0% found this document useful (0 votes)
19 views

Quality System Records: Title: Ehc - Balancing Voltage Adjustment. REV: 1.2 DATE: 16/ 01 /03 Page: 1 of 1

1. The document provides instructions for adjusting the balancing voltage of an EHC plunger coil for turbine generator units 1 through 4 at a power plant in Korba, India. 2. The balancing voltage across the coil is measured after removing the cover and rotating the plunger coil until -1.0 V appears, while varying the input voltage from 1-10V. 3. The measurements are recorded and the cover is replaced before cancelling the permit to work.

Uploaded by

Jai Gupta
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
19 views

Quality System Records: Title: Ehc - Balancing Voltage Adjustment. REV: 1.2 DATE: 16/ 01 /03 Page: 1 of 1

1. The document provides instructions for adjusting the balancing voltage of an EHC plunger coil for turbine generator units 1 through 4 at a power plant in Korba, India. 2. The balancing voltage across the coil is measured after removing the cover and rotating the plunger coil until -1.0 V appears, while varying the input voltage from 1-10V. 3. The measurements are recorded and the cover is replaced before cancelling the permit to work.

Uploaded by

Jai Gupta
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 1

NTPC

QUALITY SYSTEM RECORDS

KORBA
REV : 1.2 DATE : 16/ 01 /03 PAGE : 1 OF 1

TITLE : EHC.BALANCING VOLTAGE ADJUSTMENT.

REC No : C&I / TG 0 / R-1 JOBS UNIT NO: 1. 2. 3. 4.

REF. NO. C&I / TG-0 / WI-1 COMPLIANCE

PTW of PFW type with EHC rack HP/IP secondary fluid line isolation valves in position is obtained. The balancing voltage across the coil is measured after removing the cover by giving copy in put voltage to the coil and is recorded. The plunger coil is rotated till -1.0 V appears across it, and the mounting bolts are tightened and the value is recorded. The input voltage is varied at the copy input and the values are recorded. INPUT VOLTAGE 1.0 Volts 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 Volts Volts Volts Volts Volts Volts Volts Volts Volts BALANCING VOLTAGE Copy I / P V =

5.

PTW is cancelled after normalising the cover of the ECH.

AREA ENGINEER NAME : DESIGNATION: SIGNATURE : DATE :