Hw5-5S: Decision Theory - Online Homeworkquestion

The document describes a firm deciding on the size of a stamping plant to build based on uncertain future demand. There is a 30% chance of low demand and 70% chance of high demand. Building small would yield $40M or $52M profits depending on demand. Building medium could yield $12M or $45-50M. Building large could yield -$30M or $75M. The firm must choose the size and calculate the expected payoff.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
305 views

Hw5-5S: Decision Theory - Online Homeworkquestion

The document describes a firm deciding on the size of a stamping plant to build based on uncertain future demand. There is a 30% chance of low demand and 70% chance of high demand. Building small would yield $40M or $52M profits depending on demand. Building medium could yield $12M or $45-50M. Building large could yield -$30M or $75M. The firm must choose the size and calculate the expected payoff.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

HW5-5S: Decision Theory Online HomeworkQuestion

A firm must decide whether to construct a small, medium, or large stamping plant. A consultant's report
indicates a 0.30 probability that demand will be low and a 0.70 probability that demand will be high.
If the firm builds a small facility and demand turns out to be low, the net present value will be $40 million. If
demand turns out to be high, the firm can either subcontract and realize the net present value of $52 million or
expand greatly for a net present value of $48 million.
The firm could build a medium-size facility as a hedge: If demand turns out to be low, its net present value is
estimated at $12 million; if demand turns out to be high, the firm could do nothing and realize a net present
value of $45 million, or it could expand and realize a net present value of $50 million.
If the firm builds a large facility and demand is low, the net present value will be -$30 million, whereas high
demand will result in a net present value of $75 million.
a. Draw a decision tree for this problem.
b. Which size of facility the firm should construct? What is the expected payoff for this alternative?
a. Conclusion: Build a small facility, with an expected payoff of $48.4 million.
b. Conclusion: Build a large facility, with an expected payoff of $48.4 million.
c. Conclusion: Build a medium facility, with an expected payoff of $58.6 million.

HW6-Ch16-Scheduling Online Homework Question

The following table contains information concerning four jobs that are awaiting processing at a work center.
Job

Processing Time Due Date (days from


(days)
present time)

17

14

12

20

10

15

FCFS: What is the makespan?


a. 37 days
b. 64 days
c. 90 days
SPT: What is the average flow time?
a. 8.25 days
b. 19.75 days

c. 2.13 days
EDD: What is the average job tardiness?
a.26.25 days
b. 10.25 days
c. 6.50 days