This document discusses submarine pipeline installation methods. It provides an overview of conventional techniques like S-lay, J-lay, and reel lay which lower the pipeline from a lay barge. Unconventional methods described include surface tow, bottom tow, bottom pull, push-pull for shore approaches, control depth tow, and horizontal directional drilling. Examples are given of projects using the push-pull and bottom pull techniques to install pipelines from shore to shore.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
78 views

EMAS Talk PipelinesMay14 Slides

This document discusses submarine pipeline installation methods. It provides an overview of conventional techniques like S-lay, J-lay, and reel lay which lower the pipeline from a lay barge. Unconventional methods described include surface tow, bottom tow, bottom pull, push-pull for shore approaches, control depth tow, and horizontal directional drilling. Examples are given of projects using the push-pull and bottom pull techniques to install pipelines from shore to shore.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 14

What is a Submarine Pipeline and what are

the Typical Pipeline Installation Methods?


Dr. Ng Eng Bin, VP Engineering, EMAS AMC

14 May 2014

WIN EXECUTE SAFE DELIVERY

Agenda
Introduction
Overview of Submarine Pipeline
Installation Methodologies
Conventional Pipeline Installation
Methods
Unconventional Pipeline Installation
Methods

Installation Techniques for Submarine Pipelines


Conventional Pipeline
Installation Techniques
S-Lay
J-Lay
Reel Lay

Unconventional Pipeline
Installation Techniques
(Examples)

Surface Tow
Below Surface Tow
Bottom Tow
Bottom Pull
Push Pull Method (for Shorepull)
Control Depth Tow Method
Horizontal Directional Drilling

Conventional Pipeline Installation Methods


S-Lay

S-LAY INSTALLATION

Conventional Pipeline Installation Methods


J-Lay

J-LAY INSTALLATION

Conventional Pipeline Installation Methods


Reel Lay

REEL LAY INSTALLATION

Reel Lay
EMASs Ingleside Spool Base Texas, USA

Push-Pull Method
Project Example Ref. Geocean
Dredging for Pipeline Installation
from Shore Approach to Landfall

Buoyancy Drums to Provide


Positive Buoyancy

Completion of PUSH-PULL
Installation & Reinstatement

Surface Tow Method


Project Example Stripping of Buoyancy Drums

Surface Tow Method


Schematic: Stripping of Buoyancy Drums and Laying of Pipeline

Bottom Pull Method (Landfall to Landfall)


Project Example

Project Requirement:
8 Pipelines
2 Fiber Optic Cables

Installation Concept:
Build Pipeline & Cable
Bundle at Bukom
Bottom Pull across
Shipping Channel
Protect with Rock Berm

Tanjong Penjuru
(Singapore mainland)

Shell Bukom
Refinery (Bukom
Island)

Bottom Pull Method (Landfall to Landfall)


Schematic

Shore Approach Installation by HDD: Typical Concept


Lay Barge

1 - 2 km max

Pull Pipeline to Shore


Laybarge Located in
Water Depth 6m - 10m

Other Unconventional Pipelay Techniques

Control Depth Tow Method