PMP Formulas
PMP Formulas
Earned Value
CV = EV - AC
CPI = EV / AC
SV = EV - PV
SPI = EV / PV
EAC no variances = BAC / CPI
EAC fundamentally flawed = AC + ETC
EAC atypical = AC + BAC - EV
EAC typical = AC + ((BAC - EV) / CPI)
ETC = EAC - AC
ETC atypical = BAC - EV
ETC typical = (BAC - EV) / CPI
ETC flawed = new estimate
Percent Complete = EV / BAC * 100
VAC = BAC - EAC
EV = % complete * BAC
% COMPLETE = EV / BAC x 100
% SPENT
= AC / BAC x 100
CV% = CV / EV x 100
SV% = SV / PV x 100
PERT
PERT 3-point = (Pessimistic+(4*Most Likely)+Optimistic)/6
PERT = (Pessimistic - Optimistic) / 6
PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2
PERT Variance all activities = _sum((Pessimistic - Optimistic) / 6)^2
Classes of Estimates
Order of Magnitude estimate = -25% to +75%
Preliminary estimate = -15% to + 50%
Budget estimate = -10% to +25%
Definitive estimate = -5% to +10%
Final estimate = 0%
Project Selection
PV = FV / (1+r)^n
FV = PV * (1+r)^n
NPV = Select biggest number.
ROI = Select biggest number.
IRR = Select biggest number.
Payback Period = Add up the projected cash inflow minus expenses until you reach the initial
investment.
BCR = Benefit / Cost
CBR = Cost / Benefit
Opportunity Cost = The value of the project not chosen.
Exp. Value = Probability % x Consequence $
Communications
Communication Channels = n * (n-1) / 2
Probability
EMV = Probability * Impact in currency
Procurement
PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target Cost
Depreciation
Straight-line Depreciation:
Depr. Expense = Asset Cost / Useful Life
Depr. Rate = 100% / Useful Life
Double Declining Balance Method:
Depr. Rate = 2 * (100% / Useful Life)
Depr. Expense = Depreciation Rate * Book Value at Beginning of Year
Book Value = Book Value at beginning of year - Depreciation Expense
Sum-of-Years' Digits Method:
Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc.
Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)
SIGMA
1 sigma = 68.26%
2 sigma = 95.46%
3 sigma = 99.73%
6 sigma = 99.99%
Important Values
Control Limits = 3 sigma from mean
Control Specifications = Defined by customer; less than the control limits
Float on the critical path = 0 days
Network Diagram
Forward Pass
ES = EF of the predecessor node
EF = ES + Dur
ES
Dur
EF
Node
Backward Pass
LF = LS of the Successor
LS = LF Dur
LS
Float
LF
Slack = LF EF = LS ES
Free Float = ES(Successor) - EF(Predecessor)
You need to understand the terms and the logic relationships between the inputs, outputs and tools&
techniques. Memorizing them is not enough and will lead you nowhere.
Refer to the PMBoK 5h Edition for more details. &
Please do not hesitate to contact me anytime if you have any questions, comments, and feedbacks.
Success is yours,
Prepared By: Amr Miqdadi, PMP
[email protected]
http://www.pmlead.net
PMI, PMP, CAPM and PMBOK Guide are trademarks of the Project Management Institute, Inc.
PMI has not endorsed and did not participate in the development of this product.