Installation instructions
Subject to technical modifications / August 2013 / RGI
STRAIL level crossing systems / STRAILastic track damping systems
KRAIBURG STRAIL GmbH & Co. KG D-84529 Tittmoning Goellstrae 8
phone +49/(0)8683/701-0 fax +49/(0)8683/701-126
[email protected] www.strail.com www.strailastic.com
Installation instructions STRAILastic_R TYPE Augsburg page 2/2
August 2013 / Subject to technical modifications
Green track profiles for superstructures:
S 49 - Fastening rail clamp W14
concrete sleepers Rheda City or Inplace
independend on sleeper spacing
# 1 / REQUIREMENTS
u
The track is completely preassembled and approved for the installation of green track profiles.
Rail chambers are free of cinder and grate plates.
# 2 / PREPARATION
u Arrange
green track profiles (inner and outer profiles) along the track.
# 3 / INSTALLATION
u Place
the green track profiles so that they lie against the
rail head and rest on the fastening. Begin on one side to
knock the elements under the rail head. Take a hammer
and knock the profiles down by knocking on the surface
(1). Then join the profiles together by knocking on the front
sides in order to create a gap-free surface.
u The
profiles have to be adjusted accordingly to rail joints
(welded joints), junction boxes and other conditions.
Electric tenon saws or chain saws lend themselves to that
(danger of accident).
u The
substrate can be installed subsequently according to
the guidelines of the grass supplier.
u The
profiles can be removed for maintenance work and
then reinstalled.
The grass has to be removed partially at the profiles.
u Removing
the elements is done by inserting a crowbar into
the air vent slot at the joint and lifting it up.
u Grease
the rail head with a lubricant before the reinstalling
is carried out according to #3 of these instructions.