This document provides an analysis of rates for various construction items. It begins by defining rate analysis and explaining that material and labor rates vary by location. Each construction item is then broken down into costs for materials, labor, tools/plants, transportation, water charges, and contractor profit. Specific material and labor rates are provided for several places. Examples are given to calculate the quantities of materials needed for different concrete mixes. The final section works through the rate analysis for a conglomerate floor, showing costs for materials, labor, and contractor profit to determine the final rate.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
90 views
Er. Kashmir Dass: Prepared by
This document provides an analysis of rates for various construction items. It begins by defining rate analysis and explaining that material and labor rates vary by location. Each construction item is then broken down into costs for materials, labor, tools/plants, transportation, water charges, and contractor profit. Specific material and labor rates are provided for several places. Examples are given to calculate the quantities of materials needed for different concrete mixes. The final section works through the rate analysis for a conglomerate floor, showing costs for materials, labor, and contractor profit to determine the final rate.
ANALYSIS OF RATES To determine the rate of a particular item of work from a quantities of materials and labours required and their costs The rates of materials and labour are changing from place to place, therefore the rates o different items of work also changes from place to place
ANALYSIS OF RATES Every Estimate should be accompanied by the analysis of rates of the items provided in it . Analysis of rates comprises of 1. Cost of Material 2. Cost of Labour 3. T and P , and Sundries 4. Carriage 5. Contractors Profit
ANALYSIS OF RATES Tools and Plants ( T & P ) = 2.5 to 3 % of the labour cost Transportation cost more than 8 km is considered Water charges = 1.5 to 2 % 0f total cost Contractor s profit = 10 % ANALYSIS OF RATES Rates of Materials and Labours : 1 st class bricks = Rs 4500 per 1000 Nos. 2 nd class bricks = Rs 4000 per 1000 Nos. Brick Ballast = Rs 800 per cum Coarse sand = Rs 800 per cum Cement 50 kg bag = Rs 270 per bag Twisted bars = Rs 5000 per Quintel Bitumen = Rs 10 per kg ANALYSIS OF RATES Mason = Rs 450 per day Plaster = Rs 400 per day Carpenter = Rs 400 per day Bhishti = Rs 250 per day Mazdoor = Rs 250 per day Painter = Rs 300 per day
ANALYSIS OF RATES Earth work in excavation: Mazdoor = 33 (% cum) Mason = 1.5 Earth work in Filling : Mazdoor = 18 (% cum) Mason = 0.5 Cement concrete : Mazdoor = 15 in foundation Mason =1.5 Bhishti = 2 ANALYSIS OF RATES Cement concrete : Mazdoor = 15 Mason = 1 Bhishti = 2.5 R. Cement concrete : Mazdoor = 40 (10 cum ) Mason = 2.5 Bhishti = 5 Blacksmith = 4 Carpenter = 4 ANALYSIS OF RATES
DPC : Mazdoor = 2.5 (10 cum ) Mason = 1.5 Bhishti = 0.5 1 st class brick work : Mazdoor = 15 Mason = 8 Bhishti = 2 ANALYSIS OF RATES
Plastering work : Mazdoor = 10 ( 100 sqm) Mason = 10 Bhishti = 2 Distempering/painting/white washing : Mazdoor = 5 ( 100 sqm) Painter = 4 ANALYSIS OF RATES Example 1. Find out dry materials required for 1 cu m. C. concrete 1:4:8 in foundation.
Solution. Ratio = 1:4:8 (cement,sand and aggregate)
Sum = 1+4+8=13 cont..
Total dry mortar for 1 cu m cement concrete =1.54 cu m Therefore the following materials are required:
Cement = (1*1.54*28.8)/13 = 3.41 bags
Sand = (4*1.54)/13 = 0.47 cu m cont..
Aggregate (Brick ballast) = (8*1.57)/13 = 0.94 cu m so materials for 1 cu m cement concrete 1:4:8.
Cement 3.41 bags
Sand 0.47 cu m Ans.
Brick ballast 0.94 cu m Example 2. Find out dry materials for 1 cu m lime concrete.
Solution: Ratio = 1:2 (lime,surkhi)
Sum = 1+2 = 3 Total dry mortar for 1 cu m lime concrete = 0.40 (lime, surkhi mortar) Therefore the following materials are required.
Lime = (1*0.40)/3 = 0.13 cu m
Surkhi = (2*0.40)/3 = 0.27 cu m
Aggregate (brick ballast) = 1.00 cu m
Materials required for1 cu m lime cocrete 1:2
Lime 0.13 cu m
Surkhi 0.27 cu m Ans.
Brick ballast 1.00 cu m ANALYSIS OF RATES OF DIFFERENT ITEMS OF WORK. 1. Excavation for foundation: payment % cu m (a)Materials at the site for % cu m nil No material is required Rs. P.
(b)labour for % cu m Mazdoor 33 nos.@ 250.00/day = 8250.00
Mason 1 no. @ 450.00 = 450.00 Sundries and Tand P 3% on labour = 261.00 Total = 8961.00 (c)Add 10% contractors profit = 896.10 grand total =9857.10 say Rs. = 9857.00
Rate per % cu m = Rs. 9857.00
2.Earth filling under floors payment % cu m (a)Materials at site for %cu m Rs.P. No material is required nil (b) Labour for % cu m [email protected]/day =4500.00 Bhishti 1/[email protected]/day = 125.00 Sundries and Tand P3% on labour 465.00 = 123.75 total = 4748.75 Add 10% contractors profit = 474.87
G.Total= 5223.62 say Rs.=5224.00 Rate per % cu m = Rs. 5224.00 3. Cement concrete 1:4:8 in foundations (a) Materials at site for 1 cu m payment per cu m Cement 3.41 bags @270 bag = 929.70 Sand 0.47 cu m @800.00 per cu m=376.00
Brick ballast 0.94 cu m @ 800.00 = 752.00 Cost of labour for 10 cu m = 7520.00 (b)Labour for 10 cu m Rs. P Mason 1@ 400.00/ day = 400.00 Mazdoors 15@ 250.00/ day = 3750.00 Bhishti 2@ 250.oo/ day = 500.00 Sundries and Tand P @ 3% on labour = 139.50
Cost of for 10 cu m = 12309.50 Cost of for 1 cu m =12309.50/10 =1230.95 PROBLEM: Conglomerate floor 4 cm thick of cement concrete 1:2:4 over 10 cm thick cement concrete 1:6:18 over 10 cm sand filling.
calculation of material for 10 sq m (1) Wet mortar for cement concrete 1:2:4= 10 sq m*4cm = 10*4/100 =0.40cu m
Dry mortar = 0.40*1.54=0.616+0.62 cu m
Ratio = 1:2:4 Sum =1+2+4=7
Cement = 1*0.62*28.8/7 =2.55 bags
Sand = 2*0.62/7 = 0.18 cu m
Crusher = 4*0.62/7=0.36 cu m
(2)Wet mortar for cement concrete 1:6:18
= 10 sq m*10 cm =10*10/100
=1 cu m
Dry mortar 1*1.54 =1.54cu m
Ratio =1:6:18=1+6+18 = 25
Cement = 1*1.54*28.8/25 = 1.78 bags
Sand =6*1.54/25 = 0.37 cu m
Brick ballast = 18*1.54/2 = 1.11 cu m
(3) Sand for 10 sq m = 10 sq m* 10 cm = 10*10/10
= 1 cu m
Total dry mortar for 10 sq m conglomerate flooring.
Cement = 2.55+1.78
Sand = 0.18+0.37+1.00
Crusher = 0.46 (a) Materials at site for 10 sq m Rs.P
Cement 4.33 bags @ 270.00/bag = 1170.00
sand 1.55 cum@ 800.00 per cu m = 1240.00
Crusher 0.36 cu m @1200 /cu m = 432.00
Brick ballast 1.11 cu m@ 800 / cu m = 888.00
Cost of material for 10 sq m =3730.00
(b) Labour for 10 sq m Rs. P
Mason 2@ 400.00/ day = 900.00
Mazdoor 3@ 250.00/day = 750.00
Bhishti 1@ 250.00 / day = 250.00
Sundries T and P 3% on labour = 57.00
Cost of labour for 10 sq m = 1957.00
Cost of material and labour for 10 sq m
=5687.00
Add 10% contractors profit = 568.70 and total = 6255.70 Rate for 10 sq m = Rs.6256.00