Project Plan Elearning Template

The document outlines a 61.5 day web-based training plan consisting of four phases: a design phase to storyboard the training, a development phase to create the graphical user interface and content, a review phase for alpha and beta testing, and an integration phase to upload and test the training in the learning management system. Key milestones include kickoff, approving the storyboard, approving the GUI, completing development, alpha review, revisions, beta review, finalizing the modules, and course completion sign-off. The project is scheduled to be completed on November 3rd, 2009.

Uploaded by

bhphilly
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
84 views

Project Plan Elearning Template

The document outlines a 61.5 day web-based training plan consisting of four phases: a design phase to storyboard the training, a development phase to create the graphical user interface and content, a review phase for alpha and beta testing, and an integration phase to upload and test the training in the learning management system. Key milestones include kickoff, approving the storyboard, approving the GUI, completing development, alpha review, revisions, beta review, finalizing the modules, and course completion sign-off. The project is scheduled to be completed on November 3rd, 2009.

Uploaded by

bhphilly
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Name Duration Start Finish Predecessors Resource Names 8

T
1 Web-based Training Plan 61.5 days Mon 8/10/09 Tue 11/3/09
2 Kick-off Meeting (discuss milestones and deliverables) 1 day Mon 8/10/09 Mon 8/10/09 Customer,Vendor
3 Design Phase (Storyboard) 10 days Tue 8/11/09 Mon 8/24/09
4 Design Storyboard 5 days Tue 8/11/09 Mon 8/17/09 2 Vendor
5 Review Storyboard 2 days Tue 8/18/09 Wed 8/19/09 4 Customer
6 Revise Storyboard 2 days Thu 8/20/09 Fri 8/21/09 5 Vendor
7 Approve Storyboard 1 day Mon 8/24/09 Mon 8/24/09 6 Customer
8 Development Phase 28 days Tue 8/25/09 Thu 10/1/09
9 Design Graphical User Interface (GUI) 2 days Tue 8/25/09 Wed 8/26/09 7 Vendor
10 Approve GUI 1 day Thu 8/27/09 Thu 8/27/09 9 Customer
11 Develop Presentation/Activity pages 20 days Fri 8/28/09 Thu 9/24/09 10 Vendor
12 Develop Assessments 5 days Fri 9/25/09 Thu 10/1/09 11 Vendor
13 Review Phase 21 days Fri 10/2/09 Fri 10/30/09
14 Alpha Review 5 days Fri 10/2/09 Thu 10/8/09 12 Customer
15 Revisions 10 days Fri 10/9/09 Thu 10/22/09 14 Vendor
16 Beta Review 2 days Fri 10/23/09 Mon 10/26/09 15 Customer
17 Revisions 3 days Tue 10/27/09 Thu 10/29/09 16 Vendor
18 Finalize Module(s) 1 day Fri 10/30/09 Fri 10/30/09 17 Customer
19 Integration Phase (LMS) 1.5 days Mon 11/2/09 Tue 11/3/09
20 Upload and Test in LMS 1 day Mon 11/2/09 Mon 11/2/09 18 Customer
21 Course Completion Sign-off 0.5 days Tue 11/3/09 Tue 11/3/09 20 Customer