0% found this document useful (0 votes)
40 views

505 - Basic Scope Only: Bedroom 2

The document outlines the scope of work for interior finishing works such as plastering, tiling, drywall installation, door installation, painting and other works. It provides details of the locations where work is required to be done, notes on the current status, rates and amounts for each item. The total scope of work amounts to Rs. 143,391.80 and progress billing of Rs. 17,937.76 has been completed for some items that are 100% done.
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
40 views

505 - Basic Scope Only: Bedroom 2

The document outlines the scope of work for interior finishing works such as plastering, tiling, drywall installation, door installation, painting and other works. It provides details of the locations where work is required to be done, notes on the current status, rates and amounts for each item. The total scope of work amounts to Rs. 143,391.80 and progress billing of Rs. 17,937.76 has been completed for some items that are 100% done.
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 12

CHB

PIPE
CHASE

SCOPE

PLASTER
PIPE
CHASE

CONC
TOPPING

LOCATION
MAIDS/UTILITY/PANEL
COMMON T&B
MASTER T&B
MASTER BEDROOM
BEDROOM 1
BEDROOM 2
MAIDS/UTILITY/PANEL
COMMON T&B
MASTER T&B
LIV-DIN-KIT
MAIDS/UTILITY

TILES

COMMON T&B
MASTER T&B

DRYWALL INSTALLATION

MAIDS/UTILITY T&B
BALCONY
THRESHOLD

MAIDS/UTILITY

MASTER BEDROOM

BEDROOM 1

BEDROOM 2

LIV-DIN-KIT BULKHEAD (LM)


CEILING / BULKHEAD

NOTE
2 FACES
WHOLE
WHOLE

COMMON T&B (AREA)


MASTER T&B (AREA)

FLOOR
FLOOR
FLOOR
WALL
FLOOR
WALL
FLOOR
WALL
FLOOR
PER PC
FRAME
1 SIDE
ENCLOSURE
FRAME - RESTORE
1 SIDE
ENCLOSURE
FRAME - RESTORE
1 SIDE
ENCLOSURE
FRAME - RESTORE
1 SIDE
ENCLOSURE
FRAME
ENCLOSURE
FRAME
ENCLOSURE
FRAME
ENCLOSURE

CEILING / BULKHEA

MASTER BEDROOM BULKHEAD (LM)


BEDROOM 1 BULKHEAD (LM)

DOOR AND JAMB


INSTALLATION

BEDROOM2 BULKHEAD (LM)


MAIN DOOR
MASTER BEDROOM
MASTER T&B
BEDROOM 1
BEDROOM 2
COMMON T&B
MAIDS/UTILITY

LIV-DIN-KIT WALL

LIV-DIN-KIT CEILING

MASTER BEDROOM WALL

MASTER BEDROOM CEILING

MASTER T&B WALL

MASTER T&B CEILING


PAINTING

FRAME
ENCLOSURE
FRAME
ENCLOSURE
FRAME
ENCLOSURE

SURFACE PREP(CONCRETE)
SURFACE PREP(BOARD)
PRIMER
FIRST/TOP COAT
FINAL
SURFACE PREP(CONCRETE)
SURFACE PREP(BOARD)
PRIMER
FIRST/TOP COAT
FINAL
SURFACE PREP(CONCRETE)
SURFACE PREP(BOARD)
PRIMER
FIRST/TOP COAT
FINAL
SURFACE PREP(CONCRETE)
SURFACE PREP(BOARD)
PRIMER
FIRST/TOP COAT
FINAL
SURFACE PREP(CONCRETE)
SURFACE PREP(BOARD)
PRIMER
FIRST/TOP COAT
FINAL
SURFACE PREP(CONCRETE)
SURFACE PREP(BOARD)
PRIMER
FIRST/TOP COAT
FINAL

PAINTING

BEDROOM 1 WALL

BEDROOM 1 CEILING

COMMON T&B WALL

COMMON T&B CEILING

BEDROOM 2 WALL

BEDROOM 2 CEILING

SURFACE PREP(CONCRETE)
SURFACE PREP(BOARD)
PRIMER
FIRST/TOP COAT
FINAL
SURFACE PREP(CONCRETE)
SURFACE PREP(BOARD)
PRIMER
FIRST/TOP COAT
FINAL
SURFACE PREP(CONCRETE)
SURFACE PREP(BOARD)
PRIMER
FIRST/TOP COAT
FINAL
SURFACE PREP(CONCRETE)
SURFACE PREP(BOARD)
PRIMER
FIRST/TOP COAT
FINAL
SURFACE PREP(CONCRETE)
SURFACE PREP(BOARD)
PUTTY (BOARD)
PRIMER
FIRST/TOP COAT
FINAL
SURFACE PREP(CONCRETE)
SURFACE PREP(BOARD)
PUTTY (BOARD)
PRIMER
FIRST/TOP COAT
FINAL

505 - BASIC SCOPE ONLY


STATUS BEFORE MCDC
NOT INSTALLED
RESTORE
RESTORE

AREA
3.35
3.50
2.62

RATE
270
270
270

AMOUNT
905.42
944.78
708.59

NO TOPPING
NO TOPPING
N/A

10.29
9.85
N/A

280
280
280

NO CHB/PLASTER
NO CHB/PLASTER
NO CHB/PLASTER

3.35
3.50
2.62

270
270
270

HMS - FOR RECTIFICATION


HMS - FOR RECTIFICATION
NO TILES
NO TILES
NO TILES
NO TILES
N/A
N/A
NO WOP
WITH MAIN DOOR THRESHOLD

28.74
3.48
3.34
7.65
3.63
8.49
0.00
0.00
2.82
5.00

280
280
280
280
280
280
280
280
280
280

2,881.51
2,756.60
905.42
944.78
708.59
8,046.98
975.30
934.53
2,141.89
1,016.06
2,377.09
790.27
1,400.00
-

10.56

120
180

1,266.84
1,900.26

8.78

120
180

1,053.63
1,580.45

11.73

120
180

0.00

120
180

1,407.60
2,111.40
1,085.40
1,085.40
491.63
491.63
538.20
538.20

INCOMPLETE
INCOMPLETE
NOT INSTALLED
INCOMPLETE
NOT INSTALLED
NOT INSTALLED
HMS -RESTORATION
HMS - RESTORATION
INCOMPLETE
N/A
N/A
N/A
VERIFY LAYOUT/RESTORE
NOT INSTALLED
NOT INSTALLED
NOT INSTALLED
NOT INSTALLED
NOT INSTALLED

7.24
3.28
3.59

150
150
150
150
150
150

VERIFY LAYOUT/RESTORE
NOT INSTALLED
VERIFY LAYOUT/RESTORE
NOT INSTALLED
N/A
N/A
NOT
NOT
NOT
NOT

INSTALLED
INSTALLED
INSTALLED
INSTALLED
N/A
NOT INSTALLED
NOT INSTALLED

2.65
0.00
0.00

150
150
150
150
150
150

1.00
1.00
1.00
1.00
0.00
1.00
1.00

3500
3500
3500
3500
3500
3500
3500

6.26

51.22
25.84

90
90

939.60
939.60
396.90
396.90
3,500.00
3,500.00
3,500.00
3,500.00
3,500.00
3,500.00
4,609.52
2,325.51

BARE
77.06
28.48
5.16

250
90
90

19,263.98
2,562.84
464.20

33.63
22.43
10.71

250
90
90

8,408.44
2,019.10
964.03

33.15
10.57
3.92

250
90
90

8,286.46
951.17
352.94

14.49
11.92
0.00

250
90
90

3,622.50
1,073.23
-

11.92
0.00
3.59

250
90
90

2,981.20
322.92

3.59

250

897.00

BARE

BARE

BARE

BARE

BARE

16.36
18.05

90
90

1,472.82
1,624.73

34.42
10.25
1.55

250
90
90

8,604.30
922.19
139.47

11.80
5.29
0.00

250
90
90

2,949.03
476.06
-

5.29
0.00
3.28

250
90
90

1,322.40
294.98

3.28
0
0
0
0
0
0

250
0
90

819.38
-

BARE

BARE

BARE

BARE

N/A

N/A

TOTAL:

0
0
0
0
0

250
0
90

250

Y
TOTAL

2,558.79

STATUS
DONE
DONE
DONE

5,638.11

ON GOING
ON GOING
N/A

2,558.79

DONE
DONE
DONE

%
100%
100%
100%

100%
100%
100%

WAITING FOR SUPPLY + RECTIFICATION


WAITING FOR SUPPLY + RECTIFICATION

17,682.11

9,320.18

DONE
DONE
DONE
DONE
DONE
DONE
DONE
DONE
DONE
N/A
N/A
N/A
PENDING WITH M/E/P/F
PENDING WITH M/E/P/F
PENDING WITH M/E/P/F

100%
100%
100%
100%
100%
100%

PENDING WITH M/E/P/F


PENDING WITH M/E/P/F

6,903.45

N/A
N/A

N/A
N/A

DONE

100%

21,000.00
PLAST/SURF PREP FOR SKCOAT
READY TO PROCEED

26,199.01
PLAST/SURF PREP FOR SKCOAT
PENDING WITH M/E/P/F

11,435.48
PLAST/SURF PREP FOR SKCOAT
READY TO PROCEED

11,269.59
PLAST/SURF PREP FOR SKCOAT
PENDING WITH M/E/P/F

4,926.60
PLAST/SURF PREP FOR SKCOAT
READY TO PROCEED

4,054.43
PLAST/SURF PREP FOR SKCOAT
PENDING WITH M/E/P/F

1,219.92

PLAST/SURF PREP FOR SKCOAT


READY TO PROCEED

11,701.85
PLAST/SURF PREP FOR SKCOAT
PENDING WITH M/E/P/F

4,010.68
PLAST/SURF PREP FOR SKCOAT
READY TO PROCEED

1,798.46
PLAST/SURF PREP FOR SKCOAT
PENDING WITH M/E/P/F

1,114.35

N/A

N/A

N/A

N/A

N/A

N/A

143,391.80

TOTAL:

PROGRESS BILLING
905.42
944.78
708.59

905.42
944.78
708.59

1,266.84
1,900.26
1,053.63
1,580.45
1,407.60
2,111.40
N/A
N/A
N/A

N/A
N/A
3,500.00

N/A

N/A

17,937.76

You might also like