ORIYX Scheulde

Oriyx GTL Project, Raslaffan Activity ID Activity Name Original Duration 1800 344 Site Survey Designing AFC Drawing 56 56 168 512 MAT Submittal for Approval PO Place Material Received 168 24 240 184 Fitting and Welding Support fabrication NDT and PWHT Hydrotesting Painting 56 32 64 8 24 160 Scafolding Erection Pipe Installation Support Installation Pipe Insulation Punch list 56 8 8 56 16 24 Final Walk through and Plant Startup Punch List 16 8 5

Uploaded by

Kool Punjabi
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
50 views

ORIYX Scheulde

Oriyx GTL Project, Raslaffan Activity ID Activity Name Original Duration 1800 344 Site Survey Designing AFC Drawing 56 56 168 512 MAT Submittal for Approval PO Place Material Received 168 24 240 184 Fitting and Welding Support fabrication NDT and PWHT Hydrotesting Painting 56 32 64 8 24 160 Scafolding Erection Pipe Installation Support Installation Pipe Insulation Punch list 56 8 8 56 16 24 Final Walk through and Plant Startup Punch List 16 8 5

Uploaded by

Kool Punjabi
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Oriyx GTL Project, Raslaffan IMCO DUKHAN 19-Apr-11 14:46

Activity ID Activity Name Original Planned Start Planned FinishM M M M A A A A M M M M M J J J J J J J J J A A A A S S S S O O O O O N N NN


Duration

Oriyx GTL Project, Raslaffan 1800 13-Mar-11 30-Nov-11

Engineering 344 13-Mar-11 28-Apr-11 28-Apr-11, Engineering


A1000 Site Survey 56 13-Mar-11 21-Mar-11 Site Survey
A1010 Designing 56 22-Mar-11 30-Mar-11 Designing
A1020 AFC Drawing 168 31-Mar-11 28-Apr-11 AFC Drawing
Procurement 512 01-May-11 13-Jul-11 13-Jul-11, Procurement
A1030 MAT Submittal for Approval 168 01-May-11 29-May-11 MAT Submittal for Approval
A1040 PO Place 24 30-May-11 01-Jun-11 PO Place
A1050 Material Received 240 02-Jun-11 13-Jul-11 Material Received
Fabrication 184 14-Jul-11 09-Aug-11 09-Aug-11, Fabrication
A1060 Fitting & Welding 56 14-Jul-11 24-Jul-11 Fitting & Welding
A1070 Support fabrication 32 14-Jul-11 19-Jul-11 Support fabrication
A1090 NDT & PWHT 64 25-Jul-11 03-Aug-11 NDT & PWHT
A1110 Hydrotesting 8 04-Aug-11 04-Aug-11 Hydrotesting
A1120 Painting 24 07-Aug-11 09-Aug-11 Painting
Installation 160 10-Aug-11 04-Sep-11 04-Sep-11, Installation
A1130 Scafolding Erection 56 10-Aug-11 18-Aug-11 Scafolding Erection
A1140 Pipe Installation 8 21-Aug-11 21-Aug-11 Pipe Installation
A1150 Support Installation 8 22-Aug-11 22-Aug-11 Support Installation
A1160 Pipe Insulation 56 23-Aug-11 31-Aug-11 Pipe Insulation
A1170 Punch list 16 01-Sep-11 04-Sep-11 Punch list
Commisioning 24 05-Sep-11 07-Sep-11 07-Sep-11, Commisioning
A1180 Final Walk through & Plant Startup 16 05-Sep-11 06-Sep-11 Final Walk through & Plant Startup
A1190 Punch List 8 07-Sep-11 07-Sep-11 Punch List
Documents Work 568 08-Sep-11 30-Nov-11
A1200 Submission of Project Dossier 480 08-Sep-11 30-Nov-11

Actual Work Critical Remaining Work Summary Page 1 of 1 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.