This document outlines the chronology of schedule discussions between a contractor and company for an engineering and construction project in Malaysia. It details 9 key dates where letters and submissions were exchanged regarding the baseline schedule. The main points of discussion were the start date, installation rates for a 20" pipeline, and duration. The company initially specified a 38.95 day baseline for one pipeline but later agreed to increase it to 47 days based on technical justifications from the contractor.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
41 views

Engineering & Construction - Malaysia: TL Offshore SDN BHD

This document outlines the chronology of schedule discussions between a contractor and company for an engineering and construction project in Malaysia. It details 9 key dates where letters and submissions were exchanged regarding the baseline schedule. The main points of discussion were the start date, installation rates for a 20" pipeline, and duration. The company initially specified a 38.95 day baseline for one pipeline but later agreed to increase it to 47 days based on technical justifications from the contractor.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 4

TL OFFSHORE SDN BHD

Baseline Schedule Chronology

Engineering & Construction - Malaysia

AGENDA
1. INTRODUCTION
2. DELAY COMPENSATION SCHEME (DCS)
3. HRF START DATE
4. MOBILIZATION DATE
5. FUEL COMPENSATION
6. COST PLUS ISSUE (AUT / SURVEY / RIGGING)
7. OTHERS

2
SSB Commercial Meeting
#08

BASELINE SCHEDULE
CHRONOLOGY
N
o.

Date

1.

12th Feb
2014

Reference
CONTRACTORs
Letter L0015

Remarks

2.

27th Feb
2014

CONTRACTORs
Letter L0029

3.

5th March
2014

COMPANYs Letter
F015

Submission of Baseline Schedule Rev. 01


CONTRACTOR requested for start date on 15th
March 2014
Proposed layrate for 20 F23R-A/F14DR-A is 80
joints per day
Overall duration maintains as per previous
submission with re-sequencing of activity
Proposed layrate for 20 F23R-A/F14DR-A is
maintained 80 joints per day
COMPANY take note on the for work to
commence on 15th March 2014
COMPANY stated that based on CONTRACT
installation norm computation, the duration
for 20 F23R-A/F14DR-A is 38.95 days

4.

11th March
2014

COMPANYs Letter
F017

COMPANY advised CONTRACTOR to use 38.95


days as a Base Duration for installation of 20
F23R-A/F14DR-A

5.

18th March
2014

CONTRACTORs
Letter L0057

CONTRACTOR submitted technical clarification


and justification for the proposed layrate of 80
joints per day

6.

20th March
2014

COMPANYs Letter
F027

COMPANY
agreed
on the disruption
due to
3
SSB
Commercial
Meeting
#08
changes of pipeline wall thickness, pipeline

BASELINE SCHEDULE
CHRONOLOGY
N
o.

Date

7.

6th May 2014

Reference
CONTRACTORs
Letter L0109

Remarks

CONTRACTOR submitted schedule rev. 03C


which was revised due to additional constraint
of F23 shutdown window
Proposed layrate for 20 F23R-A/F14DR-A is
maintained 80 joints per day

8.

15th May
2014

COMPANYs Letter
F050

F23 shutdown is not additional constraint as


informed during kick-off meeting, schedule
discussion and weekly progress meeting.

9.

27th May
2014

COMPANYs Letter
F054

COMPANY agreed that the duration for


installation of 20 F23R-A/F14DR-A pipeline to
be increase from 38.95 days to 47 days.

4
SSB Commercial Meeting