0% found this document useful (0 votes)
346 views

Networks Part 3

Uploaded by

api-254501788
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
346 views

Networks Part 3

Uploaded by

api-254501788
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

ExamBusters Further Maths 3 & 4

.Try this
1 The activities and their completion times (days) needed to complete VCAA 2004 FM Exam 1
a project are shown m the digraph below
start finish
For the network shown, the length of the critical path is
A 22 days
B 23 days
C 25 days
D 26 days
E 28 days
2 The following network gives the time m days to complete the
12 activities for a building project
A, 4
start
B, 6
finish
Module 5 Q8
Examiner says
63%answered correctly
< VCAA 2002 FM Exam 1
Module 5 Q7
| Examiner says
i 51 %answered correctly
The minimum time m which this building project can be completed is
A 8 days
B 16 days
C 18 days
D 20 days
E 59 days
3 The earliest and latest start times (in days) for seven activities m a
design project are given m the following table
< VCAA 2002 FM Exam 1
Module 5 Q8
activity earliest start tune latest start tune
A 0 4
B 0 0
C 6 6
D 9 9
E 6 11
F 13 13
G 18 18
Examiner says
67%answered correctly
252
iliill
The activities that he on a critical path for this project are
A
B C. />. F, G
B A D. E, G
C C D, E, F, G
I) A B, C, D, E, F, G
E B E, G
< VGA A 2001 FM Exam 1
Module 5 Q7
Examiner says
46%answered correctly
B, 5
E,6
The directed graph above shows the activities and their respective
duration times (in days) for completing a project
What is the latest time that task B may start m order to not delay the
project7
A At the start of the project
B Two days after the start of the project
C Three days after the start of the project
D Five days after the start of the project
E Seven days after the start of the project
5 The following directed graph charts a project development with
activities and their completion times (in days) displayed on the arcs
of the graph
A, 8
start
O finish
D,5
< VGA A 2000 FM Exam 1
Module 5 Q7
Examiner says
27%answered correctly
Taking the start of the project as Day 1, the earliest time that activity
F can begin is on
A
Day 4
B Day 5
C Day8
D Day 11
E Day 13
253