Structural Steel Contract

This document is a checklist for erecting structural steel that includes over 40 items to verify before and during the project. It addresses confirming foundation readiness, identifying pre-assembly needs, ensuring necessary equipment and materials are on site, completing plans and permits, and verifying safety requirements. Inspections and sign off by the planner, superintendent, and work foremen at key stages are also required. Upon completion, as-built drawings must be updated to reflect any changes from original specifications.

Uploaded by

Rini Butarbutar
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2K views

Structural Steel Contract

This document is a checklist for erecting structural steel that includes over 40 items to verify before and during the project. It addresses confirming foundation readiness, identifying pre-assembly needs, ensuring necessary equipment and materials are on site, completing plans and permits, and verifying safety requirements. Inspections and sign off by the planner, superintendent, and work foremen at key stages are also required. Upon completion, as-built drawings must be updated to reflect any changes from original specifications.

Uploaded by

Rini Butarbutar
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

MAJOR PROJECTS

Appendix - 4
Department: Subject:

CONSTRUCTION FIWP STRUCTURAL STEEL ERECTION CHECKLIST

Number:

PCM-CP-000X-4
Revision:

FIWP ID Number: FIWP Description:


ITEM DESCRIPTION Foundation Complete Ready For Structural Steel: a) Anchor Bolts Checked And Correctly Located b) Threads Not Damaged And Lubrication Applied c) Latents Removed d) Shim Blocks Set To Height And Grouted e) Base Top Prepped Ready For Grout Items/Parts/Frames To Be PreAssembled/Erected (On/Off Site) Clearly Identified With MarkedUp Drawings Structural Members Required For PreAssembly / Erection Onsite And Available Field Supply Material Onsite And Available Area To Perform Pre-Assemble Identified (On/Off Site) And Available Crane(s) To Support Work Package Activities: a) Onsite b) Available c) Scheduled Required Rigging And Accessories Onsite And Available To Support Work Package Activities Lift Plan In Place And Ready For Use Engineered Rigging Study Required: a) Complete b) Reviewed c) Authorized For Use Transportation Requirements For Equipment, Structural Members, Tools Etc.: a) Available b) Scheduled Special Tool Requirements Clearly Identified, Listed, Onsite and Available For Use Material Requisitions Complete Ready To Be Submitted For Work Package Materials In Warehouse Bagged And Tagged Special Training / Qualification Requirements: a) Safety; SCABA, High Level Rescue Etc b) Equipment Operation; Manlift Etc. c) Other d) Training Complete Permit Requests Complete Ready To Be

Date Prepared:
YES / NO / N/A COMMENTS

UNCONTROLLED DOCUMENT PRINTED ON 04/21/08


File: STRUCTURAL STEEL.doc

Page 1 of 3

MAJOR PROJECTS

Appendix - 4
Department: Subject:

CONSTRUCTION FIWP STRUCTURAL STEEL ERECTION CHECKLIST

Number:

PCM-CP-000X-4
Revision:

Submitted For Work Package Safety Items And Concerns Identified, Listed And Addressed Hazard Assessments / Requirements: a) Hazard Identified b) Assessment Performed c) Mitigated Additional Personnel Protective Equipment Requirements Clearly Identified, Listed, Onsite And Available For Use Inspection And Testing Requirements Clearly Identified And Listed QC forms inserted into package for required inspection and sign-off Third Part Inspection And Testing: a) Available b) Scheduled Vendor Requirements: a) Required b) Available c) Scheduled Surveyor For Steel Alignment: a) Available b) Scheduled Scaffolding / Manlift Requirements: a) Identified b) Available c) Scheduled d) Built (Scaffold Only) All Required Drawings, Details And Specification Included In Work Package: a) General Arrangement b) Sections And Details c) Erection Drawings d) Piece Mark Detail Drawings e) Release For Grouting Form e) Design Change Notices f) Request For Information g) Inspection And Test Plan h) Lessons Learned Suggestion Form Structural Steel Erected, Inspected And Signed-Off As Complete As-Builts: a) Structural Steel Installed As Per Drawings And Specifications b) Changes Or Modifications Made c) Changes Or Modifications Recorded And Included on Master As-Builts Drawing Set

UNCONTROLLED DOCUMENT PRINTED ON 04/21/08


File: STRUCTURAL STEEL.doc

Page 2 of 3

MAJOR PROJECTS

Appendix - 4
Department: Subject:

CONSTRUCTION FIWP STRUCTURAL STEEL ERECTION CHECKLIST

Number:

PCM-CP-000X-4
Revision:

Planner Name (print):

Planner Signature:

Issue Date:

Superintendent Name (Print):

Superintendent Signature:

Issue Date:

Work Foreman Name:

Work Foreman Signature:

Work Start Date:

Work Foreman Name:

Work Foreman Signature:

Work Completion Date:

UNCONTROLLED DOCUMENT PRINTED ON 04/21/08


File: STRUCTURAL STEEL.doc

Page 3 of 3