The document outlines the production schedule for a project, beginning with development and research from September to October 2010, including brainstorming genres, audience research, and testing a practice trailer. Pre-production is scheduled from November to mid-December 2010, involving writing drafts of the synopsis and script, selecting locations and cast, and creating storyboards and shot lists. Principal photography is scheduled from mid-December 2010 to early January 2011. Post-production includes capturing footage, film editing from mid-January to late January, and ancillary tasks through early February. Distribution includes uploading the trailer and soundtrack to online platforms in early February and evaluating the project from February 6th to 18th.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
36 views
Production Log
The document outlines the production schedule for a project, beginning with development and research from September to October 2010, including brainstorming genres, audience research, and testing a practice trailer. Pre-production is scheduled from November to mid-December 2010, involving writing drafts of the synopsis and script, selecting locations and cast, and creating storyboards and shot lists. Principal photography is scheduled from mid-December 2010 to early January 2011. Post-production includes capturing footage, film editing from mid-January to late January, and ancillary tasks through early February. Distribution includes uploading the trailer and soundtrack to online platforms in early February and evaluating the project from February 6th to 18th.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2
Production schedule
Development/ research
Brainstorm genres - 16 September 2010
Research movie trailers - 16-17th September 2010 Research my genre trailers – 21st -22nd September 2010 Audience research - 30th September 2010 Pre audience questionnaire – 1-5th October 2010 Pre practice trailer/ audience testing 7-13 th October 2010 Audience feedback of practice trailer 17 th October 2010 End of extended research – 20th October 2010 Research into target audience socio economic group/bbfc – 30 th October 2010 Treatment/more research into target audience 2 nd November 2010
Pre production
Synopsis 1st draft - 7th November 2010
Synopsis 2nd draft – 12th November 2010 Script – 18th November - 2010 Location notes and pictures - 23rd November 2010 Cast notes and pictures - 25th November 2010 Storyboard - 28th November 2010 Storyboard 2nd draft - 2nd December 2010 Score notes - 7th December 2010 Cutaways – 10th December 2010 Shot list – 11th December 2010 Call sheets 13th December 2010
Production
Creation of production logo – 14rd December 2010
Filming- oakspark high school lift - 17th December Filming -oakspark high school lift - 19th December Filming- Piccadilly circus – 28th December Filming –Leyton – 1st January Filming Leyton – 2nd January Filming Gansthill – 2nd January Extra filming time 4th January Extra filming time 5th January
Post production
Actor release forms – 7th January
Location release forms – 7th January Capture footage onto Mac 8th January Film editing – 10th – 24rd January Start ancillary tasks 26th January – 4th February
Distribution
Upload trailer onto video to YouTube - 5 th February
Upload soundtrack to sound cloud - 5th February Evaluation 6th - 18th February