Software Project
Management (Lecture 9)
Dr. R. Mall
1
Organization of this
Lecture:
Introduction to Project Planning
Software Cost Estimation
Cost Estimation Models
Software Size Metrics
Empirical Estimation
Heuristic Estimation
COCOMO
Staffing Level Estimation
Effect of Schedule Compression on Cost
Summary
2
Introduction
Many software projects fail:
due to faulty project
management practices:
It is important to learn different
aspects of software project
management.
3
Introduction
Goal of software project
management:
enable a group of engineers to work
efficiently towards successful
completion of a software project.
4
Responsibility of project
managers
Project proposal writing,
Project cost estimation,
Scheduling,
Project staffing,
Project monitoring and control,
Software configuration management,
Risk management,
Managerial report writing and presentations, etc.
5
Introduction
A project manager’s activities
are varied.
can be broadly classified into:
project planning,
project monitoring and control
activities.
6
Project Planning
Once a project is found to be
feasible,
project managers undertake project
planning.
7
Project Planning Activities
Estimation:
Effort, cost, resource, and project duration
Project scheduling:
Staff organization:
staffing plans
Risk handling:
identification, analysis, and abatement
procedures
Miscellaneous plans:
quality assurance plan, configuration
management plan, etc.
8
Project planning
Requires utmost care and attention ---
commitments to unrealistic time and
resource estimates result in:
irritating delays.
customer dissatisfaction
adverse affect on team morale
poor quality work
project failure.
9
Sliding Window Planning
Involves project planning over
several stages:
protects managers from making big
commitments too early.
More information becomes available
as project progresses.
Facilitates accurate planning
10
SPMP Document
After planning is complete:
Document the plans:
in a Software Project
Management Plan(SPMP)
document.
11
Organization of SPMP Document
Introduction (Objectives,Major Functions,Performance Issues,Management and Technical
Constraints)
Project Estimates (Historical Data,Estimation Techniques,Effort, Cost, and Project Duration Estimates)
Project Resources Plan (People,Hardware and Software,Special Resources)
Schedules (Work Breakdown Structure,Task Network, Gantt Chart Representation,PERT Chart
Representation)
Risk Management Plan (Risk Analysis,Risk Identification,Risk Estimation, Abatement
Procedures)
Project Tracking and Control Plan
Miscellaneous Plans(Process Tailoring,Quality Assurance)
12
Software Cost Estimation
Determine size of the product.
From the size estimate,
determine the effort needed.
From the effort estimate,
determine project duration, and cost.
13
Software Cost Estimation
Effort Cost
Estimation Estimation
Size Staffing
Estimation Estimation
Duration
Estimation Scheduling
14
Software Cost Estimation
Three main approaches to
estimation:
Empirical
Heuristic
Analytical
15
Software Cost Estimation
Techniques
Empirical techniques:
an educated guess based on past experience.
Heuristic techniques:
assume that the characteristics to be
estimated can be expressed in terms of
some mathematical expression.
Analytical techniques:
derive the required results starting from
certain simple assumptions.
16
Software Size Metrics
LOC (Lines of Code):
Simplest and most widely used
metric.
Comments and blank lines should
not be counted.
17
Disadvantages of Using LOC
Size can vary with coding style.
Focuses on coding activity alone.
Correlates poorly with quality and
efficiency of code.
Penalizes higher level programming
languages, code reuse, etc.
18
Disadvantages of Using LOC
(cont...)
Measures lexical/textual complexity
only.
does not address the issues of
structural or logical complexity.
Difficult to estimate LOC from
problem description.
So not useful for project planning
19
Function Point Metric
Overcomes some of the shortcomings of
the LOC metric
Proposed by Albrecht in early 80's:
FP=4 #inputs + 5 #Outputs + 4
#inquiries + 10 #files + 10 #interfaces
Input:
A set of related inputs is counted as one input.
20
Function Point Metric
Output:
A set of related outputs is counted as one output.
Inquiries:
Each user query type is counted.
Files:
Files are logically related data and thus can be data
structures or physical files.
Interface:
Data transfer to other systems.
21
Function Point Metric (CONT.)
Suffers from a major drawback:
the size of a function is considered to be
independent of its complexity.
Extend function point metric:
Feature Point metric:
considers an extra parameter:
Algorithm Complexity.
22
Function Point Metric (CONT.)
Proponents claim:
FP is language independent.
Size can be easily derived from problem
description
Opponents claim:
it is subjective --- Different people can come
up with different estimates for the same
problem.
23
Empirical Size Estimation
Techniques
Expert Judgement:
An euphemism for guess made by
an expert.
Suffers from individual bias.
Delphi Estimation:
overcomes some of the problems of
expert judgement.
24
Expert judgement
Experts divide a software product into
component units:
e.g. GUI, database module, data
communication module, billing module,
etc.
Add up the guesses for each of the
components.
25
Delphi Estimation:
Team of Experts and a coordinator.
Experts carry out estimation
independently:
mention the rationale behind their
estimation.
coordinator notes down any
extraordinary rationale:
circulates among experts.
26
Delphi Estimation:
Experts re-estimate.
Experts never meet each other
to discuss their viewpoints.
27
Heuristic Estimation Techniques
Single Variable Model:
Parameter to be Estimated=C1(Estimated
Characteristic)d1
Multivariable Model:
Assumes that the parameter to be
estimated depends on more than one
characteristic.
Parameter to be Estimated=C1(Estimated
Characteristic)d1+ C2(Estimated Characteristic)d2+…
Usually more accurate than single variable
models.
28
COCOMO Model
COCOMO (COnstructive COst MOdel)
proposed by Boehm.
Divides software product
developments into 3 categories:
Organic
Semidetached
Embedded
29
COCOMO Product classes
Roughly correspond to:
application, utility and system programs
respectively.
Data processing and scientific programs are
considered to be application programs.
Compilers, linkers, editors, etc., are utility
programs.
Operating systems and real-time system
programs, etc. are system programs.
30
Elaboration of Product
classes
Organic:
Relatively small groups
working to develop well-understood applications.
Semidetached:
Project team consists of a mixture of
experienced and inexperienced staff.
Embedded:
The software is strongly coupled to complex
hardware, or real-time systems.
31
COCOMO Model (CONT.)
For each of the three product categories:
From size estimation (in KLOC), Boehm provides
equations to predict:
project duration in months
effort in programmer-months
Boehm obtained these equations:
examined historical data collected from a large
number of actual projects.
32
COCOMO Model (CONT.)
Software cost estimation is done
through three stages:
Basic COCOMO,
Intermediate COCOMO,
Complete COCOMO.
33
Basic COCOMO Model (CONT.)
Gives only an approximate estimation:
Effort = a1 (KLOC)a2
Tdev = b1 (Effort)b2
KLOC is the estimated kilo lines of source
code,
a1,a2,b1,b2 are constants for different
categories of software products,
Tdev is the estimated time to develop the
software in months,
Effort estimation is obtained in terms of
person months (PMs).
34
Development Effort
Estimation
Organic :
Effort = 2.4 (KLOC)1.05 PM
Semi-detached:
Effort = 3.0(KLOC)1.12 PM
Embedded:
Effort = 3.6 (KLOC)1.20PM
35
Development Time
Estimation
Organic:
Tdev = 2.5 (Effort)0.38 Months
Semi-detached:
Tdev = 2.5 (Effort)0.35 Months
Embedded:
Tdev = 2.5 (Effort)0.32 Months
36
Basic COCOMO Model (CONT.)
d
che
Effort is Effort
em
id
et
a
S
somewhat be
d ded
super-linear in Em
Or
ga
n ic
problem size.
Size
37
Basic COCOMO Model (CONT.)
Development time
sublinear function of
product size. Dev. Time
When product size ded ched
bed ide ta
increases two times, 18 Months Em Sem
development time does
14 Months
not double. gan
ic
Or
Time taken:
almost same for all the 30K 60K
three product categories. Size
38
Basic COCOMO Model (CONT.)
Development time does not
increase linearly with product size:
For larger products more parallel
activities can be identified:
can be carried out simultaneously by a
number of engineers.
39
Basic COCOMO Model (CONT.)
Development time is roughly the same for
all the three categories of products:
For example, a 60 KLOC program can be
developed in approximately 18 months
regardless of whether it is of organic, semi-
detached, or embedded type.
There is more scope for parallel activities for
system and application programs,
than utility programs.
40
Example
The size of an organic software product has
been estimated to be 32,000 lines of source
code.
Effort = 2.4*(32)1.05 = 91 PM
Nominal development time = 2.5*(91)0.38 = 14
months
41
Intermediate COCOMO
Basic COCOMO model assumes
effort and development time depend on
product size alone.
However, several parameters affect effort
and development time:
Reliability requirements
Availability of CASE tools and modern facilities to
the developers
Size of data to be handled
42
Intermediate COCOMO
For accurate estimation,
the effect of all relevant parameters
must be considered:
Intermediate COCOMO model recognizes
this fact:
refines the initial estimate obtained by the
basic COCOMO by using a set of 15 cost
drivers (multipliers).
43
Intermediate COCOMO
(CONT.)
If modern programming practices
are used,
initial estimates are scaled
downwards.
If there are stringent reliability
requirements on the product :
initial estimate is scaled upwards.
44
Intermediate COCOMO
(CONT.)
Rate different parameters on a
scale of one to three:
Depending on these ratings,
multiply cost driver values with
the estimate obtained using the
basic COCOMO.
45
Intermediate COCOMO
(CONT.)
Cost driver classes:
Product: Inherent complexity of the product,
reliability requirements of the product, etc.
Computer: Execution time, storage
requirements, etc.
Personnel: Experience of personnel, etc.
Development Environment: Sophistication of
the tools used for software development.
46
Shortcoming of basic and
intermediate COCOMO models
Both models:
consider a software product as a single
homogeneous entity:
However, most large systems are made up of
several smaller sub-systems.
Some sub-systems may be considered as organic
type, some may be considered embedded, etc.
for some the reliability requirements may be high,
and so on.
47
Complete COCOMO
Cost of each sub-system is estimated
separately.
Costs of the sub-systems are added to
obtain total cost.
Reduces the margin of error in the
final estimate.
48
Complete COCOMO
Example
A Management Information System (MIS) for an
organization having offices at several places
across the country:
Database part (semi-detached)
Graphical User Interface (GUI) part (organic)
Communication part (embedded)
Costs of the components are estimated
separately:
summed up to give the overall cost of the system.
49
Halstead's Software
Science
An analytical technique to
estimate:
size,
development effort,
development time.
50
Halstead's Software
Science
Halstead used a few primitive program
parameters
number of operators and operands
Derived expressions for:
over all program length,
potential minimum volume
actual volume,
language level,
effort, and
development time.
51
Staffing Level Estimation
Number of personnel required during
any development project:
not constant.
Norden in 1958 analyzed many R&D
projects, and observed:
Rayleigh curve represents the number of
full-time personnel required at any time.
52
Rayleigh Curve
Rayleigh curve is Rayleigh Curve
specified by two
parameters: Effort
td the time at
which the curve
reaches its
maximum td
K the total area Time
under the curve.
L=f(K, td)
53
Putnam’s Work:
In 1976, Putnam studied the problem of
staffing of software projects:
observed that the level of effort required in
software development efforts has a similar
envelope.
found that the Rayleigh-Norden curve
relates the number of delivered lines of code to
effort and development time.
54
Putnam’s Work (CONT.) :
Putnam analyzed a large number of army
projects, and derived the expression:
L=CkK1/3td4/3
K is the effort expended and L is the size in
KLOC.
td is the time to develop the software.
Ck is the state of technology constant
reflects factors that affect programmer
productivity.
55
Putnam’s Work (CONT.) :
Ck=2 for poor development environment
no methodology, poor documentation, and
review, etc.
Ck=8 for good software development
environment
software engineering principles used
Ck=11 for an excellent environment
56
Rayleigh Curve
Very small number of engineers are
needed at the beginning of a project
carry out planning and specification.
As the project progresses:
more detailed work is required,
number of engineers slowly increases
and reaches a peak.
57
Rayleigh Curve
Putnam observed that:
the time at which the Rayleigh curve
reaches its maximum value
corresponds to system testing and product
release.
After system testing,
the number of project staff falls till product
installation and delivery.
58
Rayleigh Curve
From the Rayleigh curve observe
that:
approximately 40% of the area
under the Rayleigh curve is to the
left of td
and 60% to the right.
59
Effect of Schedule Change
on Cost
Using the Putnam's expression for L,
K=L3/Ck3td4
Or, K=C1/td4
For the same product size, C1=L3/Ck3
is a constant.
Or, K1/K2 = td24/td14
60
Effect of Schedule Change on
Cost (CONT.)
Observe:
a relatively small compression in delivery
schedule
can result in substantial penalty on human
effort.
Also, observe:
benefits can be gained by using fewer
people over a somewhat longer time span.
61
Example
If the estimated development time is 1
year, then in order to develop the
product in 6 months,
the total effort and hence the cost
increases 16 times.
In other words,
the relationship between effort and the
chronological delivery time is highly nonlinear.
62
Effect of Schedule Change on
Cost (CONT.)
Putnam model indicates extreme penalty
for schedule compression
and extreme reward for expanding the
schedule.
Putnam estimation model works
reasonably well for very large systems,
but seriously overestimates the effort for
medium and small systems.
63
Effect of Schedule Change on
Cost (CONT.)
Boehm observed:
“There is a limit beyond which the
schedule of a software project cannot
be reduced by buying any more
personnel or equipment.”
This limit occurs roughly at 75% of the
nominal time estimate.
64
Effect of Schedule Change
on Cost (CONT.)
If a project manager accepts a customer
demand to compress the development
time by more than 25%
very unlikely to succeed.
every project has only a limited amount of parallel
activities
sequential activities cannot be speeded up by hiring
any number of additional engineers.
many engineers have to sit idle.
65
Jensen Model
Jensen model is very similar to
Putnam model.
attempts to soften the effect of
schedule compression on effort
makes it applicable to smaller and
medium sized projects.
66
Jensen Model
Jensen proposed the equation:
L=CtetdK1/2
Where,
Cte is the effective technology constant,
td is the time to develop the software, and
K is the effort needed to develop the
software.
67
Organization Structure
Functional Organization:
Engineers are organized into functional
groups, e.g.
specification, design, coding, testing,
maintenance, etc.
Engineers from functional groups get
assigned to different projects
68
Advantages of Functional
Organization
Specialization
Ease of staffing
Good documentation is produced
different phases are carried out by
different teams of engineers.
Helps identify errors earlier.
69
Project Organization
Engineers get assigned to a project
for the entire duration of the project
Same set of engineers carry out all the
phases
Advantages:
Engineers save time on learning details
of every project.
Leads to job rotation
70
Team Structure
Problems of different complexities
and sizes require different team
structures:
Chief-programmer team
Democratic team
Mixed organization
71
Democratic Teams
Suitable for:
small projects requiring less than five or six
engineers
research-oriented projects
A manager provides administrative
leadership:
at different times different members of the
group provide technical leadership.
72
Democratic Teams
Democratic organization provides
higher morale and job satisfaction to the
engineers
therefore leads to less employee turnover.
Suitable for less understood problems,
a group of engineers can invent better
solutions than a single individual.
73
Democratic Teams
Disadvantage:
team members may waste a
lot time arguing about trivial
points:
absence of any authority in the
team.
74
Chief Programmer Team
A senior engineer provides
technical leadership:
partitions the task among the team
members.
verifies and integrates the products
developed by the members.
75
Chief Programmer Team
Works well when
the task is well understood
also within the intellectual grasp of a single
individual,
importance of early completion
outweighs other factors
team morale, personal development, etc.
76
Chief Programmer Team
Chief programmer team is subject to
single point failure:
too much responsibility and authority is
assigned to the chief programmer.
77
Mixed Control Team
Organization
Draws upon ideas from both:
democratic organization and
chief-programmer team organization.
Communication is limited
to a small group that is most likely to benefit
from it.
Suitable for large organizations.
78
Team Organization
Democratic Team
Chief Programmer team
79
Mixed team organization
80
Summary
We discussed the broad
responsibilities of the project
manager:
Project planning
Project Monitoring and Control
81
Summary
To estimate software cost:
Determine size of the product.
Using size estimate,
determine effort needed.
From the effort estimate,
determine project duration, and cost.
82
Summary (CONT.)
Cost estimation techniques:
Empirical Techniques
Heuristic Techniques
Analytical Techniques
Empirical techniques:
based on systematic guesses by experts.
Expert Judgement
Delphi Estimation
83
Summary (CONT.)
Heuristic techniques:
assume that characteristics of a software
product can be modeled by a mathematical
expression.
COCOMO
Analytical techniques:
derive the estimates starting with some basic
assumptions:
Halstead's Software Science
84
Summary (CONT.)
The staffing level during the life cycle of a
software product development:
follows Rayleigh curve
maximum number of engineers required
during testing.
85
Summary (CONT.)
Relationship between schedule change and
effort:
highly nonlinear.
Software organizations are usually
organized in:
functional format
project format
86
Summary (CONT.)
Project teams can be organized in
following ways:
Chief programmer: suitable for routine work.
Democratic: Small teams doing R&D type work
Mixed: Large projects
87