Plan Building Work Notes
Plan Building Work Notes
Supervision of the
Building &
Construction Project
BCGBC4008A / CPCCBC4008A
C:\Documents and
C:\Documents and
Contents
Section 1
Introduction ....................................................................................................................................................... 6
Contracts ........................................................................................................................................................... 8
Tender forms and letters ................................................................................................................................... 9
Variations......................................................................................................................................................... 12
Back Charges.................................................................................................................................................... 14
Insurance claims .............................................................................................................................................. 15
Payment of delivery Invoices........................................................................................................................... 16
Progress claims and payments ........................................................................................................................ 17
Final accounts .................................................................................................................................................. 21
Cost Items .................................................................................................................................................... 21
Contract Sum ............................................................................................................................................... 21
Variations..................................................................................................................................................... 21
Deposit......................................................................................................................................................... 21
Prime cost items reconciliation ................................................................................................................... 21
Provisional sum adjustment ........................................................................................................................ 22
Progress claims received ............................................................................................................................. 22
Retention ..................................................................................................................................................... 22
Claim for extended site establishment........................................................................................................ 22
Balance payable ........................................................................................................................................... 22
Summary.......................................................................................................................................................... 23
Section 2
Introduction ..................................................................................................................................................... 26
What Site Records Should Be Kept? ................................................................................................................ 27
Types of Records.............................................................................................................................................. 28
Using the diary, calendar and planner ........................................................................................................ 28
Site instructions ........................................................................................................................................... 29
Site Reports ................................................................................................................................................. 31
Variation Requests ...................................................................................................................................... 31
Extensions of time ....................................................................................................................................... 31
Unsatisfactory Work Notices ....................................................................................................................... 33
Documentation to control material, plant and equipment............................................................................. 34
Good construction site communication .......................................................................................................... 35
Simplified communication ........................................................................................................................... 35
Communicating through the design Phase ..................................................................................................... 37
Drawing provision and distribution ............................................................................................................. 37
C:\Documents and Settings\alaws\My Documents\al\c4 resources\4007\Plan building work notes.docx:AD:vpl:ab
3
Section 3
The Operation of a Quality System in a Construction Company ..................................................................... 44
The Quality Manual ......................................................................................................................................... 45
Operating a Quality System for a Construction Project .................................................................................. 46
Controlling Quality on a Construction Site ...................................................................................................... 48
Preparatory phase ....................................................................................................................................... 48
Start-up phase ............................................................................................................................................. 48
Production phase......................................................................................................................................... 48
Description of records ................................................................................................................................. 48
Personnel qualifications .............................................................................................................................. 48
Subcontractors ............................................................................................................................................ 49
Section 4
Completion of Project Administration Processes ......................................................................................... 52
Completion Checklist for Builder ................................................................................................................. 53
Planning and Development controls ............................................................................................................... 54
Categories of Development ......................................................................................................................... 54
Development Application and Approval process ........................................................................................ 55
Documents required for Development Consent ......................................................................................... 55
Construction Certificate Drawings............................................................................................................... 57
Providing Certificates................................................................................................................................... 57
Inspections................................................................................................................................................... 58
Inspecting for Defects...................................................................................................................................... 60
Typical Defect Report .................................................................................................................................. 60
Project Close Out ............................................................................................................................................. 62
Final Application for Payment ......................................................................................................................... 63
Presenting the final account............................................................................................................................ 64
Retention and defects liability period ............................................................................................................. 66
C:\Documents and
Conduct On-Site
Supervision of the
Building &
Construction Project
BCGBC4008A / CPCCBC4008A
Section 1
C:\Documents and
Introduction
As a building contractor you will need to master contract administration. Not only do
you need a good understanding of contracts and the conditions that control the
operation of the project, you need to have or develop good interpersonal skills when
interacting with clients, architects, subcontractors, suppliers etc.
In this unit we will discuss how to fulfil your contractual obligations by way of
procedures and standard forms. This is contract administration.
The contract between the client and building contractor is used as the book of rules
in administering the work and working towards completing the contract by
performance. By performance we mean fulfilling your obligations under the contract
conditions and meeting or exceeding the expectations of the client or architect in
respect of time, cost, quality and customer service.
Communication is a fundamental element of good administration. Too often this
aspect is ignored and can lead to costly disputes that can take years to resolve and
may even cost you your business. The preparation of forms can simplify the process.
Examples of the more common forms used in residential construction are included in
this unit. These forms include:
tender letter
variations
extensions of time
site instructions
progress payments
final account
Disputes with clients are often due to a need for better administration of the overall
contract as well as onsite activities. Small matters have a tendency to escalate in
importance if left unresolved. Good communication and interpersonal skills will
develop the trust shown by the client in awarding you construction of the project in
the first place.
The job is made easier if you have good organisational skills and procedures in place
to properly document the project. Your project file should accurately record the
history of the job and should make your task of finalising the project much easier.
Contract administration is not about one thing. Its about:
communication
organisation
procedures
supervision
quality
customer service
documentation
C:\Documents and
Contracts
There are many types of pro forma contracts available for residential construction.
In New South Wales, the current contract prepared by the Office of Fair Trading for
work greater than $25,000 in value incorporates the current legislation requiring a
cooling off period, a checklist of questions which a client will be required to read and
the requirement for a brochure to be given to the client by a builder outlining dispute
resolution.
This contract is readily available through retail outlets such as Australia Post shops
and can be downloaded from the Office of Fair Trading website. Remember, it is
important that you use current forms of contracts to ensure you meet the
requirements of the Home Building Act (NSW) 1989 and any amendments.
There are comparable contracts prepared by industry associations such as the HIA
and MBA. The Australian Standards also have contracts which you should make
yourself aware of. You should make yourself aware of the differences between the
contracts and, when it is in your power to do so, adopt the most favourable one.
Remember, you need to be an expert on the contents of the contract you are using
and you must know the contract form and conditions to be used before tendering on
the project. If the contract form is unavailable at the time of tender, it is vital that you
condition your tender to advise the client of the contract it is based on.
Once you have signed a contract you are bound by the terms of agreement and
ignorance is not a defence should you find the conditions onerous or if your price
does not adequately cover the contract conditions. For example, if the contract
conditions which you tendered on do not allow for extensions of time, allowance for
this must be made in your tender, usually as a cost implication to cover any risk that
may present itself in the absence of extensions of time.
If you are not sure of the intent of a clause in a contract you should consult a legal
expert for clarification and advice.
Remember, if you do not understand a contract, do not sign it.
C:\Documents and
In addition to submitting the standard tender form provided, many builders also
prepare a tender letter that outlines these conditions. A sample, with some common
conditions included, is provided in this unit. The conditions can be quite varied and
while some are considered standard, others will be relevant to a particular project.
Examples of conditions are:
It is not uncommon for builders to use both of these documents when submitting a
tender. It is usually a condition of tendering that a completed tender form be
submitted. By not completing and submitting a tender form, a builder could
jeopardise the chances of his tender being accepted. So it is important that the
builder submits both a tender form and tender letter. The tender letter allows for the
inclusion of the necessary conditions the builder has allowed for in the price. If a
tender form is not required as a part of the tender conditions, a tender letter should
still be submitted with your offer.
If successful, the builder should insist that the tender letter be attached to the
contract and become part of the contract documents.
C:\Documents and
TENDER FORM
PROJECT:
Builders Name:
________________________________________________________
Address:
________________________________________________________
________________________________________________________
We hereby submit the following tender to construct the proposed brick veneer cottage at
20 Jersey Road Burwood, as per the plans and specification prepared by JWA Architects
P/L.
CONTRACT SUM:
__________________________________________________
(amount in words)
__________________________________________________
Signed:
______________________
Capacity:
______________________
Date:
______________________
C:\Documents and
Date
We do hereby tender to execute and complete the construction of a brick veneer dwelling
at 20 Jersey Road, Burwood, according to plans (numbered A1 to 3) and accompanying
specifications (page 1 78).
FOR THE SUM OF:
This tender is valid for a period of 28 days after which we reserve the right to review our
price and is subject to Council approval and satisfactory negotiation.
Yours faithfully
.....................................
Construction Manager
C:\Documents and
Variations
Projects are commonly subject to variations during the course of the project. Whether
initiated by the client/architect, or by you, (the building contractor), all variations need
to be recorded.
Variations are often referred to as extras but this is a misnomer and comes about
because most variations are for extra work that adds a cost to the contract sum.
Variations can be an addition, deduction or a no cost variation to the contract. For
example, a product as specified is unavailable at the time of procurement and
replaced by a product of comparable quality and at the same price.
A variation needs to be recorded and approved before ordering the product since the
specification has been altered even though there is no variation in the contract sum.
If this change is not recorded and approved, a client may use it as an issue should a
dispute arise further into the contract.
Most building contracts give the client the right to vary the contract at any time. Some
builders use variations as an opportunity to increase their profit margin by pricing the
variation work higher than it is worth. Doing this could lead to a dispute between
client and builder. As long as you cost all variations accurately (and this can be easily
substantiated) you can justify their value to the client/architect if the need arises. It
may also pay to consider the implication of the variation in terms of extra time
needed and whether you need to communicate this to have an extension of time
approved. All variations need to be approved in writing before any work associated
with that variation can begin.
Some variations may bring in safety issues for which written approval cannot be
sought and received before the work is undertaken. In these circumstances the
builder may have to proceed with the work and be prepared to argue the case with
the client at a later date. Safety is the responsibility of the builder and compliance
with the OH&S Act 2000 and OH&S Regulations 2001 is expected by Workcover
NSW. Compliance with the Act is expected under any contract.
On the following page is a pro forma for variations to a contract. The form allows the
builder to clearly describe the extent of the variation, communicate the cost and,
where necessary, change the contract sum.
The variation form and the variations should be numbered for future reference,
particularly when finalising the contract.
C:\Documents and
CONTRACT VARIATION
No.
DATE:
PROJECT:
CONTRACT PRICE
DESCRIPTION
THIS VARIATION
ADDITIONS
DEDUCTIONS
$
NET VARIATION
SIGN:
DATE:
Back Charges
When undertaking construction works there are often instances as a head contractor
when something on a clients site might get damaged and needs to be repaired by
the owner of the property. In this situation and other similar situations it is clear there
is a loss to the owner.
There are ways in which the above scenarios can be resolved efficiently and quickly
so that it does not leave a bad taste in the mouth of the owner. Remember it is
important to keep up the reputation of the company even if it costs the company a
little bit at that point in time. The quick resolution of these issues can mean that the
companys reputation is maintained.
So how do you resolve the situation;
1. The rectification can be paid for directly
2. The client can issue a negative variation and not pay this amount if this is agreed
between the parties is often the simplest resolution
Quite often it is a little bit more complex than withholding some money and more
complex scenarios arise the later into a construction project you get. For example if
there is a trade that shows up late and the cleaners have been through and they start
making a mess after the cleaners have finished... WHO PAYS? Is it right that the
builder should pay again? Is it right that the client should pay again? However the
cleaner needs to be paid and the only person to blame is the contractor that did not
show up on time. How is this resolved?
Firstly when dealing with Back charges, you must ensure that you have given every
opportunity for the contractor to fix the problem before getting it fixed. (in the above
example it would be necessary to ask the contractor to clean up the mess to the
standard that the cleaner left it so that the client can take over the property.)
Secondly IN WRITING advise the contractor that they will be charged the cost of
cleaning up the mess. THIS IS IMPORTANT.
Thirdly instruct the cleaner to do the works issuing a positive variation to the cleaner.
Fourthly issue a negative variation to the contract sum to the contractor that made
the mess that the cleaners cleaned up.
C:\Documents and
Insurance claims
Accidents occur on building sites and occasionally they damage materials or the
fabric of a building. Sometimes they are caused by malpractice or negligence and
sometimes by mistakes during construction. The main question when damage to
property, building fabric or product occurs on a building site is who pays.
The above is the reasons why we have insurance policies that cover every step of
the building process.
The biggest question is how do you make an insurance claim. This is quite often
undertaken by the insurance company. It should be noted however that there are a
number of things that you can do to help make an insurance claim.
As soon as the damage theft accident or whatever the scenario occurs it is important
to document the situation clearly and logically so that the insurance company can
see proof. This proof can be shown through photos or evidence of delivery and the
subsequent value of the product. Details in site diaries are very important.
Calling the insurance company and stating that you would like to make a claim
quoting the policy number and you can start the process rolling to recover the loss
that has occurred.
In some cases this will be money and in other cases it will be product or material.
Whatever the situation it is important to start the process as quickly as possible so
that the information can be passed onto the insurance company before it becomes
vague.
If the damage was caused by vandals or there is theft it is essential that the police
are called and a police case report number is issued by the police and that this is
given to the insurance company.
C:\Documents and
C:\Documents and
declaration signed by the subcontractors declaring that they have, and maintain a
valid workers compensation policy, have paid all pay-roll tax due and have paid all
monies payable to employees for work done under the contract.
The timing of progress claims and payments are important for your cash flow.
Ensuring that your subcontractors make claim for work before you submit your own to
the client but that their terms of payment are longer allows you to receive
payment from the client before paying subcontractors.
On the following page an example of a progress claim (invoice) and cost break up
(progress report) is included.
C:\Documents and
TAX INVOICE
ABN
18 105 199 407
DATE
21/6/08
INVOICE NO
23
INVOICE TO
PROJECT
Mr Wilt
13 Mystic Drive
Forestville
TERMS
7 days
DUE DATE
28/6/08
PROJECT
15 13 mystic
DESCRIPTION
AMOUNT
(2,600.00)
TAX SUMMARY
GST $2,600
TOTAL
$23,400.00
This claim is issued Pursuant to the building Construction Industry Security of Payment Act 1999
Contract #: 15
Date: 21/6/08
WORK BREAK UP
COMMITTED
VALUE
% COMPLETED
TO DATE
VALUE COMPLETED
TO DATE
CONTRACT WORKS
Preliminaries
10,000
50%
5,000
Demolition
5,000
100%
5,000
Excavator
8,000
75%
6,000
Concreter
20,000
25%
5,000
Carpenter
30,000
0%
SUBTOTAL CONTRACT
73,000
21,000
VARIATIONS
V01 Disposal of Asbestos
5,000
TOTAL VARIATIONS
5,000
100%
REVISED TOTAL
5,000
5,000
$26,000
$0
$26,000
LESS RETENTION
$2,600
BALANCE PAYABLE
$23,400
Final accounts
The final account is the last bill that the building contractor submits for works as
contracted. It is prepared and submitted at the stage of practical completion.
Commencing with the original contract sum and ending with the balance payable on
the contract (excluding and retention held over the defects liability period), it outlines
the financial history of the project.
So when do we reach practical completion? Practical completion is when the builder
has completed all the work in accordance with the contract documents and any
variations. Any apparent defects should have been rectified and all rubbish and
surplus material removed from the site. It is also dependant on the client accepting
the work as complete.
Preparation for the final account must be done progressively throughout the project.
Preparation cannot be delayed until the last week of onsite activity. Except for the
payment of retention at the end of the defects liability period, this is the last
opportunity to make a claim on the client. Therefore, as a builder, you need to make
sure you include all claims due to you as well as any credits due to the client. The
onus is on the builder to provide an accurate final account, free of any errors or
omissions.
Cost Items
The final account will detail all the monetary aspects or cost items of the contract and
would normally include, but not be limited to the following:
Contract Sum
This is the original contract figure that would have appeared on the signed contract
conditions of agreement.
Variations
The total cost of the variations would be included in this final account. No details of
the variations would be included here. This should have been submitted and
approved prior to the work on the variations commencing.
Deposit
Deposit paid by the client should appear on the final account.
Retention
All retention monies should be shown. Retention percentages change at the time of
practical completion. Usually, a maximum of 5 per cent of the total contract is held up
until the time of practical completion; then it reverts to 2.5 per cent for the duration of
the defects liability period. The Final Account needs to show the adjustment to 2.5%
and the outstanding retention owing.
Balance payable
This is the amount of money the client is required to pay the builder (excluding the
2.5 per cent retention), within the agreed time period. This time period should also be
stated on the final account.
C:\Documents and
Summary
The success of contract administration depends on effective communication
between all parties involved. The contractual parties must ensure that the lines of
communication are established and kept open throughout the contract period. The
fundamental aspect to create and maintain a workable relationship between the
client and builder is central to the completion of the contract to the satisfaction of all
parties.
Satisfied clients create opportunities for future work by recommending you, the
builder, to new clients.
While much of what we do as builders in contract administration is tried and tested,
there is still an element of human nature involved and you cannot rule out a clash of
personalities that can make your work environment very difficult. It is important that
the impact of your administration will impact the relationship with your client.
However, the clients experiences throughout the project are what they will convey
to others. There may be personality clashes throughout the project, however all that
can be expected is openness and honesty throughout the administration.
C:\Documents and
C:\Documents and
Conduct On-Site
Supervision of the
Building &
Construction
Project
BCGBC4008A / CPCCBC4008A
Section 2
C:\Documents and
Introduction
The communication process is probably the single most important factor in the day to
day activities of a building supervisor.
All building organisations require essential communication links between the different
levels of the hierarchy. Communication has a direct association with performance i.e.
the better the communication process, the greater the performance. Because
performance is inextricably linked to profit, it is desirable for management to adopt
sound communication strategies from the outset; this becomes a major platform in
on-site culture.
Effective communications will stop confusion occurring between the sender and
receiver of a message whether it is written or verbal. Communication is a two way
process that involves listening to the feedback supplied when instruction is given.
Feedback should be encouraged so that the supervisor can determine if the
information which is given out in digestible amounts is clearly understood.
How well you perform your activities and how they are seen by workers will be
determined importantly by your communication skills.People do not communicate all
their thoughts and feelings. People commonly use poor communication techniques
which can lead to confusion.
Confusion can be caused during communication by:
C:\Documents and
C:\Documents and
Types of Records
The types of records that should be kept on the computer, ready to be printed off or
as hard copy are:
Activities to be completed
Information on workforce numbers and activities
Meeting schedules and meeting notes
Information on materials usage
Information on plant and equipment usage
Union matters
Suppliers/deliveries
Many other aspects of recording work related information
Twice daily weather conditions
Changes to inclement weather
C:\Documents and
Site instructions
When the builder queries a design detail, the client often instructs he or she to do
something that is not clear in the documentation. If this is the case and the client
does not provide written confirmation, you as the builder should confirm the
instruction in writing by use of a site instruction. If the instruction impacts on your
subcontractors, you should also provide them with a site instruction.
A site instruction is merely written confirmation of an instruction given to you by the
client that is not clear in, or contradicts, the contract documents. For example,
although the colour of fencing specified on the drawings and in the specifications is
black, the client has changed their mind and wants the fence to be green.. They have
advised you verbally but as it is considered a small change that has no monetary
impact (not a variation) the documents have not been changed. In this case, you
need to confirm the request in writing and ask the client to sign it. Keep a copy and
distribute one to the client and to any subcontractors impacted upon by the
instruction.
When you receive an instruction from the client of the clients representative that is
not considered a variation, and not confirmed in writing, you leave yourself open to
dispute. It is vital that any instructions given to you by a client is confirmed in writing
and signed by them.
C:\Documents and
No:................
CLIENT: .................................... PROJECT: ..........................................
DAY LABOUR
SITE INSTRUCTION
TRANSMITTAL
ISSUED TO:
....................................................................
ATTENTION:
....................................................................
ISSUED BY:
SIGNATURE:
.......................................
.......................................
RECEIVED BY:
SIGNATURE:
DATE:
MEMO
............................
.......................................
.......................................
Site Reports
There is a fundamental need for the supervisor to have a good understanding of
basic report writing techniques and their application. They will be frequently
involved in activities such as performance appraisals, job instructions, job
specifications, recruitment, site diaries, progress reports and many other relevant
areas.
The communication between senior management and the supervisor requires a
daily flow of correspondence which must be quickly and effectively addressed by
the supervisor.
Performance appraisal is one task frequently assigned to the supervisor and as
such they must closely follow company policies affecting the performance of
subordinates; this appraisal is considered one of the most important on-site reports.
Any written formal or informal communication is important. Many of these are in
short report form and should be recorded electronically or copies filed accordingly.
Example Site Evaluation Report
The Site Evaluation Report consists of a general site investigation and research
involving local code officials and public/private utility organisations to identify
requirements associated with the proposed site utilisation, expansion, or redevelopment that could impact the budget or timing.
Variation Requests
Variation requests should be recorded and filed. Generally, a variation request is
priced by the sub-contractor then presented to the client, approved and signed.
After approval the sub-contractor should be told to proceed with an instruction and
the signed copy filed. An example of this kind of communication has been included
in Section 1 of these competency notes.
Extensions of time
The time taken to complete a project is all too often the cause of a dispute. This can
be the result of many factors including:
In order not to be penalised at the completion of the job should it take longer than
the original estimate, the builder has to claim an extension of time. The contract
C:\Documents and
generally outlines the circumstances that allow for such a claim. The contract
conditions and rules should be followed closely.
Some builders will claim at every opportunity. Be aware that ridiculous claims can
be challenged and you may be required to justify it. If you cannot justify a claim, you
may damage the integrity of your organisation. A claim should be backed up by
evidence and documentation (such as site diary entries).
Description:
(Project Name)
(Type of delay)
Signed:
Site Manager/Foreman
Date
C:\Documents and
This is a very simplified ITP but gives you the example as to how to write an ITP.
C:\Documents and
C:\Documents and
Simplified communication
Figure 3 illustrates a simplified methodology for communication during the different
phases of a construction project.
At the outset and/or contract stage, the ways in which project communication will be
designed to work should be agreed. Issues to be agreed include the following.
Method issues
People Issues
C:\Documents and
C:\Documents and
It allows people to get to know each other; this is likely to lead to better
communication and less confrontational attitudes as work progresses
It provides the opportunity to decide on how communications will operate
It provides the opportunity to define points of contact at each organisation
It can be used to ensure that all people have the contact details for others working
on the project.
Ensure that all relevant people attend the kick-off meeting, this may include
supervisors and major suppliers.
Manufacturers
Australian Standards Institution
Building regulatory authorities
Trade associations (e.g. Master Plumbers Association)
Insurance companies (e.g. HIA, MBA)
Consultants and research organisations
The documents available vary widely in their scope, size, and format dependent on
issues such as the intended audience and place of use for the document. Always
bear in mind that technical information is also available in formats other than paper
documents.
C:\Documents and
Communication method
Description/use
Telephone help-desks
CD ROMs
Videos
Posters
Instructions printed on
packaging
Upwards feedback
Establish means by which information can be effectively fed back up through the
formal management structure. Two key areas where this can be particularly important
are as follows:
C:\Documents and
Project Meetings
While it is almost universally accepted that no one likes going to meetings, there are
likely to be communication and build quality improvements from an appropriate
number of well structured meetings being held. The benefits from such meetings
should make the time spent worthwhile. The importance of kick-off meetings has
already been covered. Trade co-ordination meetings have also often proven to be
particularly worthwhile, especially at helping site work to progress smoothly and
informal agreements between trades to be established.
The success of formal meetings (e.g. the monthly progress meeting) is helped by
being structured, including the following:
Chairperson
Agenda
Set start and finish times
Minutes recorded
Minutes should always be circulated after the meeting and include action points with
the responsible person(s) identified and dates to be completed by. Consider inviting
all the relevant people to any meetings, but bear in mind that some people may only
need to usefully attend specific parts of a meeting.
C:\Documents and
C:\Documents and
C:\Documents and
Conduct On-Site
Supervision of the
Building &
Construction Project
BCGBC4008A / CPCCBC4008A
Section 3
C:\Documents and
C:\Documents and
The Quality Manual explains how you operate and drive the system, in the same way
that other types of manuals tell you how to operate your video recorder or service
and maintain your car.
The Quality System contains documented procedures. These are explanations of
how the company carries out its basic processes and activities. These are written in
plain English and preferably were written by the staff who normally carry out those
procedures.
A company needs to update its manual and procedures from time to time. This will be
necessary to improve its efficiency, overcome deficiencies, to take account of new
technology and materials and/or when it introduces new processes as it undertakes
different types of work.
Regular updating of Quality Management systems rectify any issues that are not
working satisfactorily such as items or processes that can be simplified.
Quality Management is not some kind of quick fix or magic. Quality Management is
developing and using a system on a day to day basis to run the companys business
and projects. Used in this way it provides assurance to customers that projects and
services will meet their requirements.
C:\Documents and
C:\Documents and
Quality
Manual
Documented
Procedures
Other
Sections
ITPs
Project
Quality
Plan
At company level
Quality
Policy
Documented
Procedures
ITPs
Figure 1 Operation of the Company Quality System at company level project level
C:\Documents and
Preparatory phase
Start-up phase
Review the contact requirements with personnel who will perform the work
Inspect start-up of work
Establish standards of workmanship
Provide training as necessary
Establish detailed testing schedule based on the production schedule
Production phase
Description of records
Personnel qualifications
C:\Documents and
Subcontractors
Include the work of all subcontractors. If a subcontractor is to perform work under this
Section, detail how that subcontractor will interface with the Contractors and/or other
sub-contractors organisations?
The quality of work carried out by contractors/workers on the site is usually measured
against a required standard. On large commercial sites Inspection Test Plans set
out in detail when, where and how each critical activity is to be checked for
conformance. Contractors must sign off each activity to show that the activity is
completed and checked for quality against the specifications. This signing off also
helps the proper sequencing of construction activities. On smaller sites such as
house construction the same principles apply however how these principles are
applied may vary dramatically.
C:\Documents and
C:\Documents and
Conduct On-Site
Supervision of the
Building &
Construction Project
BCGBC4008A / CPCCBC4008A
Section 4
C:\Documents and
The time limit for completing the remainder of the work per the list
Establish the responsibilities of the owner/client and builder for security,
maintenance, utilities, damage to the work and insurance.
Establish date for the commencement of all warranties.
C:\Documents and
Generally the minimum amount retained for each unacceptable item should be
estimated at a cost incurred to have another contractor brought in to complete or
correct the item. This includes any costs for mobilisation and/or equipment required
to correct or complete any outstanding construction deficiencies.
Water valves (an extra valve at the entry of the house is handy).
Electricity metres must be accessible to electricity authority but circuit breakers
and earth leakage safety device should be inside the house for both security
and convenience
Hot water system located preferably external to house in case of leakage
Post box
Cable entry points future faults can often be fixed quickly if these are known
Survey pegs which are required for fencing. Dividing Fences Legislation
establishes two principles:
a. Fences must suit the area, and
b. A prior written notice is required to obtain contributions from neighbours.
C:\Documents and
Categories of Development
Approval is required to carry out development in the City of Sydney, except where
expressly exempted. The Environmental Planning and Assessment Act 1979 defines
development as:
Exempt Development: minor development that does not need any approval but
must comply with specific standard provisions.
Complying Development: a subset of local development that has a low
environmental impact and that can be certified as complying with predetermined
standards. Separate complying development procedures provide a fast system for
assessing development. A Complying Development Certificate may be issued by
either the City of Sydney or an accredited certifier.
State Significant Development: is a development identified by the State
Government as being of State or regional significance. The Minister of Planning is
the consent authority.
Integrated Development: is a development where separate approvals are
required under other Acts, such as The Heritage Act 1977 or The Roads Act
1993. Here the City of Sydney refers the application to the relevant authority to
seek the terms of approval. If approval is granted, such terms of approval will be
included in the development consent. Separate approvals will still be needed
under the relevant acts, but the confirmation of an approval will be obtained early
on in the process. The approval of the relevant authority does not fetter the
discretion of Council in determination the application.
So what does all the above mean to you as a builder? In some circumstances you
will be required to obtain a Development approval and all other statutory
documentation for and on behalf of a client. So how is this undertaken, below is
C:\Documents and
outlined the various steps and stages required to obtain all the statutory approvals
this does change from one council area to another so it is important to confirm with
the particular council exactly what is required.
Shadow Diagrams
Landscape Plan where significant landscaping works are involved. Generally
prepared by a Landscape Architect or Designer.
Stormwater Management Plan for many city and suburban developments
Environmental Site Management Plan for environmentally sensitive sites
C:\Documents and
BASIX certificate
The Building Sustainability Index is a web-based planning tool put in place by the
State Government to assess the potential performance of residential developments
against a range of sustainable indices. You must provide a BASIX assessment
certificate for all new detached single dwellings and dual occupancies, multi-unit
developments and additions and alterations to house. Refer to
www.basix.nsw.gov.au for more information and use this webpage to complete your
certificate
Geotechnical report
This may be required when it is proposed to excavate to a depth of two meters or
more below the existing ground level and also in other instances depending on the
nature of the development and site circumstances.
Sample board
A sample board shows the proposed finishes of the development and may be
required for new residential developments, including single dwellings, dual
occupancies, flat buildings of three or more stories, all developments where four or
more dwellings are proposed and for all retail, commercial or mixed-use
development.
The sample board provides an example of each material to be used on the exterior of
the development and the outdoors areas of any new structures.
C:\Documents and
Makes sure that the detailed construction plans and specifications comply with
the Building Code of Australia (BCA) and any other relevant Australian standard
Certifies that the detailed construction plans and specifications are consistent
with the Development Consent
Certifies that the relevant Conditions of Development Consent have been
complied with.
The above requirements are often covered in the construction drawings, see table
below outlining the different types of drawing involved.
Construction or Working Drawings
CC Drawings
Construction
details
Providing Certificates
If a Development Consent (commonly referred to as a DA) has been approved for the
works then a Construction Certificate (CC) will be required for the works (as noted
above). This will be either issued by the building surveying department of the council
that issued the Development Consent or the CC can be issued by a Private Certifying
Authority (PCA).
As part of the development consent there are conditions that must be complied with
these are outlined in the consent. The Private Certifying Authority ensures that not
only are all the conditions complied with but that the building or development is
completed according to the plans and specifications that have been approved as part
of the consent and CC.
In order to obtain a Construction Certificate (CC) from your PCA, you will have to
provide some certificates to show that your works will comply with the consent and
also that the works will comply to the BCA and Australian standards.
C:\Documents and
Upon completion of the works the PCA or council will require the following certificates
as part of the approval process, verifying compliance with the BCA and relevant
Australian Standards:
Any engineer certificates that were required e.g. for footing design or roof design
Waterproofing for wet areas
Glass in windows and doors (provided by supplier)
Timber treatment where necessary
Termite management system where necessary
Roof trusses from manufacturer
Hydraulic certificates
Smoke detector certificate of installation
Cadastral survey report where required or requested
BASIX Certificate for residential projects
Inspections
During the building process there are a number of statutory inspections that are
required to be undertaken it is critical that the inspections are undertaken at the times
that they are supposed to. The Environmental and Planning and Assessment Act
1979 specifically outlines the mandatory or Critical stage inspections that are
required during the building process. So what are the inspections that need to be
undertaken during the building process? Below is a list of requirements for work to a
residential development:
Pre-Commencement inspection prior to works starting this ensures that all site
establishment requirements have been completed prior to starting works.
Footing and piers inspections.
Stormwater drainage inspection after pipes have been laid and prior to backfilling
trenches.
Structural engineers inspections prior to pouring concrete including termite
protection and vapour barrier.
Framework
Waterproofing
Completion inspection upon completion of the works prior to occupation of the
premises including landscaping.
C:\Documents and
There may also be other inspections that are required under the development
consent depending on the type of premises that are being constructed or built. Some
of these could be on the following list:
When it comes to a food shop quite often a health inspector is required to inspect
the premises prior to occupation.
When it comes to premises that store or use dangerous goods there are
requirements for inspections by the Environmental Protection Agency or specific
agencies depending on the type of materials or the legislation that may govern
the storage of said materials.
Councils often require an inspection to be carried out by them if new kerb and
guttering are to be installed in front of a property.
A new driveway to a property will often require council to inspect prior to pouring
concrete to view steel reinforcement and stormwater.
With the completion of the above the Private certify can issue an occupation
certificate following there completion inspection. As part of issuing an occupation
certificate, the certificates that are listed above will also be accompanied with
certificates that state that the inspections were carried out.
C:\Documents and
C:\Documents and
Plumbing
Plumbing works, fixtures or fittings are checked to see if they are in order. Any leaks,
drainage problems or other defects (e.g. lack of water pressure, slow drainage etc)
are noted.
Site Drainage
Poor site run off or lack of connection of downpipes to stormwater drainage that
results in obvious boggy areas is noted.
Electrical Wiring
The condition of the meter and switchboard, power point testing in at least 5
locations, and visual examination of the wiring in the roof space (where accessible)
and elsewhere, is checked to assess the state of electrical wiring. A further check by
a licensed electrical contractor may be recommended.
Roof Condition
The roof covering and its associated plumbing (i.e. flashing, gutters and downpipes)
are visually inspected to detect any defects (e.g. broken tiles, leaks, blocked
downpipes, etc).
Roof and Sub-floor Structure
Visual inspections from access points are undertaken to determine the condition of
the structural components. Any apparent signs of sagging, lack of support, moisture,
rot or faulty services are noted.
Insulation
The presence and adequacy of roof space insulation is reported on, where
accessible.
Paint finish
Imperfections/inconsistencies in paint finish are noted.
Floors, skirting, architraves, walls, cornice, ceilings, doors, cupboards,
appliances, etc
All visible defects are noted.
C:\Documents and
Application for payment showing all work as completed and requested amount to
be retained
List showing all items identified by the builder, certified as being completed
All copies of necessary certificates, as required by the Building Surveyor
Final release for the total amount of contract sum
Final drawings and specifications as per the contract documents
Warranty and maintenance information as required by the Contract Documents
Extra stock materials and special tools as provided in the Contract Documents
Final accounting of all requested variations for the project.
In addition to the items listed above, the Close-Out Documents shall include proof
that all equipment and maintenance demonstrations required by the contract
documents, have been successfully completed by the builder for the owner/client.
Equipment demonstrations shall be scheduled by the builder with the owner/client
given adequate notice to ensure that proper personnel may attend.
Should all prerequisites for project close-out be satisfied, the Owner/client and/or
Architect will then recommend to the builder in writing that the owner/client make final
payment to the builder.
C:\Documents and
C:\Documents and
C:\Documents and
$
120,000.00
17,500.00
Adjustment to PC items
Allowed 6,000.00
Cost 7,200.00
Adjustment to provisional sums
1,200.00
Allowed 20,000.00
Cost 18,000.00
2,000.00
138,700.00
2,000.00
136,700.00
Deposit Paid
6,000.00
120,000.00
3,417.50
129,417.50
136,700.00
129,417.50
Balance Payable
TERMS: 7 DAYS
7,282.50
Figure 1 Final account
C:\Documents and
As describe previously, the most common arrangement for retention is that retention
is deducted from progress payments at the rate of 10 per cent until the fund reaches
a maximum of 5 per cent of the contract sum. At practical completion, 2.5 per cent is
refunded to the builder, with 2.5 per cent remaining in the fund until the end of the
defects liability period. The remaining 2.5 per cent is taken as 2.5 per cent of the
adjusted contract sum (that is the original contract sum plus or minus any variations).
For example, for a contract sum of $100,000, the following would apply.
Progress
payment
1
2
3
4
5
Amount claimed
$20,000
$20,000
$20,000
$20,000
$20,000
Retention
$2,000
$2,000
$1,000
NIL
NIL
Payment received
$18,000
$18,000
$19,000
$20,000
$20,000 + $2,500
Retention released on
practical completion
As 5 per cent of the contract sum is $5,000 and 2.5 per cent is released on practical
completion, $2500 is held until the defects liability period has expired.
Note that the current Residential Building Contract published by the Office of Fair
Trading does not contain a retention clause. This is because the Home Building Act
1989 requires the builder to provide home warranty insurance.
Generally, a contract requires the client to open a joint bank account in the names of
the client and builder. All retention monies are deposited into this account and the
interest accrued is usually shared equally between the client and the builder upon
satisfactory completion of the contract and the expiration of the defects liability
period. Builders are generally not signatories to the retention bank account.
Once the defects liability period has expired and provided any defects of the
outstanding defects have been satisfactorily rectified, a written request in the form of
a letter or invoice should be submitted to the client to secure the release of the
outstanding retention. On the following page is an example of a letter that could be
used to request balance of retention.
As a builder, you are also required to hold retention on your subcontractors. An
identical retention clause used in the head contract should be included in your
subcontractor agreements.
C:\Documents and
TAX INVOICE
Invoice # 770
Ms Wels
51 Wentworth Road
STRATHFIELD NSW 2135
20 September 2004
Dear Ms Wels,
RE: ALTERATIONS AND ADDITIONS AT 51 WENTWORTH RD, STRATHFIELD
The defects liability period on the above project expired on 10 September 2004. As no
defects have become apparent, please release the balance of our retention as required by
the contract documents.
Balance of retention:
$3,417
.........................................
Construction Manager
Summary
The success of contract administration depends on effective communication between
all parties involved. The contractual parties must ensure that the lines of
communication are established and kept open throughout the contract period. The
fundamental aspect to create and maintain a workable relationship between the client
and builder is central to the completion of the contract to the satisfaction of all parties.
Satisfied clients create opportunities for future work by recommending you, the
builder, to new clients.
While much of what we do as builders in contract administration is tried and tested,
there is still an element of human nature involved and you cannot rule out a clash of
personalities that can make your work environment very difficult. It is important that
you remember this, as hindsight is quite useless in ensuring the success and
continuation of your organisation.
C:\Documents and
Activity 1
To answer the following questions, you will need a form of standard contract (such as
the Home Building Contract for work greater than $25,000 published by the Office of
Fair Trading)
1. Who must get a copy of the signed contract and its associated documents? How
long is allowed for this to be done?
2. The owner of the property must sign the contract to confirm they have received a
special document. What is the document and what does it contain?
3. Under the Home Building Act 1989, what does the statutory warranties clause
require the contractor to provide?
7. What must be included on progress claims to ensure they are paid as per the
terms of the contract?
C:\Documents and
Answers to Activity 1
1. The contractor and the builder should keep their own signed copy of the
contract with all the attachments. You have 5 business days after the contract
is entered into to do this.
2. The document is a consumer building guide that explains the operation of the
Home Building Act 1989 and the procedures for the resolution of contract and
insurance disputes.
3. The statutory warranties require the contractor to provide the agreed product,
in an appropriate state and fit for its intended purpose, complying with all the
relevant laws and delivered within the agreed time.
4. The client or owner of the property pays security deposits to authorities.
However, the builder is responsible for damage to public and council property.
5. A contractor can cease or suspend works onsite when the owner
Fails to provide evidence of title
Does not have the capacity to pay the contract price
Fails to pay progress payment within the time allowed and after the
contractor has provided another written notice to pay
Fails to advise the contractor promptly of any requirement from a statutory
or lending authority if it affects the work
Fails to perform any work or supply materials as specified in the contract
which prevents the contractor from continuing work under the contract
Denies the contractor or sub contractors access to the site
Becomes bankrupt
6. Some examples include the stove, special kitchen appliances or bathroom
products, flooring, and finishes such as tiles.
7. The period of time the client has to pay within, for example, Terms: 7 Days.
8. The contractor is required to hand over to the client all guarantees and
instruction manuals, and keys relating to the work, together with any
certificates or approvals relating to the work which may have been provided by
public authorities.
C:\Documents and