Transmission Line Supports.
Transmission Line Supports.
PART A :
I) POLE SUPPORTS :
Under this category following supports are included.
1. Wooden Poles
2. Reinforced concrete Poles ( PSC poles)
3. Tubular poles
4. Latticed poles
5. Girders
6. Rails
7. Wide based tubular hollow PSC Poles
1. WOODEN POLES :
These are poles ranging from 100mm to 200mm in diameter. In
Gujarat they are very rarely used except in the places where there is too
much of oceanic pollution & steel support are not able to stand. But, they
are widely used in places where forest is very wide & wood is available at
very cheaper rate for example Jammu & Kashmir, Himachal Pardesh,
Karnataka, Kerala, etc. The main drawback of these poles is their
uncertain life, the tendency to get eroded from within the soil.
3. TUBULAR POLES :
These can be used for voltage up to 33 KV but they are not being
used in GEB for the simple reason of high cost of fabrication & transport.
4. LATTICED POLES
These are single, tapered poles fabricated from angles which in use
in the pre independence era. Now they are not used. They can be used in
33 KV transmission lines.
5 & 6. GIRDERS & RAILS
Girders at size 150 x 150 mm & rails of 90 pounds can be used for
the transmission of 66 KV by making H frame. The tower size of girders
& rails can be utilized for the transmission line of the 33 KV & 22 KV.
II DESIGN ASPECTS:
Out of the single poles structures described above, the tubular hollow PSC
poles can withstand transverse, longitudinal, vertical stresses whereas other type
of single poles can withstand only vertical load and transverse load (to some
extent only) and as such for these type of poles wind guys have to be provided on
every 5th/ 6th locations. Also at the angle points and cut points where the tension
and deviation loads are coming, special guys are required to be provided.
D1 = ( W x 12/27),
D2=(W x 22/27)
where, x1 = (1/2)+(Th/W1)
x2 = (1/2) (Th/w1)
θ
stay
pole in lb.
θ= Angle between stay and pole in degree.
S= Tension in stay in lb.
Tension in stays S= P/Sinθ ib.
Vertical load on support = S cosθ lb.
(c) CIRPPLING LOAD ON STRUTS:
In determining the crippling load of struts.
Following formula used.
Where
P = Buckling of failing load in 1b.
L = Length of strut in inches.
I = Moment of intertia of cross section about the neutral axis.
a) Centre of gravity of the conductor loading is in the region of 2 ft. from the
pole top. This is normally the stay position.
b) In case of foundation strengths, the fulcrum point of the pole is taken as
approximately 2/3 of the depth of planting.
C = π² E 2 X π D4 Lb.
(Lx12) 64
H
h
It should be noted that the windage is taken 1.5 time the windage on one leg.
Section module = I
Dg/2 in3 .
Substituting value of I.
Z = π D4 x 2 = πDg³ in³
64 Dg. 32
= BMX12X32 lb/sq.in.
Dg3
X bracing is generally used because it may be assumed that the two poles will defect
identically and that half the total loads will be carried by each pole.
The wind load on conductor is F, which is carried as F/2 on each pole at the
appropriate level.
The wind on two poles (due to the sheltering effect) can be taken as 1.5% mean
diameter x height ; and this is allocated to the various “ pane points.”
1 Level of conductors.
2 Top of brace.
3 Bottom of brace.
4 Ground level.
This gives the forces.
P/2
Q/2
B
R/2
x
x
PART ‘B’ :
(1) INTRODUCTORY :
The aim of this Lecture is to introduce engineers to the transmission line
tower, salient features of design, with a particular reference to loading.
Towers in general means a multi storied skeletal structure. The material to be used in
construction depends upon the use to which they are put. Usually towers are made out of
timber, cement, concrete, steel and aluminium.
(a) Timber:
Temporary purpose when the tower to be erected, timber is the best
material. The durability of timber is largely affected by many natural factors and hence
usage of timber as construction material is out dated.
(b) Concrete :
Comparatively durable cost of construction is less.
Disadvantages :
(c) Steel :
Looking to the disadvantages of concrete steel can be used as the
tower construction material. It can be erected as high as upto 200metres
with comparative others. The member can be assembled at site and has
less dead weight which facilitate the erection.
The transmission towers are used to support power lines of 66KV and
above.
Towers are used to reduce the number of locations from maintenance
point of view (longer span) to get proper ground clearance & to have strong
support to withstand wind load etc.
The tower is a balanced structure with four legs. The spans of 250 meter
and above can be adopted for tower line. Towers are generally fabricated from
galvanized steel sections to avoid shutdown for painting & maintenance and for
costal area. They are pre-fabricated in the workshop & subsequently assembled &
erected at site. Hence, degree of accuracy in design & fabrication should be very
high. Entire structure is bolted (no welding or riveting is allowed).
(10) LOADING :
Load on towers are worked out with two conditions.
a) Normal condition.
b) Broken wire condition.
Where,
D = diameter of insulator disc.
n = No. of insulators.
h = height of one insulator.
P = wind pressure.
c) load due to wind pressure on tower frame is calculated by taking the area
of the fabrication material (angles) facing the wind and multiplying it by
wind pressure.
d) Deviation load :
The tower is erected in such a way that it bisects the angle of line
deviation say (D) if the conductor or ground wire tension is T, the
deviation load due to horizontal component shall be 2T sin θ/2.
10.2.2 VERTICAL LOAD :
The frame of the tower faces wind pressure ‘p’. The total force is worked
out by taking the area of windward face of each & every angle member. For
rough estimate 15 % to 20 % of the projected area (known as shadow area) is
considered at designing stage and figures are checked with actual ones after
the designing is over.
The wind force on tower frame at various parts of tower is generally added
to the transverse loads of conductors or groundwire.
In case of special towers having height above 40 meters, the wind forces
are resolved sectionswise.
LONGITUDINAL LOAD:
When a wire is broken the tension ‘T’ of the wire tries to pull the tower on
the other side and hence the structure has to offer a balancing force equivalent
to T x Cos (θ/2) here θ is the line deviation angle.
In case of suspension towers, however, the tension under broken wire is
taken on as 50 % of normal tension ‘T’.
b) Bending Stresses :
A member subjected to bending should return to it’s original condition
after a load equal to 2.5 time the maximum working load has been applied.
c) Shear stress:
Shear stresses on gross area of bolts should not exceed 2220 kg/cm² under
maximum condition.
or
5550 kg/cm² when factor of safety of 2.5 is applied.
d) Bearing Stress:
Bearing stress on the gross diameter of bolts should not exceed twice the
shear stress i.e. 2220 x 2 = 4440 Kg/cm².
e) Compressive Stress :
Ultimate compressive stress is depend upon it’s slenderness ratio i.e.
(L/r) Where
L = Length (unsupported).
r = Radius of gyration.
The tower height must be such that the clearance between the
lowest conductor and the Ground level in still airmeets the requirements of
IS.
The lines will operate in a such a way that the clearance must be
allowed between live metal & tower steel work.
The special attention is given to jumpers at section positions, as
allowance must be made for the swing of the conductor due to wind.
Swing of the Suspension = Wind span
Insulator weight span
b) MECHANICAL STRENGTH :
The mechanical design of supports must be such that under adverse
conditions of wind load i.e. or under conditions of conductor tension, or line
deviation, the support clearance should not be reduced.
11) SPECIFICATIONS :
Basic Data for preparing specification is derived from IS : 802 (PART –
I) 1973. However, keeping in view the importance and locations of various
transmission lines are made, generally to increase the safety and to reduce the
cost.
12) BASIC TECHNICAL PARTICULARS :
a1) Wind Pressure i) For conductor – 75 kg/m² acting and ground wire on full
and groundwire projected area.
ii) For tower - 150 Kg/ m² acting on 1.5 times the
projected area of wind ward face.
Clearances :
i) Minimum ground clearance : 6000mm
ii) Clearance of suspension : 915mm
string deflection upto 20º
iii) Clearance of Suspension : 800mm
string deflected upto 35º
iv) Clearance of jumper : 915mm
deflected upto 20º
v) Clearance of jumper deflected : 800mm
upto 30º
Factor of Safety
14) DESIGN
Refer sketch ‘A’. If, we want to design the leg member marked ‘j’, we have to
take the moment’s of all the transverse load on the towers at the centre of lattice
connecting these sections which is 4.287 meters in width.
Section proposed 90 x 90 x 8
This is less than 120 hence ultimate compressive strength can be worked out from
= 30228 kg.
Ultimate tensile strength = 2600 x 11 = 28600 kg.
N.C B.W.C
Compression 30228 = 2.14 30228 = 1.7
14123 17777
It is seen that F.S is more than required i.e. 2 in N.C. and 1.5 in B.W.C.
Hence, the section is safe.
For example in case of lattice a (Ref. sketch ‘A’) the total force due to ground
wire shall be resisted by members of the lattice.
c Ac = √ ab² + bc²
= √ 0.5² + .65²
650 = 0.820
820
cosά = 500 = 0.6097
α 820
N.C B.W.C
DESIGN :
1) Lower Member: N.C B.W.C
Transverse stress 1240x1.868 = 643 707 x1.860 = 367
2x1.8 2x1.8
Stress Longitudinal _____ 1531x1.868 = 2059
2x0.5
Stress Vertical 644x1.868 = 925 597x1.868 = 858
2x0.5 2x0.5
_________ ________
Total 1568 4084
2) Upper Member:
Stress Vertical 644x1.977 = 979 597x1.977= 908
2x0.65 2x0.65
( 2300 – 1440 )
(wt. of concrete) – ( wt. of each) x {Total concrete volume (of pad, pyramid,
chimney)} = 700 kg.
Factor of Safety
N.C. B.W.C.
= 2.76 2.20
b) Uplift :
= 20.358 x 1440
= 29315 Kg.
= 30015 Kg.
Factor of Safety :
N.C. B.W.C.
= 2.45 1.92
1) Cohisive
2) Non Cohisive
This type of soil is having very high bearing capacity/ and hence the
foundation depth is restricted some times to 1.5 meters only against the
normal depth of 3 meters. Besides to take care of the uplift mass concrete
is adopted i.e., excavation concrete volumes are equal. In this case since
the foundation is shallow, the stub is required to be cut to suit the
foundation depth. Figure 8.8 give an idea of such foundation.
(4 to 8 times that of normal soil)
3) Wet Foundation :
This type of foundation is adopted whenever wet or submerged
locations are encountered or otherwise at the locations which are likely to be
submerged along River or along ponds and irrigation projects. In this type of
soil R.C.C. foundations are used and they are generally in the form of steps of
250 to 300mm. Needless to emphasis that foundations have to be self
supporting under worst condition to take care off all the moments of the tower
due to all types of loads.
In this method the load diagram draw separately for each type of load
under each condition.
Under the normal condition 3 separated load diagram for vertical load,
transverse load and wind load are required to be drawn.
Under this category, the vertical, transverse and longitudinal loads under
broken wire condition are indicated on load diagrams. The wind diagram
indicated in 20.3 above holds good for this condition.
The figure 20 indicates vertical loads on the tower and the reactions under
normal condition. Figure 20d indicate the transverse load on the tower left
conductor broken condition including the reactions.
20.6 Stress Diagram:
Corresponding to Figures 20b and 20d are the two stress diagram given in
figure 20b and 20d.
Once all the stress diagrams are drawn i.e., stress diagram for vertical,
transverse and longitudinal loads under normal condition and under broken
wire condition (i.e. ground wire broken) or each and individual member under
normal condition and broken wire condition are tabulated and totaled
separately and whichever combination makes highest stress for a particular
member are adopted.
It is needless to mention that stresses of member due to different stress
diagrams is nothing but the stress diagram corresponding to each member,
multiplied by scale of the stress diagram.
20.8 Once the total stress for a member is worked out the remaining design work
is carried out as indicated in 14.2 i.e., selecting angle section and No. of bolts that will
stand to the total stress.
22) CONCLUSION :