car parking area at basement. All the fans in normal condition will work as per the PPM Level in the Fire mode all fans will work in High speed through fire alarm system. Forced ventilation is provided for Boiler room through 1 no exhaust air fan. Forced ventilation is provided for DG Area through 3 nos exhaust air fan and 4 nos 2 Stage cooling Fresh air fan. 1 nos. of Fresh air fans is located in the Same Floor Serving to B4 to Lobby M Level of the Building Staircases to provide pressurized ventilation in the Staircase. This Pressurization system will work through the Building fire alarm system.
iv

PARK HYATT HOTEL HVAC SYSTEM


v) Basement Floor (B1):

The air distribution system of Base ment-1 floor consists of 8 nos AHUs in different capacities to serve the Back office areas and Common area and 34 no. CSUs & AHUs of TR different capacities serving to the Back office areas 1 no TFA is serving to Kitchen area 2 no Fresh air units serving to Basement floor all the equipments, 2 nos of PAC Units serving to server room,1 no FCU is Serving to BMS room and also 45 nos of Chilled water cassette units different Capacities Serving to different areas .Exhaust Air from the Toilets and Kitchens are extracted thru a ductwork system connected to a 19 nos central exhaust fan s located in the Same floor. vi) Lobby Main Floor:

The air distribution system of Ground floor consists of 13 nos AHUs & CSUs in different capacities to serve the Restaurants, Kitchens Lobby areas and Common area, Coffee shop, Meeting room and Restaurants 2 no TFAs are serving to Kitchen area, 2 nos split units Serving to Security room and also 8nos of Chilled water cassette units different Capacities Serving to different areas. Exhaust Air from the Toilets and Kitchens are extracted through a ductwork system connected to a 6 nos central exhaust fan s 3located in the same floor & 3 no. are located in First Guest Floor Terrace level for Kitchen Exhaust. vii) Lobby mezzanine Floor:

The air distribution system of Lobby mezzanine Floor consists of 14 nos AHU & CSU of different capacities serving to Spa area , Common area, serving to the Restaurants, gym area, spa area and corridors .3 no TFAs are serving to Kitchen area , 1 nos FCU Serving to Spa Store and also 3nos of DSU Serving to Spa areas .Exhaust Air from the Toilets and Restaurants hoods are extracted thru a ductwork system connected to a 7 nos central exhaust fan s 6 are located in the same floor & 1 no. are located in First Guest Floor Terrace level for Spa area .

PARK HYATT HOTEL HVAC SYSTEM


viii) First Guest Floor:

The air distribution system of First floor consists of 50 nos. FCUS having 1.5, 2, TR capacities each to serve the Guest rooms, 4 nos DSU for Junior Suits and 3 nos TFA of different capacity to serve the Common area and Room s Fresh air and also 1 no TFA Serving to Specialty Restaurants .6 nos of AHUS Serving to in different capacities to serve the Ball room, Restaurants, Kitchen areas and Common area. Exhaust Air from the Toilets in Guest rooms is extracted thru a ductwork system connected to a central exhaust fan located in the Terrace floor. ix) Second Guest Floor: The air distribution system of Second floor consists of 60 nos FCUS having 1.5, 2, TR capacities each to serve the Guest rooms, 4 nos DSU for Junior Suits and 1 no TFA of 8210 cfm capacity to serve the Common area and Room s Fresh air and also Exhaust Air from the Toilets in Guest rooms are extracted thru a ductwork system connected to a central exhaust fan located in the Terrace floor. x) Third Guest Floor:

The air distribution system of Third floor consists of 60 nos FCUS having 1.5, 2, 2.5 TR capacities each to serve the Guest rooms, 4 nos DSU for Junior Suits and 1 no TFA of 8210 cfm capacity to serve the Common area and Room s Fresh air and also Exhaust Air from the Toilets in Guest rooms are extracted thru a ductwork system connected to a central exhaust fan located in the Terrace floor. xi) Fourth Guest Floor:

The air distribution system of Fourth floor consists of 61 nos FCUS having 1.5, 2, TR capacities each to serve the Guest rooms, 4 nos DSU for Junior Suits and 1 no TFA of 8210 cfm capacity to serve the Common area and Rooms Fresh air and also Exhaust Air from the Toilets in Guest rooms are
vi

PARK HYATT HOTEL HVAC SYSTEM


extracted thru a ductwork system connected to a central exhaust fan located in the Terrace floor. xii) Fifth Guest Floor:

The air distribution system of Fifth floor consists of 62 nos FCUS having 1.5, 2, TR capacities each to serve the Guest rooms and 1 no TFA of 8210 cfm capacity to serve the Common area and Room s Fresh air and also Exhaust Air from the Toilets in Guest rooms is extracted thru a ductwork system connected to a central exhaust fan located in the Terrace floor. xiii) Sixth Guest Floor:

The air distribution system of Sixth floor consists of 59 nos FCUS having 1.5, 2, 2.5 TR capacities each to serve the Guest rooms and 3 nos TFA of Different capacitys to serve the Common area and Room s Fresh air and also Exhaust Air from the Toilets in Guest rooms is extracted thru a ductwork system connected to a central exhaust fan located in the Terrace floor. xiv) Stair case Pressurization System @All the Floors:

6 nos. of Centrifugal fresh air fans of Different capacitys each are located in Terrace Serving to Different Floors of the Building Staircases to provide pressurized ventilation in the Staircase. This Pressurization system will work through the Building fire alarm system. xv) Lift well Pressurization System @All the Floors:

3 nos. of Centrifugal fresh air fans of Different capacitys each are located in Terrace Serving to Different Floors of the Building to provide pressurized ventilation in the lift well. This Pressurization system will work through the Building fire alarm system.

vii

PARK HYATT HOTEL HVAC SYSTEM


xvi) Terrace Floor:

This area is provided with supply/exhaust fans which are detailed hereunder: 14 nos. Of Axial flow fans of 7000 cfm capacity is installed in the Terrace to extract air from the Atrium area. 6 nos. Toilet exhaust fans of 6500, 8000, 2500 cfm capacity each are installed in the Terrace to extract air from the Toilets of all floors. 3 nos. Of Centrifugal Exhaust air fans of 19900, 9950 cfm capacity is installed in the Terrace to extract air from the Lift well area. 6 nos. Of Centrifugal Fresh air fans of 3400, 7140, 2340,4530,5930,7000 cfm capacities are installed in the Terrace to Staircases to provide pressurized ventilation in the Staircase. Expansion tank 2 nos. with pumps. 2.3 Air Distribution :

The supply air is distributed through factory fabricated ducts and return air is collected above false ceiling back to the AHU rooms. The supply air plenum and initial 4 meters of supply air duct are acoustically insulated 25 mm thick fiber glass matt finished with Al. perforated sheet & RP Tissue. The complete supply air duct is 100% thermally insulated externally with Al foil faced fiber glass matt of 25 mm thick to avoid any cooling loss. The supply air distribution shall be through powder coated aluminum grid diffuser and return air shall be fed back to the AHU rooms through powder coated aluminum diffusers and grilles. The supply & return air ducts within each AHU room are provided with motorized fire damper and shall be actuated on receiving signal from the fire alarm panel. Volume control dampers and sound attenuators shall be provided as required.

viii

PARK HYATT HOTEL HVAC SYSTEM


For forced ventilation areas, separate supply and exhaust fans are provided. Fresh air fans are provided for supply of outside air to all the air handling unit rooms. The fresh air fan shall be controlled using Carbon-di-oxide sensors sensing the levels within the conditioned spaces. Exhaust fans are provided for the toilets, kitchen and basement car parking areas. For the Car parking supply air fans are also provided to supply fresh air. Staircase is provided with fresh air fans to provide required pressurization incase of fire. All air handling units are hooked with fire detection system to switch off the same in case of fire.

ix