Calculating Critical Path
Calculating Critical Path
time management
Figure out the early start and early finish
Coming up with the float for each activity is useful, but you can actually do better!
When you have a long critical path, but the other paths in your network diagram are
short, then you have a lot of freedom in when you can start and finish each of the
activities that are not on the critical path. You can use early start and early finish
to get a handle on exactly how much freedom you have in your schedule.
When you find the early
start and early finish for
each task, you know exactly
how much freedom you have
to move the start dates
for those activities around
without causing problems.
Early start
Is the earliest time that an activity can start. An activity
near the end of the path will only start early if all of the
previous activities in the path also started early. If one of
the previous activities in the path slips, that will push it out.
Early finish
Is the earliest time that an activity can finish. Its the date
that an activity will finish if all of the previous activities
started early and none of them slipped.
The critical path has a duration
of 6 + 5 + 7 = 18
The other path has a duration
of 2 + 3 = 5. Its a lot
shorter than the critical path,
so there should be a lot of
play in those activities.
Even if Activity D starts
really late, since the path its
on is so much shorter than
the critical path, the project
will still be on time.
That means the early start
and early finish for D
and
E are really early they can
end a lot sooner than A, B
and C, which will free up their
resources for you to use.
Activity
D
2
Finish
Activity
B
5
6
Activity
A
Start
Activity
E
3
Activity
C
7
258 Chapter 6
Figure out the latest possible start and finish
Its also important to know how late any activity can run before it delays
the project. Thats what late start and late finish are for! They let you
figure out how late you can start a certain task and how much it can slip
before it delays your project.
This is the same network
diagram from the last page.
This path is much shorter than
the critical path, so you should
be able to start Activity D
very late and still complete
the project on time!
The path Activity D is on
has a much shorter duration
than the critical path. So
even if it has a long delay,
it still wont harm the
project.
Activity
D
2
Finish
Activity
B
5
6
Activity
A
Start
Activity
C
7
Figuring out the late start
and late finish will help you
see how much play you
have in your schedule. An
activity with a large late
start or late finish means
you have more options.
Late start
Is the latest time that an activity can start. If an activity is on
a path thats much shorter than the critical path, then it can
start very late without delaying the project but those delays
will add up quickly if other activities on its path also slip!
Late finish
Is the latest time that an activity can finish. If an activity is on
a short path and all of the other activities on that path start
and finish early, then it can finish very late without causing
the project to be late.
starting late
you are here 4 259
time management
Add early and late durations to your diagrams
You can use a method called forward pass to add the early start and
finish to each path in your network diagram. Once youve done that, you
can use backward pass to add the late start and finish. It makes your
network diagrams look a little more complicated, but it gives you a lot of
valuable information.
Design Invitations
4 8
7 11
Duration = 4
Float = 3
You can use this special
node in your network
diagram to write down
the early and late
start and finish.
The early start for
this activity is 4.
Early start and finish go in
the upper corners. Write the
name of the activity above it,
and the duration and float
inside the box.
The early finish for this
activity is 8. Theres no
way it can end before
day 8.
Write the late start in the lower-
lefthand corner. As long as the
invitation design starts by day 7, it
wont delay the critical path.
The late finish for the
Design Invitations activity is
11, which means the latest it
can finish without delaying
the schedule is on day #11.
If it hasnt finished by then,
Kathleen should worry!
Finish
Activity
B
5
Activity
A
Start
Activity
C
7
Take a forward pass through the network diagram.
Start at the beginning of the critical path and move forward through each
activity. Follow these three steps to figure out the early start and early finish!
The ES (early start) of the first activity in the path is 1. The EF (early finish)
of any task is its ES plus its duration minus one. So start with Activity A. Its
the first in the path, so ES = 1, and EF = 1 + 6 - 1 = 6.
11
Now move forward to the next activity in the path, which is Activity B in
this diagram. To figure out ES, take the EF of the previous task and add one.
So for Activity B, you can calculate ES = 6 + 1 = 7, and EF = 7 + 5 - 1 = 11.
22
Uh-oh! Activity C has two predecessors. Which one do you use to
calculate EF? Since C cant start until both B and D are done, use the one
with the latest EF. That means you need to figure out the EF of activity
D (its ES is 1, so its EF is 1 + 2 = 3). Now you can move forward to Activity
C and calculate its EF. The EF of Activity D is 2, which is smaller than Bs
EF of 11, so for Activity C the ES = 11 + 1 = 12, and EF = 12 + 7 - 1 = 18.
33
C
B
D
6
260 Chapter 6
Take a backward pass to find late start and finish
Theyre the same if
theres only one path.
But with more paths,
things get interesting!
First do the forward pass for
both paths. When you do that, you
get a different LF for Activity B,
which makes all the numbers change!
We use Activity D to calculate
the LF for Activity C because
it has the lower LS.
You can use a backward pass to figure out the late finish and start for each activity.
Now take a backward pass through the same network diagram.
The backward pass is just as easy as the forward pass. Start at the end of the path you just
took a pass through and work your way backward to figure out the late start and finish.
Finish
Activity B
Activity A
Start
Activity C
Duration
= 6
Duration
= 5
Duration
= 7
1 6
? ?
7 11
? ?
12 18
? ?
Weve already
figured out the ES
and EF, so theyre
filled in here!
Start at the end of the path, with Activity C. The LF (late finish) of the last
activity is the same as the EF. Calculate its LS (late start) by subtracting its
duration from the LF and adding one. LS = 18 - 7 + 1 = 12
11
Now move backwards to the previous activity in the pathin this case,
Activity B. Its LF is the LS of Activity C minus one, so LF = 12 - 1 = 11.
Calculate its LS in the same way as step 1: LS = 11 - 5 + 1 = 7.
22
Now do the same for Activity A. LF is the LS for Activity B minus one, so
LF = 7 - 1 = 6. And LS is LF minus duration plus one, so LF = 6 - 6 + 1 = 1.
33
Finish
Activity B
Activity A
Start
Activity C
Duration
= 6
Duration
= 5
Duration
= 7
1 6
6 1
7 11
12 8
12 18
18 12
Activity D
Duration
= 2
1 3
11 9
backward pass
Start with the critical path.
Youre calculating the latest any activity
can start and finish, so it makes sense
that you need to start at the end of the
project and work backwards and the
last activity on the critical path is always
the last one in the project. Then do
these three steps, working backwards
to the next-longest path, then the next-
longest, etc., until youve filled in the LS
and LF for all of the activities. Fill in the
LF and LS for the activities on each path,
but dont replace any LF or LS youve
already calcualted.
Activity D
Duration
= 2
1 3
? ?
Now you can move onto the next-longest path, Start-D-C-Finish. If there
were more paths, youd then move on to the next-longest one, etc.,
filling in LF and LS for any nodes that havent already been filled in.
44
you are here 4 261
time management
There are four paths in this network diagram. Fill in each of
the activity names and durations for each of the paths.
Lets take some time out to walk through this!
All of this critical path stuff seems pretty serious, right? Its one of the
toughest concepts on the exam. But dont sweat it, because its actually
not hard! It just takes a little practice. Once you do it yourself, youll
see that theres really nothing to worry about.
Were not done yet! Theres more on the next page...
Start
A
B C
D
E F
H
End
G
4 3
4
6
8 7
4
5
__
__
__
__
__
__
Finish Start
__
__
__
__
__
__
Finish Start
__
__
__
__
__
__
Finish Start
__
__
__
__
__
__
Finish Start
Calculating the ES, EF, LS, and LF
may seem complicated, but it only takes
a little practice to get the hang of it.
Once you walk through it step by step,
youll see that its actually pretty easy!
Put an asterisk (*) next
to the critical path.
262 Chapter 6
critical path practice
Take a forward pass through each of the four paths in the diagram and fill
in the early starts and early finishes for each activity. Start with the first
one.
Lets move on to the second path.
Now take another look at it, and how
it mixes with the last path. It includes
activity H, which was also in the last path.
H will have a different
ES depending on
which path you use!
So which predecessor
do you use E or
G? The idea here is
that you use the
predecessor with the
larger EF value when
you calculate the ES
for activity H (because
you want the latest
possible start date).
Remember, the early
start of the first
activity in a path is one.
The early finish of an
activity is its ES plus
its duration minus one.
The early start of an activity is the early
finish of the previous activity plus one.
Once you have the EF for both
activities E and G, you can use the
bigger one to come up with the ES for
activity H.
The next path isnt as straightforward as it looks. Start by filling in its values.
ES=__
EF=__
C
4
B
3
A
4
Finish Start
ES=__
EF=__
ES=__
EF=__
ES=__
EF=__
F
7
B
3
A
4
Finish Start
ES=__
EF=__
ES=__
EF=__
ES=__
EF=__
H
4
E
6
D
5
Finish Start
ES=__
EF=__
ES=__
EF=__
ES=__
EF=__
H
4
G
6
D
5
Finish Start
ES=__
EF=__
ES=__
EF=__
E
8
ES=__
EF=__
?
?
Wait up! These
two arent so
straightforward.
you are here 4 263
time management
Youve calculated the ES for each activity. Use that information and take a backward pass
through the paths, starting with the first two paths.
Start by filling in the LF of the
last activity in each path, which
is the same as the EF of the last
activity in the critical path.
Move backwards through the
path, filling in the LS by
subtracting the duration from
the LF and adding one. Weve
filled in the first two for you.
For activity B, you have a choice you
can calculate the LF using the LS from
either activity C or F. Use the lower value,
subtract one, and fill it in.
The LF for each
activity is the LS of
the next one on the
path minus one.
Finish up by calculating the LS and LF for the last two paths!
Activity D is another one where
you have to chose which LS to
use in order to calculate the LF.
You can either use the LS from
activity E or activity G. Use
whichever is lowest, subtract one,
and fill it in.
F
7
B
3
Finish
LF=__
LS=__
C
4
LF=__
LS=__
LF=__
LS=__
A
4
Start
LF=__
LS=__
LF=__
LS=__
H
4
G
6
D
5
Finish Start
LF=__
LS=__
LF=__
LS=__
E
8
LF=__
LS=__
First start with the critical path. Take the EF of the last activity in the critical path and use it as the LF for
the last activity in every path. If you take a minute to think about it, it makes sense to do that. The point of
LF is to figure out the absolute latest that the activity can end without making the project late. And as long
as every non-critical-path activity ends before the last activity in the critical path, then they wont be late.
Well start by giving you the LF of critical path, Start-D-E-H-Finish, which is 17.
Activities B and D have two possible
choices for which LS to use for the
calculation. For activity B, do you
use the LS of C or the LS of F? And
for activity D, do you use the activity
E or G? The answer is that you
always use the lowest value of LS
to calculate the LF. The reason is
that youre trying to find the latest
possible start date that wont make
the project late. If you use an activity
with a later LS, and the activity
really is delayed by that much, then
itll cause a delay in both following
activities. And that will make the
one with the lower LS start too late.
264 Chapter 6
For the exam, youll only have to do one or two of these calculations,
not a whole string of them like this. Youll definitely be able to
handle the exam questions now!
Now you know that activity G
can start as late as day 8 of
the project (assuming the units
are days) or it could finish
as early as day 11..
Finish
Activity B
Activity A
Start
Activity C
Duration
= 4
Duration
= 3
Duration
= 4
1 4
7 4
5 7
10 8
8 11
17 14
Activity D
Duration
= 5
1 5
5 1
Activity E
Duration
= 8
6 13
13 6
Activity G
Duration
= 6
6 11
13 8
Activity F
Duration
= 7
8 14
17 11
Activity H
Duration
= 4
14 17
17 14
If you got a few of these wrong, dont
worry. Its easy to miss one calculation, and
that leads to a problem on the whole path.
You wont have to do this kind of thing on
the job... thats what computers are for!
Project management software like Microsoft Project will
do these calculations for you. But you need to know how
to do it yourself, because when the computer is doing
critical path analysis, this is exactly how it figures it out!
Wait a minute... Ive never had to
do this for my projects at work! Ive
got projects with dozens of activities,
and this would take all day!
exercise solutions
you are here 4 265
time management
Q:
Would I really use this critical path
stuff in real life, or is it just something I
need to memorize for the PMP exam?
A: Yes, critical path analysis really is
important in real life! Sure, for a small project
with a dozen or so activities, its pretty easy
to figure out which activities are critical
and which can slip by a little bit. But what
happens if youve got a project with dozens
of team members and hundreds of activities?
Thats where critical path analysis can come
in very handy. For a project like that, youd
probably be using project management
software rather than calculating the critical
path yourself, and the software will be able
to highlight that path for you. Pay special
attention to all of the activities that are on the
critical paththose are the ones that could
potentially delay the project.
Q:What about the other numbers?
How do I use float?
A: Float is a very powerful planning tool
that you can use to figure out how well your
project is going, and to predict where your
trouble spots might be. Any activity with a
low or zero float absolutely must come in on
time, while the people performing an activity
with a larger float have more freedom to slip
without delaying the project. So you might
want to assign your superstar resources to
the low-float activities, and those people who
need a little more mentoring to the ones with
higher float.
Q:
Okay, but what about late start,
early finish, and those other numbers?
Do those do me any good?
Early and late start and finish numbers are
also very useful. How many times have
you been in a situation where youve been
asked, If we absolutely had to have this in
two months, can we do it? Or, How late can
this project realistically be? Now you can
use these numbers to give you real answers,
with actual evidence to back them up.
Heres an example. Lets say youve got an
activity in the middle of your project, and
one of your team members wants to plan a
vacation right at the time that the activity will
start. Do you need to find someone to fill in
for him? If hell be back before the late start
date, then your project wont be late! But that
comes at a cost youll have used up the
extra slack in the schedule.
Q:
I can see how the critical path is
useful on its own, but what does it have
to do with the rest of time management?
A: If you start putting together your
schedule but the activities are in the wrong
order, thats really going to cause serious
problems... and sometimes doing critical
path analysis is the only way youll really
figure out that youve made that particular
mistake. Thats why you need to pay a lot
of attention to the Activity Sequencing tools
and techniques. If youve come up with an
inefficient or inaccurate sequence, with
too many or incorrect predecessors and
dependencies, then your entire critical path
analysis will be useless.
The critical path is the path that has the longest
duration.
You should be able to figure out the number of paths in
a network diagram, and the duration of each path.
The float for an activity is the amount that its duration
can slip without causing the project to be delayed. The
float for any activity on the critical path is zero.
Youll need to know how to calculate the early start, late
start, early finish, and late finish for an activity in a
network diagram using the forward pass and backward
pass. This is the core of critical path analysis.