Hydrostatic Test Procedure
Hydrostatic Test Procedure
Revision: 1
Page 1 of 9
QUALITY CONTROL
PROCEDURE
Industrial projects company (INPEC)
Copy No.
Controlled
Uncontrolled
0.0
First issue
01/09/2012
Name
REV.
COMMENTS
DATE
Sign/date
PREPARED BY
Name
Sign/date
APPROVED BY
Name
Sign/date
ACCEPTED BY
INPEC-HT -01
Page 2 of 9
Table of Content
1) Scope
2) Reference Code
3) Testing Schedule
4) Pressure Gauges
5) Test Medium
6) Preparation for Pressure Testing
7) Filling with Test Medium and Venting
8) Test Pressure
9) Holding Time, Test Temperature and Close Examination
10)
11)
Repair Case
12)
HSE Precautions
13)
Report
14)
Attachments
Revision: 1
INPEC-HT -01
Page 3 of 9
Scope:
Reference Code:
-
Testing Schedule:
Revision: 1
INPEC-HT -01
Page 4 of 9
Pressure Gauges:
Test Medium:
Revision: 1
INPEC-HT -01
Page 5 of 9
7.1 Test medium shall be supplied to the Code item being tested
through a connection at the lowest point. The filling
connection shall be filled with a suitable valve.
7.2 Nozzles or other openings at the top of item being tested shall
be left open during filling to allow for proper and complete
venting of air.
7.3 When the item being tested is completely filled with the test
medium, all openings shall be closed, not fully secured
tightened while pumping is in progress to ensure complete
venting, and then secularly tightened.
7.4 The pressure is then raised gradually until the specified test
pressure is reached. Then all valves are securely tightened.
8
Test Pressure:
8.1 The test pressure shall be at least the test pressure required
by the applicable code and project specification.
8.2 For items constructed according to ASME Code Sec I,
- Hydrostatic pressure tests shall be applied by raising the
pressure gradually to not less than 1.5 times the maximum
allowable working pressure to be marked on the boiler and as
shown on the data report. No part of the boiler shall be
Revision: 1
INPEC-HT -01
Page 6 of 9
PT = (1.5 PST)/S
Where
P = internal design gage pressure
PT = minimum test gage pressure
S = stress value at design temperature
ST = stress value at test temperature
Revision: 1
INPEC-HT -01
Page 7 of 9
During a pressure test where the test pressure will exceed 90%
of the set pressure of pressure relief device, the device shall be
removed whenever possible. If not possible, a spindle restraint
may be used following the valve manufacturer's instructions
and recommendations.
Revision: 1
INPEC-HT -01
Page 8 of 9
Maximum metal
temperature during
close examination
Applicable Code
Section
120F (49C)
F (21C) 70
120F (49C)
F (17C) above 30
MDMT
120F (49C)
National Board
Inspection Code
10
Revision: 1
INPEC-HT -01
Page 9 of 9
11
Repair Case:
11.1 In case of items failed to pass the test, a repair process shall
be applied to these items according to ASME Code and
project specifications where the repaired items shall be
retested again according to the above mentioned steps.
12
. HSE Precautions:
12.1 HSE Head shall control all the safety related attributes to the
execution of the hydro test, where the equipments
connections shall be checked prior conduction of the test, all
the PPE of those who are involved in the test shall be worn,
and the testing area shall be barricaded.
12.2 HSE Department will conduct a safety toolbox for INPEC
staff whom are involved in the test for awareness about the
safety precautions have to be taken during the test.
13
. Report:
13.1 For hydro test, INPEC shall prepare all the tested items
related
documentation (Test package) before released to
test, and the result of test shall be recorded on the attached
Hydrostatic Test Form (Exhibit No.28- Hyd. Test Report).
14
Attachments:
Revision: 1