0% found this document useful (0 votes)
826 views

SOP HP Heaters

This document outlines standard operating procedures for charging and isolating high pressure heaters at Indiabulls Power Limited. It provides instructions for opening and closing various valves to gradually raise condensate temperatures and regulate heater levels during the charging process. Responsibilities are assigned to turbine operators, field engineers, desk engineers, and shift supervisors to follow the procedures for charging two specific high pressure heaters.

Uploaded by

Shailender
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
826 views

SOP HP Heaters

This document outlines standard operating procedures for charging and isolating high pressure heaters at Indiabulls Power Limited. It provides instructions for opening and closing various valves to gradually raise condensate temperatures and regulate heater levels during the charging process. Responsibilities are assigned to turbine operators, field engineers, desk engineers, and shift supervisors to follow the procedures for charging two specific high pressure heaters.

Uploaded by

Shailender
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 1

Standard Operating Procedure

Indiabulls Power Limited


Title:Standard Operating Procedure
for Charging and Isolation of HP Heaters Document No Issue No / Date Rev. No / Date 00/

SOP/OPNS/

Operations Department

Purpose : This procedure is used as work instruction for Turbine Operator, Desk Engineer and Field Engineer Scope : This procedure explains charging & isolation of HP Heaters Responsibility: Turbine Operator, Field Engineer, Desk Engineer & Shift In charge Procedure: Charging of HP Heater-5 Ensure opening of FD-7 &FD-9. Open start up vent of shell side. Open DR-13 & DR-16. Open EX-12 slowly for gradual rise of condensate temperature. Close drain valve EX-104 & EX-106 after opening of EX-12. Regulate DR-16 & DR-13 for maintaining normal level of HP heater-5. Assign set point for 1) DR 13=0.0 mm (NWL) 2) DR 16 =+60 Close shell side startup vent and open running vent. Ensure healthiness of FCNRV; in case of very high Heater levels. Charging of HP Heater-6 Ensure opening of FD-10 &FD-12 Open start up vent of shell side. Open DR-2 , DR-6 & DR 9 Open EX-13 bleed valve slowly for gradual rise of condensate temperature. Close drain valve EX-133 & EX-132 after opening of EX-13. Regulate DR-2for maintaining normal level of HP heater-6. Assign set point for 1)DR 2=0.0 mm(NWL) 2) DR 6 & DR 9 =+60 Close shell side startup vent and open running vent. Ensure healthiness of FCNRV, in case of very high Heater levels Cross Reference : RECORDS : Nil Nil

Page 1 of 1 Desk Engineer Prepared By Head - Operations Reviewed & Approved By