7 March 2013 Minutes of Meeting Project: Resource Optimization

The minutes summarized a meeting about optimizing resources for a project monitoring a field mouse system connected to pumps and sensors. The group discussed innovating the current setup into a remote diagnostic tool using existing resources. Plans were made to assess sensor needs, create a GUI with pump information for diagnostics, enhance protocols and text pump data like status, voltages and currents. Data would be gathered manually through event logs and automatically from instruments and PLCs. Piloting the changes at Pasay plant was slated for March 11 to May.

Uploaded by

Ready Epino
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
53 views1 page

7 March 2013 Minutes of Meeting Project: Resource Optimization

The minutes summarized a meeting about optimizing resources for a project monitoring a field mouse system connected to pumps and sensors. The group discussed innovating the current setup into a remote diagnostic tool using existing resources. Plans were made to assess sensor needs, create a GUI with pump information for diagnostics, enhance protocols and text pump data like status, voltages and currents. Data would be gathered manually through event logs and automatically from instruments and PLCs. Piloting the changes at Pasay plant was slated for March 11 to May.

Uploaded by

Ready Epino
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

7 March 2013

Minutes of Meeting
Project: Resource Optimization
Members:
Shaun
Sherwin
Aeus
Randy
Atoy
Pete
Marvin
Orly
Greg
Current Set-up

Field mouse using the local


SCADA/PLC connected to the PI
System

Next Phase

Innovate the current setup to be


used as a remote diagnostic
tool for plant and pump stations
using the current resources
Resource optimization

How?
Plans:
1. Pete - Assessment for sensors
needed
2. Atoy GUI for the pumps
includes information that will
make a diagnostic tool

3.
4.
5.

6.

a. Current per phase


b. Power
c. Voltage per phase
d. Vibration
e. Winding Temperature
f. Bearing Temperature
g. Power factor
Randy enhancements
Shaun protocols
Sherwin, Greg Texting of:
a. Pump Information such as
Status, Voltage, Current,
Etc.
b. Pumps alarm will be sent
right away.
Two ways of data gathering
a. Manual
i. EventFrames
activities by the
maintenance and
operators
b. Automatic
i. Instruments and
PLC

Advantages
1. Plant Efficiency (sample: Pasay)
2. Remote diagnostic (information
on each pump)
3. Quick asset assessment
(remotely)
Timeline
Pilot (Pasay): March 11 1st week of
May