Process Design Basis
Process Design Basis
Engineering
Practice
How to Prepare a
Process Design Basis
Anthony Pavone
SRI Consulting
their format
neers
structure requirements
Brownfield-site compatibility
Environmental, safety and vessel-
Objectives, products,
control, management
TABLE 1.
Accounting records
Tie-in list
Correspondence records
Change orders
Input/output diagram
Firewater grid
Insurance
Confidentiality/nondisclosure agreement
One-page instrumentation
specification sheets
Mutual indemnification
Vessel drawings
Taxes
Fleet vehicles
Tankage capacity
UL)
The process control philosophy to be
used in the finished plant, as well as
the type of system to be considered for
supervisory control and data acquisition (SCADA) system, should be specified in terms of either performance or
specific selection by the owner. The
level of data communication between
the process control function, the onsite
engineering and the maintenance facilities is also to be defined. In many
cases, an operating company will standardize on one particular process-control vendor in order to avoid the need
for staff cross-training. If a vendor has
been designated by the owner, this
should of course be specified in the design basis document.
With respect to the management of
the project, the process-design-basis
document should identify the owners
authorized person for approving all
design activities. The management
chains of command on both the owners side and the engineering organizations side should likewise be spelled
out. Approval mechanisms (embodied
in, for instance, change orders) for all
activities (changes inside scope and
changes outside scope) that would
incur additional cost for the project are
defined. The nature and format of the
design deliverables are to be defined
49
TABLE 3.
Engineering Practice
and reinforcing steel, insulation,
coatings, and welding rod)
Standardized piping line lists and
tie-in lists
Material balance formats
Equipment and piping one-page
process spec sheets
Pressure vessel and tank drawings
Electrical one-line drawings
Control loop drawings
The size paper to be used for reports
The size paper to be used for drawings
Type-font and letter size
Requirement and format for vendor
cuts (paper drawings, pictures, descriptive material, dimensions and
specifications of specific equipment
provided by a specific vendor)
Owners are also entitled to demand
the use of industry-wide, non-proprietary computer software for generating engineering deliverables. One
reason for this standardization is to
allow computerized translation from
one software package to another. This
entitlement pertains to the software
used for planning and scheduling,
cost estimating, process design, piping
network analysis, process simulation,
computer-aided 2D and 3D design, and
the preparation of written reports.
Project communication
CONTRACT COMMUNICATION
SPECIFICATIONS
Documents the goals and objectives
of the project
Specifies the scope of the job
Identifies the members of the team
and their coordinates
Establishes the formats for hard-copy
and electronic project deliverables
Defines the roles and responsibilities
of each team member
Defines the formats of communication
elements, data
Defines what information is to be kept
and archived
Defines binding contractual terms
Formalizes project schedule and
budget
munication involving the plant operating personnel after the plant is up and
running is a separate issue also to be
addressed in the process design basis
document, as discussed below.)
OF PLANTSITE
Subsoil characteristics
Existing facilities that may need to be
demolished or removed
Existing facilities that are to be used/
debottlenecked
Climate
Meteorology
Design for storm intensity (usually 100year basis)
Wind design requirements
Floodplain design requirements
Earthquake design criteria
Sandstorm propensity and intensity
Proximity to airports that would affect
equipment height
Contaminated soils
Snow load and intensity
Corrosive ambient air (e.g., seawater
spray, acid, chlor/alkali environment)
TABLE 5. UNUSUALLY HIGH
Economic
factor
Design
impact
High cost
of land
Equipment spacing
Cold
climate
High water
cost
High
Max. conversion/max.
feedstock/
recycle/custody transproduct cost fer metering
High
labor cost
High
capital cost
Materials selection/
process intensification/
design standards
High environjmental
liabilities
Zero discharge/onsite
treatment & disposal
dards
Controlled-substance
policy and
standards
Policy and reporting requirements
for bribery (Business Roundtable
standards)
The site chosen for the production facility is to be defined exactly. Where
is it? Why was it chosen? What are
the particular characteristics of this
site that have led the owners man-
TABLE 6.
TABLE 7.
TABLE 8.
Process incinerator
Emergency planning/evacuation
Obsolete-equipment storage
Fugitive emissions
Cafeteria
Sanitary facilities and smoking sheds
Fencing and plant security
Fire house, fire water, deluge and
monitors
Emergency showers, eye wash
Process flares and flare headers
Utilities
Incineration requirements
Hazardous solid waste treatment and
disposal
Combustion gas low-NOx burners
and two-stage lean-burn systems
Process gas treatment prior to venting
Tank breathing loss treatment before
venting; reqts. for floating roofs
Flare tip design, steam control, and
flare opacity requirements
Level of treated wastewater recycle
Cooling-water system management
51
Engineering Practice
TABLE 10.
TABLE 9.
MAJOR SAFETY-RELATED
ELEMENTS
Formal statement of management
safety philosophy
Process safety management system
Accountability
Process safety objectives and goals
Process knowledge
Technical documentation requirements
HAZOP analysis
Change-order management
Construction punch-listing
Available steam
Environment, safety
Operation, maintenance
shopped out
Turndown capability: The plant
is designed for a nameplate capacity (in, for instance, metric tons per
year) at a particular service factor
(operating hours per year divided by
8,760 hours per year). Although the
plant is designed for optimal operation at a particular throughput rate
(stream-day flowrate), business conditions may dictate that the plant run
at substantially lower-than-design
rate for an indefinite period of time.
This turndown ratio should be specified by the owner. There may also be
short-term periods (days, not weeks)
in which the plant should be capable
of running above nameplate capacity in order to recover from outages,
or build inventory in preparation for
turnaround. This turnup ratio should
also be specified.
Working capital: The owner must
provide instructions to the engineering organization as to the design
basis philosophy for the working
capital to be maintained in the plant.
Such working capital includes: the
number of days storage for feedstock,
intermediate and final products; the
additives inventory, in-process and
in-storage catalyst quantities and
spare-catalyst charge requirements;
and the inline equipment spares,
warehoused equipment spares, parts
spares, and construction/maintenance equipment. The owner should
provide instructions on the choice of
purchased equipment versus leased
equipment, especially for fleet and
construction vehicles, distributor
held spares and OEM held spares.
Communication system: The owner
should provide guidance as to the
preferred system for in-plant and
ex-plant communication for the completed and operating facility, including both fixed-line and mobile-line
capability and capacity. If a system operator is required, the owner
should specify the reporting requirements for that operator (usually part
of plant security). External communications capabilities with the owners
headquarters, and with local law enforcement, environmental regulators,
coast-guard and marine officials,
and governmental officials should
Project execution
in Table 10.
Edited by Nicholas P. Chopey
Author
Anthony Pavone manages single-client project
engagements for SRI Consulting (4300 Bohannon Dr., #200, Menlo Park, CA 94025; Phone:
+1 650 384 4311; Fax: +1 650 384 4275; email:
[email protected]). He has been with
SRIC for 16 years; previously, he spent 10 years
with Exxon and 8 years in design and construction with Badger and Parsons. His experience
is subdivided equally among consulting, design
and plant operations; this work has included
petrochemical-plant and pipeline financial
analysis, process and project design, construction management and startup, plant operations,
capital asset valuation, feasibility studies, feedstock purchases, and market pricing. Tony has
also been teaching the chemical engineering
process-design course at Stanford University
since 1994. He has published articles in Chemical Engineering, Chemical Processing, Journal of
Systems Management, Cogeneration and Competitive Power Journal, Chemistry and Industry,
Petroleum Technology Quarterly, and Signal
Magazine. A licensed professional engineer, he
holds B.S. and M.S. degrees in chemical engineering from Rensselaer Polytechnic Institute,
and an M.B.A. from the Massachusetts Institute
of Technology.
Circle 24 on p. 78 or go to
adlinks.che.com/5830-24