Standard Planning Procedure
Standard Planning Procedure
1.0 PURPOSE
2.0 SCOPE
3.0 DEFINITIONS
4.0 PROCEDURE
6.0 ATTACHMENTS/APPENDICES
The purpose of this procedure is to define the requirements for the planning and scheduling
activity on projects. The objective is to develop plans and schedules and then to monitor,
analyse, report and forecast performance in such a manner that projects are delivered on or
ahead of schedule. This objective will be achieved if:
• Planners/schedulers fully understand the scope of the project and are pro-active both in
interpreting the Clients requirements and producing project schedules.
• The project team effectively ‘buys-in’ and owns the project schedule.
• The schedule is pro-actively analysed & reviewed to identify any potential restraints
to progress. Any restraints identified being reviewed with all appropriate project team
members, including the Project Manager.
• Any Specific project requirements should be identified and included in the Project
Quality Plan
• The objectives of the Global / Regional / Industry / Quality Systems are met
2.0 SCOPE
This procedure is applicable to all planning and scheduling activities from project kick-off to
project closure. These activities include schedule generation and subsequent maintenance,
progress measurement and reporting and resource planning. This will necessitate the
incorporation of information provided by sub-contractors, vendors and construction
contractors.
3.0 DEFINITIONS
Planning The breakdown of work into its component events, and the
sequencing, resourcing and strategy of those events.
Critical Path Network (CPN) A representation of activities and/or events with their inter-
relationships and dependencies.
Precedence Network A network diagram in which the nodes symbolise the project
activities.
Performance Measurement The original project quality, HSE, budget & contract duration
Baselines objectives set by Management at Commencement.
Change Process The formal system by which key parameters of cost, scope
and schedule are changed
4.0 METHOD
Every project shall have a plan and/or a schedule which will be prepared by the Project
Planner/Scheduler in co-ordination with the Project Manager, Construction Manager,
Contracts Administrator and Discipline Leads. For minor projects, engineering studies, etc.
the Project Manager may elect to prepare the schedule. Milestone schedules shall be
sufficient for small projects.
Plans and schedules will be updated and issued at a minimum of monthly intervals and more
frequently if deemed necessary by the Client or the Project Manager.
Critical activities must be identified. Detailed schedules should be developed on a rolling wave
principle.
All planning deliverables will contain a signature block and be approved for project use by the
Project Planner/Scheduler, Discipline Leads, Construction Manager, Project Controls
Manager, Project Manager, and by the Client (where appropriate).
It is the responsibility of the Project Planner/Scheduler to make the project team aware of the
key milestones. The Project Planner/Scheduler must inform the Project Manager of all
scheduling problems or potential problems. It is the Project Manager’s responsibility to hold
the project team accountable for making the necessary recoveries and meeting all further
milestones, thus ensuring successful project completion.
The Project Planner/Scheduler shall utilise the recent project experience of other planners &
departments as well as the cost & schedule department databases for planning norms.
The Company maintains a number of schedule & resource templates which can be utilised for
projects. Specific Company layout, resource and activity coding is set out within these
templates and the P5 User Manual.
The project shall be structured to enable the collection of progress and work-hour expenditure
such that roll up from detailed levels to higher summary levels is possible.
The Planner/Scheduler is responsible for ensuring that the various progress measurements
used throughout the project are a fair representation of the actual project progress. As a
minimum, the following should be provided:
The Planner/Scheduler is also responsible for providing information to assist with the
management of resources required to execute the work. These tasks include, but are not
limited to:
• At the earliest possible stage, using the best available data, by assessing the
Scope of Services and material quantities to provide management with an
overall resource overview of the project.
• From the project approved budgets assess the quantities of major resources required,
issue discipline resource manpower requirement to Project Manager and Lead Discipline
Engineers and determine if the supply may be a limiting factor.
• Provide and update forecasts of discipline manpower requirement and other facilities
• Seek and obtain details of Client schedule requirements (e.g. shutdown windows) and
incorporate into the master schedule.
• Establish an IT environment in which schedule data can be shared & efficiently managed
between parties
• Review the Purchase Order and Sub Contract Planning & Scheduling detailed
requirements or co-ordination procedures
• Issue the necessary schedules to the Vendors and Sub-contractors showing the required
key start and finish dates. Critical and interface activities must be highlighted.
• Review these schedules with the project team to enable subsequent review and
agreement with the Vendor/Sub-contractor. When accepted by the Vendor/Sub-
contractor, incorporate into the master schedule.
• Ensure that reported progress meets the requirements of the project and that sufficient
time is given to analysing the data to highlight variances and propose corrective actions
as necessary.
At various stages in each project, interactive planning sessions may be held with the Client
and the Project team (including, where relevant, sub-contractors, vendors and construction
contractors) with the intention of obtaining buy-in to the agreed schedule by all parties. This
is designed to facilitate the production of an integrated project schedule which highlights the
key constraints and major issues which impact successful execution. Alignment with key
execution strategies is essential. The main tool is a time phased wall mounted bar chart
which should be readily accessible to all parties involved in the project and can form the basis
of the detailed schedules as well as recording key risks, assumptions and opportunities.
The Planner/Scheduler must produce documents that help co-ordinate, inform and optimise
the schedule of a project. This can only be achieved if such documents are well thought out,
agreed with the Project Manager and Discipline Leads and issued in a timely fashion.
Each project should be examined and, along with the Project Manager, a determination made
as to which types of schedules will be appropriate. The schedules to be utilised shall be
stated in the Project Procedures.
Upon receipt of instructions to proceed with the project, and prior to the first issue of the
agreed Project Schedule, the project will be controlled with advanced 30 day or 60 day
project initiation action list / Start Up Schedule to ensure that early activities are identified and
acted upon to protect the overall schedule.
The following types of schedules have been categorised for convenience, refer to
Attachment 6.1.
4.7 LEVEL 1 - MAJOR MILESTONE SCHEDULES
Typical Applications Proposals, at the planning stages of a major project, small studies,
engineering projects with a low level of complexity, few activities and
short duration, as a monthly summary of Level II and III schedules.
Timing/Frequency Updated and issued monthly within five working days of the close-out
date.
Typical Applications Major proposals and studies, engineering projects with a medium
level of complexity, small construction projects, contract payment
milestones.
Progress ‘S’ Curve for each phase will indicate schedule % complete
and actual % complete.
Layout/Format Schedule will be a bar chart or logic network with critical path
identified, refer to Attachment 6.3.
Timing/Frequency Updated and issued at least monthly, within five working days of the
close-out date.
Typical Applications On all complex engineering-only projects and all EPC projects. Also
on smaller projects where elements of the schedule are extremely
critical and, hence, need to be managed at this level.
Typical Analysis Typically at this level the schedule should be analysed for the top 5
critical paths and the current critical activities highlighted to the team.
The logic and durations within these critical paths should be
continually addressed to ensure schedule robustness.
Forecast man hours / productivity to go and resourcing levels should
be analysed for consistency
Trend analysis on key parameters e.g. Material deliveries to site,
pipe work productivity, schedule float usage etc
Typical Application On any project that has special scheduling needs defined by the
Project Controls Manager in the Project Procedures. Every
construction project that involves direct control of the labour.
Layout/Format As per the project needs. Two week look-ahead’s for field activities.
Display summary information on project notice boards
Timing/Frequency As required. Two week look-ahead’s are rolling every week and
issued at least two working days before the first week and should be
reviewed at the progress meeting as to their viability.
The project detailed schedule is a quality record. Baseline data, schedule updates, key
changes to scope and methodology should all be recorded and kept within the filing and
document record system for subsequent contract requirements, post project close out &
reporting. The Project Close Out procedure requires an analysis of the key project
parameters for subsequent use on further projects and cost & schedule database upkeep of
metrics & benchmark data.
6.0 ATTACHMENTS
1) BARCHART/SCHEDULE OF MILESTONES
LEVEL II
SUB- COMMISSIONING
ENGINEERING PROJECT DISCIPLINES
MANAGEMENT CONSTRUCTION CONTRACTORS/ 1) NETWORK/BARCHART DETAILING
DISCIPLINE MECH/ELECT WORK PACKAGES
PROJECT MANAGEMENT VENDORS
PROCESS/ ETC 2) 'S' CURVE-INDIVIDUAL DISCIPLINE
PIPING, ETC SERVICES CURVES
PROCUREMENT 3) MANPOWER HISTOGRAMS-DISCIPLINE
MANNING REQUIRMENTS
ETC 4) SUMMARY WBS REPORT EXPENDED/
ACHIEVED/FORECAST/PRODUCTIVITY/ETC.
LEVEL IV