Power System Analysis: Economic Dispatch
Power System Analysis: Economic Dispatch
Announcements
Read Chapter 12, concentrating on
sections 12.4 and 12.5.
Read Chapter 7.
Homework 12 is 6.59, 6.61, 12.19,
12.22, 12.24, 12.26, 12.28, 12.29,
7.1, 7.3, 7.4, 7.5, 7.6, 7.9, 7.12,
7.16; due Thursday, 12/3.
Economic Dispatch:
Formulation
The goal of economic dispatch is to determine
the generation dispatch that minimizes the
instantaneous operating cost, subject to the
constraint that total generation = total load +
losses
Minimize
CT @ Ci ( PGi )
i 1
Such that
m
PGi PD PLosses
i 1
Initially we'll
ignore generato
limits and the
losses
3
Unconstrained Minimization
This is a minimization problem with a single
equality constraint
For an unconstrained minimization a
necessary (but not sufficient) condition for a
minimum is the gradient of the function must
be zero,
The gradient generalizes
f (x) 0 the first derivative
for multi-variable problems:
f (x) f (x)
f (x)
f (x) @
,
,K ,
1
2
n
4
Economic Dispatch
Lagrangian
i 1
i 1
Ci ( PGi ) ( PD PGi )
(no losses)
PD PGi 0
i 1
$/h
$/h
500 PG1 PG 2 0
7
Economic Dispatch
Example, contd
We therefore need to solve three linear equations
20 0.02 PG1
0
15 0.06 PG 2
500 PG1 PG 2 0
0
1 P G1
0.02
20
0
0.06 1 P G 2 15
1 0
500
1
PG1
312.5 MW
P 187.5 MW
G 2
26.2 $/MWh
Lambda-Iteration Solution
Method
Discussion on previous page leads to lambdaiteration method:
this method requires a unique mapping from a value
of lambda (marginal cost) to each generators MW
output:
for any choice
PGi ( ).of lambda (common marginal cost),
the generators collectively produce a total MW
output,
the method then starts with values of lambda below
and above the optimal value (corresponding to too
little and too much total output), and then iteratively
brackets the optimal value.
11
Lambda-Iteration Algorithm
Pick L and H such that
m
L
P
(
Gi ) PD 0
i 1
H
P
(
Gi ) PD 0
i 1
H L Do
While
M ( H L ) / 2
If
M
H
M
P
(
0
Then
Gi
D
i 1
Else L M
End While
12
Lambda-Iteration: Graphical
View
13
Lambda-Iteration Example
Consider a three generator system with
IC1 ( PG1 ) 15 0.02 PG1
$/MWh
IC2 ( PG 2 ) 20 0.01PG 2
$/MWh
IC3 ( PG 3 ) 18 0.025PG 3
$/MWh
15
PG1 ( )
0.02
18
PG 3 ( )
0.025
20
PG 2 ( )
0.01
14
Lambda-Iteration Example,
contd
m
L
L
Pick so
PGi (
) 1000 0 and
i=1
m
H
P
(
Gi ) 1000 0
i=1
Try L 20 then
i 1
15 20 18
1000 670 MW
0.02
0.01 0.025
Try H 30 then
1230 MW
i 1
15
Lambda-Iteration Example,
contd
Pick convergence tolerance 0.05 $/MWh
M ( H L ) / 2 25
Then since
H
P
(25)
1000
280
we
set
25
Gi
i 1
Since 25 20 0.05
L
P
(22.5)
1000
195
we
set
22.5
Gi
i 1
16
Lambda-Iteration Example,
contd
Continue iterating until H L 0.05
*
18
Generator MW Limits
Generators have limits on the minimum
and maximum amount of power they can
produce
Typically the minimum limit is not zero.
Because of varying system economics
usually many generators in a system are
operated at their maximum MW limits:
Baseload generators are at their maximum
limits except during the off-peak.
19
Lambda-Iteration Limit
Example,contd
Again we continue iterating until the convergence
condition is satisfied.
With limits the final solution of , is 24.43 $/MWh
(compared to 23.53 $/MWh without limits).
Maximum limits will always cause to either increase
or remain the same.
Final solution is:
PG1 (24.43) 300 MW (at maximum limit)
PG 2 (24.43) 443 MW
PG 3 (24.43) 257 MW
22
23
Inclusion of Transmission
Losses
The losses on the transmission system are a
function of the generation dispatch.
In general, using generators closer to the
load results in lower losses
This impact on losses should be included
when doing the economic dispatch
Losses can be included by slightly rewriting
the Lagrangian to include losses PL:
L(PG , )
Ci ( PGi )
i 1
PD PL ( PG ) PGi
i 1
24
Impact of Transmission
Losses
PD PL ( PG ) PGi .
i 1
i 1
The necessary conditions for a minimum are now:
L(PG , )
Ci ( PGi )
dCi
L
PL
(PG , )
( PGi ) 1
( PG ) 0
PGi
dPGi
PGi
PD PL ( PG ) PGi 0
i 1
25
Impact of Transmission
Losses
dC
P
( PGi ) 1 L ( PG ) 0
dPGi
PGi
dCi
1
( PGi )
dPGi
PL
1 P ( PG )
Gi
i
PL
at the slack bus is
1 P ( PG )
always unity!
Gi
26
Impact of Transmission
Losses
The condition for optimal dispatch with losses is then
L1 IC1 ( PG1 ) L2 IC2 ( PG 2 ) Lm ICm ( PGm )
1
Li
. So, if increasing PGi increases
PL
1 P ( PG )
Gi
PL
the losses then
( PG ) 0 Li 1.0
PGi
This makes generator i appear to be more expensive
(i.e., it is penalized). Likewise Li 1.0 makes a generator
appear less expensive.
27
Calculation of Penalty
Factors
1
Li
PL
1
PGi
28
PL
( PG ) 0.0387
PG 2
PL 0.37 MW
0.037
PG 2
10 MW
L2 0.9627
L2 0.9643
29
30
Supply
curve for
thirty bus
system
5.00
2.50
0.00
0
100
200
Total Area Generation (MW)
300
400
31
Security Constrained ED
or Optimal Power Flow
Transmission constraints often limit
ability to use lower cost power.
Such limits require deviations from
what would otherwise be minimum
cost dispatch in order to maintain
system security.
Need to solve or approximate power
flow in order to consider transmission
constraints.
33
Security Constrained ED
or Optimal Power Flow
34
Security Constrained
Dispatch
Bus 2
-22 MW
4 MVR
22 MW
-4 MVR
Bus 1
1.00 PU
357 MW
179 MVR
1.00 PU
0 MW
37 MVR
100%
194 MW OFF AGC -142 MW
49 MVR
232 MVR AVR ON
145 MW 100%
-37 MVR
Home Area
Bus 3
Scheduled Transactions
100.0 MW
-122 MW
41 MVR
100 MW
124 MW
-33 MVR
1.00 PU
179 MW
89 MVR
448 MW AGC ON
19 MVR AVR ON
Multi-Area Operation
In multi-area system, rules have been
established regarding transactions on tie-lines:
In Eastern interconnection, in principle, up to
nominal thermal interconnection capacity,
In Western interconnection there are more
complicated rules
44 MW
-42 MW
-31 MW
0.99 PU
3
1.05 PU
1
106 MW -37 MW
AGC ON
62 MW
79 MW
2
40 MW
20 MVR
1.00 PU
-32 MW
80 MW
30 MVR
110 MW
40 MVR
38 MW
-61 MW
1.04 PU
31 MW
-77 MW
5
-39 MW
40 MW
94 MW
AGC ON
-14 MW
1.01 PU
130 MW
40 MVR
168 MW AGC ON
-40 MW
20 MW
-20 MW
1.04 PU
6
Left area
has one
bus
40 MW
1.04 PU
20 MW
200 MW
Left Area Cost
0 MVR
4189 $/MWH
200 MW AGC ON
-20 MW
Top area
has five
buses
No net
interchange
between
Any areas.
200 MW
Right Area Cost
0 MVR
4715 $/MWH
201 MW AGC ON
37
Area Losses
7.09 MW
-40.1 MW
0.0 MW
System has
40 MW of
Loop Flow
Left
Area Losses
0.33 MW
Right
40.1 MW
0.0 MW
Actual
flow
between
areas
Scheduled
flow
Area Losses
0.65 MW
-4.8 MW
0.0 MW
Left
Area Losses
-0.00 MW
Area Losses
9.44 MW
Right
104.8 MW
100.0 MW
100 MW Transaction
between Left and Right
Note that
Tops
Losses hav
increased
from
7.09MW to
9.44 MW
Area Losses
4.34 MW
Transaction has
actually
39
decreased