100% found this document useful (1 vote)
672 views40 pages

Schedule Risk Analysis

This document provides an overview of schedule risk analysis (SRA). It discusses how SRA can quantify the impacts of uncertainties and risks on a project schedule using probabilistic techniques. The key steps in SRA involve developing a risk register, building a schedule risk model that incorporates uncertainty distributions and correlations between risks, running Monte Carlo or Latin Hypercube simulations to calculate probabilistic schedule outcomes, and analyzing the results. SRA provides a more accurate understanding of project completion dates than deterministic scheduling alone.

Uploaded by

surajthakur
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
672 views40 pages

Schedule Risk Analysis

This document provides an overview of schedule risk analysis (SRA). It discusses how SRA can quantify the impacts of uncertainties and risks on a project schedule using probabilistic techniques. The key steps in SRA involve developing a risk register, building a schedule risk model that incorporates uncertainty distributions and correlations between risks, running Monte Carlo or Latin Hypercube simulations to calculate probabilistic schedule outcomes, and analyzing the results. SRA provides a more accurate understanding of project completion dates than deterministic scheduling alone.

Uploaded by

surajthakur
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 40

Schedule Risk

Analysis
(SRA)
Pedram Daneshmand
Associate Director
Blue Visions Management Pty Ltd
Slide 1 of 18

Content
Project Time Management
Risk & Opportunities
Project Risk Management
Schedule Risk Analysis
Results Review
Action Plan

Slide 2 of 18

Project Time Management


History
Every project must be managed against a
schedule;
Project Scheduling has been around a
long time;
Scheduling is one of the most widely
practiced project management disciplines
(Archibald and Villoria 1967).
Project Time Management includes the
processes required to accomplish timely
completion of the project (PMBOK, 2004).
Slide 3 of 18

Project Time Management


Process

Activity Definition
Activity Sequencing (logic)
Activity Resource Estimating
Activity Duration Estimating
Schedule Development
Schedule Control

(PMBOK, 2004)

Slide 4 of 18

Project Time Management


Schedule Development
The Schedule Development process
includes selecting a scheduling Method,
scheduling Tool, incorporating project
specific data within that scheduling tool
to develop project specific schedule
Model, and generating Project Schedule.
(PMI-PS for Scheduling, 2007)

Slide 5 of 18

Schedule Development
Methods
Logic-based Scheduling Methods (LSM)

Deterministic Techniques

E.g. Critical Path Method (CPM), Resource


Optimisation, Critical Chain Method (CCM), etc.

Stochastic Techniques

E.g. Probabilistic Evaluation and Review Technique


(PERT), PNET, Monte Carlo Simulation (MCS), etc.

Repetitive Scheduling Methods (RSM)

Line of Balance (LOB)


Flowline Method
Slide 6 of 18

Schedule Development
Inputs
Planners develop the project schedule by
using:

Available templates;
Available
quantities,
resources
and
productivity rates;
Available work/scope statements;
Available construction logic; and
these add uncertainties to schedule
Other All
assumptions/documents
e.g. calendars,
and reduce the confidence level. What
PMP, etc.
about risks and opportunities in the
schedule?

Slide 7 of 18

Schedule Development
Outputs
The outputs of Schedule Development
process are:

(Deterministic)
(Deterministic)
(Deterministic)
(Deterministic)

Project Schedule;
Schedule Model Data
Schedule Baseline
Resource Requirements

With all those uncertainties in the inputs


and the possible risks and opportunities in
the schedule, the question is, how
confident we are in this schedule?
Slide 8 of 18

Schedule Development
Major Challenges
Uncertainties due to assumptions;
Logic, constraints, resources, calendars
and activity durations are not always
clear and agreed;
What-If Scenarios; and
Risks and Opportunities
To have a realistic schedule, Schedule
Development process should be improved
by using Schedule Risk Analysis. In other
words Project Time Management and
Project Risk Management need to
be
Slide 9 of 18

Schedule Development
Risks & Opportunities
Every schedule has
uncertainties/assumptions.
EveryEffect
schedule
on project has risks and
(positive or negative)
opportunities.
Time
Scope
Quality

Cost

So, Risks and


Opportunities should be
managed effectively to
minimize the surprises!!
Slide 10 of 18

Project Risk Management


Process
AS/NZS ISO 31000:2009

Analyse Risks
Evaluate Risks

MONITOR AND REVIEW

Identify Risks

RISK ASSESSMENT

COMMUNICATE AND
CONSULT

Establish Context

Treat Risks

Slide 11 of 18

Project Risk Management


Risk Assessment
Risk Assessment include

Risk Identification (both Uncertainties and


Events)
Risk Analysis
Qualitative
Quantitative (Schedule Risk Analysis or SRA)

Risk Evaluation
The goal is to have a better
understanding of risks / opportunities
and their overall impact on project
completion date. This will bridges the
gap between traditional CPM schedule
Slide 12 of 18

Project Risk Management


Risk Analysis
Risk Analysis is the process to
comprehend the nature of risks (or
opportunities) and to determine the level
of risks (or opportunities) in the schedule

Risk analysis provides the basis for risk


evaluation
and
decisions
about
risk
treatment; and
By Schedule
Risk Analysis
(SRA), we
Risk Analysis
includes
risk estimation.
model the risks and opportunities
(uncertainties and events) within the
complexity of the interrelationships
between the various tasks of theSlide 13 of 18

Schedule Risk Analysis


(SRA)
SRA is a probabilistic analysis to quantify
the impacts to a project, program or
portfolio as a result of carrying
uncertainties and/or risks and
opportunities or to simulate the possible
what-if scenarios.
Relying on a accurate most likely
schedule as a base, SRA takes the
project time management to the next
level of accuracy and confidence.
Slide 14 of 18

Schedule Risk Analysis


Overview

Available data gathering


Schedule Review
Technical Research
Risks & Opportunities Register

Both Uncertainties and Events

Schedule Risk Model


Simulation
Results and Discussions
Slide 15 of 18

Schedule Risk Analysis


Data Gathering
Required information for a SRA

Well-developed project scope;


Quality estimate excluding contingency and
escalation;
Schedule reflecting the estimate;
Risk management policy/processes in your
organisation;
Risk checklist presenting typical risks and
opportunities;
Risk & Opportunities Template;
16 of 18
Schedule Risk Templates/Models;Slide
and

Schedule Risk Analysis


Schedule Review
How
to
schedule?

review

the

deterministic

Validation of all quantities (most likely);


Validation of all productivity rates (most
likely);
Validation of all durations (most likely);
Minimum number of constraints;
Complete logic network;
Reasonable duration for tasks; and
Reasonable Critical Path.
Slide 17 of 18

SRA Schedule Review


Sample Report
Confidential

Slide 18 of 20

Schedule Risk Analysis


Technical Research
When the team is confident that the
project deterministic schedule reflects
the most likely case, the technical
research can begin.

Historical data research


Interviews
Internet searches, etc.

Issues may include items such as site


access, Environmental Approvals,
inclement weather, construction
productivity concerns, construction
modifications, equipment and material
Slide 19 of 18

Schedule Risk Analysis


Risk Register
The Technical Research will enable the
schedule risk analyst to complete the
Risk Register file:

The identified risks & opportunities


Likelihood of the identified risks and
opportunities
Impacted activities
Schedule and/or Cost Impact/s
Schedule and/or Cost Variations
Correlation of risks and opportunities to one
Slide 20 of 18
another

Schedule Risk Analysis


Risk Register (Sample)
Confidential

Slide 21 of 18

SRA Risk Register (Sample)


Rain details

Slide 22 of 18

SRA Risk Register


Quality Check
Major risks and opportunities been
identified;
The
likelihood
and
impacts
been
assessed;
Risk Matrix aligned with the companys
risk management policy;
Impacts checked against the allocated
calendars;
Correlations
between
risks
been
Slide 23 of 18
identified;

SRA Schedule Risk Model


Uncertainties & Events
Developing the Schedule Risk Model
involves modelling the potential impacts
and the likelihood of the risks and
opportunities on the project and then
applying those to the schedule.
Two aspects of the risks and opportunities
should be modelled within the schedule:

Estimate Uncertainties (Optimistic, Most


Likely and Pessimistic)
Events including probabilistic branching
Slide 24 of 18

SRA Schedule Risk Model


Probability Distributions
Probability Distribution is a way to
indicate the likelihood of values between
the optimistic and pessimistic values.
Probability Distribution can be:

Uniform (flat),
Normal (bell shaped),
Beta (skinny bell shaped),
Triangle (pyramid shaped), or
Customised (user defined).
Slide 25 of 18

SRA Schedule Risk Model


Probability Distributions

Slide 26 of 18

SRA Schedule Risk Model


Special Conditions
Special conditions which needs extra
attention:

Probabilistic Branching which considers the


situation where the outcome of an event can
cause in two or multiple possible courses of
activities.
Correlation between risks
Positive Correlation: occurs when one risk goes
higher, so must the other.
Negative or Adverse Correlation: occurs when one
risk increases, the other must decrease.

Slide 27 of 18
Inclement Weather or other external

SRA Schedule Risk Model


Inclement Weather
Inclement Weather can be a significant
factor in a project schedule. Very often
there is good data available but
understanding the impact on the
schedule is challenging.
A proper modelling will allow the team to
define risk assessment criteria for
inclement weather conditions in the
schedule, and include these uncertain
weather conditions in the risk analysis.
Slide 28 of 18

SRA Schedule Risk Model


Inclement Weather
There are two distinct ways of defining
inclement weather events:

Event with results in an uncertain number of


non working days scattered throughout a
period, e.g. rain or snow.
Event with results in a single block of non
working time with a probability of occurrence,
e.g. chance of a hurricane in a period.

Slide 29 of 18

Schedule Risk Analysis


Simulation Methods
The SRA performs multiple simulations of
the project using random samplings of
the relevant risks and opportunities
considering their probability and impact.
Two popular methods:

Monte Carlo Simulation (MCS) faster method


but has a larger possibility of sampling error
Latin Hypercube Sampling (LHS) slower
method but less sampling errors
Slide 30 of 18

Schedule Risk Analysis


Simulation Process
Analysis does the simulation through
multiple samplings or iterations.
Each iteration is picking one sample point
from each activity and calculating the
project outcome.
User defines the number of iteration (e.g.
1000, 5000, etc) depending on the
complexity of the project and its risk
model.
Slide 31 of 18

Schedule Risk Analysis


Simulation Tools
Main tools been widely used for
simulation are:

Primavera Risk Analysis (previously known as


Pertmaster)
@Risk for Project
Crystal Ball
The next slides are presenting results
from simulations by using Primavera
Risk Analysis.
Slide 32 of 18

Schedule Risk Analysis


Sample Programme
Confidential

Confidential

Slide 33 of 18

Schedule Risk Analysis


Finish Date Histogram
Confidential

Slide 34 of 18

Schedule Risk Analysis


Histogram & Statistics
Confidential

Slide 35 of 18

Schedule Risk Analysis


Criticality Index Tornado
Confidential

The Criticality Index of


an activity is the
proportion of the
iterations in which the
activity was critical.
Usually more attention
will be given to the
activities with Criticality
Index of more than
50%.

Slide 36 of 18

Schedule Risk Analysis


Criticality Path Report
Confidential

The Criticality Path


Report highlights the
path through the
project containing the
tasks with the highest
Criticality Index values.
Percent Criticality is the
probability that an
activity will be on the
critical path; this
indicates the relative
importance of the
activity to other
Slidein
37 of
18
activities
the

Schedule Risk Analysis


Criticality Distribution Profile
Confidential

Criticality Distribution
Profile plots the spread
of Criticality Index in a
project which gives an
indication of the
number and threat of
near to critical path.
A high percentage
(more than 40%)
indicates a relatively
tight programme.

Slide 38 of 18

Schedule Risk Analysis


Action Plan
The accuracy of the SRA outcomes
should be improved through a number of
iterations of this process.
Based on the initial results, the team
should:

Review the risk register and make modifications where


require;
Make changes to the risk model accordingly;
Run the simulation again and repeat the process to
achieve the most cost-effective risk mitigation plan;
Finalise the Risk Action Plan as well as the Contingency
Slide 39 of 18
Plan; and

About the Author


Pedram Daneshmand, Associate
Director
Blue Visions Management
Pedram is a civil engineer with over 15 years experience in the construction industry. He is
highly skilled and technically proficient in many aspects of construction including
Programming, Programme Performance Measurement, Quantitative Risk Analysis, Contract
Management, Schedule Risk Analysis (SRA), Cost Risk Analysis (CRA), Project
Monitoring & Controls (PMC) Systems, Earned Value Performance Measurement technique
(EVPM) and POW (Program of Work) Planning & Controls.
As an industry innovation award winner for his programming and risk analysis skills,
Pedram is currently an Associate Director with Blue Visions Management leading a team of
planning and controls professionals within the infrastructure sector. With more than 15
articles in the professional conferences/journals, he is been regularly invited to the technical
presentations as one of the industry leaders in his field.
Slide 40 of 18

You might also like