Introduction To Project Management - Report
Introduction To Project Management - Report
Management
Definition of a project
Project as a temporary endeavor undertaken to create a unique product,
service, or result. The temporary nature of projects indicates a definite
beginning and end. The end is reached when the projects objectives have
been achieved or when the project is terminated because its objectives
will not or cannot be met, or when the need for the project no longer
exists.
Characteristics:
On any project, you will have a number of project constraints that are
competing for your attention. They are cost, scope, quality, risk,
resources, and time.
Cost is the budget approved for the project including all necessary
Project Management
Project Management attempts to organize and systemize the tasks in a
project to minimize the number of surprises that one may encounter.
Project management and project managers concern themselves with the
following key areas:
Scheduling
Budgeting
Managing resources
Tracking and reporting progress
Project scheduling using the PERT/CPM method involves the three basic phases :
Planning
Scheduling
Constructing a time chart showing the start and finish times for each
activity as well its relationship to other activities in the project.
Pinpointing the critical activities that require special attention if the project
is to be completed on time.
Show the amount of slack/float times on non-critical activities.
Controlling
Using the network diagram and the time chart to make periodic progress
reports.
Updating the network.
CPM Calculations
A critical activity is an activity that has no leeway in determining its start and
finish times. If a critical activity runs late, then the entire project will run late. A
noncritical activity is an activity that allows some scheduling slack, meaning it
can be advanced or delayed without affecting the completion time of the project.
An event is defined as a point in time when activities are completed and another
activity is started. In terms of a network, an event corresponds to a node.
Ej = Earliest occurrence time of event j
Lj = Latest occurrence time of event j
Dij = Duration of activity
The critical path calculations involve two passes:
The forward pass determines the earliest occurrence times of the events and
the backward pass calculates their latest occurrence time.
Forward Pass (Earliest Occurrence Times):
The computation starts at node 1 and advance recursively to end node n.
Step 1:
Set E1=0 (indicates the project starts at node 1 and time 0). The first
node of the network will never have any nodes going into it, so that is why it will
always be zero.
General step j:
Step 3: Calculate Ej for every node until you reach the final node, n.
Backward Pass (Latest Occurrence Times Lj)
Once you have computed the forward pass, the backward pass computations
start at the final node n and end at node 1.
Step 1: Set Ln= En (indicates that the earliest and latest occurrence of the last
node of the project are the same.
General step j:
Step 3: Calculate Ej for every node until you reach the final node, n.
PERT CALCULATIONS
Pert differs from CPM in that it bases the duration of an activity on three
estimates:
The PERT method was motivated by the assumption that the activity time was a
random variable with a beta distribution. Unlike the normal distribution, which
has an infinite range and is symmetrical, the beta distribution has a minimal and
maximum value, and is capable of assuming a wide variety of shapes. A typical
beta distribution can be seen in the Fig. 1
Fig. 1
The purpose of PERT is to analyze the probability that a critical path will be
finished by any given time. The analysis proceeds as followed:
Let T equal the total time that will be taken by the activities on a critical
path.
Find the probability that the value of T will turn out to be less than or equal
to any specified value of interest.
o The activity times are independent random variables. This is a valid
assumption for most PERT networks.
o The random variable T has an approximately normal distribution.
This assumption relies on the central limit theorem, which in broad
terms states that the sum of independent random variables is
approximately normally distributed.
To find the variance of a path, we add all the variance for a path we wish to take.
For example if we have a path consisting of activities starting at activity A and
finishing at activity D, such that, A BCD, and we wish to find the probability
that we can complete activity D within 5 days, we will need to know the standard
deviation of the path, but to do that we must know the variance of the path. The
variance of the path is just calculated by adding the variance of each activity.
Var T
Finally, we now need to convert T to a standard normal random variable, Z, in
the usually way:
Z=
T-
Recall that is mean (the expected completion time). We know use the Z score
to calculate the probability.
MS Project
Initiation Phase: During the initiation phase, the project objective or need
is identified. A feasibility study is conducted to investigate whether each
option addresses the project objective and a final recommended solution is
determined. Once the recommended solution is approved, a project is
initiated to deliver the approved solution and a project manager is
appointed. The major deliverables and the participating work groups are
identified, and the project team begins to take shape. Approval is then
sought by the project manager to move onto the detailed planning phase.
Planning Phase: The project solution is further developed in as much
detail as possible and the steps necessary to meet the projects objective
are planned. In this step, the team identifies all of the work to be done.
The projects tasks and resource requirements are identified, along with
the strategy for producing them. Once the project team has identified the
work, prepared the schedule, and estimated the costs, the three
fundamental components of the planning process are complete.
Implementation Phase: The project plan is put into motion and the work
of the project is performed. It is important to maintain control and
communicate as needed during implementation. Progress is continuously
monitored and appropriate adjustments are made and recorded as
variances from the original plan. In any project, a project manager spends
most of the time in this step. During project implementation, people are
carrying out the tasks, and progress information is being reported through
regular team meetings. The project manager uses this information to
maintain control over the direction of the project by comparing the
progress reports with the project plan to measure the performance of the
project activities and take corrective action as needed.
Closing Phase: The emphasis is on releasing the final deliverables to the
customer, handing over project documentation to the business,
terminating supplier contracts, releasing project resources, and
communicating the closure of the project to all stakeholders. The last
remaining step is to conduct lessons-learned studies to examine what
went well and what didnt.
Project Scheduling
1. Defining Activities/Tasks
It documents the specific activities needed to fulfill the deliverables.
2. Task List
The project activity list is a list of everything that needs to be done to
complete your project, including all the activities that must be
accomplished to deliver each work package.
3. Milestones
All of the important checkpoints of your project are tracked as milestones.
Bar Rollup
Calendar
Network Diagram
Detail Gantt
Gantt Chart
Levelling Gantt
Relationship Diagram
Resource Allocation
Resource Graph
Resource Sheet
Tracking Gantt
5. Critical Path
The critical path describes the sequence of tasks that would enable the
project to be completed in the shortest possible time. It is based on the
idea that some tasks must be completed before others can begin. A
critical path diagram is a useful tool for scheduling dependencies and
controlling a project.
Resource Planning
Resources are the people, supplies and equipment that enables you to complete
the tasks in the project. In MS Project
One can keep track of the tasks that are being performed by resources.
One can identify potential resource shortages that may lead to missing of
scheduled deadlines thus leading to the extension of the project.
One can identify underutilized resources.
One can identify the cost of each task and that of the project as a whole.