Pipeline Design and Construction
Pipeline Design and Construction
Step by Step
An interstate offshore gathering line, other than low-stress, on which construction was begun after July 31, 1977, that transports hazardous liquid.
A pipeline, on which construction was begun after July 11, 1991, that transports carbon dioxide.
195.100 Scope.
This subpart prescribes minimum design requirements for new pipeline systems constructed with steel pipe and for relocating, replacing, or otherwise changing existing systems
(c) Except as provided in 195.5, no operator may operate any part of any of the following pipelines unless it was designed and constructed as required by this part:
An interstate offshore gathering line, other than low-stress, on which construction was begun after July 31, 1977, that transports hazardous liquid.
A pipeline, on which construction was begun after July 11, 1991, that transports carbon dioxide.
E = seam joint factor F = design factor * 2 St/O.D. Used to determine low stress
Construction
195.200 Scope.
This subpart prescribes minimum requirements for constructing new pipeline systems constructed with steel pipe and for relocating, replacing, or otherwise changing existing systems
Pipeline Construction
1. Surveying. The right-of-way is a narrow strip of land that contains the pipeline(s) and is where all onsite construction activities occur. After a planned or proposed route is determined, it is surveyed to determine the parameters that will be needed to complete the project.
Pipeline Construction
1. Maps & Materials. Once the pipeline is surveyed, ROW is purchased, alignment sheets (maps) are drawn and material lists are generated.
195.202 Compliance with specifications or standards. 195.206 Material inspection.
Pipeline Construction
2. Clearing & Grubbing. The ROW is cleared of brush and trees, and leveled to give workers and equipment access to build, inspect and maintain the pipeline.
Pipeline Construction
3. Right-of-way preparation. The right-of-way will be graded, and pads may be built to allow for the movement of ditchers, additional equipment, materials and other pipeline construction activities.
Pipeline Construction
4. Hauling and stringing the pipe. Lengths of pipe are moved from stockpile sites to the right-ofway. They are lined up along the right-of-way, ready for welding.
Stringing
Stringing is the delivery and distribution of line pipe where it is needed on the right-of-way and when it is needed
Pipeline Construction
5. Bending the pipe. A pipeline must cross over hills and curve around special places such as lakes and sacred sites. A specialized pipebending machine is used to bend some pipe to the shape of the land. The pipe retains its strength and remains circular where it is bent because of the characteristics of steel and the bending techniques used.
Bending
Bent to Fit
The pipe must be bent to reflect the general contours of the right-of-way.
Pipeline Construction
6. Welding. A technique where another metal is melted and used to join lengths of pipe. Automatic welding machines are used where possible and some hand welding also takes place. A rigorous quality assurance and quality control program is followed to ensure the strength and quality of the welding.
Welding
Beveling Machine
Welder Tractor
Firing Line
The workers responsible for the filler pass and the cap bead, which complete the joint
Good Weld?
Radiography
195.234 Welds: Nondestructive testing.
Pipeline Construction
7. Digging the trench. The way the trench or ditch is dug, and what equipment is used, depends mainly on the type of soil. Alternates include bucket wheel trenchers. Other digging equipment will include backhoes or trackhoes
195.246 Installation of pipe in a ditch. 195.248 Cover over buried pipeline. 195.250 Clearance between pipe and underground structures.
Ditching or Trenching
STOP DIGGING!!!
Trench Boxes
TAPS
Trans-Alaska Pipeline System In this case the pipeline is not lowered in-Its lowered up!
Pipeline Construction
8. Lowering the pipe. Tractors with special arms called sidebooms are used to lower the pipe into the trench. Care is taken to avoid damaging the pipe and its exterior coating.
Pipeline Construction
8. Lowering the pipe. Different tools are used to help facilitate the lowering in process. These include slings, rollers, cradles and pipe tongs. As the pipe is lowered in, a holiday detector or jeep is used to locate voids in the coating.
Pipelayer or Sideboom
Lowering In
195.246 Installation of pipe in a ditch. 195.248 Cover over buried pipeline. 195.250 Clearance between pipe and underground structures.
Fabrication
9. Installing valves and special
fittings. Valves and other connections are part of a pipeline. These assemblies are installed as the pipeline is constructed. They include shut-off valves that can block off sections of the pipeline for maintenance.
195.254 195.256 195.258 195.260 Aboveground components. Crossing of railroads and highways. Valves: General. Valves: Location.
Pipeline Construction
10. Crossings. A pipeline will need to cross rivers and streams, roads, railroads and other pipelines. Plans are developed in advance. Water crossings can be completed either by "open cut" techniques or by horizontal directional drilling.
Pipeline Construction
10. Crossings. (CONTINUED) The selection of a crossing method depends upon site specific criteria such as fish habitat, water flow, and soil conditions such as rocks and boulders. Generally, horizontal directional drilling is selected for major river crossings where local soil conditions permit the technique.
195.256 Crossing of railroads and highways.
Boring Machine
Directional Drilling
Pipeline Construction
11. Backfilling the trench. Before testing the pipeline, the ditch is backfilled. Sometimes the excavated soil is used to fill the trench and sometimes other selected backfill is used. Care is taken to protect the pipe coating from potential damage.
195.252 Backfilling.
Backfilling
Padding Machine
Tie-In
12. Tie-in. Collective term for the construction tasks bypassed by regular crews on pipeline construction. Tie-in includes welding road and river crossing, valves, portions of the pipeline left disconnected for hydrostatic testing, and other fabrication assemblies, as well as taping and coating the welds.
Pipeline Construction
13. Testing. A variety of methods will be used to ensure the integrity of the assembled pipeline and to comply with code.
195.304 195.305 195.307 195.306 195.308 195.310 Test pressure. Testing of components. Pressure testing aboveground breakout tanks. Test medium. Testing of tie-ins. Records.
Pipeline Construction
14. Dewatering. If water is used as a test medium, dewatering of the pipeline is done with dewatering pigs. The water should be disposed of in an environmentally sensitive manner.
Pipeline Construction
15. Cleaning up. The pipeline right-of-way and temporary facilities such as camps will be reclaimed.
Electromagnetic Interactions Induced voltages can be Between Power Transmission produced through capacitive, inductive and conductive Pipelines Lines and line couplings with the power
The continuous growth of energy consumptionthe power difficulties Intensity depends on and the in establishing new ROWs for line, pipeline and soil transmission power lines and metal characteristics and geometric pipelines increase the tendency to site them along the same configuration between the power routes. Consequently, electromagnetic pipeline. line and the problems can arise. Electric shocks to people who contact the pipeline Damage to can be produced under coating, insulating Voltages pipeline insulating joints normalcathodicconditions and systems and operating protection
during short-circuit occurrences at the power line
Construction spreads - whats going on during construction: Surveying, staking & pre-construction condition documentation Environmental Mitigation Relocation/replacement precautions near/over live lines Clearing, stumping, grubbing & grading Stringing & bending Welding & Coating Trenching, double ditching/HDD & bores Road and stream x-ings (rip-rap, flume & trench, etc.,) Lowering-in Tie-ins catheading Coatings, corrosion & backfill Hydro (pre & post testing), de-water, clean & dry Purging Commissioning Hot taps & stopples Final clean-up