0% found this document useful (0 votes)
77 views15 pages

Project Implementations

The document consists of a series of questions related to project engineering and implementation, focusing on payment schedules, work orders, variation orders, and project completion certifications. It outlines specific timeframes and conditions under which contractors can claim payments, extensions, and variations. The content is structured as a quiz format, testing knowledge on various regulations and procedures in project management.

Uploaded by

Can I Pee?
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
77 views15 pages

Project Implementations

The document consists of a series of questions related to project engineering and implementation, focusing on payment schedules, work orders, variation orders, and project completion certifications. It outlines specific timeframes and conditions under which contractors can claim payments, extensions, and variations. The content is structured as a quiz format, testing knowledge on various regulations and procedures in project management.

Uploaded by

Can I Pee?
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

Project Engineer

Project Implementation

Question 1 of 42

For progress payment after the first, payments can be made once every _____.

 week

 two weeks

 month

 quarter of the year

Question 2 of 42

The DPWH shall not issue a work suspension order if the interruption is due to
intermittent conditions which renders the site unworkable, instead ____ is used.

 Extra Work Order

 Contract Time Extension

 Work Resumption Order

 Monthly Time Suspension Report

Question 3 of 42

What is the maximum limit of additive Variation Order allowed under RA 9184?

 15% of the approved budget for the contract

 10% of the approved budget for the contract

 10% of the original contract price

 15% of the original contract price


Question 1 of 42

Retention money refers to the amount equal to ___ of the progress payments, before
deductions are made, that is withheld by the Procuring Entity to cover the uncorrected
discovered defects and third-party liabilities.

 10%

 5%

 20%

 15%

Question 2 of 42

It is a document issued by the implementing office certifying that the project is


accepted by the same, after successful completion of all contractual obligations,
requirements, and/or specifications, including any required correction of
defects/deficiencies.

 Final Payment

 Pre-Final Inspection Report

 Certificate of Completion

 Certificate of Final Acceptance

Question 3 of 42

Request letter by the contractor to the implementing office for contract time extension
(CTE) shall be done

 5 days after contract expiration

 within 30 calendar days after such work has been commenced or


after the circumstances leading to such claim have arisen

 within 28 calendar days after such work has been commenced or after the
circumstances leading to such claim have arisen

 within 45 calendar days after such work has been commenced or after the
circumstances leading to such claim have arisen
Question 4 of 42

Based on the Inspection Report for Final Acceptance, the Head of the IO shall issue to
the contractor a Notice of Defects/ Deficiencies and Required Corrective Repair Works,
with the instructions for the contractor to commence the repair works within ___ days
and to complete within ___ days, from receipt of the aforesaid Notice.

 10 & 90 respectively

 10 & 28 respectively

 7 & 90 respectively

 7 & 30 respectively

Question 5 of 42

In exceptional cases where it is urgently necessary to complete the original scope of


work, the Head of the Procuring Entity may authorize a positive VO that will make the
cumulative value beyond 10% but not more than ____ of the original contract
price. [**Not yet done in actual setup]

 15%

 20%

 25%

 30%

Question 6 of 42

It is a written order to the contractor to resume construction operation covered by a


previous Work Suspension Order, after the cause of or reason for the work suspension
has been resolved.

 Variation Order (VO)

 Work Suspension Order (WSO)

 Work Resumption Order (WRO)


 Contract Time Extension (CTE)

Question 7 of 42

It is a written authority, prior to the contract expiration, granting the contractor


additional time beyond the approved completion in order to carry out remaining works
or any additional works, on account of other special circumstances that warrant such
additional contract time.

 Variation Order (VO)

 Work Suspension Order (WSO)

 Work Resumption Order (WRO)

 Contract Time Extension (CTE)

Question 8 of 42

It is a written order to the contractor to suspend the contract work wholly or partly for
such period as may be deemed necessary.

 Variation Order (VO)

 Work Suspension Order (WSO)

 Contract Time Extension (CTE)

 Work Resumption Order (WRO)

Question 9 of 42

What should be prepared by the Contractor after the Pre-Construction Survey?

 As-Built Plans

 As-Staked Plans

 Revised Plan

 Original Plans
Question 10 of 42

The applicable liquidated-damages is at least ____ percent of the cost of the


unperformed portion for every day of delay

 1/10 of 1%

 1/5 of 5%

 1/10 of 5%

 1/5 of 1%

Question 11 of 42

A form of variation order to cover the introduction of new work necessary for the
completion, improvement or protection of the project which was not included as items
of work in the original contract.

 Contract Time Extension

 Change Order

 Work Resumption Order

 Extra Work Order

Question 12 of 42

A form of variation order to cover any increase / decrease in quantities of original work
items in the contract.

 Extra Work Order

 Work Resumption Order

 Contract Time Extension

 Change Order

Question 2 of 42
What is timeframe of the contractor to claim for variation order if the contractor
commenced work without approved VO?

 within 28 calendar days

 within 21 calendar days

 within 14 calendar days

 within 7 calendar days

Question 4 of 42

What is timeframe of the contractor to claim for variation order if there is a


circumstance or reason that justify a claim for Variation Order?

 within 21 calendar days

 within 28 calendar days

 within 7 calendar days

 within 14 calendar days

Question 8 of 42

After a pre-final inspection is conducted on a project and having verified an


accomplishment of 95% or more, which of the following is issued?

 Final Inspection Certificate

 Acceptance Certificate

 Punch List

 Turnover Certificate

Question 12 of 42

Under no circumstances shall a contractor proceed to commence work under any


Variation Order or Extra Work Order, UNLESS it has been approved by the HoPE,
provided it is within the ___ limit.
 3%

 5%

 10%

 20%

Question 13 of 42

The total “retention money” shall be due for release after

 Certificate of Completion

 75% completion of work

 Certificate of Final Acceptance

 50% completion of work

Question 14 of 42

Issued by the implementing office after the one-year defects liability period

 NOA

 NTP

 Certificate of Acceptance

 Certificate of Completion

Question 15 of 42

What should be prepared by the Contractor after the Pre-Construction Survey?

 Original Plans

 Revised Plan
 As-Staked Plans

 As-Built Plans

Question 16 of 42

The Contractor shall have the right to suspend work operation on any or all
projects/activities if the delay in the payment of contractor’s claim for progress billing
beyond ___ calendar days.

 10

 30

 45

 15

Question 17 of 42

It is a document issued by the implementing office certifying that the contract works/
deliverables has been factually and satisfactorily completed

 Final Payment

 Pre-Final Inspection Report

 Certificate of Completion

 Certificate of Final Acceptance

Question 18 of 42

For progress payment, the procuring entity shall pay the contractor the amounts
certified by the procuring entity’s representative within ___ days

 30

 15

 45
 28

Question 19 of 42

The contractor shall have the right to suspend work operations due to the following
reasons, except for:

 Delay in the payment of contractor's claim for progress billing


beyond 30 calendar days

 Non-Availability of Construction Materials

 There exist right-of-way problems

 Peace and order conditions make it extremely dangerous

Question 20 of 42

The Procuring Entity must recover the advance payment by deducting from the
progress payments to the contractor ____ until the advance is fully recouped within the
duration of the contract, and before full payment is made to the contractor.

 20%

 15%

 25%

 10%

Question 21 of 42

The timeframe from the lapse of the one-year DLP of the project up to the conduct for
inspection for acceptance shall not exceed ___ calendar days

 12

 28

 30
 7

Question 22 of 42

The total amount of Liquidated Damages is deducted to?

 Final Billing

 Advance Payment

 Bond

 Progress Billing

Question 23 of 42

It is a document issued by the implementing office certifying that the project is


accepted by the same, after successful completion of all contractual obligations,
requirements, and/or specifications, including any required correction of
defects/deficiencies.

 Certificate of Final Acceptance

 Certificate of Completion

 Pre-Final Inspection Report

 Final Payment

Question 24 of 42

An instruction issued by the Implementing Unit to cover any increase/decrease in


quantities, including the introduction of new work items that are not included in the
original contract or reclassification of work items that are either due to change of plans,
design or alignment to suit actual field conditions

 Variation Order

 Time Variance

 Contract Time Extension


 Price Escalation

Question 25 of 42

The Contractor shall have the right to suspend work operations on any or all
projects/activities along the critical path of activities after ___ from the date of receipt of
a written notice from the Contractor to the Implementing Office, due to various valid
reasons.

 10 cd

 15 cd

 30 cd

 45 cd

Question 26 of 42

At least _____ prior to the lapse of the DLP, the DPWH Project Management Team (PrMT)
may conduct a Preliminary Inspection jointly with the contractor

 1 month

 3 months

 2 months

 None of the above

Question 27 of 42

Defects Liability Period (DLP) is ____ from the date of completion of the project up to the
date of final acceptance.

 10 years

 5 years
 2 years

 1 year

Question 28 of 42

The following are done in an as-staked survey, except:

 Staking the limit for clearing and grabbing

 Locating proposed facilities

 Verifying actual field condition

 Geotechnical Investigation

Question 29 of 42

The time duration for preparation and submission of as-staked plan shall commence
from the date of acceptance of ____ by the contractor.

 Notice to Proceed (NTP)

 Certificate of Completion (CoC)

 Certificate of Final Acceptance (CFA)

 Notice of Award (NOA)

Question 30 of 42

Advance payment must not exceed ___ of the total contract price.

 10%

 15%

 20%

 25%
Question 31 of 42

When should the advance payment be released?

 After notice to proceed (NTP)

 After mobilization

 After certificate of completion (CoC)

 After certificate of final acceptance (CFA)

Question 32 of 42

What is timeframe of the contractor to claim for variation order if the contractor
commenced work without approved VO?

 within 28 calendar days

 within 7 calendar days

 within 14 calendar days

 within 21 calendar days

Question 33 of 42

Which of the following financial controls should be imposed if the project is delayed?

 Penalty by way of additional bond

 Withhold progress billing

 Confiscation of surety bond

 Liquidated damages

Question 34 of 42
If, after ___ completion, the work is satisfactorily done and on schedule, no additional
retention shall be made; otherwise, the ten percent (10%) retention shall continue to be
imposed.

 20%

 30%

 50%

 70%

Question 35 of 42

What is timeframe of the contractor to claim for variation order if there is a


circumstance or reason that justify a claim for Variation Order?

 within 21 calendar days

 within 28 calendar days

 within 14 calendar days

 within 7 calendar days

Question 36 of 42

The Contractor shall have the right to suspend work operations on any or all
projects/activities along the critical path of activities after ___ from the date of receipt of
a written notice from the Contractor to the Implementing Office, due to various valid
reasons.

 10 cd

 30 cd

 45 cd

 15 cd

Question 37 of 42
Issued by the implementing office after the one-year defects liability period

 NOA

 Certificate of Completion

 Certificate of Acceptance

 NTP