25m deep 2) Ditto not exceeding 1.00m deep 3) Ditto not exceeding 2.00m deep 4) Ditto not exceeding 4.00m deep 4) 50mm sand blinding to receive manhole 5) 150mm thick concrete base 6) BRC in concrete base 7) Sawn formwork to side of concrete base n.e 150mm high 8) 150mm half round VC pipe 9) Concrete benching 10) One brick wall 11) Concrete cover slab 12) Sawn formwork to side of concrete cover slab 13) Plastering to wall and edge of concrete cover slab 14) Cement rendering to concrete benching 15) Cement rendering to concrete nil cover slab 16) Mild steel step 17) Heavy duty galvanized iron manhole cover 18) Testing Unit M3 M3 M3 M3 M2 M2 M2 M No M2 M2 M2 M M2 M2 M2 No No Item
SCHEDULE OF MANHOLE ITEM MH1 MH2 MH3 MH4 SIZE OF MANHOLE 750mmx600mm 750mmx750mm 1000mmx1000mm 1000mmx900mm THICKNESS OF WALL 225 225 225 225 DEPTH OF EXCAVATION 919mm 1719mm 2869mm 4019mm CHANNEL Straight + Bend Straight + Bend Straight + Y Junction Straight + Y Junction TYPE OF COVER Heavy GI Heavy GI Heavy GI Heavy GI
I)
II)
Size of Manhole
= G.L ( I.L Thickness 0f round channel) + cover slab = 15.00 ( 14.30 0.019) + 0.120 = 0.839m Size of manhole 1 (MH1) = 750mm x 600mm ( From schedules ) MH2 G.L I.L 15.00 13.50
I)
II)
Size of Manhole = G.L ( I.L Thickness 0f round channel) + cover slab = 15.00 ( 13.50 0.019) + 0.120 = 1.639m Size of manhole 1 (MH1) = 750mm x 75mm ( From schedules )
I)
II)
Size of Manhole = G.L ( I.L Thickness 0f round channel) + cover slab = 15.00 ( 12.35 0.019) + 0.120 = 2.789m Size of manhole 1 (MH1) = 1000mm x 900mm ( From schedules )
I)
II)
Size of Manhole
= G.L ( I.L Thickness 0f round channel) + cover slab = 15.00 ( 11.20 0.019) + 0.120 = 3.939m Size of manhole 1 (MH1) = 1000mm x 900mm ( From schedules )
SCHEDULE OF MANHOLE
MH2
Straight + Bend