Labour Productivity Chart in Uae

This document contains productivity rates for various construction works. It lists 64 items of formwork activities along with their crew size, hourly production rate, and production per 10 hours. It then lists additional masonry, plastering, ceramic, tiling, kerbing, block paving, manhole and drainage construction activities with similar crew size, rate and productivity details. The document provides a standardized reference for estimating productivity of common construction works.

Uploaded by

Abraham Alex
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
91% found this document useful (33 votes)
67K views9 pages

Labour Productivity Chart in Uae

This document contains productivity rates for various construction works. It lists 64 items of formwork activities along with their crew size, hourly production rate, and production per 10 hours. It then lists additional masonry, plastering, ceramic, tiling, kerbing, block paving, manhole and drainage construction activities with similar crew size, rate and productivity details. The document provides a standardized reference for estimating productivity of common construction works.

Uploaded by

Abraham Alex
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 9

Item No.

CREW SIZE HourIy Production


Production Rate Per 10 hrs.
SM
FW FORMWORK
FW01 Formwork to footings 2 CARPENTERS, 1 HELPER 1.2 12
FW02 Formwork to isolated footings 2 CARPENTERS, 1 HELPER 1.6 16
FW03 Formwork to rafts 2 CARPENTERS, 1 HELPER 1.4 14
FW04 Formwork to rafts D>0.75m 2 CARPENTERS, 1 HELPER 1.8 18
FW05 Formwork to tie beams 2 CARPENTERS, 1 HELPER 1 10
FW06 Formwork to high level tie beams D>0.45M 2 CARPENTERS, 1 HELPER 1.2 12
FW07 Formwork to Neck Columns 2 CARPENTERS, 1 HELPER 4
FW08 Formwork to U/G Water tank 2 CARPENTERS, 1 HELPER 6
FW09 Formwork to basement retaining walls 2 CARPENTERS, 1 HELPER 9
FW10 Formwork to columns (small size) 2 CARPENTERS, 1 HELPER 7
FW11 Formwork to Columns (large size) 2 CARPENTERS, 1 HELPER 9
FW12 Formwork to D/S beam internal (shallow) 2 CARPENTERS, 1 HELPER 6
FW13 Formwork to D/S beam external (Deep) 2 CARPENTERS, 1 HELPER 7
FW14 Formwork to D/S beam external (Shallow) 2 CARPENTERS, 1 HELPER 4
FW15 Formwork to D/S beam external (Deep) 2 CARPENTERS, 1 HELPER 6
FW16 Formwork to lift walls single core 2 CARPENTERS, 1 HELPER 6
FW17 Formwork to lift walls multi core 2 CARPENTERS, 1 HELPER 8
FW18 Formwork to slab decking (10ft) hourdi 2 CARPENTERS, 1 HELPER 1.6 16
FW19 Formwork to slab decking (>10ft) hourdi D/S beams 2 CARPENTERS, 1 HELPER 1.2 12
FW20 Formwork to slab decking (>10ft) hourdi 2 CARPENTERS, 1 HELPER 1.2 12
FW21 Formwork to slab decking (>10ft) hourdi 2 CARPENTERS, 1 HELPER 1 10
FW22 Formwork to staircase (non spiral) 2 CARPENTERS, 1 HELPER 4
FW23 Formwork to balcony parapets 2 CARPENTERS, 1 HELPER 6
FW24 Formwork to roof parapets 2 CARPENTERS, 1 HELPER 8
D = DEPTH Page 1 of 7
U. GR. = UNDERGROUND
D/S = DECK - SLAB
> = GREATER THAN
< = LESS THAN
PRODUCTIVITY RATES FOR ALL PROJECT WORKS:
(Rev 0, May 2000)
Item No. CREW SIZE HourIy Production
Production Rate Per 10 hrs.
FW 25 shutter Manufacture for pile caps 1 CARPENTER + 1 HELPER 2.00 20
FW 26 shutter Fix for pile caps CARPENTER + 1 HELPER 1.50 30
FW 27 Deshutter footings/pile caps 1 HELPER 6.00 60
FW 28 Shutter make column necks 1 CARPENTER + 1 HELPER 1.50 15
FW 29 Shutter fix column necks 1 CARPENTER + 1 HELPER 1.20 12
FW 30 Deshutter Column necks 1 HELPER 4.80 48
FW 31 Shutter make tie beams 1 CARPENTER + 1 HELPER 1.20 12
FW 32 shutter fix tie beams 1 CARPENTER + 1 HELPER 1.00 10
FW 33 Column shutter making 1 CARPENTER + 1 HELPER 1.20 12
FW 34 Column shutter fixing 1 CARPENTER + 1 HELPER 1.00 10
FW 35 Column deshuttering 1 HELPER 4.00 40
FW 36 Walls shutter making 1 CARPENTER + 1 HELPER 1.50 15
FW 37 Walls shutter fixing 1 CARPENTER + 1 HELPER 0.80 80
FW 38 De shutter Tie beam shutter 1 HELPER 4.00 40
FW 39 Wall formwork deshuttering 1 HELPER 3.20 32
FW 40 Staircase formwork making 1 CARPENTER + 1 HELPER 0.80 8
FW 41 staircase formwork fixing 1 CARPENTER + 1 HELPER 0,8 8
FW 42 Staircase formwork deshuttering 1 HELPER 1,6 16
FW 43 Drop beams formwork making 1 CARPENTER + 1 HELPER 1.00 10
FW 44 Drop beams formwork fixing 1 CARPENTER + 1 HELPER 0.80 8
FW 45 Drop beams formwork stipping 1 HELPER 3.20 32
FW 46 suspended slab formwork fixing 1 CARPENTER + 1 HELPER 1.20 12
FW 47 suspended slab formwork deshutter 1 HELPER 5.00 50
FW 48 Formwork fixing for sunshades 1 CARPENTER + 1 HELPER 0.70 7
FW 49 Parapet formwork making 1 CARPENTER + 1 HELPER 1.20 12
FW 50 Parapets formwork fixing 1 CARPENTER + 1 HELPER 1.00 10
FW 51 Parapets formwork stripping 1 HELPER 4.00 40
FW 53 Fixing of lintle formwork 1 CARPENTER + 1 HELPER 0.50 5
FW 54 Deshutter lintle formwork 1 HELPER 2.00 20
FW 55 Deck formwork fixing 1 CARPENTER + 1 HELPER 1.50 15
FW 56 Deck Formwork deshuttering 1 HELPER 6.00 60
FW 57 Pipe scaffolding erection for slab 1 SCAFFOLDER 0.85 85
FW 58 inverted beam shutter fixing 1 CARPENTER + 1 HELPER 1.00 10
FW 59 De-Shuttering Manholes, square - circular (Timber) 1 CARPENTER + 1 HELPER 4m
2
40m
2
FW 60 Manhole Shutter erection - square or circular(Timber) 1 CARPENTER + 1 HELPER 1,5 m
2
15m
2
FW 61 Metal Shutter for Manholes 1 CARPENTER + 1 HELPER 1m
2
10m
2
FW 62 Metal Shutter for Precast Beams 2 CARPENTERS + 2 HELPERS 3M
2
30M
2
FW 63 Metal Shutter for Pile caps 2 CARPENTERS + 2 HELPERS 3M
2
27M
2
FW 64 Metal Shutters for Pile cap Beams 2 CARPENTERS + 2 HELPERS 3M
2
30M
2
Page 2 of 7
PRODUCTIVITY RATES FOR ALL PROJECT WORKS:
(Rev 0, May 2000)
Item No. CREW SIZE HourIy Production
Production Rate Per 10 hrs.
Per Unit
M MASONARY WORKS
MBW 01 Hollow Blockwork (100, 150 & 200 mm) 1 MASON, 1 HELPER 12 Nos 120 NR
MBW 02 Hollow Blockwork (large panels) 1 MASON, 1 HELPER 14 Nos. 140 NR
MBW 03 Solid blockwork 1 MASON, 1 HELPER 9,5 95 NR
MBW 04 Solid Blockwork as Raft forms 1 MASON, 1 HELPER 11 110 NR
MPL PLASTERWORK 1.2
MPL 01 Plaster (internal), walls final coat 1 MASON, 1 HELPER 1.6 16 SM
MPL 02 Plaster (internal), walls rush coat 2 HELPER 1.4 150 SM
MPL 03 Plaster (internal), walls mesh 1 HELPER 1.8 100 SM
MPL 04 Plaster (internal), walls hacking 1 HELPER 1 100 SM
MPL 05 Plaster (internal), walls guide point 1 MASON, 1 HELPER 1.2 100 SM
MPL 06 Plaster (internal), walls corner beads 1 MASON, 1 HELPER 10 SM 100 SM
MPL 07 Plaster (external), walls with grooves 1 MASON, 1 HELPER 10 SM 10 SM
MPL 08 Plaster (external), walls without grooves 1 MASON, 1 HELPER 1,2 12 SM
MPL 09 Plaster (external), walls rush coat 2 HELPER 15 SM 150 SM
MPL 10 Plaster (external), walls mesh 1 HELPER 10 SM 100 SM
MPL 11 Plaster (external), walls hacking 1 HELPER 10 SM 100 SM
MPL 12 Plaster (external), walls guide points 1 MASON, 1 HELPER 10 SM 100 SM
MPL 13 Plaster (external), walls corner beads 1 MASON, 1 HELPER 10 SM 100 SM
MPL 14 Plastering of Arches/Mullians 1 MASON, 1 HELPER 0.8 80
MPL 15 Floor screed 50mm thick 1 MASON, 1 HELPER 2 20
MPL 16 Roof screed 100 mm thick 1 MASON, 1 HELPER 1.5 15
MPL 17 Mosiac floor Tiles fixing 1 MASON, 1 HELPER 1.6 1.5
MPL 18 Floor Screed 25mm thick 1 Mason + 1 Helper 0,6 6
MCR CERAMIC WORKS
MCR 01 Ceramic tiles to walls by mortar 1 MASON, 1 HELPER 1.2 8 SM
MCR 02 Ceramic tiles to walls, mortar to corridors 1 MASON, 1 HELPER 1 9 SM
MCR 03 Ceramic tiles to walls, cut pieces 1 MASON 2 20 SM
MCR 04 Ceramic tiles to walls grouting 1 HELPER 5 50 SM
MCR 05 Ceramic tiles to walls, by glue 1 MASON, 1 HELPER 1,2 12 SM
MCR 06 Ceramic tiles to walls, corridors, by glue 1 MASON, 1 HELPER 1,3 13 SM
MCR 07 Ceramic tiles to walls, by glue, cut pieces 1 MASON 2 20 SM
MCR 08 Ceramic tiles to walls, by glue, grouting 1HELPER 5 50 SM
MCR 09 Ceramic tiles to floors 1 MASON, 1 HELPER 1 10 SM
MCR 10 Ceramic tiles to floors in halls 1 MASON, 1 HELPER 1,2 12 SM
MCR 11 Ceramic tiles to floors, cut pieces 1 MASON 2 20 SM
MCR 12 Ceramic tiles to floors, grouting 1 HELPER 5 50 SM
MCR 13 Marble flooring 1 MASON + 1 HELPER 0.60 60
Item No. CREW SIZE HourIy Production
Production Rate Per 10 hrs.
Per Unit
MCR 11 Ceramic tiles to floors, cut pieces 1 MASON 2 20 SM
MCR 12 Ceramic tiles to floors, grouting 1 HELPER 5 50 SM
MCR 13 Marble flooring 1 MASON + 1 HELPER 0.60 60
(Rev 0, May 2000)
PRODUCTIVITY RATES FOR ALL PROJECT WORKS:
PRODUCTIVITY RATES FOR ALL PROJECT WORKS:
(Rev 0, May 2000)
Page 3 of 7

Item No. CREW SIZE HourIy Production
Production Rate Per 10 hrs.
Per Unit
MCR CERAMIC WORKS
MCR 13 Ceramic skirting by glue 1 MASON, 1 HELPER 2,5 M 25 METRE
MCR 14 Ceramic skirting by glue to halls, corridors 1 MASON, 1 HELPER 3 M 30 METRE
MTW TILING WORKS
MTW 01 Mosiac / Terrazo tiles to roofs 1 MASON, 1 HELPER 1,6 16 SM
MTW 02 Mosiac / Terrazo tiles to floors 1 MASON, 1 HELPER 1,4 14 SM
MTW 03 Mosiac skirting to halls 1 MASON, 1 HELPER 2,5 25 METRE
MTW 04 Mosiac skirting flush / recessed 1 MASON, 1 HELPER 1,4 14 METRE
MTW 05 Grouting / sealing to roof / floor tiles 1 HELPER 2,5 25 METRE
MKP KERBING / BLOCK PAVING WORKS
MKP00 P.C.C. Curve kerb base (to curves) 1 MASON, 1 HELPER 2,5 25 METRE
MKP01 PCC to kerb base (Straight line) 1 MASON, 1 HELPER 3,0 30 METRE
MKP02 Haunching to kerb base (Dumpes) 1 MASON, 1 HELPER 4 40 METRE
MKP03 kerbstonse (Without PCC) 1 MASON, 1 HELPER 1,5 15 METRE
MKP04 nterlock paving on pre prepared sub - base 1 MASON, 1 HELPER 2 SM
MKP05 Screed works including preparation 1 MASON, 1 HELPER 1,5 15 SM
MKP06 Haunching ot Kerb Base (Mixing Truck) 1 MASON, 1 HELPER 10 M 100M
DRW MANHOLE/ DRAINAGE CONSTRUCTION
DRW 01 Excavation for drains / manholes 1 HELPER 5 CM
DRW 02 Backfill to drains / manholes 1 HELPER 10 CM
DRW 03 Blockwork to manholes 1 MASON, 1 HELPER 2 NOS
DRW 04 Plaster to manholes 1 MASON, 1 HELPER 2 NOS
DRW 05 Benching to manholes 1 MASON, 1 HELPER 4 NOS
DRW 06 Fix covers to manholes 1 MASON, 1 HELPER 2 NOS
DRW 07 Fix gulley traps 1 MASON, 1 HELPER 1 NO
DRW 08 Laying of P.V.C. sleeves 4" - 12" 4 HELPER 24M 240M
MLW MISCELLANEOUS LABOUR WORKS
MLW01 Bitumen paint to concrete blockwork surfaces 1 HELPER 4 40 SM
MLW02 Bitumin painting Bases / piles 1 HELPER 7.00 70
MLW03 Hacking of concrete surfaces 1 HELPER 5 50 SM
MLW04 fixing of flexcell sheets 1 HELPER 6 SM
MLW05 pile cutting/dressing 1 HELPER 1 NO
MLW06 pile cutting/dressing (small diameter) 1 HELPER 2 NOS
MLW07 Vertical sealant (12 mm) 1 HELPER 2,5 25 METRE
MLW08 Horizontal sealant (12 mm) 1 HELPER 5 50 EMTRE
MLW09 Roof preparation for lw concrete 1 MASON, 1 HELPER 5 50 SM
MLW10 Angle fillet fixing 1 MASON, 1 HELPER 4 40 EMTE
MLW11 Hourdi block shifting and fixing to slab 2 HELPER 20 200 NOS
MLW12 Polythene sheet fixing 1 HELPER 3m 30
MLW13 Shaping of Soil Blinding 1 MASON + 1 HELPER 1 M 10M
MLW14 Protection Board installation 1 CARPENTER + 1 HELPER 8M2 80M
2
MCW MISCELLANEOUS CARPENTARY WORKS
MCW 01 A/C subframe manufacture / fixing 1 CARPENTER 5 NOS
MCW 02 Door subframe manufacture / fixing 1 CARPENTER 4 NOS
MCW 03 Water bar fixing 1 CARPENTER 2 M 20 METRE
Page 4 0f 7
PRODUCTIVITY RATES FOR ALL PROJECT WORKS:
(Rev 0, May 2000)
Item No. CREW SIZE HourIy Production
Production Rate Per 10 hrs.
Per Unit
CPW CONCRETE PLACEMENT WORKS
CPW01 Concrete to pile caps by pump 6 MASONS, 18 HELPERS, 1 CARPENTER 180 CM
Standard rate 1 man 1 hr. 10m3
CPW02 Concrete to PCC blinding (100 mm thick) 1 MASON, 10 HELPERS 27 CM
CPW03 Concrete to slabs/beams, by pump 6 MASONS, 18 HELPERS, 1 CARPENTER 180 CM
CPW04 Concrete to slabs / beams by crane 1 MASON, 6 HELPERS, 0.5 OPERATOR 8,10 27 CM
CPW05 Concrete to walls / columns, by pump 4 MASONS, 16 HELPERS, 2 CARPENTERS 1.2 81 CM
CPW06 Concrete by site mix 1 MASON, 12 HELPERS , 0.5 CARPENTER 1.6 9 CM
CPW07 Concrete Columns 8 HELPERS 1.40 10
CPW08 Concrete suspended slab (pump) 3 MASONS + 6 HELPERS 1.80 150
CPW09 Concrete parapets/staircases 8 HELPERS 1.00 7
CPW10 Blinding concrete 50 mm (readymix) 1 MASON + 4 HELPER 8,0 80
CPW11 Blinding concrete 50 mm (sitemix) 1 MASON + 8 HELPER 1.00 10
CPW12 Concrete footings & pile caps 1 MASON + 4 HELPER 12.00 120
CPW13 Concrete tiebeams, ground beams 1 MASON + 5 HELPER 6.00 60
CPW14 Concrete column necks 8 HELPER 1.50 15
CPW15 Concrete Ground slab 3 MASONS + 6 HELPER 1,5 15
CPW16 Concrete to precast slabs, beams 2 MASONS + 1 HELPER 3m3 30 M
3
GLW GENERAL LABOUR WORKS
GLW01 Unloading reinforcement ((Flat Bed Truck) 4 HELPERS 2 Nos
GLW02 Loading reinforcement to slab (With Crane) 4 HELPERS (Flat Bed Truck loads) 40 Nos. 2 Nos
GLW03 Loading blockwork to site (with Wheel Burrow) 1 HELPER 400 Nos.
GLW04 Loading mortar to site location
GLW05 Mixing mortar for distribution 0, 3 L mixer 4 HELPER 6M3
GLW06 Site mixing of ready mix for distribution Hand mix 3M3
GLW07 Loading ready mix to site location
NTRA NON TARGET RELATED ACTIVITES
NTRA01 Stacking of formwork 2 HELPERS
NTRA02 Curing of Substructure works 2 HELPERS
NTRA03 Curing of beams / slabs Hessiant Water 2 HELPERS
NTRA04 Curing of columns (Hessiant Water) 1 MASON + 2 HELPERS 1.6 (L.M) 36 M
NTRA05 Builders work make good chases 1.2 (L.M)
NTRA06 Site cleaning 1 HELPER 25 250 M
2
NTRA07 Repairs to finished works 1
Page 5 of 7
PRODUCTIVITY RATES FOR ALL PROJECT WORKS:
(Rev 0, May 2000)
Item No. CREW SIZE
NTRA08 Maintenance of site services 2 HELPERS
NTRA09 Operators for mixers 2/MXER
NTRA10 Operators for compaction equipment 1 UNT
NTRA11 Office boy ARABTEC 1 / CONSULTANT 1
NTRA12 Watchman 2 MN
NTRA13 Storekeeper 1/SHFT
Page 6 of 7
NON MEASURABLE
PRODUCTIVITY RATES FOR ALL PROJECT WORKS:
(Rev 0, May 2000)
Item No. CREW SIZE HourIy
Production Rate
RF REINFORCEMENT
RF 01 Fix Rebar to footings & tie beams 1 STEEL FXER 25
RF 02 Fix Rebar to walls, columns, beams, solid slabs 1 STEEL FXER 20
RF 03 Fix rebar to ribs of hourdi slab 1 STEEL FXER 18
RF 04 Fix rebar to mesh reinforcement 1 STEEL FXER 15
RF 05 Fix rebar to hidden beams 1 STEEL FXER 20
RF 01 Fix Rebar to footings & tie beams 1 STEEL FXER 78
RF 02 Fix Rebar to walls, columns, beams, solid slabs 1 STEEL FXER 38
RF 03 Fix rebar to ribs of hourdi slab 1 STEEL FXER 35
RF 04 Fix rebar to mesh reinforcement 1 STEEL FXER 15
RF 05 Fix rebar to hidden beams 1 STEEL FXER
RFC 01 Steel cutting and bending 18.25 mm 1 STEEL FXER 50.00
RFC 02 Steel cutting and bending 8 - 16 mm 1 STEEL FXER 40.00
EXCAVATION
EX 1 Manual Excavation 1 HELPER
EX 2 Backfill + levelling 1HELPER
EX 3 Shaping of sloped earth for blinding for bases including compaction 1 MASON + 2 HELPER
PRODUCTIVITY RATES FOR ALL PROJECT WORKS:
(Rev 0, May 2000)
Productivity Rates for TiIIing
Size. (Cms) Location Area Manpower Production Rate Remarks
(Sqm. Per day)
30 X 30 Floor Kitchen 1 Mason, 1 Helper 14 Residential Area by Sub-Contractor
30 X 30 Floor with pattern Corridor 1 Helper, 2 Masons 10 Residential Area by Sub-Contractor
40 X 40 Floor Bed room 1 Mason, 1 Helper 22-25 Residential Area by Sub-Contractor
20 X 20 Floor Store (small area) 1 Mason, 1 Helper 10 Residential Area by Sub-Contractor
30 X 60 Floor Bathroom 2 Mason, 1 Helper 6 Residential Area by Sub-Contractor
30 X 30 Floor + Wall Bathroom 2 Mason, 1 Helper 5
10 X 10 Wall Kitchen 1 Mason, 1 Helper 8-9 Residential Area by Sub-Contractor
30 X 60 Wall Corridor 1 Mason, 1 Helper 14-15 Residential Area by Sub-Contractor
30 X 30 Wall Bathroom 2 Mason, 1 Helper 7 Residential Area by Sub-Contractor
Residential Area by Sub-Contractor
Notes:
1. 1 Day = 10 hrs.
2. Gang Size:
1 Mason + 1 Helper for Kitchen and Bedroom.
2 Mason + 1 Helper for Bathroom.
(Rev 0, May 2000)
PRODUCTIVITY RATES