Dewatering Method Statement

The document outlines a two-phase dewatering method for a commercial residential building site in Abu Dhabi. Phase one involves installing temporary deep wells inside the plot during excavation to lower the groundwater table from -3.10m to below the maximum excavation level of -11.30m. Phase two uses a land gravity drain system and electrical submersible pumps to further dewater the site during construction behind a secant pile wall shoring system.

Uploaded by

Adnan Jadoon
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
227 views

Dewatering Method Statement

The document outlines a two-phase dewatering method for a commercial residential building site in Abu Dhabi. Phase one involves installing temporary deep wells inside the plot during excavation to lower the groundwater table from -3.10m to below the maximum excavation level of -11.30m. Phase two uses a land gravity drain system and electrical submersible pumps to further dewater the site during construction behind a secant pile wall shoring system.

Uploaded by

Adnan Jadoon
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

DEWATERING METHOD STATEMENT

Project : Commercial Residential Building @ E-25/ C-66, Abu


Dhabi
Main Contractor : Metac General Contracting Co. LLC
Dewatering By : Khansahjeb Sykes LLC
Based on the following information provided to us , we would put forward the method of dewatering for
the above project:
Area to dewater

: A perimeter of 304 Lm

Reference Level

: +/- 0.00 m EGL

Ground water table

: - 3.10 m

Max. Excavation level

: - 11.30m generally and varying from -11.0m to -13.0m for pile caps.

Shoring

: Secant Pile Wall

System
We propose a system consisting of two phases viz. first phase by means of temperory deep wells
installed inside the plot during excavation, and second phase by means of land gravity drain
system during construction, all in conjunction with electrical submersible pumps.

Equipments
Pumpex PC 1301H or similar submersible