Distech - Protocols Explained
Distech - Protocols Explained
User Guide
1. Version 2.0 - May 2016:
• Added information for the ECx-Display.
2. Version 2.1 - Minor updates
3. Version 2.2 - Updated user guide with content regarding the new generation of ECB/ECL-VAVs
4. Version 2.3 - May 2018 - Minor miscellaneous corrections.
5. Version 2.4 - July 2018 - Minor correction to supported quantities of EC-Multi-Sensors
6. Version 2.5 - Dec. 2020 - Minor update: SmartInstaller renamed to Software Center.
Network Guide_UG_25_EN
While all efforts have been made to verify the accuracy of information in this manual, Distech Controls
is not responsible for damages or claims arising from the use of this manual. Persons using this man-
ual are assumed to be trained HVAC professionals and are responsible for using the correct wiring
procedures, correct override methods for equipment control and maintaining safe working conditions in
fail-safe environments. Distech Controls reserves the right to change, delete or add to the information
in this manual at any time without notice.
Distech Controls, the Distech Controls logo, and Innovative Solutions for Greener Buildings are regis-
tered trademarks of Distech Controls, Inc. BACnet is a registered trademark of ASHRAE. All other
trademarks are property of their respective owners.
TABLE OF CONTENTS
CHAPTER 1
Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
About BACnet®. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
About LONWORKS® . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
About Subnetworks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
About This User Guide . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Purpose of the User Guide. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Intended Audience . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Referenced Documentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Conventions Used in this Document . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Related Documentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Acronyms and Abbreviations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
CHAPTER 2
BACnet MS/TP Communication Data Bus Fundamentals . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
BACnet MS/TP Data Transmission Essentials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
BACnet MS/TP Data Bus is Polarity Sensitive. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Maximum Number of BACnet MS/TP Devices on a Data Bus Segment and Baud Rate . . . . . . . 14
Data Bus Segment MAC Address Range for BACnet MS/TP Devices . . . . . . . . . . . . . . . . . 14
Device Loading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
About Setting Built-in EOL Terminations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
Only a Daisy-Chained Data Bus Topology is Acceptable . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
Data Bus Physical Specifications and Cable Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
Data Bus Topology and EOL Terminations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
When to Use EOL Terminations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
When to use EOL Terminations with BACnet MS/TP Thermostats . . . . . . . . . . . . . . . . . . . . 21
About Setting Built-in EOL Terminations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Only a Daisy-Chained Data Bus Topology is Acceptable . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Data Bus Shield Grounding Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
ECB 24V Powered Controller Data Bus Shield Grounding Requirements. . . . . . . . . . . . . . . 24
ECB-PTU Line-Powered Data Bus Controller Shield Grounding Requirements . . . . . . . . . . 25
Data Bus Shield Grounding Requirements When Mixing Both ECB 24V-Powered Controllers
and ECB-PTU Line-Powered Controllers. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
Using Repeaters to Extend the Data Bus. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
Device Addressing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
Setting the Controller's MAC Address Through a DIP Switch . . . . . . . . . . . . . . . . . . . . . . . . 38
Setting the Controller's MAC Address Through a Connected Allure EC-Smart-Vue Sensor . 39
Setting the Controller's MAC Address Through the color LCD Screen of a 50 Series Controller
39
Power Supply Requirements for 24V Controllers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
BACnet MS/TP is a Three-Wire Data Bus . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
Avoid Ground Lift . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
Techniques to Reduce Ground Lift . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
About External Loads. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
Peak Current . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
Transformer Selection and Determining the Maximum Power Run Length . . . . . . . . . . . . . . 43
Recommended 24V Power Cable . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
24VAC Power Supply Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
ECx-4XX I/O Extension Module Power Supply Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
Typical Device BACnet MS/TP LAN and Power Wiring Diagram . . . . . . . . . . . . . . . . . . . . . . . . . 49
Network Guide 1
Table of Contents
CHAPTER 3
LonWorks Communication Bus Fundamentals . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
Network Architecture. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
EC-Net Network Architecture . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
TP/FT 10 Network Topologies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
Bus Topology . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
Free Topology . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
Network Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
TP/FT 10 Cable Specifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56
Extending the Network . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59
Grounding a Network . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60
Grounding Shielded Twisted Pair Cable. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60
Building Entrance Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60
Power Supply Requirements for 24V Controllers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61
About External Loads . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61
Transformer Selection and Determining the Maximum Power Run Length . . . . . . . . . . . . . 61
Recommended 24V Power Cable . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64
24V Power Supply Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64
ECx-4XX I/O Extension Module Power Supply Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . 66
CHAPTER 4
Subnetwork Installation Guidelines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69
About the Subnetwork Data Bus . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70
Subnetwork Connection Method . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70
Subnetwork Module Compatibility and Supported Quantity Charts . . . . . . . . . . . . . . . . . . . 71
Subnetwork Module Connection. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74
Subnetwork Data Bus Length. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 75
Cat 5e Cable Subnetwork Data Bus . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79
Cat 5e Cable Subnetwork Data Bus Cable Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . 79
Cat 5e Cable Subnetwork Bus Topology and End-of-Line Terminations . . . . . . . . . . . . . . . 80
Setting the Subnet ID Addressing for Room Devices . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84
Setting the Allure EC-Smart-Air and EC-Smart-Comfort Communicating Sensor Series' Subnet ID
Address . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86
Setting the EC-Multi-Sensor Series' Subnet ID Address . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 88
Setting the ECx-Light and ECx-Blind Series' Subnet ID Address . . . . . . . . . . . . . . . . . . . . . . . . 89
2-Wire Subnetwork Data Bus . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 92
2-Wire Subnetwork Data Bus Topology and End-of-Line (EOL) Terminations . . . . . . . . . . 93
2-Wire Subnetwork Data Bus Shield Grounding Requirements . . . . . . . . . . . . . . . . . . . . . . 94
ECx-4XX I/O Extension Module Addressing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 95
Power Supply Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 96
CHAPTER 5
Controller Installation and Maintenance Tasks with an Allure EC-Smart-Vue Sensor . . . . . . . . . . . . 97
Commissioning a Controller with an Allure EC-Smart-Vue Sensor. . . . . . . . . . . . . . . . . . . . . . . 98
Setting the Allure EC-Smart-Vue Sensor's Subnet ID Address . . . . . . . . . . . . . . . . . . . . . . 98
Commissioning Controllers. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 99
Setting the Baud Rate for ECB-Series Controllers (optional) . . . . . . . . . . . . . . . . . . . . . . . 101
Connecting to the LAN through an Allure EC-Smart-Vue Sensor . . . . . . . . . . . . . . . . . . . 102
LAN through an Allure EC-Smart-Vue Sensor for a LonWorks Network . . . . . . . . . . . . . . 104
LAN through an Allure EC-Smart-Vue Sensor for a BACnet Network . . . . . . . . . . . . . . . . 106
CHAPTER 6
2 Network Guide
TABLE OF CONTENTS
BACnet Troubleshooting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 109
CHAPTER 7
LonWorks Troubleshooting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 115
CHAPTER 8
ECx-4XX Series I/O Extension Module Specific Troubleshooting . . . . . . . . . . . . . . . . . . . . . . . . . . 121
CHAPTER 9
Allure EC-Smart-Vue Sensor Troubleshooting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 123
CHAPTER 10
ECx-Light/Blind Series Troubleshooting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 127
APPENDIX A
Typical BACnet EIA-485 Data Bus Transmission Example . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 129
APPENDIX B
How to Set a Dip Switch . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 131
APPENDIX C
Metric Conversions for Wire Gauge . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133
Network Guide 3
Table of Contents
4 Network Guide
Introduction
CHAPTER 1
Introduction
This section provides an overview of the user guide.
Topics
Introduction
About This User Guide
Acronyms and Abbreviations
Network Guide 5
Introduction
This document describes best practices, specifications, wiring rules, device termination, and
application information to implement robust and reliable communications networks.
About BACnet®
The BACnet® ANSI/ASHRAE™ Standard 135-2008 specifies a number of Local Area Net-
work (LAN) transport types. Distech Controls' controllers use both BACnet IP and BACnet
Master-Slave/Token-Passing (MS/TP) communications data bus (based on EIA 485) as a
local network for internetworking of supervisory controllers and field controllers.
About LONWORKS®
The LONWORKS standard ANSI/CEA-709.1-B specifies a number of Local Area Network (LAN)
transport types. Distech Controls' controllers use a twisted pair "free topology" communica-
tions data bus operating at 78 kbit/s as a local network for internetworking of supervisory con-
trollers and field controllers.
LONWORKS is one of several network types of the BACnet® ANSI/ASHRAE™ Standard; how-
ever, no Distech Controls' controllers are compatible with this network type except for an EC-
Net.
About Subnetworks
The Distech Controls' controllers and devices (BACnet and LONWORKS) use the subnetwork
data bus to support various expansion / extension modules such as the following: Allure
Series sensors, ECx-4XX I/O Extension Module, ECx-Light 4 / ECx-Light 4D / ECx-Light
4DALI, ECx-Blind 4 / ECx-Blind 4LV, and EC-Multi-Sensor series.
6 Network Guide
Introduction
For BACnet
This User Guide describes the best practices for installing a BACnet MS/TP LAN and reviews
the specifications, device limits, BACnet MS/TP LAN cable requirements, best wiring prac-
tices, the importance of rigorous grounding practices, 24 volt power supply wiring require-
ments, BACnet MS/TP data bus termination and shield grounding, setting the MAC address
and Device Instance for devices on a BACnet MS/TP LAN, and finally LAN troubleshooting.
This user guide is intended to provide BACnet LAN information to instruct a user to install and
configure a BACnet MS/TP LAN. However, this guide is not intended to instruct the user on
how configure the devices connected to the LAN, to use network management tool software,
to program a device to share points on the network, or the procedure to install a given device.
For this information, refer to the device's hardware installation guide and its related program-
ming user guide.
For LONWORKS
This User Guide describes the best practices for installing a LONWORKS LAN and reviews
the specifications, device limits, LAN cable requirements, best wiring practices, grounding
practices, 24 volt power supply wiring requirements, LONWORKS network termination, and
finally LAN troubleshooting.
This user guide is intended to provide LONWORKS LAN information to instruct a user to install
and configure a LONWORKS LAN. However, this guide is not intended to instruct the user on
how configure the devices connected to the LAN, to use network management tool software,
to program a device to share points on the network, or the procedure to install a given device.
For this information, refer to the device's hardware installation guide and its related program-
ming user guide.
For Subnetworks
This user guide also describes the best practices for installing the subnetwork used for Distech
Controls' expansion / extension modules; for example, the cable requirements, best wiring
practices, grounding practices, power supply wiring requirements, data bus termination, and
device addressing.
Network Guide 7
Intended Audience
This user guide is intended for system designers, integrators, electricians, and field techni-
cians who have experience with control systems, and who want to learn about how to make a
successful BACnet MS/TP LAN or LONWORKS installation. It is recommended that anyone
installing and configuring the devices specified in this user guide have prior training in the
usage of these devices.
Referenced Documentation
The follow documentation is referenced in this document.
Junction Box and Wiring Guideline for Twisted Pair LONWORKS® Networks:
This document is available on Distech Controls SmartSource website at the following link:
[Link]
8 Network Guide
Introduction
Notes
This is an example of Note text. Wherever the note-paper icon appears, it means the
associated text is giving a time-saving tip or a reference to associated information of
interest.
Related Documentation
Refer to the Hardware Installation Guide for the devices you are installing.
Network Guide 9
Acronyms and Abbreviations
Acronym Definition
ID Identifier
OD Outside Diameter
MS/TP Master-Slave/Token-Passing
10 Network Guide
BACnet MS/TP Communication Data Bus Fundamentals
CHAPTER 2
BACnet MS/TP Communication Data
Bus Fundamentals
This chapter describes the BACnet MS/TP Communications Data Bus operating principles.
Topics
Network Guide 11
BACnet MS/TP Data Transmission Essentials
The BACnet MS/TP data bus protocol is part of the BACnet® ANSI/ASHRAE™ Standard 135-
2008 that uses the EIA-485 (RS-485) physical layer standard for data transmission (herein
called the data bus). Multiple data buses can be logically tied together as each BACnet MS/TP
data bus is assigned a unique Network Instance that distinguishes it from other data buses in
the BACnet MS/TP Local Area Network (LAN). An example of an interconnected BACnet MS/
TP data bus is shown in Figure 22.
EIA-485 is a standard that defines the electrical characteristics of the receivers and drivers to
be used to transmit data in a differential (balanced) multipoint data bus that provides high
noise immunity with relatively long cable lengths which makes it ideal for use in industrial envi-
ronments. The transmission medium is inexpensive and readily-available twisted pair shielded
cable.
While there are many possible LAN topologies for an EIA-485 data bus, only devices that are
daisy-chained together are allowed with BACnet MS/TP (see Figure 5). A spur is only permit-
ted when it is connected to the data bus through a repeater (see Using Repeaters to Extend
the Data Bus on page 28).
End-of-line (EOL) terminations are critical to error-free EIA-485 data bus operation. The
impedance of the cable used for the data bus should be equal to the value of the EOL termina-
tion resistors (typically 120 ohms). Cable impedance is usually specified by the cable manu-
facturer.
Table 1: Common Identification Labels for BACnet MS/TP Data Bus Polarity for Distech Controls' Products
(Ground symbol)
EC-BOS - + S
Thermostat - + Ref
12 Network Guide
BACnet MS/TP Communication Data Bus Fundamentals
Table 1: Common Identification Labels for BACnet MS/TP Data Bus Polarity for Distech Controls' Products
Except for an EC-BOS and ECB-PTU Line-Powered Controllers, never connect the
shield of the BACnet MS/TP data bus to the Reference terminal. See Data Bus
Shield Grounding Requirements on page 24 for more information.
Table 2: Common Identification Labels for BACnet MS/TP Data Bus Polarity for other Manufacturers
U- U+ COM
Sig- Sig+
Data- Data+
When interfacing with BACnet MS/TP devices from other manufacturers, refer to
the documentation provided with the device to correctly wire the device.
Network Guide 13
Maximum Number of BACnet MS/TP Devices on a
Data Bus Segment and Baud Rate
The following technical parameters limit the number of devices on a BACnet MS/TP Data Bus
Segment.
• The BACnet MS/TP Data Bus Segment has a hard limit on the number of devices that can
communicate due to the device addressing scheme (the MAC Address Range for BACnet
MS/TP Devices). See Data Bus Segment MAC Address Range for BACnet MS/TP
Devices on page 14.
• Each device presents an electrical load on the BACnet MS/TP Data Bus Segment. This is
called device loading. The number of devices that can be connected to a BACnet MS/TP
Data Bus Segment is limited by the loading of each device. See Device Loading on page
15.
• Choosing a low baud rate can cause BACnet MS/TP Data Bus congestion that can limit
the amount of data that can be efficiently exchanged between devices connected to the
BACnet MS/TP Data Bus. For example, at 9600 baud, the maximum number of devices is
reduced to 25 due to the increased time it takes for token passing between devices. The
recommended baud rate is 38 400. See Baud Rate on page 16.
• Distech Controls recommends that you connect no more than 50 of our ⅛ or ½-load
devices on a single BACnet MS/TP Data Bus Segment when a baud rate of 19 200 or
higher is used (preferably 38 400 baud). This is to ensure that the BACnet MS/TP Data
Bus has enough bandwidth to efficiently communicate network variables between control-
lers.
• Up to 128 devices (with device MAC addresses in the range of 0 to 127) that are BACnet
MS/TP Masters (that can initiate communication).
• Up to 128 devices (with device MAC addresses in the range of 128 to 255) that are BAC-
net MS/TP Slaves (cannot initiate communication).
However, it is recommended that any given data bus segment have no more than 50 devices,
when a baud rate of 19 200 or higher is used for the BACnet MS/TP Data Bus. A repeater
counts as a device on each data bus segment to which it is connected.
All Distech Controls' devices are categorized as BACnet MS/TP Masters, that is, their device
MAC address can be set in the range of 0 to 127 only.
14 Network Guide
BACnet MS/TP Communication Data Bus Fundamentals
Device Loading
Each device presents an electrical load on the BACnet MS/TP Data Bus Segment. This is
called device loading. The use of full load devices limits the number of devices connected to a
BACnet MS/TP Data Bus Segment to 32 devices. Distech Controls' BACnet MS/TP devices
are ⅛-load devices and ½-load devices, which allows more devices to be connected to the
BACnet MS/TP Data Bus Segment, as compared to full load devices.
However, if a data bus segment is interoperating with devices that are full-load, ½-load, ¼-
load, or ⅛-load, then the device that supports the fewest devices on the same data bus is the
one that sets the limit for the maximum total number of devices for that data bus segment. For
example, you plan to put on one data bus the following devices:
Quantity of Equivalent
Maximum devices supported by
Manufacturer devices full-load
the manufacturer
(example) devices
Manufacturer Y 26 26 32
(full load devices)
1. This is limited by the maximum number of master devices allowed on a BACnet MS/TP Data
Bus.
The solution for the above example is to create two data bus segments connected together by
a repeater and then split up the devices between the data bus segments, ensuring again that
the maximum number of devices on each separate data bus is not exceeded. See Using
Repeaters to Extend the Data Bus on page 28.
Network Guide 15
Baud Rate
Most devices will have a range of baud rate settings and possibly an AUTO setting that
detects the baud rate of other devices transmitting on the data bus and adjusts the baud rate
of the device accordingly. Typical baud rates are 9600, 19 200, 38 400, and 76 800. The baud
rate setting determines the rate at which data is sent on the BACnet MS/TP data bus.
All devices on the data bus must be set to the same baud rate. Therefore, the chosen baud
rate must be supported by all devices connected to the data bus.
• Set the baud rate of two controllers on a BACnet MS/TP Data Bus Segment to the same
baud rate to provide failover protection.
For example, set the baud rate of the EC-BOS (if equipped) and one other controller to 38
400 baud. If the EC-BOS becomes unavailable and there is a power cycle, the controller
will set the baud rate for the BACnet MS/TP Data Bus.
• Set all other devices to automatically detect the baud rate, if this option is available.
Figure 1: Setting the Baud rate on two Controllers on a BACnet MS/TP Data Bus Segment for Failover
Protection
To set the baud rate for ECB series controllers, see Setting the Baud Rate for ECB-Series
Controllers (optional) on page 101.
Refer to the controller's Hardware Installation Guide for how to identify and set a controller's
built-in EOL terminations.
16 Network Guide
BACnet MS/TP Communication Data Bus Fundamentals
Network Guide 17
Data Bus Physical Specifications and Cable Require-
ments
Cables composed of stranded conductors are preferred over solid conductors as stranded
conductor cable better resist breakage during pulling operations. Distech Controls strongly
recommends that the following data bus segment cable specifications be respected.
Table 5: BACnet MS/TP Data Bus Segment Physical Specifications and Cable Requirements
Parameter Details
Media Twisted pair, 24 AWG (see also Metric Conversions for Wire
Gauge on page 133).
Shield grounding The shield on each segment is connected to the electrical system
ground at one point only; see Data Bus Shield Grounding Require-
ments on page 24.
Distributed capacitance Less than 100 pF per meter (30 pF per foot). The ideal is less than
between conductors 60 pF per meter (18pF per foot).
Distributed capacitance Less than 200 pF per meter (60 pF per foot).
between conductors and
shield
Data bus bias resistors 510 ohms per wire (max. of two sets per segment)
Shielded cable offers better overall electrical noise immunity than non-shielded cable.
Unshielded cable or cable of a different gauge may provide acceptable performance for
shorter data bus segments in environments with low ambient noise.
Table 6: Distech Controls Recommended Cable Types for BACnet MS/TP Data Buses
300 meters (1000 feet), 24 AWG Stranded, CB-BACN6BL1000 3.75mm (0.148 in.)
Twisted Pair Shielded Cable - FT6, Rated
for Plenum Applications
18 Network Guide
BACnet MS/TP Communication Data Bus Fundamentals
Distech Controls BACnet cable offers the best performance over the full range of baud rates,
cable lengths, and number of connected devices. This is primarily due to lower conductor-to-
conductor capacitance of this cable.
Network Guide 19
Data Bus Topology and EOL Terminations
The first and last device on the data bus must have End-of-Line (EOL) termination resistors
connected across the two data lines/wires of the twisted pair. These resistors serve the follow-
ing purposes:
• EOL terminations dampen reflections on the data bus that result from fast-switching (high-
speed rising and falling data edges) that otherwise would cause multiple data edges to be
seen on the data bus with the ensuing data corruption that may result. The higher the
baud rate a data bus is operating at, the more important that EOL terminations be properly
implemented. Electrically, EOL terminations dampen reflections by matching the imped-
ance to that of a typical twisted pair cable.
• EIA-485 data bus transmitters are tri-state devices. That is they can electrically transmit 1,
0, and an idle state. When the transmitter is in the idle state, it is effectively offline or dis-
connected from the data bus. EOL terminations serve to bias (pull-down and pull-up) each
data line/wire when the lines are not being driven by any device. When an un-driven data
bus is properly biased by the EOL terminations to known voltages, this provides increased
noise immunity on the data bus by reducing the likelihood that induced electrical noise on
the data bus is interpreted as actual data.
Figure 2: EOL Terminations Must be Enabled at Both the First and Last Device on the Data Bus
Devices with built-in EOL terminations are factory-set with the EOL termination disabled by
default.
The BACnet/IP to MS/TP Adapter does not have EOL Termination (and BACnet MS/
TP Data Bus biasing) capabilities to be used at the end of a BACnet MS/TP data
bus. Instead, use the BACnet/IP to MS/TP Router for this application.
20 Network Guide
BACnet MS/TP Communication Data Bus Fundamentals
The BACnet MS/TP data bus must be biased. This bias can only be provided by built-in EOL
termination resistors (ones set with jumpers or DIP switches - refer to the controller's Hard-
ware Installation Guide for how to identify and set a controller's built-in EOL terminations). If a
BACnet MS/TP data bus has a BACnet MS/TP thermostat at one end of the BACnet MS/TP
data bus and an EC-BOS at the other end, you must set the built-in EOL termination in the EC-
BOS so that proper biasing is provided to the BACnet MS/TP data bus.
Figure 3: Typical EOL Terminations with BACnet MS/TP Thermostats with Biasing Provided by the EC-
BOS Built-in EOL Termination set to ON
When a BACnet MS/TP data bus has a BACnet MS/TP thermostat at one end of the BACnet
MS/TP data bus and an EC-BOS at the other end without its built-in EOL termination enabled,
fish-tail the BACnet MS/TP data bus back to a controller in which the built-in EOL termination
can be set. This will provide the necessary biasing to the BACnet MS/TP data bus.
Figure 4: Fish-tailing the BACnet MS/TP Data Bus to use a Controller with Built-in EOL Termination that
will Provide Biasing to the BACnet MS/TP Data Bus
Network Guide 21
About Setting Built-in EOL Terminations
ECB-PTU Series Line-Powered Controllers use DIP switches (found alongside those DIP
switches used to set the MAC address) to enable the build-in EOL resistors and biasing cir-
cuitry.
ECB 24V Powered Controllers have built-in EOL terminations. These Controllers use jumpers
to enable the EOL resistors and biasing circuitry.
Refer to the controller's Hardware Installation Guide for how to identify and set a controller's
built-in EOL terminations.
Figure 5: Typical BACnet MS/TP LAN Topology Showing How Devices are Daisy-Chained Together to Form One
Data Bus Segment
22 Network Guide
BACnet MS/TP Communication Data Bus Fundamentals
Network Guide 23
Data Bus Shield Grounding Requirements
The EIA-485 data bus standard requires that the data bus must be shielded against interfer-
ence. A BACnet MS/TP data bus must also be properly grounded.
For ECB 24V-Powered Controllers: The data bus' cable shields must be twisted together and
isolated with electrical tape at each device. Note that for ECB 24V-Powered Controllers, the
power supply transformer's secondary that is connected to the 24V COM terminal is grounded.
This provides the ground reference for the data bus (see BACnet MS/TP is a Three-Wire Data
Bus on page 41). If the controller is at the end of the BACnet MS/TP data bus, simply isolate
the data bus shield with electrical tape.
For ECB-PTU Line-Powered Controllers: The data bus' cable shields must be twisted together
and connected to the COM terminal at each ECB PTU Line-Powered Controller. Keep the
cable shield connections short and take steps at each device to isolate the cable shield from
touching any metal surface by wrapping them with electrical tape, for example. Note that for
ECB-PTU Line-Powered Controllers, the data bus' cable shield provides the ground reference
for the data bus (see BACnet MS/TP is a Three-Wire Data Bus on page 41). If the controller is
at the end of the BACnet MS/TP data bus, simply connect the data bus shield to the COM ter-
minal (see Figure 15).
Grounding the shield of a data bus segment in more than one place will more than
likely reduce shielding effectiveness.
Figure 7: Typical Cable-Shield Grounding Requirements for a BACnet MS/TP Data Bus Segment with a Building
Controller located at the End of the Data Bus
Bus Master (Building Controller) Typical BACnet 24VAC- Typical BACnet24VAC- Typical BACnet 24VAC- Typical BACnet 24VAC-
Powered Controller Powered Controller Powered Controller Powered Controller
NET+
NET+
NET+
NET-
NET-
NET-
NET-
S + -
Electrical The shield of the Data Bus Shields: Twist Data Bus Shields: Twist Data Bus Shield:
System data bus must be together and Isolate together and Isolate Isolate with
Ground connected to the with electrical tape with electrical tape electrical tape
electrical system
ground at one point
only – usually at the
Data Bus: Shielded Twisted Pair Cable
Building Controller,
Data Bus Shield:
when present
Connect to the ‘S’
terminal
24 Network Guide
BACnet MS/TP Communication Data Bus Fundamentals
Figure 8: Typical Cable-Shield Grounding Requirements for a BACnet MS/TP Data Bus Segment with a Building
Controller located in the Middle of the Data Bus
Typical BACnet24VAC- Typical BACnet 24VAC- Bus Master (Building Controller) Typical BACnet 24VAC- Typical BACnet 24VAC-
Powered Controller Powered Controller Powered Controller Powered Controller
NET+
NET+
NET+
NET-
NET-
NET-
NET-
S + -
Data Bus Shield: Data Bus Shields: Data Bus Shields: Twist Data Bus Shield:
Isolate with Connect to the ‘S’ together and Isolate Isolate with
electrical tape terminal with electrical tape electrical tape
Data Bus Shields: Twist Data Bus: Shielded Twisted Pair Cable
together and Isolate
with electrical tape Electrical The shield of the data bus must be connected to
System the electrical system ground at one point only –
Ground usually at the Building Controller , when present
Figure 9: Typical Cable-Shield Grounding Requirements for a BACnet MS/TP Data Bus Segment without a
Building Controller
Typical BACnet24VAC- Typical BACnet24VAC- Typical BACnet 24VAC- Typical BACnet24VAC- Typical BACnet24VAC-
Powered Controller Powered Controller Powered Controller Powered Controller Powered Controller
NET+
NET+
NET+
NET+
NET+
NET-
NET-
NET-
NET-
NET-
Data Bus Shield: Data Bus Shields: Twist Data Bus Shields: Twist Data Bus Shield:
Isolate with together and Isolate together and Isolate Isolate with
electrical tape with electrical tape with electrical tape electrical tape
Figure 10: Typical Cable-Shield Grounding Requirements for a BACnet MS/TP Data Bus Segment with a Building
Controller located in the End of the Data Bus
Network Guide 25
Figure 11: : Typical Cable-Shield Grounding Requirements for a BACnet MS/TP Data Bus Segment with
a Building Controller located in the Middle of the Data Bus
Typical BACnet Line- Typical BACnet Line- Bus Master (Building Controller) Typical BACnet Line- Typical BACnet Line-
Powered Controller Powered Controller Powered Controller Powered Controller
NET+
NET+
NET+
NET+
COM
COM
COM
COM
NET-
NET-
NET-
NET-
S + -
Data Bus Shield: Data Bus Shields: Twist Data Bus Shields: Data Bus Shields: Twist Data Bus Shield:
Connect to ‘COM’ Together and Connect Connect to the ‘S’ Together and Connect Connect to ‘COM’
Terminal to ‘COM’ Terminal terminal to ‘COM’ Terminal Terminal
Figure 12: Typical Cable-Shield Grounding Requirements for a BACnet MS/TP Data Bus Segment without
Building Controller
Typical BACnet Line- Typical BACnet Line- Typical BACnet Line- Typical BACnet Line- Typical BACnet Line-
Powered Controller Powered Controller Powered Controller Powered Controller Powered Controller
NET+
NET+
NET+
NET+
NET+
NET-
NET-
NET-
NET-
NET-
COM
COM
COM
COM
COM
Data Bus Shields: Data Bus Shields: Twist Data Bus Shields: Twist Data Bus Shields: Twist Data Bus Shields:
Connect to ‘COM’ Together and Connect Together and Connect Together and Connect Connect to ‘COM’
Terminal to ‘COM’ Terminal to ‘COM’ Terminal to ‘COM’ Terminal Terminal
Data Bus: Shielded Twisted Pair Cable Electrical The shield of the data bus must be connected to
System the electrical system ground at one point only,
Ground ideally in the middle of the data bus as shown
Figure 13: Typical Cable-Shield Grounding Requirements for a BACnet MS/TP Data Bus Segment with a Building
Controller located in the End of the Data Bus
26 Network Guide
BACnet MS/TP Communication Data Bus Fundamentals
Figure 14: Typical Cable-Shield Grounding Requirements for a BACnet MS/TP Data Bus Segment with a Building
Controller located in the Middle of the Data Bus
Figure 15: Typical Cable-Shield Grounding Requirements for a BACnet MS/TP Data Bus Segment without
Building Controller
Typical BACnet 24VAC- Typical BACnet Line- Typical BACnet 24VAC- Typical BACnet24VAC- Typical BACnet Line-
Powered Controller Powered Controller Powered Controller Powered Controller Powered Controller
NET+
NET+
NET+
NET+
NET+
COM
COM
NET-
NET-
NET-
NET-
NET-
Data Bus Shield: Data Bus Shields: Twist Data Bus Shields: Twist Data Bus Shields:
Isolate with Together and Connect together and Isolate Connect to ‘COM’
electrical tape to ‘COM’ Terminal with electrical tape Terminal
Network Guide 27
Using Repeaters to Extend the Data Bus
A BACnet MS/TP data bus segment can be up to 1220 meters (4000 feet) long with up to a
maximum of 50 devices. When a greater length is required, a solution is to use a repeater. A
repeater increases the maximum total length of the data bus.
If your BACnet MS/TP network has an EC-BOS, it may be more cost effective to add one or
two MS/TP network cards to the EC-BOS in place of an MS/TP Repeater. A standard EC-BOS
can support up to four MS/TP networks when equipped with two optional MS/TP network
cards. Furthermore, network performance is increased as each MS/TP network will have lower
communication latency since each MS/TP network has its own token to pass between
devices. See BACnet MS/TP Data Bus Token-Passing Overview on page 32.
With up to 50 devices per MS/TP network, this allows up to a total of 200 devices to be con-
nected to an EC-BOS. See Figure 22.
Using a Repeater to Extend the Length of the BACnet MS/TP Data Bus
Repeaters can be used to extend a BACnet MS/TP data bus up to 3660 meters (12 000 feet)
maximum total length. Do not use more than two repeaters on a BACnet MS/TP LAN.
A BACnet MS/TP repeater is a bi-directional device that regenerates and strengthens the
electrical signals that pass through it. It creates two electrically-isolated BACnet MS/TP data
bus segments that transparently enable devices on one side of the repeater to communicate
with any device on the other side. The two BACnet MS/TP data bus segments have the same
requirements of an ordinary BACnet MS/TP data bus segment; that is, each BACnet MS/TP
data bus segment:
Distech Controls recommends that you connect no more than 50 of our ⅛ or ½-load devices
on all BACnet MS/TP Data Bus repeater segments when a baud rate of 19 200 or higher is
used (preferably 38 400 baud). This is to ensure that the BACnet MS/TP Data Bus has enough
bandwidth to efficiently communicate network variables between controllers.
Do not use more than two repeaters on a BACnet MS/TP data bus.
A repeater can only connect two BACnet MS/TP data bus segments even if it has
ports to support more than two BACnet MS/TP data bus segments.
A repeater can be added anywhere to a data bus segment including the end of the segment as
shown below.
28 Network Guide
BACnet MS/TP Communication Data Bus Fundamentals
When third party devices are connected to a data bus segment, the number of devices that
can be connected to that data bus segment may be reduced. See Device Loading on page 15.
Network Guide 29
Figure 18: Repeater Connections when it is the First or Last Device on its Respective Data Bus Segment
BACnet MS/TP data bus BACnet MS/TP data bus
Typical BACnet Device Typical Typical BACnet Device
Bias and EOL termination is Bias and EOL termination is
BACnet
provided by this controller’s provided by this controller’s
Device
EOL ON internal EOL Termination internal EOL Termination EOL ON
No Built -in EOL
being set to ON Termination being set to ON
NET+
NET+
NET+
NET-
NET-
NET-
Data Bus Shields: Twist
together and Isolate with
electrical tape
< 25 ft The data bus shield must be connected to the electrical system ground at
one point only – usually at the Building Controller , when present
The BACnet MS/TP Data Bus must be biased. This bias can only be provided by built-in EOL
termination resistors (ones set with a jumper or DIP switch). When a repeater is the first or last
device on its respective data bus segment, use the following methods to provide MS/TP Data
Bus biasing and EOL termination as applicable to your situation:
1. On the BACnet MS/TP data bus segment shown in Figure 18, bias and EOL termination
is provided by a controller's built-in EOL termination being set to ON. In this case the con-
nection to the repeater cannot be more than 7.6 meters (25 feet) from this controller.
2. On the BACnet MS/TP data bus segment shown in Figure 18, a 120Ω EOL Termination
resistor is added to the repeater's terminals. Biasing for this BACnet MS/TP data bus seg-
ment is provided by the built-in EOL termination being set to ON at the last controller at the
other end of this data bus.
See When to Use EOL Terminations on page 20 for more information. The shield of one data
bus must be grounded at one point as specified in see Data Bus Shield Grounding Require-
ments on page 24. The shields of the two data buses must be connected together and isolated
with electrical tape as shown in Figure 18. Refer to the controller's Hardware Installation Guide
for how to identify and set a controller's built-in EOL terminations.
30 Network Guide
BACnet MS/TP Communication Data Bus Fundamentals
Device Addressing
Device addressing allows the coordinated transfer of messages between the intended devices
on the BACnet MS/TP data bus and with devices connected to the internetwork. For this, each
device connected to the BACnet MS/TP data bus is identified by a MAC address, a Device
Instance number, and a Network Number:
Both the MAC Address and the Device Instance must be set for each device and are essential
for proper BACnet LAN operation.
For an example of how MAC address, Device Instance number, and Network Number apply to
a typical BACnet network, see Figure 22.
The MAC Address is a number from 0 to 255; however we recommend reserving some MAC
Addresses for common commissioning and maintenance tasks. For example, when a portable
adaptor is set to use one of these reserved MAC Addresses, it can be temporarily connected
with certainty to any BACnet MS/TP data bus of any site without conflicting with other devices
already connected to the BACnet MS/TP data bus. We strongly recommend that the MAC
address of each MS/TP port of an EC-BOS be always set to 0.
Table 7: Recommended BACnet MS/TP Bus MAC Address Values / Ranges for BACnet MS/TP Data
Bus Devices
MAC Address
Usage Devices
Value / Range
Network Guide 31
Table 7: Recommended BACnet MS/TP Bus MAC Address Values / Ranges for BACnet MS/TP Data
Bus Devices
MAC Address
Usage Devices
Value / Range
2 Reserved Other
The BACnet MS/TP data bus protocol is a peer-to-peer, multiple-master protocol that shares
data bus bandwidth by passing a token between Master devices on the data bus that autho-
rizes the device that is holding the token to initiate communications on the data bus. Once the
device has completed its request(s), it closes the communications channel, passes the token
to the next Master device (making it the current Master), and liberates the data bus.
The token is passed through a short message from device to device on the BACnet MS/TP
data bus in consecutive order starting from the lowest MAC address (MAC Address = 0) to the
next MAC Address.
Gaps or pockets of unassigned device MAC Addresses should be avoided as this reduces
data bus performance. Once a master has finished making its requests, it must poll for the
next master that may exist on the Data Bus. It is the timeout for each unassigned MAC
Address that slows down the data bus.
The way MAC Addresses are assigned is not a physical requirement: Devices can be daisy-
chained on the data bus in any physical order regardless of their MAC Address sequence. The
goal is to avoid gaps in the device MAC Address range.
Slave devices cannot accept the token, and therefore can never initiate communications. A
Slave can only communicate on the data bus to respond to a data request addressed to it from
a Master device. Gaps in slave device MAC Addressing have no impact on BACnet MS/TP
data bus performance.
32 Network Guide
BACnet MS/TP Communication Data Bus Fundamentals
Figure 19: Setting the Max Master on the Data Bus Master (Building Controller) to the Highest MAC Address Used
on the BACnet MS/TP Data Bus
Once a device has the token, it can make a number of information requests to other devices
on the BACnet intranetwork. The maximum number of requests is limited by the Max Info
Frames parameter. Once the device has made the maximum number of requests it is permit-
ted to make according to the Max Info Frames parameter, the device passes the token to the
following device with the next higher MAC address. This makes the BACnet MS/TP Data Bus
more reactive for all devices by preventing a device from hanging on to the token for too long.
Ordinary BACnet MS/TP devices should have the Max Info Frames parameter set to between
2 and 4. The Data Bus Master (Building Controller) should have the Max Info Frames param-
eter set to 20.
To prevent the passing of the token to unused MAC Addresses situated after the final Master
device, the Max Master parameter must be set. By default, the Max Master for the Data Bus
Master (Building Controller) is set to 127 which allows for the theoretical maximum of 127
devices besides the Data Bus Master to be connected to the data bus.
In practice, the actual number of devices connected to a data bus is far less, resulting in a gap
between the highest MAC Address of any device connected to the data bus and the value set
for Max Master. This gap unnecessarily slows-down the data bus with Poll for Master
requests.
When commissioning a BACnet MS/TP Data Bus, it is useful to start with the Max Master set
to 127 so as to be able to discover all devices connected to the data bus. Then, once all
devices have been discovered and the MAC Addressing is finalized by eliminating any gaps in
the address range, set the Max Master (maximum MAC Address) in the EC-BOS (Building
Network Guide 33
Controller) to the highest Master device's MAC Address number to optimize the efficiency of
the data bus.
The Max Master and Max Info Frames are parameters used to optimize a BACnet MS/TP
Data Bus. This is set in the Data Bus Master (EC-BOS Building Controller) for the MS/TP port
of the Data Bus Master and for each BACnet MS/TP device connected on that port.
A Configure MS/TP Devices tool is available to automate this task. This tool:
• Can only be used with a live database during commissioning. If you add more devices to
the data bus, you must run this tool again.
• Automatically calculates the value for the Max Master by finding the highest Master device
MAC Address on the connected BACnet MS/TP data bus plus 1.
• Sets the Max Master for all master devices including the Data Bus Master (EC-BOS).
• Sets the Max Info Frames for all master devices excluding the Data Bus Master (EC-
BOS).
For the Data Bus Master (EC-BOS), set the Max Info Frames to 20 in the screen shown in
Figure 21 as this is a device that will make more requests for service from other devices on the
network. In general, according to the way a device is programmed, the Max Info Frames may
have to be set to a higher value than for other devices. For example, when Roof Top Unit Con-
trollers are used with VAV controllers that use gfxApplications code, they should also have
their Max Info Frames set to a higher value such as 5, as Roof Top Unit Controllers will poll
many VAV controllers for information.
34 Network Guide
BACnet MS/TP Communication Data Bus Fundamentals
1. Right-click the Link node in the Nav tree and select Ms/Tp Configuration.
2. The Configure Ms/Tp devices dialog box is displayed. The network must be live; the Sta-
tus shown in Configure Ms/Tp devices window must be {ok}.
Figure 20: Setting the Max Master on the Data Bus Master (EC-BOS) to the Highest MAC Address Used
on the BACnet MS/TP Data Bus
Network Guide 35
Figure 21: Setting the Max Info Frames on the Data Bus Master (EC-BOS)
Default Device Instance Number Numbering System for Distech Controls' con-
trollers
By default, controllers from Distech Controls automatically self-assign a Device Instance num-
ber generated from the unique MAC Address assigned to the controller during installation. The
Device Instance number is calculated as follows:
This Numbering system is sufficient for a BACnet network that has only one Building Control-
ler. For larger BACnet networks that have more than one Building Controller (to form a BACnet
intranetwork), set the MAC Addresses, Device Instance Numbers and Network Numbers
according to the numbering scheme below.
Good network planning requires a well thought-out numbering scheme for device MAC
Addresses, Device Instance Numbers (DI), and Network Numbers. We recommend the follow-
ing scheme, as it reuses the MAC Address and Network Number in the Device Instance num-
ber to make it easier for a network administrator to know where a device is located in the
network. This is shown below.
36 Network Guide
BACnet MS/TP Communication Data Bus Fundamentals
Table 8: Recommended Numbering Scheme for MAC Addresses, Instance Numbers, and Network
Numbers
BACnet MS/TP Device Instance Number = 10 000 to 4 190 256 10 006 where MAC
EC-BOS BACnet MS/TP Network Number * =6
1000 + MAC Address
Figure 22: BACnet MS/TP Numbering System for MAC Addresses, Device Instance Numbers, and Network
Numbers
When discovering devices with an EC-BOS which has the routing option config-
ured, it will discover all BACnet devices connected to all EC-BOS controllers. Make
sure to add only the devices connected to the MS/TP port of the specific EC-BOS
being configured. Using this numbering system will greatly help to identify those
devices that should be added to a given EC-BOS.
Network Guide 37
Setting the Controller's MAC Address
An example of how to set the device's MAC address DIP switch is shown below for a Distech
Controls' ECB 24V-powered controller on the left, and for a Distech Controls' ECB-PTU 208
controller on the right.
ON
Unused Unused
DIP switches for
enabling / disabling
the internal EOL
Termination
The address is the sum of the numbers set to ON. For example, if the second (2), fifth (16),
and seventh (64) DIP switches are set to ON (or to the right position), the device MAC address
is 82 (2 + 16 + 64). Addresses from 3 to 127 are recommended to be used (see Table 7). See
also How to Set a Dip Switch on page 131.
The controller must be power cycled after the MAC address DIP switch setting has been
changed for the new MAC address setting to take effect.
For more information about how to set the device's MAC address, refer to the device's hard-
ware installation guide.
38 Network Guide
BACnet MS/TP Communication Data Bus Fundamentals
If the MAC Address is set with through the color LCD Screen, the change is made immediately
without any need to power cycle the controller.
BACnet network connections between buildings must be made using BACnet/IP or FOX as
shown below.
Network Guide 39
BACnet/IP Broadcast Management Device Service
Though BACnet/IP or FOX uses IP protocol to communicate, a standard IP router does not
forward broadcast messages which are important in BACnet to identify services that are avail-
able within the BACnet internetwork.
When two Building Controllers communicate to each other over a standard IP connection that
is separated by an IP router, both Building Controllers need the BACnet/IP Broadcast Man-
agement Device (BBMD) service to be configured and operational.
The BBMD service identifies BACnet messages on the BACnet MS/TP network that are
intended for a device located on another BACnet network. The BBMD service encapsulates
these messages into an IP message to the appropriate BBMD service of the other BACnet
MS/TP network(s). The BBMD service on these networks strips out the encapsulation and
sends the BACnet message on to the appropriate devices.
When sending BACnet messages across a standard IP connection that has an IP router, there
must be one BBMD service running on each BACnet MS/TP network.
40 Network Guide
BACnet MS/TP Communication Data Bus Fundamentals
Note: ECB/ECL-VAV controllers are insulated devices and therefore may not be
grounded. When not grounded, the reference for the BACnet MS/TP data bus is
made by connecting the shield of the BACnet MS/TP data bus to the controller's
COM terminal to provide a signal reference. This shield is grounded at one point
only - see Figure 13.
If the power run from the power supply is relatively long and it supplies power to many
devices, a voltage will develop over the length of wire. For example, a 1000 ft of 18 AWG cop-
per wire has a resistance of 6.4 Ohms. If this wire is supplying 1 Ampere of current to con-
nected devices (as shown in Figure 25), the voltage developed across it will be 6.4 volts. This
effect is called ground lift.
Network Guide 41
Figure 25: Ground Lift from a Long Power Run with a 24VAC Device
If the 24V COM terminal is the signal reference point for the data bus, ground lift offsets the
data bus voltage reference that is used to interpret valid data levels sent on the data bus. If the
ground lift is more than 7 volts peak, there is a risk of data corruption and offline events due to
the device being incapable of correctly reading data signals from the data bus. Thus it is
important to keep the power supply (transformer) as close to the controller as possible.
A controller can support a maximum of two Allure Series sensor models equipped with a CO2
sensor. See Subnetwork Module Compatibility and Supported Quantity Charts on page 71 for
how many Allure EC-Smart-Vue sensors are supported by a given controller model. The
remaining connected Allure Series sensor models must be without a CO2 sensor.
For the ECB-VAV model, see the room device calculator spreadsheet available for download
from our website to determine the power requirements and supported quantities of connected
subnet modules: VAV-Smart Room Control Device [Link]
42 Network Guide
BACnet MS/TP Communication Data Bus Fundamentals
Peak Current
Particular attention should be paid to the peak current absorbed by devices that are powered
by an AC circuit. Most Distech Controls 24VAC devices use half-wave rectifiers to supply their
onboard electronics (this is common with most controls manufacturers). With this configura-
tion, the peak AC current is approximately 2.5 times the average RMS AC current. The ECB/
ECL-VAV controllers are isolated full-wave rectified with power factor correction. The peak AC
current is approximately 1.4 times the average RMS AC current.
When calculating a controller’s power consumption to size the 24VAC transformer, you must
also add the external loads the controller is going to supply, including the power consumption
of any connected subnet module (for example, Allure™ Series Communicating Sensors).
If only one 24VAC transformer is available, determine the maximum number of daisy-chained
VAV controllers that can be supplied on a single power cable supplied by a 100 VA trans-
former, according to the controller’s expected power consumption including external loads, the
cable’s wire gauge, and the total cable length from the following figures (Figure 26 and Figure
27). Any installation condition that is outside of the parameters of the following graph should
be avoided.
Network Guide 43
Figure 26: Maximum number of VAV Devices on a Daisy-Chain at Evenly Spaced Intervals
13 F
12
C
11 E
10
9
8
7
6
5 A VAV + SmartVue (AWG18)
3
C VAV + SmartVue + 2DO (1,6VA each) (AWG18)
D VAV + SmartVue + 2DO (1,6VA each) (AWG16)
2
E VAV + SmartVue + SmartVue CO2 + 2DO (1,6VA each) (AWG18)
1
F VAV + SmartVue + SmartVue CO2 + 2DO (1,6VA each) (AWG16)
0
100 200 300 400 500 600 700 800 900 1000
(30) (60) (90) (120) (150) (180) (210) (240) (270) (300)
Figure 27: Maximum Number of VAVS Devices on a Daisy-Chain at Evenly Spaced Intervals
7
Max VAVS in Daisy‐Chain
0
100 150 200 250 300 350 400 450 500
(30) (45) (60) (75) (90) (105) (120) (135) (150)
44 Network Guide
BACnet MS/TP Communication Data Bus Fundamentals
For non-VAV devices, determine the appropriate size transformer for the job as follows:
1. Add up the power requirements of all devices plus all external loads (see About External
Loads on page 42). Multiply the total power needed by a multiplier of 1.3, as a security
margin. For example, to power five devices (15 VA each), the total load is 75 VA multiplied
by 1.3 is 98 VA. Choose a size of transformer just over this amount: For example, a 100
VA model.
2. When the total load of a number of devices requires a transformer with a rating greater
than 100 VA, use two or more transformers. Ensure that the load to be connected to each
transformer follows the guideline of Step 1 above.
Always use a separate transformer for each ECL-600 series controller and for each
of its associated I/O Extension Modules. See ECx-4XX I/O Extension Module
Power Supply Requirements on page 47.
Network Guide 45
Maintain consistent polarity when connecting controllers and devices to the transformer, as
shown in Typical Device BACnet MS/TP LAN and Power Wiring Diagram on page 49. That is,
the 24V COM terminal of each controller and each peripheral must be connected to the same
terminal on the secondary side of the transformer. This transformer terminal must be con-
nected to the building's ground. This ensures that the reference terminals of all devices con-
nected to any BACnet MS/TP data bus in the building are at the same potential.
Most Distech Controls devices use the 24V COM terminal as the signal reference point for the
data bus (see Table 1 and Figure 3) for common device terminal labels). As a consequence,
you must wire the power supply (for any given number of devices) as shown in Figure 28, such
that the transformer's secondary that is connected to 24V COM / C terminals is connected to
the building's ground at the power supply. This ensures that the 24V COM /C terminals of all
devices connected to any BACnet MS/TP data bus in the building are at the same electrical
potential.
Maintain consistent
polarity when connecting BACnet Thermostat
24 VAC/COM controllers and devices to
the transformer. RC
to Ground –
At The 24V COM / C C
Transformer terminals of all devices
Only must be connected to the
power supply bus that is
grounded.
BACnet Device
24V AC/DC
24V COM
Ground
GND connection is
isolated from
24V COM
BACnet Device
24V AC/DC
24V COM
GND
46 Network Guide
BACnet MS/TP Communication Data Bus Fundamentals
When an ECB-600 is used with one or more ECx-4XXs (I/O Extension Modules), always use a
separate transformer for each ECB-600 series controller and for each of its associated I/O
Extension Modules. See Transformer Selection and Determining the Maximum Power Run
Length on page 43 for how to choose an appropriate transformer. One terminal on the second-
ary side of each of these transformers must be connected to the building's ground and to the
respective controller's or I/O Extension Modules' 24V COM terminal. See Figure 29.
Note that the shield of the 2-Wire subnetwork data bus cable must also be grounded, prefera-
bly at the ECB-600. See also 2-Wire Subnetwork Data Bus Shield Grounding Requirements
on page 94.
Network Guide 47
Figure 29: Power wiring - AC for ECB-600 with ECx-4XXs: The 24V COM Terminal of all Devices must
be Connected to Ground
Ground
Neutral
Line Subnetwork Bus Cable Shield Must
be Connected to Electrical System
Ground – At the ECB -600 Only
24 VAC
Transformer
ECB-600
Fuse: 4 A Max . 24V AC /DC
Fast Acting 24V COM
24 VAC
Transformer
ECx -4XX
Fuse: 4 A Max . 24V AC /DC
Fast Acting 24V COM
48 Network Guide
BACnet MS/TP Communication Data Bus Fundamentals
An overview of the BACnet MS/TP LAN and power wiring is shown below.
Network Guide 49
50 Network Guide
LonWorks Communication Bus Fundamentals
CHAPTER 3
LONWORKS Communication Bus Funda-
mentals
This chapter describes the LONWORKS Communications Bus operating principles.
Topics
Network Architecture
TP/FT 10 Network Topologies
Extending the Network
Grounding a Network
Power Supply Requirements for 24V Controllers
ECx-4XX I/O Extension Module Power Supply Requirements
Network Guide 51
Network Architecture
A single-segment EC-Net Network shown with EC-Net Supervisor and EC-Net Pro.
LONWORKS network connections between buildings must be made using TCP/IP with FOX as
shown below.
52 Network Guide
LonWorks Communication Bus Fundamentals
Network Guide 53
TP/FT 10 Network Topologies
The physical routing of the communication channel defines the network topology. The channel
and transceiver types define the requirements and limitations of each wiring topology.
TP/FT 10 network segments require termination for proper data transmission performance.
Free topology and bus network topology differ in their termination requirements. The following
sections describe the various network topologies, their terminator types and termination pro-
cedures.
Bus Topology
A bus topology is a physical routing of the communication channel that includes a distinct
beginning and end. It is also known as a daisy-chain topology.
For bus topology type networks, use the following terminators at each end of the bus topology
channel (2 terminators per channel in total):
R1 = 105Ω, ±1%, ⅛W
C1 = 100µF, ≥50V
C2 = 100µF, ≥50V
54 Network Guide
LonWorks Communication Bus Fundamentals
Free Topology
Free topology is a flexible wiring structure for communication channels that include ring, star,
loop and/or combination wiring structures. A free topology does not have restrictions such as
branching restrictions, stub length limits, device separation requirements or strict termination
guidelines. The free topology transmission specification only has two requirements that must
be met for proper system operation. The distance from each transceiver to all other transceiv-
ers and to the termination must not exceed the maximum node-to node distance. If multiple
paths exist (i.e. a loop topology) then the longest path should be used for calculations. The
maximum total wire length is the total length of wire within a segment. See Network Cables on
page 55 for detailed information about wiring lengths and network cable considerations.
For free topology type networks (TP/FT 10 only), use the terminator shown below for each free
topology channel. It is recommended to always place the terminator near the router for consis-
tency.
R1 = 52.3Ω, ±1%, ⅛W
C1 = 100µF, ≥50V
C2 = 100µF, ≥50V
Network Cables
The following section identifies the type of cabling that may be used in a TP/FT 10 twisted pair
LONWORKS network. The recommendations presented herein are intended to assist network
integrators and OEMs and are provided for informational purposes only.
Network Guide 55
For more information and detailed explanations on network topology and wire length restric-
tions refer to the Junction Box and Wiring Guideline for Twisted Pair LONWORKS® Networks.
These guides can be downloaded from Echelon's web site at [Link].
Parameter Details
Maximum number of 64
devices per segment
Note: A maximum of 128 devices per channel can be installed
on a TP/FT 10 when a router or repeater is used. See Extending
the Network on page 59 for more information.
Type 1:
22 AWG (Ø0.65mm), 1 twisted pair (1P), stranded conductor (STR), tinned copper (TNC),
PVC insulation, PVC jacket, unshielded, plenum FT6, CSA 600V, UL 300V.
Parameter Details
Conductor Gauge (AWG) 22 AWG (see also Metric Conversions for Wire Gauge on
page 133).
56 Network Guide
LonWorks Communication Bus Fundamentals
Parameter Details
Untwisted wires or cables containing flat or parallel untwisted conductors must not
be used on an LONWORKS twisted pair channel. The use of theses wires/cables may
result in improper network operation and could, in certain circumstances, result in
damage to nodes connected to such a channel.
In a bus topology, the maximum wire length is 1400 meters (4593 feet). The maximum stub
length on a TP/FT 10 channel is 3 meters (10 feet). A stub is a section of unterminated trans-
mission line that branches off the main transmission line of interest. The branch line is termi-
nated as an open circuit.
In a free topology, the maximum length is 400 meters (1312 feet) node-to-node and 500
meters (1640 feet) total wire length.
In the event that the limits on the number of transceivers or total wire distance are
exceeded, then one FTT physical layer repeater can be added to interconnect two
segments and double the overall system capability.
Type 2:
16 AWG (Ø1.3mm), 1 twisted pair (1P), stranded conductor (STR), tinned copper (TNC), PVC
insulation, PVC jacket, unshielded, plenum FT6, CSA 600V or UL 300V.
Parameter Details
Conductor 16 AWG (see also Metric Conversions for Wire Gauge on page 133).
Gauge (AWG)
In bus topology, the maximum wire length is 2700 meters (8858 feet). The maximum stub
length on a TP/FT 10 channel is 3 meters (10 feet).
Network Guide 57
In free topology, the maximum length is 500 meters (1640 feet) node-to-node and 500 meters
(1640 feet) total wire length.
For more information about extending the network to a sensor, see Connecting to
the LAN through an Allure EC-Smart-Vue Sensor on page 102.
58 Network Guide
LonWorks Communication Bus Fundamentals
In the event that the limits on the number of transceivers or total wire distance are exceeded,
then one repeater or a router can be added to interconnect two segments and double the over-
all system capability.
A maximum of 128 devices per channel can be installed on a TP/FT 10. However, after 64
devices you must add a repeater in order to add more devices up to the 128 device limit. Alter-
nately, once you have 64 devices on an FT 10 channel you can add a router instead of a
repeater. However the router will create a new channel for your new devices. A router is rec-
ommended for optimal performance.
Network Guide 59
Grounding a Network
It is recommended to use shielded cable only when the network cable is outside of
the building since it will be subjected to electromagnetic interference (EMI).
The twisted pair is terminated according to the guidelines listed in the previous sections. The
cable shield should be grounded using a capacitor to tie the shield to earth ground and a large
value resistor should be used to bleed off any static charge on the shield.
Tie the shield to earth ground through a capacitor, instead of with a direct connection. This
prevents DC and 50/60 Hz ground paths from forming through the shield. Typical values for
Cc and Rb are as follows:
The cable shield should be grounded at least once per segment, and preferably at each node.
Grounding the shield at every node (using the shield grounding circuit shown in Figure 35) will
assist in suppressing 50/60Hz standing waves.
60 Network Guide
LonWorks Communication Bus Fundamentals
A controller can support a maximum of two Allure Series sensor models equipped with a CO2
sensor. See Subnetwork Module Compatibility and Supported Quantity Charts on page 71 for
how many Allure Series sensors are supported by a given controller model. The remaining
connected Series sensor models must be without a CO2 sensor.
For the ECL-VAV model, see the room device calculator spreadsheet available for download
from our website to determine the power requirements and supported quantities of connected
subnet modules: VAV-Smart Room Control Device [Link]
When calculating a controller’s power consumption to size the 24VAC transformer, you must
also add the external loads the controller is going to supply, including the power consumption
of any connected subnet module (for example, Allure™ Series Communicating Sensors).
If only one 24VAC transformer is available, determine the maximum number of daisy-chained
VAV controllers that can be supplied on a single power cable supplied by a 100 VA trans-
former, according to the controller’s expected power consumption including external loads, the
cable’s wire gauge, and the total cable length from the following figures (Figure 36 and Figure
37). Any installation condition that is outside of the parameters of the following graph should
be avoided.
Network Guide 61
Figure 36: Maximum number of VAV Devices on a Daisy-Chain at Evenly Spaced Intervals
13 F
12
C
11 E
10
9
8
7
6
5 A VAV + SmartVue (AWG18)
3
C VAV + SmartVue + 2DO (1,6VA each) (AWG18)
D VAV + SmartVue + 2DO (1,6VA each) (AWG16)
2
E VAV + SmartVue + SmartVue CO2 + 2DO (1,6VA each) (AWG18)
1
F VAV + SmartVue + SmartVue CO2 + 2DO (1,6VA each) (AWG16)
0
100 200 300 400 500 600 700 800 900 1000
(30) (60) (90) (120) (150) (180) (210) (240) (270) (300)
62 Network Guide
LonWorks Communication Bus Fundamentals
Figure 37: Maximum Number of VAVS Devices on a Daisy-Chain at Evenly Spaced Intervals
7
Max VAVS in Daisy‐Chain
3
VAVS + SmartVue (AWG18)
VAVS + SmartVue (AWG16)
2
VAVS + SmartVue + 2DO (1,6VA each) (AWG18)
VAVS + SmartVue + 2DO (1,6VA each) (AWG16)
1 VAVS + SmartVue + SmartVue CO2 + 2DO (1,6VA each) (AWG18)
VAVS + SmartVue + SmartVue CO2 + 2DO (1,6VA each) (AWG16)
0
100 150 200 250 300 350 400 450 500
(30) (45) (60) (75) (90) (105) (120) (135) (150)
For non-VAV devices, determine the appropriate size transformer for the job as follows:
• Add up the power requirements of all devices plus all external loads (see About External
Loads on page 61). Multiply the total power needed by a multiplier of 1.3, as a security
margin. For example, to power five devices (15 VA each), the total load is 75 VA multiplied
by 1.3 is 98 VA. Choose a size of transformer just over this amount: For example, a 100
VA model.
• When the total load of a number of devices requires a transformer with a rating greater
than 100 VA, use two or more transformers. Ensure that the load to be connected to each
transformer follows the guideline of Step 1 above.
Always use a separate transformer for each ECL-600 series controller and for each
of its associated I/O Extension Modules. One terminal on the secondary side of each
of these transformers must be connected to the building's ground and to the respec-
tive controller's or I/O Extension Modules' 24V COM terminal. See ECx-4XX I/O
Extension Module Power Supply Requirements on page 66.
Network Guide 63
Maintain consistent polarity when connecting controllers and devices to the transformer. That
is, the 24V COM terminal of each controller and each peripheral may be connected to the
same terminal on the secondary side of the transformer. This transformer terminal must be
connected to the building's ground.
For any given number of devices, wire the power supply as shown in Figure 38 and Figure 39.
Maintain consistent polarity when connecting controllers and devices to the transformer. That
is, the 24V COM terminal of each controller and each peripheral should be connected to the
same terminal on the secondary side of the transformer.
Connecting the power source to Electrical System Ground is not a requirement for
proper system operation. However it is good installation practice to do so in order to
maintain the same potential between all controllers and Protective Earth.
Figure 38: Power wiring – 24VAC: Maintain Consistent Polarity with all Controllers’ Power Connections
Fuse: 4 A Max .
Controller 1 Fast Acting
24V AC/DC
24V COM 24 VAC AC
Transformer
Controller 2
24V AC/DC
24V COM OPTIONAL : Connect to Electrical System
Ground - At Power Supply Only
64 Network Guide
LonWorks Communication Bus Fundamentals
Figure 39: Power wiring - 24VDC: Maintain Consistent Polarity with all Controllers' Power Connections
Fuse: 4 A Max .
Controller 1 Fast Acting
24V AC/DC
24V COM 24 VDC
Controller 2
24V AC/DC
24V COM OPTIONAL : Connect to Electrical System
Ground - At Power Supply Only
Maintain consistent
polarity when connecting BACnet Thermostat
24 VAC/COM controllers and devices to
to Ground – the transformer. RC
At Transformer The 24V COM / C C
Only terminals of all devices
(OPTIONAL) must be connected to the
power supply bus that is
grounded.
BACnet Device
24V AC/DC
24V COM
Ground connection
GND is isolated from
24V COM
(OPTIONAL)
BACnet Device
24V AC/DC
24V COM
GND
Network Guide 65
ECx-4XX I/O Extension Module Power Supply
Requirements
When an ECL-600 is used with one or more ECx-4XXs (I/O Extension Modules), always use a
separate transformer for each ECL-600 series controller and for each of its associated I/O
Extension Modules. See Transformer Selection and Determining the Maximum Power Run
Length on page 61 for how to choose an appropriate transformer. One terminal on the second-
ary side of each of these transformers must be connected to the building's ground and to the
respective controller's or I/O Extension Modules' 24V COM terminal. See Figure 41.
Note that the shield of the 2-wire subnetwork bus cable must also be grounded, preferably at
the ECL-600. See also 2-Wire Subnetwork Data Bus Shield Grounding Requirements on page
94.
66 Network Guide
LonWorks Communication Bus Fundamentals
Figure 41: Power wiring - AC for ECL-600 with ECx-4XXs: The 24V COM Terminal of all Devices must
be Connected to Ground
G round
Neutral
Line
Subnetwork Bus Cable Shield Must
be Connected to Electrical System
Ground – At the ECL -600 Only
24 VAC
Transformer ECL-600
Fuse: 4 A Max . 24V AC /DC
Fast Acting 24V COM
Network Guide 67
68 Network Guide
Subnetwork Installation Guidelines
CHAPTER 4
Subnetwork Installation Guidelines
This chapter describes the subnetwork installation guidelines. This subnetwork supports a
range of expansion / extension modules.
Topics
About the Subnetwork Data Bus
Cat 5e Cable Subnetwork Data Bus
Setting the Allure EC-Smart-Air and EC-Smart-Comfort Communicating Sensor Series' Subnet
ID Address
Setting the EC-Multi-Sensor Series' Subnet ID Address
Setting the ECx-Light and ECx-Blind Series' Subnet ID Address
2-Wire Subnetwork Data Bus
Network Guide 69
About the Subnetwork Data Bus
ECL and ECB Distech Controls' controllers use the subnetwork data bus to support various
optional modules that add extra inputs, outputs, sensor inputs (temperature, humidity, CO2,
motion, receive wireless commands from a remote control), and interactive screen menus for
user control. The subnetwork data bus uses the EIA-485 (Electronic Industries Alliance) stan-
dard for data transmission.
• All ECB and ECL series controllers are equipped with an RJ-45 Subnet Port to quickly
connect expansion modules and sensors in a daisy-chained fashion to the subnetwork
using a Cat 5e cable (standard straight Ethernet patch cable). Any device that connects to
a controller's Subnet Port is collectively referred to as room devices.
• In addition, the ECB-600 and ECL-600 Series controllers can be connected to one or two
ECx-4XX I/O Extension Modules using the same subnetwork data bus, however the con-
nection is made through the controller's Subnet+ and Subnet screw-type terminal block
connectors using a 2-wire twisted-pair shielded cable.
Allure EC-Smart-Vue series Room Device: Sensors Cat 5e cable with RJ-45 connec-
tors - See Cat 5e Cable Subnet-
Allure EC-Smart-Comfort series work Data Bus on page 79.
Allure EC-Smart-Air sensor
series
EC-Multi-Sensor series
ECx-Blind-4 / ECx-Blind-4LV
ECx-4XX Series I/O Extension Extension Module 2-wire twisted-pair shielded cable
Module - See 2-Wire Subnetwork Data
Bus on page 92.
70 Network Guide
Subnetwork Installation Guidelines
Table 16: Subnetwork Module Compatibility and Maximum Supported Quantity Chart
Permitted Subnet
Controller ID Addressing Maximum
Subnetwork Data Bus Device
Model Quantity Allowed
Range1
EC-Multi-Sensor series 1 to 4
ECx-Blind-4 / ECx-Blind-4LV
Network Guide 71
Table 16: Subnetwork Module Compatibility and Maximum Supported Quantity Chart
Permitted Subnet
Controller ID Addressing Maximum
Subnetwork Data Bus Device
Model Quantity Allowed
Range1
EC-Multi-Sensor series 1 to 4
ECx-Blind-4 / ECx-Blind-4LV 25
ECx-Blind-4 / ECx-Blind-4LV 25
ECx-Blind-4 / ECx-Blind-4LV 25
72 Network Guide
Subnetwork Installation Guidelines
Table 16: Subnetwork Module Compatibility and Maximum Supported Quantity Chart
Permitted Subnet
Controller ID Addressing Maximum
Subnetwork Data Bus Device
Model Quantity Allowed
Range1
ECx-Blind-4 / ECx-Blind-4LV 25
1. The indicated addressing ranges group together the permitted addressing ranges for those
devices.
The following devices use different Subnet address ranges so that the same Sub-
net ID of one device will not conflict with that of another device that is on a different
Subnet address range:
• 1 address range for Allure EC-Smart-Vue sensors
• 1 address range for Allure EC-Smart-Comfort and Allure EC-Smart-Air sensors
• 1 address range for EC-Multi-Sensors
• 1 address range for ECx-Light/Blind expansion modules
• 1 address range for ECx-Display
For example, an Allure EC-Smart-Vue sensor and an Allure EC-Smart-Air sensor
can have the same Subnet ID, but an Allure EC-Smart-Air sensor and an Allure
EC-Smart-Comfort sensor must have a different Subnet ID. Consequently, you can-
not set both an ECx-Light-4 and an ECx-Blind-4 to have a Subnet ID as 1.
2. See the room device calculator spreadsheet available for download from our website to
know the permitted quantities for these controller models: VAV-Smart Room Control Device
[Link]
3. A controller can support a maximum of two (2) Allure Series sensor models equipped with a
CO2 sensor. Any remaining connected Allure Series sensor models must be without a CO2
sensor.
4. These models support a recommended maximum of 4 sensors (Allure Series sensor series
and EC-Multi-Sensor series) combined in total. Each Allure Series sensor model equipped
with a CO2 sensor counts as 2 sensors (for example, you cannot connect any other sensors
if you connect two Allure Series sensor models equipped with a CO2 sensor or you can con-
nect up to two other non-CO2 sensors if you connect one Allure Series sensor models
equipped with a CO2 sensor). When a longer system response time is acceptable, up to 4
Network Guide 73
Allure Series sensor series (no more than 2 of which are equipped with a CO2 sensor) and
up to 4 EC-Multi-Sensor series can be connected in total.
5. Up to 8 light and 8 blind/shade outputs total, provided by a maximum of 2 × ECx-Light and 2
× ECx-Blind room devices.
Figure 42: Subnetwork Module Connection to ECB-600 / ECL-600 Series Controllers Example
For use with an ECB-600 / ECL-600 Series Controller Only
ECx-Subnet
Adapter
ECx-Display
1. This includes the following models only: ECB/ECL-VAV Series, ECB-PTU / ECL-PTU Series,
ECB/ECL-103, ECB/ECL-203 Series, ECB/ECL-300 Series, ECB/ECL-400 Series
When the Allure EC-Smart-Vue sensor is used with certain controller models, the
subnetwork data bus can extend the LAN to the Allure EC-Smart Vue sensor to pro-
vide convenient network access. See Connecting to the LAN through an Allure EC-
Smart-Vue Sensor on page 102.
74 Network Guide
Subnetwork Installation Guidelines
For all controllers that do not support the 2-Wire subnetwork data bus , the maximum length of
the Cat 5e cable subnetwork data bus is 600 ft (180 m). See Figure 44.
• When no ECx-4XX I/O Extension Module is connected to the controller, the maximum
length of the Cat 5e subnetwork data bus is 600 ft (180 m). See Figure 44.
• When no Cat 5e subnetwork extension module is connected to the controller, the maxi-
mum length of the 2-Wire subnetwork data bus is 1 000 ft (300 m). See Figure 46.
• When both ECx-4XX I/O Extension Modules (using the 2-wire subnetwork data bus) and
subnetwork extension modules (using the Cat 5e cable subnetwork data bus) are con-
nected, the total maximum length of all subnetwork data buses is 1 000 ft (300 m), of
which the length of the Cat 5e subnetwork data bus can be no more than 600 ft (180 m).
See Figure 47.
See below:
Figure 44: Maximum Length of the Cat 5e Cable Subnetwork Data Bus, ECB/ ECL2 Series Controllers
600 ft (180 m) Maximum Length
Typical ECB /
ECL Controller Light or Sunblind
Expansion Module Typical Room Devices
For ECB/ECL-PTU Series controllers, the maximum length between two consecutive devices
on the subnetwork data bus is 100 ft (30 m).
For controllers that support an ECx-Display, the maximum length of the Cat 5e cable subnet-
work data bus used to connect a controller to an ECx-display as a stub is 6.5 ft. (2m). The
maximum total length of the Cat 5e cable subnetwork data bus remains 600 ft. (180 m).
When other subnetwork devices are used, use an ECx-Subnet Adapter to connect to those
devices.
Network Guide 75
Figure 45: Subnetwork Module Connection with an ECx-Display Connected as a Stub Example
600 ft [180 m] Maximum Length
6.5 ft [2m]
Maximum Cat 5e Cable Sub network Bus
ECx-Subnet
Adapter
Figure 46: Maximum Length of the 2-Wire Subnetwork Data Bus, ECB-600 / ECL-600 Series Controllers
When both ECx-4XX Series Extension I/O Modules and any Cat 5e subnetwork expansion
module are used with an ECB-600 or ECL-600 Series controller, the total maximum length of
all subnetwork data buses is 1 000 ft (300 m). That is, any length of the Cat 5e cable subnet-
work data bus will reduce the maximum length of the 2-Wire Subnetwork Data Bus.
The example below shows that if the length of the Cat 5e Cable Subnetwork Data Bus (used
to connect to the Allure Series sensors) is 500 ft (150 m) then the length of the 2-Wire Subnet-
work Data Bus (used to connect to the ECx-4XXs Series) can only be a maximum of 500 ft
(150 m), for a maximum 1 000 ft (300 m) total length.
76 Network Guide
Subnetwork Installation Guidelines
Figure 47: Example of the Distribution of the Total Subnetwork Data Bus Length Example
ECx-Subnet
Adapter
EC-Multi
Sensor
ECx-Display
The maximum length of the Cat 5e cable subnetwork data bus used to connect a controller to
an ECx-display as a stub is 6.5 ft. (2m). The maximum total length of the Cat 5e cable subnet-
work data bus remains 1 000 ft. (300 m). When other Cat 5e cable subnetwork devices are
used, use an ECx-Subnet Adapter to connect to those devices.
Figure 48: Example of the Distribution of the Total Subnetwork Data Bus Length with an ECx-Display Connected
as a Stub Example
ECx-Display
EC-Multi
Sensor 6.5 ft [2m]
Maximum
Network Guide 77
A controller can support a maximum of two (2) Allure Series sensor models equipped with a
CO2 sensor; the remaining connected models must be without a CO2 sensor. See Subnet-
work Module Compatibility and Supported Quantity Charts on page 71 for the quantity of room
devices supported by each controller model.
For instance, if the subnetwork for the controller model supports a subnetwork with 12 Allure
Series sensors in total, then 10 Allure Series sensor models must be without a CO2 sensor
and the remaining two (2) Allure Series sensor models can be equipped with a CO2 sensor.
To ensure proper operation, it is recommended to distribute the sensors throughout the length
of the subnetwork.
EC-Smart-Vue Subnetwork
Cat 5e Cable with RJ-45 Connectors
Bus: 600 ft (180 m) Maximum
Typical ECB−600 /
ECL−600 Controller
2x... 10x...
78 Network Guide
Subnetwork Installation Guidelines
The Cat 5e Cable subnetwork data bus is used to connect compatible room devices (Table 15)
to any Distech Controls ECB/ECL series controller. See Subnetwork Module Compatibility and
Supported Quantity Charts on page 71 for a list of compatible extension / expansion modules.
Table 17: Cat 5e Cable Subnetwork Data Bus Physical Specifications and Cable Requirements
Parameter Details
Maximum number of room devices See Subnetwork Module Compatibility and Supported Quan-
tity Charts on page 71. See also the controller’s datasheet.
Subnet ID Addressing Configuration See Setting the Subnet ID Addressing for Room Devices on
page 84.
RJ-45 Pin Configuration Four (4) pairs required. Straight-through wiring. Crimp con-
nectors as per T568A or T568B (both cable ends must be
crimped the same way).
Distributed capacitance Less than 100 pF per meter (30 pF per foot)
Maximum total length of the Cat 5e 300 m (1 000 ft.) Maximum – See Subnetwork Data Bus
Cable subnetwork data bus plus the Length on page 75.
2-Wire subnetwork data bus
Maximum length of the Cat 5e 180 m (600 ft.) Maximum – See Subnetwork Data Bus
Cable subnetwork data bus Length on page 75.
Network Guide 79
Table 17: Cat 5e Cable Subnetwork Data Bus Physical Specifications and Cable Requirements
Parameter Details
EOL terminations Must be set / enabled on the last room device only. This
does not apply to the ECx-Display.
Distech Controls recommends the Cat 5e cables shown below. Cables fitted with connectors
are crimped as T568B.
Table 18: Distech Controls Recommended Cable Types to use for the Cat 5e Cable Subnetwork Data Bus
1. Outer cable diameter – This does not take into account the RJ-45 connector.
80 Network Guide
Subnetwork Installation Guidelines
room devices and ECx-4XX Series I/O Extension Module EOL terminations are factory set to
OFF (except for the EC-Multi-Sensor).
When one or more room devices are connected to the Subnet Port of an ECB/ECL-VAV
series, ECB/ECL-103 to -400 Series, or ECB/ECL-PTU Series controllers, only the EOL termi-
nations of the last room device is set to ON. All other room devices on the subnetwork data
bus must have their EOL terminations set to OFF. The controller must be the first device on
the Cat 5e Cable Subnetwork data bus as its internal EOL termination is permanently enabled.
The ECx-Display does not have any EOL terminations to be set and as such should not be
installed as the last device on the subnetwork bus. See Figure 47.
Network Guide 81
Figure 51: Setting the EOL Terminations on the Cat 5e Cable Subnetwork Data Bus for the ECB/ECL-
VAV Series and ECB/ECL-103 to -400 Controllers
Controller Series:
ꞏ ECL-VAVS / ꞏ ECB-VAVS / Back of Allure
ECL-VAV ECB-VAV Remove the EC-Smart-Vue
ꞏ ECL-PTU ꞏ ECB-PTU EOL jumper
ꞏ ECL-103 ꞏ ECB-103
ꞏ ECL-203 ꞏ ECB-203
EOL set to ON
ꞏ ECL-300 ꞏ ECB-300
at the last ON
ꞏ ECL-400 ꞏ ECB-400
EOL
sensor at the
OFF
end of the Bus
Figure 52: Setting the EOL Terminations on the Cat 5e Cable Subnetwork Data Bus for the ECB/ECL-
VAV Series and ECB/ECL-103 to -400 Controllers (Allure EC-Smart-Comfort)
Controller Series:
ꞏ ECL-VAVS / ꞏ ECB-VAVS / Back of Allure
ECL-VAV ECB-VAV Remove the EC-Smart-Comfort
ꞏ ECL-PTU ꞏ ECB-PTU EOL jumper
ꞏ ECL-103 ꞏ ECB-103
ꞏ ECL-203 ꞏ ECB-203
ꞏ ECL-300 ꞏ ECB-300 EOL set to ON at
ꞏ ECL-400 ꞏ ECB-400 the last sensor at
the end of the Bus
82 Network Guide
Subnetwork Installation Guidelines
Figure 53: Setting the EOL Terminations on the Cat 5e Cable Subnetwork Data Bus for the ECB/ECL-
PTU Series Controllers
Depending on the type of expansion module, the subnetwork data bus EOL may be
set by configuring jumpers or DIP switches. Refer to the expansion module's hard-
ware installation guide for how to identify and set a room devices' built-in EOL termi-
nations.
When one or more Allure Series sensors are installed with an ECB/ECL-600, only the EOL ter-
minations of the ECB/ECL-600 and the last Allure Series sensor are set to ON. All other Allure
Series sensors must have their EOL terminations set to OFF. This is shown below:
Network Guide 83
Figure 54: Setting the EOL Terminations on the Allure Series sensor Subnetwork Data Bus for the ECB/
ECL-600
Controller Series:
ꞏ ECB-600
ꞏ ECL-600 Inside
ECB/ECL-600 Back of Allure
EOL OFF EC-Smart-Vue
EOL ON
EOL set to ON
at the last ON
EOL
For ECB-600 / ECL-600, set the sensor at the
OFF
Subnetwork EOL to ON end of the Bus
If an ECx-4XX Series I/O Extension Module is used with both a Cat 5e room device and an
ECB/ECL-600 controller, see 2-Wire Subnetwork Data Bus on page 92 for how to set the EOL
terminations.
Table 19: Subnetwork Module Compatibility and Maximum Supported Quantity Chart
Allure EC-Smart-Comfort Dip Switch located next to the RJ- Setting the Allure EC-Smart-Air
series 45 subnet connectors and EC-Smart-Comfort Commu-
nicating Sensor Series' Subnet ID
Allure EC-Smart-Air Address on page 86
series
84 Network Guide
Subnetwork Installation Guidelines
Table 19: Subnetwork Module Compatibility and Maximum Supported Quantity Chart
ECx-Light-4 / DIP switch located next to Subnet Setting the ECx-Light and ECx-
ECx-Light-4D / Port connectors Blind Series' Subnet on page 75
ECx-Light-4DALI
ECx-Blind-4 /
ECx-Blind-4LV
Network Guide 85
Setting the Allure EC-Smart-Air and EC-Smart-Com-
fort Communicating Sensor Series' Subnet ID
Address
86 Network Guide
Subnetwork Installation Guidelines
Figure 55: Setting the Allure EC-Smart-Air or EC-Smart-Comfort communicating sensor’s Subnet ID
Address
S et the S ubnet E OL
ID A ddress Termination
Table 20: Allure EC-Smart-Air or EC-Smart-Comfort communicating sensor's Subnet ID Address DIP Switch
Settings
Switch Position
Allure EC-Smart-Air or EC-Smart-Comfort
communicating sensor's Subnet ID Address
1 2 3 4
OFF ON OFF 2
ON ON OFF 3
OFF OFF ON 4
ON OFF ON 5
OFF ON ON 6
Figure 55 shows an example of how to set the Allure EC-Smart-Air or EC-Smart-Comfort com-
municating sensor's Subnet ID address DIP switch to 6 and how to set the EOL termination to
ON.
Network Guide 87
Setting the EC-Multi-Sensor Series' Subnet ID
Address
Each EC-Multi-Sensor connected to a controller's Subnet Port must be set to a unique subnet
ID address. This address should correspond to the block number of the associated Multi Sen-
sor block in EC-gfxProgram. The address is set through the rotary selector located next to the
Subnet Port connector.
2 3
Set the Subnet EOL Jumper: EOL is enabled
4
0 1
7 8
Back of
EC-Multi-Sensor
Use a small screwdriver (for example, a precision or jeweler's screwdriver) to set the selector.
Figure 56 shows an example of how to set the EC-Multi-Sensor Series' Subnet ID address DIP
switch to 1 and the EOL termination is ON.
Once an EC-Multi-Sensor is installed, the following tip can be used during system
commissioning to verify if the EC-Multi-Sensor is set to the correct subnet ID
address for the zone in which it is physically located.
Run EC-gfxProgram in debug mode for the controller with 4 Multi Sensor block
instances, 1 to 4. Set a remote control to zone ID 0, then aim it at the EC-Multi-Sen-
sor and press a command (fan speed button for example). In EC-gfxProgram, see
which block instance shows an output (RemoteFanSpeed).
Usually it is easier to reassign Multi Sensor block numbers in EC-gfxProgram code
than it is to change the Subnet ID Address of an installed EC-Multi-Sensor.
88 Network Guide
Subnetwork Installation Guidelines
Each ECx-Light and ECx-Blind Series' connected to a controller's Subnet Port must be set to a
unique subnet ID address. The address is set through the DIP switch located next to the Sub-
net Port connectors.
Figure 57: Setting the ECx-Light and ECx-Blind Series' Subnet ID Address (Typical)
↓
O
N 1 2 3 4
↓
O
N 1 2 3 4
Table 21: ECx-Light and ECx-Blind Series’ Subnet ID Address DIP Switch Settings
Switch Position
Expansion Module’s Subnet ID (MAC) Address
1 2 3 4
ON ON OFF OFF 3
Figure 57 shows an example of how to set the ECx-Light and ECx-Blind series' Subnet ID
address DIP switch to 1 and how to set the EOL termination to OFF.
Often only one type of expansion module is connected to the controller; for example, one ECx-
Light-4 and one ECx-Blind-4 model. By leaving the Subnet ID address DIP switch at 0 (factory
default position) for these two expansion modules, the ECx-Light and ECx-Blind room device
sets its own Subnet ID Address according to its model type so no configuration is necessary.
Network Guide 89
Table 22: ECx-Light and ECx-Blind Series' Automatic Subnet ID Address when the DIP Switch is set to 0
1 2 3 4
If you connect a second expansion module of the same type to the controller's subnetwork
data bus, you must set at least one of the two expansion modules' MAC DIP switch to a
unique (that is, unused) subnet ID (MAC) address and then set the same value in Default
address in EC-gfxProgram. See "Manage Light and Sunblind Module Instances" in the EC-
gfxProgram User Guide.
Figure 58: In EC-gfxProgram: Default Address: Setting an Expansion Modules' Subnet ID (MAC)
Address for this Expansion Module Instance
In EC-gfxProgram, when the connection status for the controller is Connected, this scans the
controller's subnetwork data bus for connected expansion modules, when each expansion
module has a unique subnet ID (MAC) address on the controller's subnetwork data bus. Using
this feature will delete any previously configured expansion modules. See "Manage Light and
Sunblind Module Instances" in the EC-gfxProgram User Guide.
90 Network Guide
Subnetwork Installation Guidelines
Learn is only available after 2 minutes of the controller having been powered up.
This information is no longer available after 30 minutes. Reboot the controller if
Learn is unable to find the connected modules (in Project Synchronization, select
Download to device and Reboot controller only).
Network Guide 91
2-Wire Subnetwork Data Bus
The 2-Wire subnetwork data bus is used to connect ECx-4XX Series I/O Extension Modules to
an ECB-600 or ECL-600 controller. The specifications for this cable are shown in Table 23.
The polarity of the 2-wire subnetwork data bus must be respected as shown in Figure 62. All
terminals identified as SUBNET+ must be connected to the same conductor. Likewise, all ter-
minals identified as SUBNET- must be connected to the same conductor.
Cables composed of stranded conductors are preferred over solid conductors as stranded
conductor cable better resist breakage during pulling operations. Distech Controls strongly
recommends the following 2-wire subnetwork data bus cable specifications be respected.
Table 23: Cat 5e Cable Subnetwork Data Bus Physical Specifications and Cable Requirements
Parameter Details
Distributed capacitance Less than 100 pF per meter (30 pF per foot)
Maximum total length of the Cat 5e Cable 300 m (1 000 ft.) Maximum – See Subnet-
subnetwork data bus plus the 2-wire subnet- work Data Bus Length on page 75.
work data bus
92 Network Guide
Subnetwork Installation Guidelines
Table 24: Distech Controls Recommended Cable Types for the 2-Wire Subnetwork Data Bus
When ECx-4XX I/O Extension Modules are connected to an ECB-600 / ECL-600 controller's
Subnet+ and Subnet connectors, only the EOL terminations of the ECB-600 / ECL-600 and
the last ECx-4XX are set to ON. All other ECx-4XX I/O Extension Modules must have their
EOL terminations set to OFF. This is shown below.
For the 2-wire subnetwork data bus, only a daisy-chain topology is acceptable and
T-connections and routers are not allowed.
Figure 60: Setting the EOL Terminations on the ECx-4XX Subnetwork Data Bus
Typical ECB-600 / Typical ECx-4XX Series Extension I/O Modules – For use
ECL-600 Controller with an ECB-600 / ECL-600 Series Controller Only
EOL ON EOL ON
For ECx-4XX:
For ECB-600 / ECL-600, the - Last daisy-chained ECx-4XX:
Subnetwork EOL is set to ON EOL Jumper is ON
- All other ECx-4XX:
EOL Jumpers are OFF
When ECx-4XX I/O Extension Modules are connected to an ECB-600 / ECL-600 controller's
Subnet+ and Subnet connectors and with one or more Allure Series sensor(s) are connected
to the controller's Subnet Port, only the EOL terminations of the last ECx-4XX and the last
Network Guide 93
Allure Series sensor are set to ON. All other ECx-4XX I/O Extension Modules and Allure
Series sensors must have their EOL terminations set to OFF. This is shown below.
Figure 61: Setting the EOL Terminations on the Subnetwork Data Bus when Cat 5e Room Devices are used
For use with an ECB-600 / ECL-600 Series Controller Only
Inside
Back of Allure ECx-4XX
EC-Smart-Vue EOL OFF
The shielding of the 2-Wire subnetwork data bus cable must be connected to the electrical
system ground at one point only, preferably at the ECB-600/ECL-600 as shown below.
ECB-600
ECx-4XX ECx-4XX
ECL-600
SUBNET +
SUBNET +
SUBNET+
SUBNET -
SUBNET -
SUBNET -
94 Network Guide
Subnetwork Installation Guidelines
For more information about 2-Wire subnetwork data bus grounding, see:
• ECx-4XX I/O Extension Module Power Supply Requirements on page 47 for ECB-600
controllers.
• ECx-4XX I/O Extension Module Power Supply Requirements on page 66 for ECL-600
controllers.
Table 25: ECx-4XX I/O Extension Module Address DIP Switch Settings
Switch Position
Value
1 2 4
ON OFF OFF 1
OFF ON OFF 2
ON ON OFF 3
OFF OFF ON 4
ON OFF ON 5
OFF ON ON 6
ON ON ON 7
An example of how to set an ECx-4XX I/O Extension Module address DIP switch is shown
below.
Network Guide 95
Figure 63: Typical ECx-4XX I/O Extension Module Address DIP Switch Set to 2
• Transformer Selection and Determining the Maximum Power Run Length on page 43 for
ECB-600 controllers.
• Transformer Selection and Determining the Maximum Power Run Length on page 61 for
ECL-600 controllers.
96 Network Guide
Controller Installation and Maintenance Tasks with an Allure EC-Smart-Vue Sensor
CHAPTER 5
Controller Installation and Maintenance
Tasks with an Allure EC-Smart-Vue
Sensor
This chapter describes how to use an Allure EC-Smart-Vue sensor to perform installation and
maintenance tasks including commission a controller.
Topics
Commissioning a Controller with an Allure EC-Smart-Vue Sensor
Network Guide 97
Commissioning a Controller with an Allure EC-
Smart-Vue Sensor
Commissioning a controller with an Allure EC-Smart-Vue sensor involves the following tasks:
ECB and ECL Series controllers can be commissioned with an Allure EC-Smart-Vue sensor.
The default Subnet ID for an Allure EC-Smart-Vue sensor is 1. To commission an ECB / ECL
Series controller, the Allure EC-Smart-Vue sensor's Subnet ID must be set to 1. If the Allure
EC-Smart-Vue sensor's Subnet ID has been set to another value (for example, the display
flashes error code 1 with the Bell icon when the Allure EC-Smart-Vue sensor is connected to a
controller for commissioning), change the Subnet ID to 1 as follows:
1. Connect an Allure EC-Smart-Vue sensor to the controller with a Cat 5e patch cable. Wait
for the Bell icon and the number 1 to flash on the display.
2. Press and hold the Menu button for 5 seconds to enter the password menu. 10000 is
shown on the display.
Screen Timeout: 15 seconds
OR
3. Use the down button to set the number to 9995 (this is the default password).
Screen Timeout: 15 seconds
OR
4. Press the Menu button to submit the password. Upon submitting the password, the
GEN CFG menu appears on the display.
98 Network Guide
Controller Installation and Maintenance Tasks with an Allure EC-Smart-Vue Sensor
OR
5. Press the down button once to enter the GEN CFG submenu
6. Press the Menu button several times until SUBNET ID appears on the display. The
current controller's Subnet ID is shown.
OR
7. For commissioning purposes, use the up and down buttons to set the controller's
Subnet ID to 1. Tip: Hold down either the up or down button to fast-advance the display
value. Otherwise use the up and down buttons to set the controller's Subnet ID to the
ComSensor block instance value programmed in the controller with EC-gfxProgram.
9. Press and hold the Menu button for 5 seconds to exit the configuration menu.
The Allure EC-Smart-Vue sensor can now be used to go from one ECB/ECL Series controller
to the next for commissioning purposes.
When the controller has been programmed, each connected Allure EC-Smart-Vue's Sensor
must be assigned a unique Subnet ID.
Commissioning Controllers
To commission a controller with a MAC Address DIP switch located on the faceplate or under
the cover (in the case of an ECB-103 or ECB-VAV Series controller - when equipped), first set
the DIP switch to 0 (all off - this is the factory default setting when the controller is shipped).
When using an Allure EC-Smart-Vue sensor for commissioning a controller (before code is
downloaded to the controller from EC-gfxProgram), connect an Allure EC-Smart-Vue sensor
to the controller with its Subnet ID set to 1.
For ECB-VAV and ECL-VAV Series controllers, commissioning can be used to perform appli-
cation selection if needed. Applications are preloaded programs that enable the ECB-VAV and
ECL-VAV to control a typical VAV box. See the ECL-VAV or ECB-VAV Preloaded Application
User Guide for more Information.
Network Guide 99
For ECB Series controllers only, during commissioning, the Allure EC-Smart-Vue sensor is
used to set the controller's BACnet® MAC Address. Set the connected ECB Series controller's
MAC Address as follows:
1. Connect an Allure EC-Smart-Vue sensor to the controller with a Cat 5e patch cable. Wait
for the display to show the room temperature.
2. Press and hold the Menu button for 5 seconds to enter the password menu. 10000 is
shown on the display.
OR
3. Use the down button to set the number to 9995 (this is the default password).
Screen Timeout: 15 seconds
OR
4. Press the Menu button to submit the password. Upon submitting the password, the
GEN CFG menu appears on the display.
Screen Timeout: 30 seconds
OR
5. Press the down button once to enter the GEN CFG submenu. The MAC ADDRESS
menu is shown with the current controller's BACnet MAC Address.
Screen Timeout: 30 seconds
OR
6. Use the up and down buttons to set the controller's MAC Address. Only addresses from 1
to 127 are recommended to be used.
8. Press and hold the Menu button for 5 seconds to exit the configuration menu.
Once the controller's communication network is operational, the controller can be programmed
with EC-gfxProgram. For each Allure EC-Smart-Vue sensor, set its Subnet ID number to the
block number of its associated CommSensor block in EC-gfxProgram. This is done in the
Allure EC-Smart-Vue sensor's GEN CFG menu under SUBNET ID.
By default, the baud rate for the controller is factory set to automatically detect the current
communication baud rate of the connected BACnet MS/TP network (AUTO setting). This is
the preferred setting for a controller. However, at least one controller on the BACnet MS/TP
network data bus must have its baud rate set to act as the master for setting the baud rate on
the BACnet MS/TP network. The preference is to set the building controller's baud rate (if
present). Otherwise, set the baud rate on one controller that will set the baud rate for all other
controllers.
When the baud rate is set to AUTO, the controller cannot initiate any communication
until it has detected the baud rate of the BACnet MS/TP network. If all controllers on
the BACnet MS/TP network are set to AUTO, then all controllers will not communi-
cate.
A method to increase the availability of the BACnet MS/TP network is to also set the baud rate
of a second controller on the BACnet MS/TP network so that it can provide failover service. In
this scenario, should the first controller that is to set the baud rate fail or should it take longer
than usual to boot after a power failure, this second "failover controller" will set the baud rate of
all other controllers on the BACnet MS/TP network, thereby allowing all other controllers to
establish communications with each other. This provides redundancy and helps to eliminate a
single point of failure. See Baud Rate on page 16.
1. Connect an Allure EC-Smart-Vue sensor to the controller with a Cat 5e patch cable. Wait
for the display to show the room temperature.
2. Press and hold the Menu button for 5 seconds to enter the password menu. 10000 is
shown on the display.
Screen Timeout: 15 seconds
OR
3. Use the down button to set the number to 9995 (this is the default password).
Screen Timeout: 15 seconds
OR
4. Press the Menu button to submit the password. Upon submitting the password, the
GEN CFG menu appears on the display.
OR
5. Press the down button once to enter the GEN CFG submenu.
6. Press the Menu button several times until BAUD RATE appears on the display. The
current controller's baud rate is shown.
OR
7. Use the up and down buttons to set the controller's baud rate. AUTO detects and uses the
baud rate currently being used by the BACnet MS/TP network.
9. Press and hold the Menu button for 5 seconds to exit the configuration menu.
The next sections explain how to bring to the LONWORKS network and BACnet network to the
Allure EC-Smart-Vue sensor. Both are handled slightly differently since there can only be a
limited number of enabled controllers on a LONWORKS network, whereas BACnet has no lim-
itations.
Figure 64: Overview of the Allure EC-Smart-Vue sensor Subnetwork Data Bus with LAN Access
- Temporary
Commissioning and
Maintenance
Connection
- No EOL Resistors are
Necessary EC-Net Pro
Certain controller models support the ability to bring the LAN to the Allure EC-Smart-Vue sen-
sor, while other controller models do not.
ECB/ECL-PTU Series No -
ECB/ECL/VAVS
All LONWORKS controllers have Net to Subnet Port Settings jumpers which when enabled will
bring down the LONWORKS network to the Allure EC-Smart-Vue sensor (for jumper locations
see Figure 66 and Figure 67).
The image below shows a typical LONWORKS network data bus topology with only a few con-
trollers enabled for LAN access at the Allure EC-Smart-Vue sensor.
For maximum cable lengths and cable specifications for a LONWORKS network data bus topol-
ogy, refer to Network Cables on page 55.
The length of the Allure EC-Smart-Vue sensor subnetwork data bus must also comply with the
restrictions shown in Subnetwork Data Bus Length on page 75.
To connect the main LONWORKS network to the Cat 5e Cable subnetwork data bus, set the
two Net to Subnet Port Settings jumpers inside the ECL series controller to Enable. The fac-
tory-set default is disabled. Refer to the controller's Hardware Installation Guide for how to
identify and set a controller's Net to Subnet Port jumpers.
Net to Subnet
Port Settings
Enable
Disable
Enable
Disable
Figure 67: Figure 5 4: Dip Switch and Jumper Identification and Configuration
NETWORK ADDRESS
8 7 6 5 4 3 2 1
ON
Network
Addressing
Cover Removed
BIAS
BIAS
EOL
1 2 3
* Factory-default positions
On each Allure EC-Smart-Vue sensor, make sure that the BAC/LON jumper is set to the LON
position. This should be done for all Allure EC-Smart-Vue sensors, in case you wish to enable
network access in the future.
BAC
LON
To temporarily access the LONWORKS LAN for commissioning and maintenance purposes,
connect a LONWORKS USB Network Interface to the stereo audio plug port located on the
lower edge of the Allure EC-Smart-Vue sensor. Then wire a standard 3.5 mm (?") three-con-
ductor (stereo jack) or two-conductor (mono jack) as shown below.
Figure 69: 1/8" (3.5 mm) Stereo or Mono Jack Connection for a LONWORKS Network Interface
- Temporary
Mono Jack Stereo Jack Commissioning and
Maintenance
Connection
To LON USB
Network Interface
EC-Net Pro
LON USB Network
Interface
BAC
LON
To temporarily access the LAN for commissioning and maintenance purposes, connect a por-
table adaptor to the stereo audio plug located on the lower edge of the Allure EC-Smart-Vue
sensor.
The BACnet MS/TP adaptor must have an electrically-isolated RS-485 port. Other-
wise a ground path from the BACnet network will be made through the computer
that will disrupt BACnet network communications.
Figure 71: 1/8" (3.5 mm) Stereo Jack Connection for a Portable Adapter
LAN Access
Connector
BACnet MS/TP Adaptor
NET+ with Isolated RS-485 Port
NET-
Shield
Cable Supplied with
BACnet MS/TP Adaptor
NET+ (White)
NET- (Red) - Temporary
Shield (bare) Commissioning and
Maintenance
To BACnet MS/TP Connection
Adaptor - No EOL Resistors are
Necessary EC-Net Pro
The following BACnet MS/TP adapter is available from Distech Controls: BACnet/IP to MS/TP
Adapter, part number NC-BASRTPBXX.
CHAPTER 6
BACNET TROUBLESHOOTING
You can use this Troubleshooting Guide to help detect and correct issues that you may
encounter.
Controller is powered Fuse has blown (for Disconnect the power. Check the fuse integrity. Reconnect the power.
but does not turn on 24V controllers)
Power supply polarity Verify that consistent polarity is maintained between all controllers and the trans-
former. Ensure that the COM terminal of each controller is connected to the same
terminal on the secondary side of the transformer. See Power Supply Require-
ments for 24V Controllers on page 41.
The device does not Verify that the transformer used is powerful enough to supply all controllers. See
have power / poor- Power Supply Requirements for 24V Controllers on page 41.
quality power (for 24V
controllers)
Device does not com- Absent or incorrect 1. Check if the device is showing the 'Poor- Quality Power' status code (for 24V
municate on the BAC- supply voltage (for controllers). See Table 30 for a list of fault codes.
net MS/TP network 24V controllers) 2. Check power supply voltage between 24VAC/DC ±15% and 24V COM pins
and ensure that it is within acceptable limits (for 24V controllers).
3. Check for tripped fuse or circuit breaker.
Overloaded power 1. Check if the device is showing the 'Poor- Quality Power' status code. SeeTable
transformer (for 24V 30 for a list of fault codes.
controllers) 2. Verify that the transformer used is powerful enough to supply all controllers.
See Transformer Selection and Determining the Maximum Power Run Length on
page 43.
Network not wired Double check that the wire connections are correct.
properly
Max Master parameter Configure the Max Master to the highest MAC Address of any device on the MS/
TP data bus. See Setting the Max Master and Max Info Frames on page 34.
There is another con- Each controller on a BACnet MS/TP data bus must have a unique MAC Address.
troller with the same Look at the MAC Address DIP switch on the faceplate of each controller. If it is set
MAC Address on the to 0 (all off), use an Allure EC-Smart-Vue sensor to check the MAC Address.
BACnet MS/TP data
bus
There is another con- Each controller on a BACnet intranetwork (the entire BACnet BAS network) must
troller with the same have a unique Device ID. Use an Allure series communicating sensor to check
Device ID on the BAC- the Device ID of each controller. See Adopting a Numbering System for MAC
net intranetwork Addresses, Device Instance Numbers, and Network Numbers on page 36.
BACnet data bus Ensure the polarity of the BACnet data bus is always the same on all devices.
polarity is reversed. See BACnet MS/TP data bus is polarity sensitive on page 146.
Cut or broken wire. Isolate the location of the break and pull a new cable.
The BACnet data bus See Adopting a Numbering System for MAC Addresses, Device Instance Num-
has one or more bers, and Network Numbers on page 167.
devices with the same
MAC Address.
The baud rate for all At least one device must be set to a baud rate, usually the data bus master. See
devices are set to Setting the Baud Rate for ECB-Series Controllers (optional) on page 101.
AUTO
The device is set to a See if the STATUS LED on the device is showing a fault condition. See Table 28
MAC Address in the for a list of fault codes.
range of 128 to 255. This range is for slave devices that cannot initiate communication. All Distech
Controls' devices are master devices and must their MAC Address set accord-
ingly. See Device Addressing on page 164.
The maximum num- Use a repeater to extend the BACnet data bus. See Maximum Number of BACnet
ber of devices on a MS/TP Devices on a Data Bus Segment and Baud Rate on page 148.
data bus segment has
been exceeded.
The STATUS LED is The device has auto- See Table 28 for a list of fault codes.
blinking diagnosed a fault con-
dition
Controller communi- Network length Check that the total wire length does not exceed the specifications of the Network
cates well over a short Guide. See Data Bus Physical Specifications and Cable Requirements on page
network, but does not 151.
communicate on large
network Wire type Check that the wire type agrees with the specification of the Network Guide: See
Data Bus Physical Specifications and Cable Requirements on page 151.
Network wiring prob- Double check that the wire connections are correct.
lem
Absent or incorrect Check the network termination(s). Incorrect or broken termination(s) will make the
network termination communication integrity dependent upon a controller's position on the network.
Number of controllers The number of controllers on a channel should never exceed 50. Use a router or
on network segment a repeater: See Data Bus Segment MAC Address Range for BACnet MS/TP
exceeded Deviceson page 148.
Max Master parameter Configure the maximum number of master device on the MS/TP network in all
devices to the controller's highest MAC address used on the MS/TP trunk. BAC-
net MS/TP Data Bus Token-Passing Overview on page 165.
Hardware input is not Input wiring problem Check that the wiring is correct according to the module's hardware installation
reading the correct manual and according to the peripheral device's manufacturer recommendations.
value
Open circuit or short Using a voltmeter, check the voltage on the input terminal. For example, for a dig-
circuit ital input, a short circuit shows approximately 0V and an open circuit shows
approximately 5V. Correct wiring if at fault.
Configuration problem Using the controller configuration wizard, check the configuration of the input.
Refer to the controller's user guide for more information.
Over-voltage or over- An over-voltage or over-current at one input can affect the reading of other inputs.
current at an input Respect the allowed voltage / current range limits of all inputs. Consult the appro-
priate datasheet for controller input range limits.
Hardware output is not Fuse has blown (Auto Disconnect the power and outputs terminals. Then wait a few seconds to allow
operating correctly reset fuse, for 24V the auto-reset fuse to cool down. Check the power supply and the output wiring.
controllers) Reconnect the power.
Output wiring problem Check that the wiring is correct according to the module's hardware installation
manual and according to the peripheral device's manufacturer.
Configuration problem With EC-gfxProgram, check the configuration of the output; for example, is it
enabled? Refer to the EC-gfxProgram User Guide for more information.
0-10V output, 24VAC Check the polarity of the 24VAC power supply connected to the actuator while
powered actuator is connected to the controller. Reverse the 24VAC wire if necessary.
not moving
Wireless devices not Device not associated Using the device configuration wizard, check the configuration of the input. Refer
working correctly to controller to the controller's device's user guide for more information.
Power discharge 1. Recharge device with light (if solar-powered) or replace battery (if battery-pow-
ered).
2. Ensure sufficient light intensity (200lx for 4 hours/day).
Device too far from the Reposition the device to be within the range of the Wireless Receiver. For infor-
Wireless Receiver mation on typical transmission ranges, refer to the Open-to-Wireless™ Solution
Guide.
Configuration problem With EC-gfxProgram, check the configuration of the input; for example, is it
enabled? Refer to the EC-gfxProgram User Guide for more information
Refer to the controller's Hardware Installation Guide for how to identify and set a controller's
configuration jumpers and switches.
RX LED not blinking Data is not being received from the BACnet If there is no communication, See Table 27.
MS/TP data bus.
TX LED not blinking Data is not being transmitted onto the BACnet
MS/TP data bus.
POWER constant on Power is available at the device. However this If not lit, see See Power Supply Requirements for 24V
does not mean that the quality of supplied Controllers on page 41 for the power requirements.
power is good. See Power Supply Require-
ments for 24V Controllers on page 41.
Table 29: STATUS LED Interpretation for Normal Operation with ECB Devices
Fast blink continuous: Firmware upgrade in progress Controller operation is temporarily unavailable. The new
firmware is being loaded into memory. This takes a few
seconds. Do not interrupt power to the device during this
(150ms On, 150ms time.
Off, continuous)
Table 29: STATUS LED Interpretation for Normal Operation with ECB Devices
Table 30: STATUS LED Fault Condition Interpretation for ECB Devices
Long Long Long blink Offline The device has not received a BACnet token, and therefore cannot communicate
on the network: Verify that the controller's MAC Address is unique on the BACnet
MS/TP Data Bus - see About the MAC Address on page 31. Make sure the con-
(800ms On, 300ms
troller's baud rate is the same as the BACnet MS/TP Data Bus' baud rate (see
Off, 800ms On, 300ms
Maximum Number of BACnet MS/TP Devices on a Data Bus Segment and Baud
Off, 800ms On)
Rate on page 14). Verify that the Max Master is set high enough to include this
controller's MAC Address (see Setting the Max Master and Max Info Frames on
page 34).
Short Short Long blink Poor-quality power. The voltage at the 24VAC/DC and 24VCOM terminals was not at an acceptable
The device has level during power up.
browned-out (for 24V
(150ms On, 300ms controllers)
Off, 150ms On, 300ms
Off, 800 ms On)
Short Long blink Invalid MAC address The device's MAC address is set to zero (0) or is set to an address higher than
the Max Master. See BACnet MS/TP Data Bus Token-Passing Overview on page
(150ms On, 300ms 32.
Off)
Table 31: Verify that the Following Recommendations have been Carried Out Before Calling Technical Support
Recommendation Description
Properly terminate the BACnet MS/ EOL terminations must be enabled / installed at either end of the data bus only. See Figure
TP data bus 71.
Avoid duplicate MAC Addresses Verify that no device has a duplicate MAC Address by checking the MAC Address DIP switch
settings on all devices on the data bus, including segments connected by a repeater.
If necessary, isolate devices from the data bus to narrow-down the number of devices that
may be at fault.
All devices must be set to the same When all devices are set to AUTO baud rate, at least one device must be set to a baud rate,
baud rate usually the data bus master. See Maximum Number of BACnet MS/TP Devices on a Data
Bus Segment and Baud Rate on page 148.
Recommendation Description
The data bus is polarity sensitive Ensure that the polarity of all data bus wiring is consistent throughout the network. See BAC-
net MS/TP data bus is polarity sensitive on page 146.
Do not overload the data bus with COV reports create the most traffic on the BACnet MS/TP data bus. Set the COV report rate
Change of Value (COV) reporting to the largest value that provides acceptable performance. Only map COV reports for values
that are necessary. For mapped analog points that are continuously changing, try increasing
the COV increment on these points or set the COV minimum send time flag to true to send
the value at a regular frequency.
Do not leave address holes in the Assign MAC Address to device starting at 3, up to 127. Do not skip addresses. Set the maxi-
device’s MAC Address range mum MAC Address in the ECY Series Controller to the final MAC Address number actually
installed.
NOTE: The physical sequence of the MAC Address of the devices on the data bus is unim-
portant: For example, the MAC Address of devices on the data bus can be 5, 7, 3, 4, 6, and 8.
Only daisy-chained devices are Eliminate T-taps and star configurations. Use a router to connect a data bus spur.
acceptable
Connect no more than five devices to BACnet MS/TP devices require good power quality. See Power Supply Requirements for
a power supply transformer (for 24V 24VAC-Powered Controllers on page 171.
controllers)
CHAPTER 7
LONWORKS TROUBLESHOOTING
You can use this Troubleshooting Guide to help detect and correct issues that you may
encounter.
Device does not com- The device does not See Power Supply Requirements for 24V Controllers on page 61.
municate on the LON- have power / poor-
WORKS MS/TP quality power.
network
Cut or broken wire. Isolate the location of the break and pull a new cable.
The maximum num- Use a repeater to extend the BACnet data bus. See Network Cables on page 55.
ber of devices on a
data bus segment has
been exceeded.
Absent or incorrect 1. Check if the device is showing the 'Poor Power Quality' status code (for 24V
supply voltage controllers). See Table 35 for a list of fault codes.
2. Check power supply voltage between 24VAC/DC ±15% and 24V COM pins
and ensure that it is within acceptable limits (for 24V controllers).
3. Check for tripped fuse or circuit breaker.
Overloaded power 1. Check if the device is showing the 'Poor Power Quality' status code. See Table
transformer (for 24V 35 for a list of fault codes.
controllers) 2. Verify that the transformer used is powerful enough to supply all controllers.
See Transformer Selection and Determining the Maximum Power Run Length on
page 61.
Network not wired Double check that the wire connections are correct.
properly
Too many Allure EC- Disable the Net to Subnet Port Settings jumpers on all controllers. If communica-
Smart-Vue sensors tions are re-established, re-enable only a few Allure EC-Smart-Vue sensors to
are providing network have network access.
access
The STATUS LED is The device has auto- See Table 33 for a list of fault codes.
blinking diagnosed a fault con-
dition
Controller is powered Fuse has blown (for Disconnect the power. Check the fuse integrity. Reconnect the power.
but does not turn on 24V controllers)
Power supply polarity Verify that consistent polarity is maintained between all controllers and the trans-
former. Ensure that the COM terminal of each controller is connected to the same
terminal on the secondary side of the transformer. See Power Supply Require-
ments for 24V Controllers on page 61.
Controller communi- Network length Check that the total wire length does not exceed the specifications of the Network
cates well over a short Guide. See Data Bus Physical Specifications and Cable Requirements on page
network, but does not 151.
communicate on large
network
Wire type Check that the wire type agrees with the specification of the Network Guide: See
Data Bus Physical Specifications and Cable Requirements on page 151.
Network wiring prob- Double check that the wire connections are correct.
lem
Absent or incorrect Check the network termination(s). Incorrect or broken termination(s) will make the
network termination communication integrity dependent upon a controller's position on the network.
Extra capacitance Make sure that no extra capacitance is being connected to the network other than
the standard FTT circuit, and a maximum of a 3 meter stub (in bus topology).
Number of controllers The number of controllers on a channel should never exceed 50. Use a router or
on network segment a repeater: See Data Bus Segment MAC Address Range for BACnet MS/TP
exceeded Deviceson page 148.
Hardware input is not Input wiring problem Check that the wiring is correct according to the module's hardware installation
reading the correct manual and according to the peripheral device's manufacturer recommendations.
value
Open circuit or short Using a voltmeter, check the voltage on the input terminal. For example, for a dig-
circuit ital input, a short circuit shows approximately 0V and an open circuit shows
approximately 5V. Correct wiring if at fault.
Configuration problem Using the controller configuration wizard, check the configuration of the input.
Refer to the controller's user guide for more information.
Over-voltage or over- An over-voltage or over-current at one input can affect the reading of other inputs.
current at an input Respect the allowed voltage / current range limits of all inputs. Consult the appro-
priate datasheet for controller input range limits.
Hardware output is not Fuse has blown (Auto Disconnect the power and outputs terminals. Then wait a few seconds to allow
operating correctly reset fuse, for 24V the auto-reset fuse to cool down. Check the power supply and the output wiring.
controllers) Reconnect the power.
Output wiring problem Check that the wiring is correct according to the module's hardware installation
manual and according to the peripheral device's manufacturer.
Configuration problem With EC-gfxProgram, check the configuration of the output; for example, is it
enabled? Refer to the EC-gfxProgram User Guide for more information.
0-10V output, 24VAC Check the polarity of the 24VAC power supply connected to the actuator while
powered actuator is connected to the controller. Reverse the 24VAC wire if necessary.
not moving
Wireless devices not Device not associated Using the device configuration wizard, check the configuration of the input. Refer
working correctly to controller to the controller's device's user guide for more information.
Power discharge 1. Recharge device with light (if solar-powered) or replace battery (if battery-pow-
ered).
2. Ensure sufficient light intensity (200lx for 4 hours/day).
Device too far from the Reposition the device to be within the range of the Wireless Receiver. For infor-
Wireless Receiver mation on typical transmission ranges, refer to the Open-to-Wireless™ Solution
Guide.
Configuration problem With EC gfxProgram, check the configuration of the input; for example, is it
enabled? Refer to the EC gfxProgram User Guide for more information
Refer to the controller's Hardware Installation Guide for how to identify and set a controller's
configuration jumpers and switches.
RX LED not blinking Data is not being received from the If there is no communication, see Table 32.
BACnet MS/TP data bus.
POWER constant on Power is available at the device. If not lit, see Power Supply Requirements for 24V Controllers on
However this does not mean that page 61 for the power requirements.
the quality of supplied power is
good. See Power Supply Require-
ments for 24V Controllers on page
61.
Table 34: STATUS LED Interpretation for Normal Operation with ECB Devices
Fast blink continuous Firmware upgrade in progress Controller operation is temporarily unavailable. The
new firmware is being loaded into memory. This takes
: a few seconds. Do not interrupt power to the device
(150ms On, 150ms Off, continuous) during this time.
Table 35: STATUS LED Fault Condition Interpretation for ECL Devices
Long Long Long blink The controller is offline Set the controller Online
Long Short Short Short blink The controller is in bypass Set the controller Online
mode
(800ms On, 300ms Off, 150ms On,
300ms Off, 150ms On, 300ms Off,
150ms On)
Short Short Long blink Poor-quality power; The device The voltage at the 24VAC/DC and 24VCOM terminals
has browned-out (for 24V con- has gone below the device's acceptable limit during
trollers) power up.
(150ms On, 300ms Off, 150ms On,
300ms Off, 800 ms On)
Fast blink 12x: Wink The wink function is used to identify a device.
Table 36: Verify that the Following Recommendations have been Carried Out Before Calling Technical Support
Recommendation Description
Properly terminate the BACnet MS/ EOL terminations must be enabled / installed at either end of the data bus only. See TP/FT 10
TP data bus Free Topology Network Termination on page 55.
Connect no more than five devices to LonWorks devices require good power quality. See TP/FT 10 Free Topology Network Termi-
a power supply transformer (for 24V nation on page 55.
controllers)
CHAPTER 8
ECx-4XX Series I/O Extension Module
Specific Troubleshooting
For general troubleshooting of an ECx-4XX Series I/O Extension Module, first follow the trou-
bleshooting for a controller - see BACnet Troubleshooting on page 109 and LonWorks Trou-
bleshooting on page 115. Then follow the troubleshooting tips shown below.
Table 37: Troubleshooting ECx-4XX Series I/O Extension Module Device Specific Symptoms
Device does not com- Absent or incorrect supply voltage 1. Check power supply voltage between 24VAC/DC ±15% and
municate on the BAC- 24V COM pins and ensure that it is within acceptable limits (for
net MS/TP network 24V controllers).
3. Check for tripped fuse or circuit breaker.
Cut or broken wire. Isolate the location of the break and pull a new cable.
Overloaded power transformer Verify that the transformer used is powerful enough to supply all
controllers. See ECx-4XX I/O Extension Module Power Supply
Requirements on page 47.
Network not wired properly Double check that the wire connections are correct.
Absent or incorrect network termina- Check the network termination(s). See 2-Wire Subnetwork Data
tion Bus Topology and End-of-Line (EOL) Terminations on page 93.
There is another controller with the Each I/O Extension Module on the subnetwork data bus must have
same Subnet ID on the subnetwork a unique Subnet ID. Look at the Subnet ID DIP switch on the face-
data bis plate of each I/O Extension Module. See ECx-4XX I/O Extension
Module Addressing on page 95.
Network length Check that the total wire length does not exceed the specifications
of the Network Guide. See About the Subnetwork Data Bus on
page 70.
Wire type Check that the wire type agrees with the specification shown in 2-
Wire Subnetwork Data Bus Physical Specifications and Cable
Requirements on page 92.
CHAPTER 9
Allure EC-Smart-Vue Sensor Trouble-
shooting
Table 38: Allure EC-Smart-Vue Sensor Normal Operation
When the Allure EC-Smart- Firmware upgrade in prog- Wait for the upgrade to complete. Do not disconnect the Allure EC-
Vue sensor is connected to ress Smart-Vue sensor from the controller as the upgrade will only restart
a Controller, the LCD dis- once it is reconnected.
play on the Allure EC-
Smart-Vue sensor is blank
with the backlight ON for
about 30 to 45 seconds
Allure EC-Smart-Vue sen- Is the Allure EC-Smart-Vue Verify that the Allure EC-Smart-Vue sensor is connected to the control-
sor screen is blank & back sensor connected to the ler and that the patch cables are plugged-in to the connectors. See Cat
light is off controller? 5e Cable Subnetwork Data Bus on page 79 for more information.
Is power being supplied to There may be no power being supplied from the controller. Check if the
the controller? controller has power or if the controller's internal fuses have blown or
tripped.
Was the patch cable made Verify that the RJ-45 crimp connectors were installed on the cable cor-
onsite? rectly. See Cat 5e Cable Subnetwork Data Bus Cable Requirements on
page 79.
Device is not communicat- Is the address correctly set Each Allure EC-Smart-Vue sensor must be set to a unique address for
ing with controller to a unique address? each controller. See Commissioning a Controller with an Allure EC-
Smart-Vue Sensor on page 98.
Is the device too far from Verify the distance between the device and the controller. See Subnet-
controller? work Data Bus Length on 75.
Is there a configuration With EC-gfxProgram, check the configuration of the sensor, for exam-
problem? ple, is it enabled? Refer to the EC-gfxProgram User Guide for more
information.
Have the subnetwork EOL Only the last module on the subnetwork data bus must have its EOL
settings been correctly set? termination set to ON. See Figure 51, Figure 53, and Figure 54. When
one or more ECx-400 Series IO Extension modules are connected to
the controller, only the last ECx-400 must have its EOL termination set
to ON. See Figure 61.
Controller cannot communi- Too many Allure EC-Smart- Disable the Net to Subnet Port Settings jumpers on all controllers (for
cate on the LONWORKS Vue sensors are providing jumper location, see LAN through an Allure EC-Smart-Vue Sensor for a
network (ECL controllers network access LonWorks Network on page 104). If communications are re-estab-
only) lished, re-enable only a few Allure EC-Smart-Vue sensors to have net-
work access.
Allure EC-Smart Vue sen- Does the connected con- When the Allure EC-Smart-Vue sensor is connected to a controller, its
sor motion detector window troller have Allure EC- firmware is loaded from the controller. In this case, the controller has an
indicator is always ON Smart-Vue sensor firmware earlier version of Allure EC-Smart-Vue sensor firmware that does not
that supports the motion support the motion or CO2 sensor. To upgrade to the latest Allure EC-
The Motion or CO2 output and CO2 sensor? Smart-Vue sensor firmware, download the firmware from the Software
of the associated ComSen- Center and refer to the firmware upgrade procedure in the EC-gfxPro-
sor block always reads gram User Guide.
NULL in EC-gfxProgram
The CO2 sensor readings Immediately after installing If the CO2 sensor readings seem unusual or show inconsistencies
are too high, too low, or the Allure EC-Smart-Vue between sensors in the same building right after installation, the follow-
inconsistent between sen- sensor with CO2 sensors, ing reasons should be taken into consideration:
sors are the CO2 sensor read- - Concentration levels in each space may be different
ings incoherent? - The installer may have unintentionally blown into the sensor while
installing it.
- The sensor may have been dropped or mishandled during shipment
causing a minor shift in the original factory calibration.
Allow up to 14 days of operation (without power interruptions) for the
sensor to calibrate itself according to its new environment.
Table 40: Error code Interpretation for Allure EC-Smart-Vue Sensor Symptoms
Clock icon flashing for 15 Cannot communicate with Wait for the communication link to the controller to be established.
seconds controller. Verify wiring.
Verify that all Allure EC-Smart-Vue sensor's Subnet IDs are unique for
After 15 seconds: Error this controller. See Setting the Allure EC-Smart-Vue Sensor's Subnet
code 1 with Bell icon ID Address on page 98.
Error code 2 with Bell icon Invalid configuration. In EC-gfxProgram, resynchronize the code with the controller.
Contact Distech Controls customer support.
Error code 3 with Bell icon Allure EC-Smart-Vue sen- With EC-gfxProgram, check the configuration of the sensor, for exam-
sor is not properly config- ple, is the ComSensor block enabled? Refer to the EC-gfxProgram
ured in the controller User Guide for more information.
CHAPTER 10
ECx-Light/Blind Series Troubleshoot-
ing
Table 41: Troubleshooting ECx-Light / Blind Series Symptoms
Allure EC-Smart-Vue sen- Is the Allure EC-Smart-Vue Verify that the Allure EC-Smart-Vue sensor is connected to the control-
sor screen is blank & back sensor connected to the ler and that the patch cables are plugged-in to the connectors. See Cat
light is off controller? 5e Cable Subnetwork Data Bus on page 79 for more information.
Is power being supplied to There may be no power being supplied from the controller. Check if the
the controller? controller has power or if the controller's internal fuses have blown or
tripped.
Was the patch cable made Verify that the RJ-45 crimp connectors were installed on the cable cor-
onsite? rectly. See Cat 5e Cable Subnetwork Data Bus Cable Requirements
on page 79.
Expansion module is not Is the address correctly set Each expansion module must be set to a unique address for each con-
communicating with control- to a unique address? troller. See Commissioning a Controller with an Allure EC-Smart-Vue
ler Sensor on page 98.
Is the device too far from Verify the distance between the device and the controller. See Subnet-
controller? work Data Bus Length on 75.
Is there a configuration With EC-gfxProgram, check the configuration of the sensor, for exam-
problem? ple, is it enabled? Refer to the EC-gfxProgram User Guide for more
information.
Have the subnetwork EOL Only the last module on the subnetwork data bus must have its EOL
settings been correctly set? termination set to ON. See Figure 51, Figure 53, and Figure 54. When
one or more ECx-400 Series IO Extension modules are connected to
the controller, only the last ECx-400 must have its EOL termination set
to ON. See Figure 61.
Hardware input is not read- Input wiring problem Check that the wiring is correct according to the module's hardware
ing the correct value installation manual and according to the peripheral device's manufac-
turer.
Open circuit or short circuit Using a voltmeter, check the voltage on the input terminal. For exam-
ple, for a digital input, a short circuit shows approximately 0V and an
open circuit shows approximately 3.3V. Correct wiring if at fault.
Configuration problem With EC-gfxProgram, check the configuration of the input; for example,
is it enabled? Refer to the EC-gfxProgram User Guide for more infor-
mation.
Over-voltage or over-cur- An over-voltage or over-current at one input can affect the reading of
rent at an input other inputs. Respect the allowed voltage / current range limits of all
inputs. Consult the appropriate datasheet for controller input range lim-
its.
Hardware output is not Output wiring problem Check that the wiring is correct according to the module's hardware
reading the correct value installation manual and according to the peripheral device's manufac-
turer.
Configuration problem With EC-gfxProgram, check the configuration of the output; for exam-
ple, is it enabled? Refer to the EC-gfxProgram User Guide for more
information.
APPENDIX A
Typical BACnet EIA-485 Data Bus
Transmission Example
The graph below shows electrical signals for the transmission of one byte of data (hexadeci-
mal D3, least significant bit first). Note that when idle, the BACnet MS/TP data bus is biased
such that the Net + connection is positive with respect to the Net - connection.
Space
Mark
Mark Space Mark
Net + Mark Mark
Stop
The permitted voltage levels of an EIA-485 transmitter and receiver are shown below.
Permissible
Range
Maximum
+2 Volts
+0.2 Volts Transition Operating
Voltage VNet-,Net+ Voltage VNet-,Net+ Range
Region
-0.2 Volts
-2 Volts
Permissible
Range
-7 Volts -7 Volts
-1.5 -5 V
The receiver is also protected against the temporary application of 24VAC and against tran-
sients. However, such events will interrupt data reception.
Noise induced onto the conductors of the data bus cable will be common to both Net + and
Net - data bus wires - that is to say, the noise will be of the same amplitude and polarity as the
conductors in the cable are so close together. For this reason the EIA-485 data bus is differen-
tial data bus. The receiver nulls out common mode induced noise picked up on the data bus
wire by subtracting the negative input from the positive input. This greatly reduces the impact
that induced noise has on the data bus.
Figure 74: Common-Mode Noise is Significantly Attenuated by a Differential EIA-485 Line Receiver
Induced common-mode noise transient
Noise transient
attenuation
APPENDIX B
How to Set a Dip Switch
DIP switches are used to set the address of a device. In the following table, A & B represent
the binary ON / OFF setting for the DIP switch required for a given decimal value shown in the
table.
B
000 001 010 011 100 101 110 111
A
0000 0 1 2 3 4 5 6 7
0001 8 9 10 11 12 13 14 15
0010 16 17 18 19 20 21 22 23
0011 24 25 26 27 28 29 30 31
0100 32 33 34 35 36 37 38 39
0101 40 41 42 43 44 45 46 47
0110 48 49 50 51 52 53 54 55
0111 56 57 58 59 60 61 62 63
1000 64 65 66 67 68 69 70 71
1001 72 73 74 75 76 77 78 79
1010 80 81 82 83 84 85 86 87
1011 88 89 90 91 92 93 94 95
ON
A B
For example
82 = A: 1010 & B: 010
APPENDIX C
Metric Conversions for Wire Gauge
The following table provides information about metric wire equivalents for wire gauge.