Acceptance Sampling Procedures
Acceptance Sampling Procedures
Decide whether to reject the whole lot based on the inspection results
Type of sample
An acceptance plan is negotiated and decided by Producer (supplier) & consumer (buyer)
must negotiate.
Example 1:
An inspector takes a sample of 20 items from a lot. His policy is to accept a ot if no more
than 2 defectives are found in the sample. Assuming that a lot is 5 % defective, what is
the probability that he will accept the lot or reject the lot?
In this example, we have
20!
0.05 0 (1 0.05) ( 200) = 0.3585
0!(20 0)!
f (1) =
20!
0.051 (1 0.05) ( 201) = 0.3774
1!(20 1)!
f ( 2) =
20!
0.05 2 (1 0.05) ( 20 2) = 0.1887
2!(20 2)!
The lot is disposed off in shorter time so that scheduling and delivery are improved
The problem of monotony and inspector error induced by 100 percent inspection is
minimized
Rejection (rather than sorting) of nonconforming lots tends to dramatize the quality
deficiencies and to urge the organization to look for preventive measures
Proper design of the sampling plan commonly requires study of the actual level of quality
required by the user. The resulting knowledge is a useful input to the overall quality
planning.
The acceptance sampling procedure can be represented as follows.
Ho False
Accept H0
Accept the lot
Correct Decision
Type II Error
Accepting a Poor
Quality Lot
Reject H0
Reject the lot
Type I Error
Rejecting a Good
Quality Lot
Correct Decision
Decision
Total cost
No inspection
NpA
Sampling
nI + (N-n)pAPa + (N-n)(1-Pa)I
100% inspection
NI
1.
2.
3.
Double-sampling plans
One of the following decisions, based on the information in the initial sample, is
made
Accept the lot
Reject the lot
Take a second sample
If a second sample is taken, information in both the samples is used to
decide acceptance or rejection
Multiple sampling-plans
Module 21
Example 2:
N=10000 , n = 89 and c=2
The probability of acceptance for different values of p, fraction defective are shown in the
following table.
Comparison of two different OC curves with regard to their discriminatory power is done in the
following figure.
The
and
The following figure shows the effect of sample size on the OC curves. It is noted that the
discriminatory power of the sampling plan increases with sample size.
Indifference Quality Level (IQL) is a quality level somewhere between the AQL and
LQL. It is frequently defined as the quality level having a probability of acceptance of 0.5
for a given sampling plan
Average Outgoing Quality (AOQ) is the average quality of rejected and accepted lots
Type-A and Type-B OC Curves:
Type-B OC curve is constructed with the assumption that the sample is taken from a
large lot or from a stream of lots selected at random from a process.
Binomial distribution is the exact probability distribution for calculating the probability
of acceptance.
Type-A OC curve is used to calculate probability of acceptance for an isolated lot of
finite size.
The exact sampling distribution of the number of defective items in the sample is the
hypergeometric distribution.
As the size of the lot increases, the lot size has a decreasing impact on the OC curve.
If the lot size is at least 10 times the sample size, the two types of curves are almost same.
Type-A OC curve always lies below the Type-B OC curve.
OC curve for single-sampling with c=0: The curves are shown in the figure below
Sampling plans with c=0 have OC curves that are complex through out their range.
Probability of acceptance drops very rapidly even for small values of lot fraction
defective.
This is hard on the vendor and some times uneconomical for the consumer.
From slide 14, for n=89, AQL=1%, Pa=0.78 for c=1 and Pa=0.41 for c=0
Designing a Single-Sampling Plan with a Specified OC Curve
The Poisson distribution yields a good approximation when n is at least 16, N at least 10
times n and p is less than 0.1.
The Poisson distribution as applied to acceptance sampling is
np ( np ) r
P (r ) = e
r!
where, P(r) is the probability of exactly r defectives in sample of n.
Module 22
Rectifying inspection
Corrective action required after rejection of lots.
Generally, rejected lots are 100% inspected, with defective items removed for rework or
replaced by good items.
Such sampling programs are called Rectifying Inspection Programs
Average Outgoing Quality (AOQ) is the quality in the lot that results from the application
of rectifying inspection.
If the lots are from a process with p fraction defective, then In lots of size N, ,
1. n items contain no defectives as defectives are
replaced
2. N-n items contain no defectives if the lot is rejected
3. N-n items contain p(N-n) defectives if the lot is accepted
Expected number of defectives is Pa(N-n)
Therefore, AOQ = Pap(N-n)/N
If N is large relative to n, Approximately, AOQ= Pap
The curve that plots AOQ against incoming quality, p is called AOQ curve
From the AOQ curve, we note that average outgoing quality is good both for good and
very bad incoming qualities.
The maximum ordinate on the curve represents the worst possible average quality that
results from the rectifying plan.
This point is called the Average Outgoing Quality Limit (AOQL)
AOQL is an average level of quality, across a large stream of lots and it does not give
assurance that an isolated lot will have quality no worse than AOQL.
If the lot has no defectives, the amount of inspection per lot =n
If all are defectives, the amount of inspection per lot = N
If the lot quality is 0<p<1, then the Average Total Inspection (ATI) per lot will be
ATI = n + (1 Pa)(N n)
Example 3:
Draw the OC curve of the single-sampling given with sample size 300 and acceptance number 5.
We first fix tentative probabilities of acceptance (Pa)
Consider the table shown below
n
np
Pa
300
0.98
300
0.95
300
0.70
300
0.50
300
0.20
300
0.05
300
0.02
Pap
Search the cumulative Poisson distribution table under c=5 column for a value close to the
required Pa value and note the corresponding np value . For this np calculate the corresponding
p. Complete the table and draw the required curve.
np
Pa
Pap
=AOQ
300
2.0
0.0067
0.983
0.0065
300
2.6
0.0087
0.951
0.00827
300
4.4
0.0147
0.70
0.0106
300
5.6
0.0187
0.512
0.00957
300
7.8
0.025
0.210
0.00526
300
10.5
0.035
0.05
0.00175
300
12.0
0.04
0.02
0.0008
From the above table the OC curve can be constructed which is given in the following
Example 4:
In a double sampling plan, N=5000, n1=100, c1=0, n2=100, c2=1
(a) Use Poissons table to compute the probability of acceptance of a 1% defective lot.
(b) assume that a lot rejected by this sampling plan will be 100% inspected. What will be the
AOQ if the submitted product is 1% defective? Considering the inspection of both
rejected lots, what will be the avarage number of articles inspected per lot if the
submitted product is 1% defective?
No of defective articles = 5000x0.01=50 No of non-defective articles= 5000-50=4950
(a) n1p=100x0.01=1
From Poissons table, PI(0)=0.368
Accept the lot if
I)
Zero defective in the first sample
II)
One defective in the first sample and zero defective in the second sample
PI(1)= 0.736-0.368=0.368
For the second sample, N=5000-100=4900,
No of defectives=49
P=49/4900=0.01,
n2p=100x0.01=1
PII(0)=0.368
Therefore, probability of acceptance,
Pa=PI(0) + PI(1)xPII(0)
= 0.368+0.368x0.368=0.5034
(b) AOQ=Paxp=0.5034x0.01=0.005034 or 0.5034 %
Average no of articles inspected =PI(0)n1+PI(1)(n1+n2) + (1-Pa)N
i.e. 0.368 x100+0.368x0.368x200+ (1-0.5034)5000=2547
Designing a single sampling plan with stated value of P0.5
The quality P0.5 is the lot or process quality that has a probability of acceptance of 0.5 and is
called as the indifference quality.
The single acceptance plan is designed by using the following approximate formula
n = (c + 0.67) / P0.5
A vendor selects P0.5 = 0.02 and acceptance number 1. How many lots are likely to accepted if he
has 1000 lots each of quality 2.5% and 1.5%?
n=(1+0.67)/0.02 = 84.
1) np = 84(0.015)=1.26. From cumulative Poissons table (c=1), Pa=0.641
2) np= 84(0.025) = 2.1, From table, Pa = 0.38.
No. of lots likely to be accepted = 0.641(1000) + 0.38(1000)
= 1021
Module 23
A multiple sampling plan is an extension of double sampling plan more than two
samples are required
If at any stage the number of defective items is less than or equal to the corresponding
acceptance number, the lot is accepted.
If at any stage the number of defective items is greater than or equal to the corresponding
rejection number, the lot is rejected.
These plans generally involve less total inspection compared to single or double sampling plans
guaranteeing the same protection, but usually require higher administrative costs and higher
caliber inspection personnel
Sample
Sample
size
Combined samples
Size
Acc. No.
Rej. No.
First
n1
n1
c1
r1
Second
n2
n1+n2
c2
r2
Third
n3
n1+n2+n3
c3
r3
Fourth
n4
n1+n2+n3+n4
c4
r4
Fifth
n5
n1+n2+n3+n4+n5
c5
c5+1
Rejection
Acceptance
The equations for the two limit lines for specified values of p1, 1- , p2, and
(Acceptance line)
where
are
(Rejection line)
And
Numerical example:
Design a sequential sampling plan for the following specifications:
= 0.05,
= 0.2,
p1 = 0.1
p2 = 0.3
Comparison of plans
In general double sampling is preferred.
Multiple and sequential sampling are used where cost of inspection is high.
In a single sampling plan the lot does not have to wait.
In multiple sampling plans indecision may continue for a long time more storage space
is necessary.
Published sampling plans
The sampling plans discussed so far are individual sampling plans.
A sampling scheme is an overall strategy specifying the way in which sampling plans are
to be used.
Military standard 105 E:
Developed during world war II
A derivative civilian standard also available ANSI / ASQC Z1.4
The primary focal point is AQL
Provides for single, double and multiple samplings
For each type provision is made for normal, tightened and reduced inspection
Dodge Romig sampling plan:
Dodge and Romig developed these set of inspection tables.
Two types of sampling plans are presented
LTPD protection
Specified AOQL
For both approaches, single and double sampling tables are available
For critical components and parts these plans are preferred to AQL oriented plans.