100% found this document useful (1 vote)
352 views

Pipeline Design and Construction

The document describes the 11 key steps for designing and constructing an oil or gas pipeline, including: 1) Surveying the right-of-way 2) Clearing and grading the land 3) Welding sections of pipe together 4) Lowering the pipe into trenches 5) Installing valves and fittings It provides relevant regulations for each construction activity from 49 CFR 195, which governs pipeline safety.

Uploaded by

Arnela Hodzic
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
352 views

Pipeline Design and Construction

The document describes the 11 key steps for designing and constructing an oil or gas pipeline, including: 1) Surveying the right-of-way 2) Clearing and grading the land 3) Welding sections of pipe together 4) Lowering the pipe into trenches 5) Installing valves and fittings It provides relevant regulations for each construction activity from 49 CFR 195, which governs pipeline safety.

Uploaded by

Arnela Hodzic
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 86

Pipeline Design & Construction

Step by Step

195.401 General requirements (Subpart F)


(c) Except as provided in 195.5, no operator may operate any part of any of the following pipelines unless it was designed and constructed as required by this part: 195.5 Conversion
to service subject to this part.

195.401 General requirements (Subpart F)


(c) (1) An interstate pipeline, other than low-stress, on which construction was begun after March 31, 1970, that transports hazardous liquid.

195.401 General requirements (Subpart F)


(c)
(2)

An interstate offshore gathering line, other than low-stress, on which construction was begun after July 31, 1977, that transports hazardous liquid.

195.401 General requirements (Subpart F)


(c) (3) An intrastate pipeline, other than low-stress, on which construction was begun after October 20, 1985, that transports hazardous liquid.
(4)

A pipeline, on which construction was begun after July 11, 1991, that transports carbon dioxide.

195.401 General requirements (Subpart F)


(c) (5) A low-stress pipeline on which construction was begun after August 10, 1994.

Pipelines from the Well to the Refinery and Market

Part 195 Subpart C


Design Requirements

195.100 Scope.
This subpart prescribes minimum design requirements for new pipeline systems constructed with steel pipe and for relocating, replacing, or otherwise changing existing systems

195.401 General195.5 Conversion to service subject to requirements.


this part.

(c) Except as provided in 195.5, no operator may operate any part of any of the following pipelines unless it was designed and constructed as required by this part:

195.401 General requirements.


(c) (1) An interstate pipeline, other than low-stress, on which construction was begun after March 31, 1970, that transports hazardous liquid.

195.401 General requirements.


(c)
(2)

An interstate offshore gathering line, other than low-stress, on which construction was begun after July 31, 1977, that transports hazardous liquid.

195.401 General requirements.


(c) (3) An intrastate pipeline, other than low-stress, on which construction was begun after October 20, 1985, that transports hazardous liquid.
(4)

A pipeline, on which construction was begun after July 11, 1991, that transports carbon dioxide.

195.401 General requirements.


(c) (5) A low-stress pipeline on which construction was begun after August 10, 1994.

195.106 Internal design pressure.


P = (2 St/OD)* x E x F

E = seam joint factor F = design factor * 2 St/O.D. Used to determine low stress

Part 195 Subpart D

Construction

Pipeline Construction Sequence

195.200 Scope.
This subpart prescribes minimum requirements for constructing new pipeline systems constructed with steel pipe and for relocating, replacing, or otherwise changing existing systems

Pipeline Construction
1. Surveying. The right-of-way is a narrow strip of land that contains the pipeline(s) and is where all onsite construction activities occur. After a planned or proposed route is determined, it is surveyed to determine the parameters that will be needed to complete the project.

195.210 Pipeline location.

195.210 Pipeline location.


ROW must be selected to avoid, as far as practicable:
areas containing private dwellings industrial buildings places of public assembly

195.210 Pipeline location.


Pipeline may not be located within 50 feet of any:
private dwelling industrial building places of public assembly

unless 12 of cover is added.

Pipeline Construction
1. Maps & Materials. Once the pipeline is surveyed, ROW is purchased, alignment sheets (maps) are drawn and material lists are generated.
195.202 Compliance with specifications or standards. 195.206 Material inspection.

195.202 Compliance with specifications or standards.


Each pipeline system must be constructed in accordance with comprehensive written specifications or standards that are consistent with the requirements of this part.

195.206 Material inspection.


No pipe or other component may be installed unless it has been visually inspected at site.

Pipeline Construction
2. Clearing & Grubbing. The ROW is cleared of brush and trees, and leveled to give workers and equipment access to build, inspect and maintain the pipeline.

Track-Type Tractor or Dozer

195.204 Inspection - general.


Inspection must be provided to ensure the installation of pipe or pipeline systems in accordance with the requirements of this subpart.

195.204 Inspection - general.


No person may be used to perform inspections unless that person has been trained and is qualified in the phase of construction to be inspected.

Pipeline Construction
3. Right-of-way preparation. The right-of-way will be graded, and pads may be built to allow for the movement of ditchers, additional equipment, materials and other pipeline construction activities.

Pipeline Construction
4. Hauling and stringing the pipe. Lengths of pipe are moved from stockpile sites to the right-ofway. They are lined up along the right-of-way, ready for welding.

Stringing
Stringing is the delivery and distribution of line pipe where it is needed on the right-of-way and when it is needed

Pipeline Construction
5. Bending the pipe. A pipeline must cross over hills and curve around special places such as lakes and sacred sites. A specialized pipebending machine is used to bend some pipe to the shape of the land. The pipe retains its strength and remains circular where it is bent because of the characteristics of steel and the bending techniques used.

Bending

Hydraulic Pipe Bending Machines

Pneumatic Bending Mandrel

Bent to Fit
The pipe must be bent to reflect the general contours of the right-of-way.

195.212 Bending of pipe.


Pipe may not have a wrinkle bend. Each field bend must comply with the following:

195.212 Bending of pipe.


not impair serviceability have a smooth contour pipe with longitudinal weld, must be in neutral axis unless-made with internal mandrel pipe is <12 or has diameter to w.t. ratio <70

Pipeline Construction
6. Welding. A technique where another metal is melted and used to join lengths of pipe. Automatic welding machines are used where possible and some hand welding also takes place. A rigorous quality assurance and quality control program is followed to ensure the strength and quality of the welding.

Welding

Beveling Machine

External Line-up Clamps

Pneumatic Internal Lineup Clamp

Automatic External Welder

Automatic Internal Welder

Pipe Facing Machine

Welding Truck Rig

Welder Tractor

The Pipe Gang


The workers responsible for positioning the pipe, aligning it, and making the initial welds.

Firing Line
The workers responsible for the filler pass and the cap bead, which complete the joint

195.208 Welding of supports and braces.


May NOT be welded to pipe which operates over 100 psig.

Good Weld?

Radiography
195.234 Welds: Nondestructive testing.

Field Joint Coating


Mill coated pipe has a cutback of 6-9 inches at the end of the pipe to not interfere with welding. This cutback must be coated once the weld is complete.
195.557 Which pipelines must have coating for external corrosion control? 195.559 What coating material may I use for external corrosion control?
195.561 When must I inspect pipe coating used for external corrosion control? 195.581 Which pipelines must I protect against atmospheric corrosion and what coating material may I use?

Pipeline Construction
7. Digging the trench. The way the trench or ditch is dug, and what equipment is used, depends mainly on the type of soil. Alternates include bucket wheel trenchers. Other digging equipment will include backhoes or trackhoes
195.246 Installation of pipe in a ditch. 195.248 Cover over buried pipeline. 195.250 Clearance between pipe and underground structures.

Hydraulic Excavator or Trackhoe

Backhoe or Rubber-Tired Hoe

Trencher or Ditching Machine

Ditching or Trenching

First Rule of Holes:

When youre in one . . .

STOP DIGGING!!!

Trench Boxes

TAPS
Trans-Alaska Pipeline System In this case the pipeline is not lowered in-Its lowered up!

Supported aboveground by vertical support members

Pipeline Construction
8. Lowering the pipe. Tractors with special arms called sidebooms are used to lower the pipe into the trench. Care is taken to avoid damaging the pipe and its exterior coating.

Pipeline Construction
8. Lowering the pipe. Different tools are used to help facilitate the lowering in process. These include slings, rollers, cradles and pipe tongs. As the pipe is lowered in, a holiday detector or jeep is used to locate voids in the coating.

Pipelayer or Sideboom

Lowering In

195.246 Installation of pipe in a ditch. 195.248 Cover over buried pipeline. 195.250 Clearance between pipe and underground structures.

Fabrication
9. Installing valves and special
fittings. Valves and other connections are part of a pipeline. These assemblies are installed as the pipeline is constructed. They include shut-off valves that can block off sections of the pipeline for maintenance.
195.254 195.256 195.258 195.260 Aboveground components. Crossing of railroads and highways. Valves: General. Valves: Location.

Pipeline Construction
10. Crossings. A pipeline will need to cross rivers and streams, roads, railroads and other pipelines. Plans are developed in advance. Water crossings can be completed either by "open cut" techniques or by horizontal directional drilling.

Pipeline Construction
10. Crossings. (CONTINUED) The selection of a crossing method depends upon site specific criteria such as fish habitat, water flow, and soil conditions such as rocks and boulders. Generally, horizontal directional drilling is selected for major river crossings where local soil conditions permit the technique.
195.256 Crossing of railroads and highways.

Boring Machine

Directional Drilling Machine

Horizontal Drilling Rig

Directional Drilling

Pipeline Construction
11. Backfilling the trench. Before testing the pipeline, the ditch is backfilled. Sometimes the excavated soil is used to fill the trench and sometimes other selected backfill is used. Care is taken to protect the pipe coating from potential damage.
195.252 Backfilling.

Backfilling

Track-Type Tractor or Dozer

Padding Machine

Tie-In
12. Tie-in. Collective term for the construction tasks bypassed by regular crews on pipeline construction. Tie-in includes welding road and river crossing, valves, portions of the pipeline left disconnected for hydrostatic testing, and other fabrication assemblies, as well as taping and coating the welds.

Pipeline Construction
13. Testing. A variety of methods will be used to ensure the integrity of the assembled pipeline and to comply with code.
195.304 195.305 195.307 195.306 195.308 195.310 Test pressure. Testing of components. Pressure testing aboveground breakout tanks. Test medium. Testing of tie-ins. Records.

Pipeline Construction
14. Dewatering. If water is used as a test medium, dewatering of the pipeline is done with dewatering pigs. The water should be disposed of in an environmentally sensitive manner.

Pipeline Construction
15. Cleaning up. The pipeline right-of-way and temporary facilities such as camps will be reclaimed.

Electromagnetic Interactions Between Power Transmission Lines and Pipelines


The continuous growth of energy consumption and the difficulties in establishing new ROWs for transmission power lines and metal pipelines increase the tendency to site them along the same routes. Consequently, electromagnetic problems can arise. Electric shocks to people who contact the pipeline Damage to pipeline insulating coating, insulating joints and cathodic protection systems

Electromagnetic Interactions Induced voltages can be Between Power Transmission produced through capacitive, inductive and conductive Pipelines Lines and line couplings with the power
The continuous growth of energy consumptionthe power difficulties Intensity depends on and the in establishing new ROWs for line, pipeline and soil transmission power lines and metal characteristics and geometric pipelines increase the tendency to site them along the same configuration between the power routes. Consequently, electromagnetic pipeline. line and the problems can arise. Electric shocks to people who contact the pipeline Damage to can be produced under coating, insulating Voltages pipeline insulating joints normalcathodicconditions and systems and operating protection
during short-circuit occurrences at the power line

Electromagnetic Interactions Between Power Transmission Lines and Pipelines


Pipeline induced voltages should be compared to safety limits established by industry codes. Underground sections of pipeline checked with respect to the risks of damage to pipeline coating. Above-ground sections checked for risks of potential electric shocks to people. Voltage across insulating joints compared to the voltage withstand capability. Cathodic protection systems checked for maximum voltages at their connection to the pipeline.

Other Safety Considerations


When driving on the Right-of-Way - watch out for HEAVY EQUIPMENT!

Other Safety Considerations


Wild animals are about in the woods be careful!

Other Safety Considerations


Overhead power lines and equipment-dont be in contact with equipment or stand near (water, mud other conductors) Wear proper personal protective equipment Beware of lengths of welded pipe on skids without proper cribbing Dont stand near pipe being lifted from ground Dont stand near pipe truck being unloaded
Note improperly chocked pipe

Other Safety Considerations


Sideboom A-frames dont fall up Sidebooms can flip over when lifting pipe Sidebooms can roll over backward on an incline Be aware of worn cables or slings Hydraulic hoses can break causing unintended equipment movement

Other Safety Considerations


Be aware of trenching and shoring safety precautions Dont stand near the edge of an excavation Dont enter an unsafe excavation Equipment vibrations can cause a cave-in Welding can cause a flash Welding at night near glass can reflect the same damaging radiation Avoid touching the tail of the jeep

Pipeline Construction Sequence

Construction spreads - whats going on during construction: Surveying, staking & pre-construction condition documentation Environmental Mitigation Relocation/replacement precautions near/over live lines Clearing, stumping, grubbing & grading Stringing & bending Welding & Coating Trenching, double ditching/HDD & bores Road and stream x-ings (rip-rap, flume & trench, etc.,) Lowering-in Tie-ins catheading Coatings, corrosion & backfill Hydro (pre & post testing), de-water, clean & dry Purging Commissioning Hot taps & stopples Final clean-up

You might also like