Networks Part 3
Networks Part 3
.Try this
1 The activities and their completion times (days) needed to complete VCAA 2004 FM Exam 1
a project are shown m the digraph below
start finish
For the network shown, the length of the critical path is
A 22 days
B 23 days
C 25 days
D 26 days
E 28 days
2 The following network gives the time m days to complete the
12 activities for a building project
A, 4
start
B, 6
finish
Module 5 Q8
Examiner says
63%answered correctly
< VCAA 2002 FM Exam 1
Module 5 Q7
| Examiner says
i 51 %answered correctly
The minimum time m which this building project can be completed is
A 8 days
B 16 days
C 18 days
D 20 days
E 59 days
3 The earliest and latest start times (in days) for seven activities m a
design project are given m the following table
< VCAA 2002 FM Exam 1
Module 5 Q8
activity earliest start tune latest start tune
A 0 4
B 0 0
C 6 6
D 9 9
E 6 11
F 13 13
G 18 18
Examiner says
67%answered correctly
252
iliill
The activities that he on a critical path for this project are
A
B C. />. F, G
B A D. E, G
C C D, E, F, G
I) A B, C, D, E, F, G
E B E, G
< VGA A 2001 FM Exam 1
Module 5 Q7
Examiner says
46%answered correctly
B, 5
E,6
The directed graph above shows the activities and their respective
duration times (in days) for completing a project
What is the latest time that task B may start m order to not delay the
project7
A At the start of the project
B Two days after the start of the project
C Three days after the start of the project
D Five days after the start of the project
E Seven days after the start of the project
5 The following directed graph charts a project development with
activities and their completion times (in days) displayed on the arcs
of the graph
A, 8
start
O finish
D,5
< VGA A 2000 FM Exam 1
Module 5 Q7
Examiner says
27%answered correctly
Taking the start of the project as Day 1, the earliest time that activity
F can begin is on
A
Day 4
B Day 5
C Day8
D Day 11
E Day 13
253